HomeMy WebLinkAboutSolaris PHASE INSPECTION CALENDER
2010
Sun Mon Tue Wed Thu Fri Sat 1 2 3
4
Jason Miller – BCER
PHASE 4 5
BCER acceptance letter
6
Mike McGee – Fire Dept.
7
Martin – TOV
Leonard – Public works
Warrin - Planning
8 9 10
Jason Miller – BCER
PHASE 7 11
BCER acceptance letter 12
Mike McGee – Fire Dept. 13
Martin – TOV
Leonard – Public works
Warrin - Planning 14
15 16 17 18 19 20 21 22 23 24 25
Jason Miller – BCER
PHASE 9 26
BCER acceptance letter 27
Mike McGee – Fire Dept. 28
Martin – TOV
Leonard – Public works
Warrin - Planning 29 30 31
May
2010
Sun Mon Tue Wed Thu Fri Sat 1 2 3 4 5 6 7 8 9
Jason Miller – BCER
PHASE 10 10
BCER acceptance letter 11
Mike McGee – Fire Dept. 12 13 14
Martin – TOV
Leonard – Public works
Warrin - Planning 15 16 17 18 19 20 21 22
Jason Miller – BCER
PHASE 5 23
BCER acceptance letter 24
Mike McGee – Fire Dept. 25
Martin – TOV
Leonard – Public works
Warrin - Planning 26 27 28 29 30
June
2010
Sun Mon Tue Wed Thu Fri Sat 1 2 3 4 5 6 7 8 9 10 11 12 13 14
15 16 17 18 19 20
Jason Miller – BCER
PHASE 11 & 12 21
BCER acceptance letter 22
Mike McGee – Fire Dept 23
Martin – TOV
Leonard – Public works
Warrin - Planning 24 25 26 27 28 29 30 31