HomeMy WebLinkAboutB10-0320H �'
�
HEPWORTH-PAWLAK GEOTECHNICAL
^ � �
�v
�
7
CONSTRUCTION ACTIVITY REPORT
Client: Frank Taplin Job No.: 110 044A
1505 Rising Glen Road
West Hollywood, California 90069
Project: Taplin Residence, 915 Forest Road, Vail, Colorado
Weather: Clear, calm, dry
5620 County Road 154
Glenwood Springs, CO 81601
Phone: 970-945-7988
Fax:870-945-8454
hpgeo@hpgeotech.com
Day: Tuesday
Date: 10/19/10
Page: 9 of 1
Temperature: 45°F at 8:20 am
Contractor's Construction Activities: B&Y Drilling was preparing to apply "flash" coat betwesn
ground nails #38 and #40, and #44 and #58 (see attachec! nail
layout for numbering) at proposed permanent ground nail wall.
Equipment in Use:
None
HP Gaotech's Site Activities: Observed reinforcing steei for second rvw, west wing wall and
third row of ground nails at proposed permanent ground nail
wall.
Verbal Communication:
Excavation for the second row, west wing wall and third row of
nails, and erection of reinforcing steel had been performed
prior to our arrival to the site, but ground nails had not been
installed. Nails #38 through #40 were observed to slight[y
descend in etevation with the existi�g ground slope. The soils
exposed along the cut face consisted of natural granular soils
on the east half and weathered to competent bedrock on the
west half. We understand that a thin "flash" coat of shotcrete
will be applied to the cut face prior to instalting the ground
nails in order to prevent ravelling of the cut face.
Reinforcing steel observed between nails #38 and #40, and #44
and #58 appeared to be in substantial conformance with the
details shown on Sheet 6 of 6 of the design drawings.
Nails #41 through #43 are located in the area of the rough
graded access ramp into the site and could not be prepared for
na91 installation.
We informed Terry Bond with Beck Building Company of our
observations.
disfribution:
Beck Building Company — Attn: Terry Bond {terry@beckbui(ds.com)
Trevor L. Knelf, P.E.
Fie1d Technician
8230--- lnsideComer� --'----�-----^—�--8230
Outside Comer---, _ . _ .
8220 -------
�
1
w • •
°— 8210 --- 21 �
.W
� 41
111
8200 -------
8190---------
��Yeh and Associates, Inc.
Consulting Geo[echnical Fngineers
t 70 Mei Ray Road Glenwaod Sprinr�s, CO 8160 S
Phonr: (970) 384-1500 Fax: (970) 384-1501
----------8220
B 17 18 79 20 m
1 • • � • �
� 37 � � � —8210 °
r— s— — �
� 56 57 Q m
� • • �j,j
-----------82��
-------------------- 8190
NAIL LENGTH SCHEDULE
• 20 feet
u�;�,ne�c r.:
B&cl' Drillinpd 16c.
Roj�ci Numha:
ziaiss
uner EY RDJ U°�c: p+„jca.
n�� � SeptembeC 23. 2010
RDJ
SCALE� HORIZ�NTAL 1' = 10'
VQRTICAL 1' = LO'
Elevation View
Shxl Nun�:
Tsplin Rcddeocc q oC6
H�
�
HEPWORTH-PAWLAK GEOTECH�lICAL
CONSTRUCTION ACTIVITY REP�RT
Client: Frank Taplin Job No.: 110 044A
1505 Rising Glen Road
West Hollywood, California 90069
Project: Taplin Residence, 'i15 Forest Road, Vail, Colorado
5020 County Road 954
Glenwood Springs, CO 81fi01
Phone: 970-945-7988
Fax: 970-945-8454
hpgeo@hpgeotech.com
Day: Wednesday
Date: 9/29/10
Page: 1 of 1
Weather: Clear, calm, dry Temperature: 54°F at 8:10 am
Contractor's Constructian Activities: Idle
Equipment in Use:
None
HP Geotech's Site Activities: Observed reinforcing stee{ for first row of ground nails at
proposed permanent graund nail wall, building Grid Lines 6, 7
and E. The wall was designed by Yeh and Associates, Inc. and
design drawings (Yeh and Associates, Project Number 210-158,
dated September 23, 2010) were provided by Beck Building
Company for aur use. The wal! will be contructed by B&Y
Drilling, Inc. The wall is proposed to have a maximum he[ght of
15 feet. Atotal of 58 nails are proposed to be instafled in 3 rows
of 20, 20 and 18, top to bottom, respectively.
