>>> Mike McGee 03/26/2009 5:09 PM >>>
Vail Fire & Emergency Services has reviewed the plans submitted for the above project. Findings and comments are as follows:
Life Safety sheet LS - LC plan notes include “options” related to CO2 ventilation and fuel storage. The applicant must select the desired option and submit plans accordingly.
VT01 - VT05 do not indicate ventilation elements for pressurization, graphics, control sequencing or alarm and detection. Recommend developing an “elevator package” that includes the
foregoing.
A5 Vertical Circulation - Plans must be coordinated with smoke control system. The FPE should place a Review Stamp on these sheets. A separate smoke control “package” is required but
it is reasonable they review the A5 plans to avoid potential conflict.