HomeMy WebLinkAbout08. Dobson_Arena_Council_Memo_and_Presentation_06042024_-_FinalDobson Arena Renovation – Program Update
| Vail Town Council June 4th, 2024
Dobson Arena Update – June 4, 2024
2
Agenda:
•Recap Results of Program Analysis and Costs
•Make recommendation to Town Council on Preferred Option
•Seek approval from Town Council to move to Design Development
Dobson Arena Update – June 4, 2024
2
P
•Contract Reconciliation with Top Ranked GC
•Finalization of reconciled project budget and scope for base program as the basis of the initial budget
•Refinement of program options and cost to build out three major project options
OUR ‘NEXT STEPS’ FROM THE LAST COUNCIL PRESENTATION:
Dobson Arena Update – June 4, 2024
2
Results of our Recent Work:
•The Team of Vail Rec District, TOV, Populous, HyderMcHugh and Cumming have vetted
Multiple Program Options
•We landed on three major options tailored to your request – started with 6 options
•Program has been revised and scope has been reduced to meet budget
•Our contingency is at the expected level relative to development of design
•The budget has been sliced, diced and picked apart
•We continue to develop alternates so that we may maximize program if costs improve
Dobson Arena Update – June 4, 2024
2
Dobson Arena Update – June 4, 2024
Let’s Recap the Major Options
Option A Option B Option C
Dobson Ice & MEP / Finish Refresh
Throughout
Alternate Analysis for Max Program
Enhancement While Reinforcing Roof
Full Renovation Incl. Replacing Roof
Structure
Replace MEP Y Y Y
Replace Ice Y Y Y
Refreshed Locker Rooms Y Y Y
Expanded Locker Rooms N Y Y
Add South Seating N Y Y
South Expansion N Y - reduced Y
Lounge/Concessions N Y - reduced Y
West Expansion N Y - reduced Y
Reinforcing the Roof N Y Y
Rigging Capacity N Y Y - roof replaced
Replace Roof Structure N N Y
New Layout per SD drawings N Y - Modified Y
Full SD Interior Finishes Refresh Only Y - reduced Y
Full SD Exterior Finishes Refresh Only Y - reduced Y
Low Voltage Scope Minimal Y - reduced Y
North Restrooms N Y - Alternate Price N
Site Enhancements N Y-reduced Y
2
Dobson Arena Update – June 4, 2024
Option A Option B Option C
Dobson Ice & MEP / Finish Refresh
Throughout
Alternate Analysis for Max Program
Enhancement While Reinforcing Roof
Full Renovation Incl. Replacing Roof
Structure
Current Budget Update
Hard Cost $25,418,043 $42,467,540 $59,204,745
Soft Cost $8,074,749 $12,482,228 $14,209,139
Total $33,492,792 $54,949,768 $73,413,884
Targeted Budget $55,391,228 $55,391,228 $55,391,228
Variance -$21,898,436 -$441,460 $18,022,656
The Budget for Each Major Option
How we compare to Budget.
Any savings that we have
identified on Option B are
being allocated to contingency
with a goal of adding restroom
fixtures and office space
2
Dobson Arena Update – June 4, 2024
Construction Duration 14 months 18.5 months 22 months
Option A Option B Option C
Dobson Ice & MEP / Finish Refresh
Throughout
Alternate Analysis for Max Program
Enhancement While Reinforcing Roof
Full Renovation Incl. Replacing Roof
Structure
The Schedule for Each Major Option
•Lose one ice season •Lose one ice season •Lose two ice seasons
•Spring of ‘26 start
•8% escalation is a
real risk
2
Dobson Arena Update – June 4, 2024
•Refreshed locker rooms
•Refresh of Finishes
•Full Replacement of MEP
•Essentially as it Exists Today regarding program space
•Reinforcing Roof is an Additional: $2.4M
•Reduced HVAC Mechanical Option: ($1.08M)
•Adds an ADA elevator
•Lowest Budget
•Shortest Schedule – Spring Start – 14.5 month project
•Lose one season of ice use
Option A – Repair and Refresh
Let’s Review the Options:
2
Dobson Arena Update – June 4, 2024
Add Image of existing facility as
is
2
Dobson Arena Update – June 4, 2024
•Reinforced Roof – Keeps the Dobson Look
•Refreshed locker rooms with Expansion
•Provides Full Equitable Solution for Locker Rooms
•Expanded South Lobby & New West Entry
•Sets the Stage for the Civic Center Master Plan
•Full Replacement of MEP
•Updated Envelope will Reduce Operating Costs
•Resolves ADA Access
•Lounge, Concessions and Bathrooms are Improved
•Exterior and Interior Refreshed
•Enhanced Flexibility for Events
•Restrooms designed for Max Hockey Event
•Alternate for North Bathrooms to be Priced
Option B – Recommended Program within Targeted Budget of $55.4M
2
Dobson Arena Update – June 4, 2024
2
Dobson Arena Update – June 4, 2024
2
Dobson Arena Update – June 4, 2024
2
Dobson Arena Update – June 4, 2024
2
Dobson Arena Update – June 4, 2024
2
Dobson Arena Update – June 4, 2024
2
Dobson Arena Update – June 4, 2024
2
Dobson Arena Update – June 4, 2024
2
Dobson Arena Update – June 4, 2024
2
Dobson Arena Update – June 4, 2024
2
Dobson Arena Update – June 4, 2024
2
Dobson Arena Update – June 4, 2024
2
Dobson Arena Update – June 4, 2024
2
Dobson Arena Update – June 4, 2024
2
Dobson Arena Update – June 4, 2024
2
Dobson Arena Update – June 4, 2024
•All In Revamp of Dobson
•New Roof Structure with New Roof
•Larger South Expansion
•Refreshed Site Hardscapes
•Refreshed locker rooms w Expansion
•New West Entry
•Full Replacement of MEP
•Larger Lounge Concessions
•Full Complement of Restrooms for Max
Event
•Provides Mezzanine level
•Option C cannot start until Spring of 2026
Option C – Full Remodel including New Raised Roof
Structure
GH0
2
Recommendations:
•Option C is not viable without substantial additional funds
•Option A resolves our ice and mechanical/electrical issues but falls short of the vision
•Option B restores and enhances Dobson as Vail’s key Recreation and Events venue for
the next 40 years
We are seeking permission to take the following next steps:
•Finalize the Program Option Choice with your Approval
•Move to Design Development Phase
•Start the PEC and DRB entitlement Process
•Meet Again with the Building and Fire to Confirm Progress
•Start the Preconstruction Process in Earnest and Conduct Additional Investigations to
Refine Design, Budget and Schedule
Dobson Arena Update – June 4, 2024
Aug. 25 – Sep.
27, 2023
Reconciliation with Top Ranked
Firm
Feb 7. – July 16,
2024
Design Development Phase
Start is on hold until program
is verified and approved by
TOV
Mar. 20, 2024
Tentative Contractor Start
June 4, 2024
Town Council Approval of
Program Option and move to
DD’s
July 2024
Town Council 50%
DD/Entitlement Authorization
to Seek PEC/DRB Approval
October 2024
Town Council Approval of DD
Price and Design; Permission to
move to CD’s
November 2024
to January 2025
Targeted Construction
Documents phase
March 2025
Town Council Approval of Final
GMP & Approval to Award
March 2025 to
Fall 2026
Target Construction Phase with
Early Demo Permit
Project Milestones
Dobson Arena Update – June 4, 2024
GH0
GH1