Excavation for the first raw of nails and erection of reinforcing
steel had been performed prior to our arrival to the siie, bu#
ground nails had not been instalfecl. The west wing wall portion
was not excavated. The soils exposed along the cut face
consisted of existing fill and natural granular soils. Existing
faotings were observed in the area of nails #9 and #10 (see
attached nail layout for numberirtg). Nails #1 through #4 are
located in the area of the rough graded access ramp into the
siie and were not prepared for nail installation. Nail #18 will be
installed with west wing wafl naifs #19 and #20 at a later date.
We understand that a thin "flash" coat of shotcrete will be
applied to the cut face prior to installing the ground nails in
order to prevent ravelling of the cut face.
Reinforcement steel observed between nails #5 and #17
appeared to be in substantial conformance with the details
shown on Sheet 6 of 6 of ihe design drawings wiih the
following exceptions noted below.
1. Wefcled wire fabric was partia(ly erected around the existing
foo#ings which protruded out from the excavated face and
rebar was not observed at nails #9 and #10.
2. Vertical bars consisted af IVo. 4 rebar spaced at
approximately 4 1/2" o.c. The grade of the rebar is not known.
cont...
3. Horizontal walers consisted of No. 4 rebar spaced at
approximately 4 912" o.c. The grade of the rebar is not known.
No splice overlap was specifed on the design drawings, but
typically measured between 27 and 29 inches in length.
Verbal Communication: We informed Terry Bond with Beck Building Company of our
observations and deviations from the design drawings noted
above.
Ttte ground nail wall engineer of recorc! {Richard Johnson with
Yeh and Associates} accepted the rebar spacing as
constructed verbally in a telephone conversation conducted in
the job trailer while on-site. The engineer also verified #hat the
"f[ash" coat application was a typical construction technique
and was acceptable at this site. The engineer was not aware of
the rebar size discrepancy and stated that he woutd investigate
the matter.
Mr. Bond informed us the earthwork contractor would be on-
site later in the day to sawcut the protruding footing and B&Y
wouid complete steel reinforcement erection the following day.
He also requested a follow-up site visit to observe the
completed work.
distribution:
Beck Building Company—Attn: Terry 8ond (terry@beckbuilds.com)
Trevor L. Knell, P.E.
Field Technician
8230----- ------------------ 8230
lnside Comer�
Outside Comer�
8220 — — —
m
a�
"
° 8210 — — —
�
>
m
w
8200 ---
— — — 8220
a�
�'
c
— — — 8210 °
m
>
m
w
---------------------------s2ao
8190----------------------------�---- 8190
NAIL LENGTH SCFiEDULE
� 20 feet
��Yeh and Associates, Inc.
Consulting Geotechnical Engineus
170 Mel Ray Road Glenwood Springs, CO 81601
Phonr: (970) 384-]500 Fax: (970) 3841501
Dcsi�ml kr
BfiY Dr1ll[n�, Inc.
Pmjca Nudcr:
ziaise
[kawr �+Y RDd n'�c Pndca:
C�� �� J Septcmbv 23, 2050
SCALE� HCIRIZONTAL 1' = 10'
VERTICAL 1' = 10'
Elevation View
Shccl Numbm.
T¢pUn Realdenee 4 of 6
H�
�
HEPWORTH-PAWL.AK GEOTECHIVECAL
CONSTRUCTION ACTIVITY REPORT
5020 County Road 154
Glenwood Springs, CO 81601
Phone: 970-945-7988
Fax: 970-945-8454
hpgeo@hpgeotech.com
Client: Frank Taplin Job No.: 1'10 044A Day: Friday
1505 Rising Glen Road Date: 10/1110
West Hollywood, California 90069 Page: 1 of 1
Project: Taplin Residence, 115 Forest Road, Vail, Colorado
Weather: Clear, calm, dry Temperature: 45°F at 8:30 am
Contractor's Construction Activities: B&Y Dril(ing was preparing to apply "flash" coat between
ground nails #5 and #17 (see attached nail fayout for
numbering) at proposed lower levef, permanent ground nail
wali.
Equipment in Use:
None
HP Geotech's Site Activities: Observed completed reinforcing steel erection at first row of
ground nails as a foflow-up to aur 9129110 site visit. Reinforcing
steel observed between ground nails #5 and #17 appeared to
be in subs#antial conformance with the details shown on Sheet
6 of 6 of the design drawings.
Rebar sizing had been corrected from No. 4 to No. 5 since our
9/29/10 site visit.
Application of the "flash" coat wifl be per#ormed later today.
Verbal Communication: We informed Terry Bond with Beck Building Company of our
observations.
distribution:
Beck Building Company—Attn: Terry Bond {terry@beckbuilds.com)
Trevor L. Knell, P.E.
Field Technician
8230------�—
Incir�n('n.ne ` --�--"--�------
8220 — — — —
,-.
�i '
� �
c
� 8210 — — —
>
a�
W
— — — 8230
— — — 8220
m
m
c
----8210 °
m
>
m
`w
6200 ----------------------------------8200
8990---------------
��Yeh and Associates, Tnc.
Cqnsulting Geotcchnical Engineers
170 Mel Ray Road Glenwood Springs, CO 81601
Phonr: (970) 384I500 Fax: (970) 384-I501
, . _ � m : -n t�°�,. , -��: .��,.... � . _ w. �
------------------ 8190
NAIL LENGTH SCHEDULE
• 20 feet
SGALE: HORIZONTAL 1' _ (0'
VERTICAL L' = LO'
n�a r,�:
ss�v nr�iu.�, �o�
►,�,�N�„�,� Blevation View
ziaisa
IklNTIy;
R� �a �O�' ShceLNun6a:
n,�� M, Sepiember 23, 2010 Tapli� Rpldence 4� 6
RDJ
��
�
HEPWORTH-PAWLAK GEOTECHNICAL
CONSTRUCTION ACTIVITY REPQRT
Client: Frank Taplin Job No.: 110 044A
1505 Rising Glen Road
West Hollywood, California 90069
Project Taplin Residence, 115 Forest Road, Vail, Colorado
5020 County Road 154
Glenwood Springs, CO 81641
Phon e: 970-945-7988
Faz: 970-945-8454
hpgeo@hpgeotech.com
Day: Tuesday
Date: 't 0/5110
Page: 1 of 1
Weather: Clear, calm, dry Temperature: 68°F at 91:OQ am
Contractor's Construction Activities: B&Y Drilling installed ground nails #7 through #17 and a test
nail (see attached nail layout for numbering).
Equipment in Use:
BD 700E air-track drill rig, grout plan#, air compressor
HP Geotech's Site Activities: �bserved installation of ground naifs #7 through #17 and a test
nail between nails #12 and #13. Grout tubes were attached to
the bars with duct tape. Grout consisted of Quikrete Type IIII
pfaced in drill holes after inserting prepared bars. Nails were
installed in substantial accordance with the design drawings
(Yeh & Associates, dated 9/23/90), provided.
Verbal Communication:
We informed Terry Bond with Beck Building Company of our
observations.
distribution:
Beck Suitding Company—Attn: Terry Bored {terry@beckbuilds.com}
Louis Eller, SET
Field Technician
8230-----�--
Inside Camer� — � — �
Outside Comer�
8220 —
.:
a�
w
c
� 82�d —
m
>
a�
w
—,.—,�^�------ 8230
��-�� n,-�c.,�
8200 — — — �— — —
8190------,.
— — � — — — — — 8220
s n ts is zo �
1 • � • • �
c
�' s~ ---82i0 °
m
>
� • • °'
w
------------------------8200
---------------------- 8190
NAIL LENGTH SCHEDULE
• 20 feet
��Yeh and Associates Inc
Consulting Geotechnical Engineers
170 Mel Ray Road Glenwood Springs, CO 8i601
Phone: (970) 3841500 Fax: (970) 384-1501
SCALE: HORIZONTAL 1' = 10'
VERTICAL 1' = k0'
n�� r.�
BdcY Drllliag, Iue.
P�;«�N�«: Elevation View
:ioasa
o�,.,� nY
RDJ �0' Projcce SnxvNumbv:
����,. Sepiember23,2(110 T�plioAesidcnce 1of6
RDJ
H�
�
HEPWORTH-PAWLAK GEOTECHNICAL
CONSTRUCTION ACTIVITY REPORT
5020 County Road 954
Glsnwood Springs, CO 81601
Phone: 970-945-7988
Fax: 970-945-8454
hpgeo@hpgeotech.com
Client; Frank Taplin Job No.: 110 044A Day: Friday
1505 Rising Glen Road Date: 10/8/10
West Hollywood, California 90069 Page: 1 of 1
Pr4ject: iapfin Resictence, 915 Forest Road, Vail, Colorado
Weather: Clear, calm, dry Temperature: 65°F at '12:30 pm
Contractor's Construction Activities: B&Y Drilling was preparing to apply "flash" coat between
ground nails #18 and #20, and #26 and #37 (see attached naif
layout for numbering) at proposed permanent ground nail wall.
Equipment in Use:
None
HP Geotech's Sife Activities: Observed reinforcing steel for first row, west wing waf! and
second row of ground nails at proposed permanent ground nail
wall.
Verbal Communication:
Excavation for the first row, west wing wall and second row of
nails and ereciion of reinforcing steel had been performed prior
to our arrival to the site, but ground nails had not been
installed. Nails #18 through #20 were observed to descend in
elevation with the existing ground slope. The soils exposed
along the cut face consisted mainly of natural granular soils
with weathered bedrock near the bottom of the cut face at the
west side. We understand that a thin "flash" coat of shotcrete
will be applied to the cut face prior to installing the ground
naifs in order to prevent raveUing of the cut face.
Reinfqrcing steel observed between nails #'(8 and #20, and #2fi
and #37 appeared to be in substantial conformance with #he
details shown on Sheet 6 of 6 of the design drawings.
Nails #21 through #25 are located in the area of the rough
graded access ramp into the site and could not be prepared for
nai) installation.
Nails #38 through #40 will be instafled with the third row of
nails.
We informed Terry Bond (via telephone) with Beck Building
Company of our observations.
distribution:
8eck Bui[ding Company — Attn: 7erry Bond {terry@beckbuilds.com)
Trevor L. Knell, P.E.
8230---------------
InsideComer --�"--`---------- 8230
Outside Corner� �
e+an n..��.,�
8220 ----------
� I 3 4
v • • • • •
21 y� � �
� sz�o ---- —72 � � 25
>
�
�
w . . . .
8200 ----------
�------8220
17 18 19 ?A �
• • � • Q�
� �'° �—`$2�a �
�
>
• � °'
w
—`----8200
8190 ----------------
��Yeh and Associates, Inc.
Consulting Geotechnical Engineers
170 tr1el Ray Road Glenwood Springs, CO 81601
Phonr: (970) 384-1500 Fax: (970) 384-1501
,
Na � r�.,�_m � ��°+,�w�^;,,,,�_-_ °�, � ��.w . w,._
------------- 8190
NAIL LENGTH SCHEDULE
• 20 feef
SCALE� HOR[ZONTAL L' = LO'
VERT[CAL 1' _ !0'
Dai�ywl Pcr.
B&Y DAIIIp�, Inc.
�*+�•: Elevation View
ziaisa
w..m hy: RDd uaie:
r`°�oc'r sn�MN�n,e�r.
�� �,. Sepiember 23, 2010 T�plin Ruidmtt 4 of 6
RDJ
� �
�
HEPWORTH-PAWLAK GEOTECHNICAL
CONSTRUCTlON ACTIVITY REPORT
Client: Frank Taplin
1505 Rising Glen Road
West Hoilywoad, California 90069
5020 County Road 154
Gfenwood Springs, CO 81601
Phone: 970-945-7988
Fax: 870-845-8454
hpgeo@hpgeotech.com
Job No.: 110 Q44A Day: Monday
Date: 10191l10
Page: 1 of 9
Project: Taplin Residence, 115 Forest Road, Vail, Colorado
Weather: Clear, calm, dry Temperature: 58°F at 11:00 am
Contractor's Construction Activities
Equipmenf in Use:
B&Y Drilling insialled ground nails #5, #6, #18 through #20 and
#26 through #37 (see attached nail layout for numbering).
BD 700E air-irack drill rig, grout plant, air compressor
HP Geotech's Site Activities: Observed installation of ground nails #5, #6, #18 through #20
and #26 through #37. Grout tubes were attached to the bars
with duct Eape. Grout consisted of Quikrete Type I/fl placed in
drill holes after inserting prepared bars. A bar was not be
placed at nail #27 because of contact with nail #26. Naifs were
installed in substantial accordance with the design drawings
(Yeh 8, Associates, dated 9/23/1Q), provided.
Verbal Communication: None
distribution:
BecEc 8utlding Company — Attn: Terry 8ond (terry@beckbuilds.comj
Louis Eller, SE7
Field Technician
$230------
[nside Comer � ' — — — —' — ' — ' � — — — 8230
Outside Comer
Strip Drains
8220 ---------- --
-------- --------8220
w
� � 3 9 11 12 13 14 15 18 17 18 19 20 �
v • � • • � � � • � � � ♦ � • • ♦ • • • �
� $2 � d--� -- 21 � 23 24 � 26 27 a 29❑ ❑90 31 32 33 3q � �7 3g � C
�p � � �� � �__82�� �
N 41 42 43 � 45 46 7 48 99 O 51 52 53 � O O y7 O �
w ' • • • • • � • • • . • • • • • • w
8200 ---------------------------
------8200
8190 ------------------
---------------8990
NAIL LENGTH SCHEDULE
• 20 feet
��Yeh and Associates. Inc.
Consut[ing Geotcchnical Fngineers
170 Mel Ray Road Glenwood Springs, CO 81601
Phane: (970) 384-] S00 Fax: (970) 3841501
SCALE� HORIZONTAL 1' = LO'
VERTICAL I' = Lp'
:CCl�CV1SIOII Deaq;m+IF�r.
k..;,;,.�,� �ad6r B&Y Drilling, Ioc.
ProjcctNumlrcr. Elevation View
ziaiss
�� � RDJ � Projon:
Shat N�h�r,
�y�� � Scptember 23.2010 Taplin Ro+�Mcrrce 4 of 6
RD.t
NOTE: THIS PERMIT MUST BE POSTED ON JOBSITE AT ALL TIMES
.�
�ow�o�vn� '
Town of Vail, Community Development, 75 South Frontage Road, Vail, Colorado 81657
p. 970.479.2139, f. 970.479.2452, inpsections 970.479.2149
ADD/ALT SFR BUILD PERMIT Permit #: B10-0320
Job Address: 115 FOREST RD VAIL
Location......: 115 FOREST ROAD
Parcei No....: 210107113030
OWNER 115 COMPANY 09/24/2010
4960 S LAFAYETfE LN
ENGLEWOOD
CO 80113
APPLICANT BECK BUILDING COMPANY
P.O. BOX 4030
VAIL
CO 81658
License: 117-A
CONTRACTOR BECK BUILDING COMPANY
P.O. BOX 4030
VAIL
CO 81658
License: 117-A
09/24/2010 Phone:970-949-1800
09/24/2010 Phone:970-949-1800
Description:
GRADING PERMIT AND SHOTCRETE WALL FOR NEW SINGLE FAMILY
RESIDENCE
Occupancy: R3 Single Family Residence
Type Construction:VB
Project #:
Valuation:
Total Sq Ft Added:
Status . . :
Applied . . :
Issued . .. :
Expires . ..:
PRJ10-0195
ISSUED
09/24/2010
10/01/2010
03/30/2011
$54, 000.00
0
..............«....�..,..........,......._.._.......,...,,......,.,.....,....._.= FEE SUMMARY ......_,_,,.,,.,....,...,,.............._,,..,..,...,.......................__..
Building Permit Fee-----> $671.75 Will Cal Fee---------------------> $4.00 Total Calculated Fees-----------> $1,992.39
Plan Check-----------------> $436.64 Use Tax Fee--------------------> $880.00 Additional Fees---------------------> $0.00
Add'I Plan Check Hours-> $0.00 Restuarant Plan Review----> $0.00 TOTAL PERMIT FEES-----------> a1,992.39
Investigation-----------------> $0.00 Recreation Fee----------------> $0.00
Payments-------------------------> a1,992.39
Total Calculated Fees--------> $1,992.39 BALANCE DUE------------------------> �0.00
............................... ..._.,.......,,..........,,,..............,,.,.,...,....»,,.,,......,................,.,..........,....,........_•___......,,...........,,..............,.
DECLARATIONS
I hereby acknowledge that I have read this application, filled out in full the information required, completed an accurate plot plan, and state that all the information
as required is correct. I agree to comply with the information and plot plan, to comply with all Town ordinances and state laws, and to build this structure
according to the towns zoning and subdivision codes, design review approved, International Building and Residential Codes and other ordinances of the Town
applicable thereto.
REQUESTS FOR INSPECTION SHALL BE MADE TWENTY-FOUR HOURS IN ADVANCE BY TELEPHONE AT 970.479.2149 OR AT OUR OFFICE FROM
8:00 AM - 4:00 PM.
d�Uc (3UIl.DtN(�
� 2� /�•/•(O
. Signat wner or Contractor Date
%t/Z�vr C . 130 ��
Print Name
b Id_a It_construction_pe rm it_041908
wk#fXwfY�4i��RRR��fffwwftwY%4/�fRx���ffwfYYf�#ZI+�**���RffNNMwffwYftlf��41f4�ff4t�f�ifkRxtkfNRkwww#�fx#f*f4444ffxxxNwfwfwwf��f4k�l�444x�xfxxx�fwfRfYfwlflf�ififf�fRf�flRfffx���fffffk
APPROVALS
Permit #: 610-0320 as of 10-01-2010 Status: ISSUED
4tYefY`iF�kf4*+tlk4i4**fRf'f'1ttYYi1'*ki#fRtrff`f'ff'itfifffYrtTY'k'4*#t#444ff4f'fV�trhf V1frtfA'fhfff#4WLi/l*4fefR�}fRYrRR4ffA'ttikY(fdlf#«f#4f'4f##f' V rtA'iRrt4rt'k�k'k4ift4f#�/Y':!#}lfff'ARfrfififitYrtffYetY`ffii4lf#4:t44lt4l41rw
Item: 05100 BUILDING DEPARTMENT
09/24/2010 Martin Action: CR 1. Include plans
for the shotcrete wall signed by the engineer of record
2. Provide the soils report for the proposed work.
3. All sheets to be sealed by the registrant.
4. Include the valuation of the prosed work on the permit
application
5. Show location of erosion control and method to be
used, ie silt fencing.
10/01/2010 Martin Action: AP
Item: 05400 PLANNING DEPARTMENT
09/29/2010 bgibson Action: AP plans routed to A-1
Item: 05500 PUBLIC WORKS
09/29/2010 csalli Action: PA approval for
grading/shotcrete wall submittal.
V ttrtM�RertffrtrtflYlYY`rtrtY`ii(44ttR}*441r41r�fM�4trYr1fr1t4V f�k4M�A'i`#i`4�l�fifRR#}}#wftr4lrtrith}rRfrlrinFtrNtrwYlfifrMIItY`Y1nFirtil`4iiffr4#*f}f+txftr��rt#fRR/RfrtA'�FrtYefY`�k4#il+1r+�MLf4itL4�t�4R41rt�+�Vtrf`�fifxlrfilr}f'f'ffffRfrMtrfYff
See the Conditions section of this Document for any that may apply.
bld_alt_construction_perm it_041908
•4RRfRf��t}xtttkwfwfl#tff4***#f}}fk�4fYrtt�wili4iii44}}xRli�fNNfwwfftY*�wxf�f##*4�i#i�##}44��fti�ktw;kfwwfMwf�tff44iRfi#++i}ffw}leRklwetwrtwwwwwwMYkMf�����4Riti+i#f*iffiii�f*!i#�if��f
CONDITIONS OF APPROVAL
Permit #: 610-0320 as of 10-01-2010 Status: ISSUED
�fflr�lrRR�fRRfYYNRY'iYYYYf�F#i!il4klff'frtefAlffriRiRAfY.'kf#*#*444AA�ltr4RRRiRRV VfefYrkiFfYrfA'�k�klt4f*1`*lrfr#i}441r#*4RffrRRV}rkfY'RYrY`rt'4fr###'Rf**#44f1r41rdfdlrR#iRfrt}r*iRftHiFfYikltrfrR'k#'M#tYrifRw'A44fr1ff`##*!!4lrf'ftRR
Cond: 12
(BLDG.): FIELD INSPECTIONS ARE REQUIRED TO CHECK FOR CODE
COMPLIANCE.
Cond: 44
(BLDG 2009): (SFR) SMOKE DETECTORS ARE REQUIRED PER SECTION
R314 OF THE 2009 IRC, IF APPLICABLE UNLESS A MONITORED FIRE
ALARM SYSTEM IS REQUIRED.
Cond: 42
(BLDG 2009) CARBON MONOXIDE DETECTORS REQUIRED TO BE
INSTALLED PER 2009 IRC R315
Cond: CON0011645
SPECIAL INPECTION AGREEMNET TO BE REVISED TO INCLUDE SOIL
NAILING AND SHOTCRETE WALL. SPECIAL INSPECTION REQUIRED ON
THESEITEMS
bld_a It_constru ctio n_perm it_041908
************************************r****�**************************************************
TOWN OF VAIL, COLORADOCopy Reprinted on 10-01-2010 at 13:34:39 ]0/O1/2010
Statement
*********+*****+****************+++******.*************�*************************.**********
Statement Number: R100001459 Amount: $1,992.39 10/O1/201001:34 PM
Payment Method: Check Init: LC
Notation: ck # 18992
-----------------------------------------------------------------------------
Permit No: B10-0320 Type: ADD/ALT SFR BUILD PERMIT
Parcel No: 2101-071-1303-0
Site Address: 115 FOREST RD VAIL
Location: 115 FOREST ROAD
Total Fees: $1,992.39
This Payment: $1,992.39 Total ALL Pmts: $1,992.39
Balance: $0.00
***+*�**�********************+**************************************************************
ACCOUNT ITEM LIST:
Account Code Description Current Pmts
-------------------- ------------------------------ ------------
BP 00100003111100 BUILDING PERMIT FEES 671.75
PF 00100003112300 PLAN CHECK FEES 436.64
UT 11000003106000 USE TAX 4% 880.00
WC 00100003112800 WILL CALL INSPECTION FEE 4.00
-----------------------------------------------------------------------------
BUILDING PERMIT APPLICATION
Separate permits are required for electrical, plumbing, mechanical, fireplace, etc.
Project Street Address:
R I S _ �oR�3r �A�
(Number) (Street) (Suite #)
Building/Complex Name:
Contractor Information:
Company: 'g � (3Nt�,DtN G GMPaNr
Company Address: p. O. QO�C �030
City: V A1 � State: � Zip: a�s� 8
Contact Name:
Contact Phone: ( y%8 • i7�j
E-Mail �E�Y � $E�.�C iUI L{�,i' • GpM ,
Town of Vail Contractor Registration No.:
. .i:S�..
Contractor i ature (required) �
Property Information
Parcel #: /ZI O�- 0 7�— �3 -' 0.30
(For parcel #, contact Eagle County Assessors Office at 970-328-8640 or
visit www.eaglecounty.us/patie)
Tenant Name: 8 t� ZZ. TR•P�,(/J
owner Name: �,15 con� PRNY
Valuations (Labor & Materials)
Building:
Plumbing:
Electrical:
Mechanical: (including fireplace)
Total:
� ��% ODO .
$
$
$ SY o� • �-
Office Use: /� C ,�
Project #: %�� � � " � J ( T �
DRB #:
�
Building Permit
Lot #: Block Subdivision: •
�
r�
�
�
Detailed Scope and Location of Work:
C?R�F.Driv 6 �L�R.+Mi � �6 f�i oTc/�7�
��(%'u► .
��+�f �ool�c�rrio� �in. Ne.� �o�r� ix m -r
(use adddiona s eet if necessary) �����y �
.
Work Class:
New (� Addition ( ) Remodel ( ) Repair ( ) Other ( )
Work Type
Interior ( ) Exterior (�(j Both ( )
Type of Building:
Single-Family �} Duplex ( ) Multi-Family ( )
Commercial ( ) Other (
Does a Fire Alarm Exist? Yes (}(� No () ;�
Monitored Alarm? Yes (x) No () �� u �
�
Does a Sprinkler System Exist? Yes (� No () ;
;#& Type of Existing Fireplaces: Gas Appliances
� Gas Log Wood/Pellet Wood Burning
'#& Type of Proposed Fireplaces: Gas Appliances
' Gas Log Wood/Pellet Wood Burning _
_ _ __ _ __
Date Received:
15-May-10
- i
�
�
�ow�roFV� �
Job Name:
Job Address:
Permit No.:
SPECIAL INSPECTION AND TESTING AGREEMENT
(To applicants of proJects requlring Special Inspection or Testing per Section 1701 of the IBC)
The owner or his/her representative, on the advice of the design p�ofessional in responsible charge, shall
complete, seal, sign and submit a oopy of the 5pecial Inspection Agreement and Structural Tests
Scheduled to the Town of Vail for review and approval. Signatures are required on both pages;
photocopied or faxed signatures are acceptable.
The owner and his/her general contractor, where applicable, shali also adcnowledge the following
conditions applicable to Special Inspection Testing:
1. Contractor is responsible for proper notification to the Inspection or Testing agency for items
listed.(Page 1) (IBC 1704)
2. Only the testing laboratory should take samples and transport them to their laboratory.
3. Copies of all laboratory reports and inspections are to be sent directly to the Town of Vail by the Testing
agency on a weekly basis.
4. Inspection agency to submit names and qualifications of on-site special inspectors to the Town of Vail
for review and approval.( Page 2)
5. The special inspector is responsible to immediately notify the Town of Vail Building O�cial in writing of
any concems and/or problems encountered.
6. �t is the responsibility of the contractor to review the Town of Vail approved plans for additional
inspection or testing requirements that may be noted. A pre-construction conference at the job site is
rec;ommended to review special inspection procedures.
7. The special inspector shall use only the Town of Vail approved drawings.
8- All special inspection field reports must be left on site for review by the Town of Vail staff prior to
required inspections or re-inspections.
BEFORE OCCUPANCY WILL BE GRANTED: The special inspection agency shall submit a signed and
sealed statement that all items requiring testing and inspection were fulfilled and reported. Those items not
tested and/or inspected shall be noted in this statement. A copy of the statement shall be maintained at the
job site for the Building Inspector's review prior to final inspection.
Acknowledgement:
Owner:
Signature Print Name Date
Speaallnspec�ion-� N-7 GEdTE
Agency: `E---J-,^,�� . �- TREVOR 1,�44�� 4 �
Signature Print Name ��
Project
Arch/Eng:
�Signature Print Name Date
Contractor: r, � Qp,�,�
9'.10 •/o
' nature Print Name Date
�FCk f3ui ca+N4 � .
-3-
. • • .
�
�
�owxo�v� .
SPECIAL INSPECTION AND TESTING SCHEDULE
(IBC 1704)
Project Name: PeRnit #
Owner's Name:
Testing Inspection s�y�amre �� —
�� '� GEo�N ►�
Agency: c �'�.-� � �12.EVOp. �- • I�t�1Eid�
Testing Inspection Signature p� N�e
ate
Hereby certifies that the Testing/lnspection Agency named above has been engaged to perform structural tests and
inspections during construction as checked bebw, to satisfy all applicable portions of the Building Code.
Prior to final inspection, the Inspection Agency shall submit a statement that all items of designated work pertormed
were reported. Any items checked but not tested or inspected will be noted and explained. Whenever any designated
items on the list are ready for sampling, testing, or inspection, it shall be the responsibility of the contractor to give
timely notioe to the Inspection agency so that the required services may be pertortned.
REINFORCING STEEL:
Tensile & Bend, one set per heat per tons
� Inspection of Placement
Inspection of Welding
Epoxy
MASONRY:
Prefim• AccePtance Tests (Masonry Units, Wall Prisms)
Subsequent Tests (Mortar, Grout, Field Wall Prisms)
Inspection of Placement and Grouting
Reinforoing Tests
Inspection of Reinforcing Piacement
Tendon Tests
Inspection of Tendon Placement
Inspection of Concrete Placement
Inspectian of Concrete Batching
Inspection of Panel Attachment 8 Inserts
Compression Tests
Inspection of StressingJTransfer
PILING, CAISSONS, CAPS, TIES:
inspection of Reinforcing Placement
Inspection of Concrete Placement
InspecUon of Concrete Batching
Specify other tests, inspections or specia/ instructions nequired.
�
UNDERPINNiNG:
Temporary/permanent
Inspedion of Steel Fabricafion
InspecUon oi Reinforcing 8, Forms
Inspection of Concrete Placement
Inspection of Tiebacks
SOIL NAILS:
Temporary Shoring
Permanent Watl
STRUCTURAL STEEL:
Sample 8 Test (list spec�c members below)
Shop Identificabon & Welding Inspection
Shop Ultrasonic Inspection
Shop Radiography
Field Welding Inspection
Field Bofting InspecGon
Field Ult�asonic Inspection
Field Radiography
Meta� �edc Welding Inspecdon
FIREPROOFING:
Inspection 8 Placement
SOIL3:
�_ Acceptance Tests
�_ Moisture-Density Determinadon
�_ Field Density
Drilied Piers
Deep Fou�datlon
STRUCTURAL WOOD:
tnspection of Fabrication
Inspectfon of Truss Jant Fabrication
Sample & Test Components
inspection of Glu Lam Fabrication
SMOKE CONTROL:
SPECIAL CASES:
SPECIAL INSPECTION:
Seismic Resistance
Wind Requirements
B
& DRILLING, INC.
Y
PROPOSAL (REV2)
September 17, 2010
PO Box 1878
Rifle, Colorado 81650
Phone (970) 625-2608
Fax(970)625-1502
SUBMITTED TO:
Beck Building Company
C/O Matt Hill
PO Box 4030
Vail, CO 81658
(970) 949-1800 Office
(970) 949-4335 Fax
email: matt ,beckbuilds com
email: robvn(a�beckbuilds com
JOB NAME & ADDRESS:
Taplin Residence, 115 Forest Road; Vail, CO
We hereby propose the installation of:
-1,400 SF of Permanent Soil Nail Shotcrete wall with a max working height of 16'
�
Unit Unit of
Item Price Measure QuantiTy Costs
(15 dav construction durationl
PSNW $34.37
w/ Max working height of 16'
Design
Testing
Mobilization
Total
$2,200.00
$2,200.00
$1,500.00
SF
LS
LS
LS
1,400
$48,118.00
$2,200.00
$2,200.00
$1,500.00
$54,018.00
• The above work to be completed in a substantial and workmanlike manner at the
provided unit cost pricing.
• This proposal must be accepted as provided and delivered to B& Y Drilling, Inc.,
30 days from above date, or it shall expire. Pricing is valid for 30 days after the
acceptance date of this proposal. After the 30 day period is breached B&Y will
be allowed to update it's material pricing.
• B& Y Drilling, Inc. is not responsible for costs associated with drilling into ANY
utilities. Locating andlor removal of all nearby utilities to be completed by others
prior to startup of drilling operation.
• Wall layout, alignment, survey, property limit locations, and necessary easements
conducive to the work to be provided by Prime Contractor.
• Work is assumed to progress as one continuous operation. Down time not due to
B& Y Inc. will be billed at hourly rates.
• Prime Contractor is to provide all necessary permits and bonds pertaining to the
work being conducted.
• Equipment for loading, unloading, and placement of materials from the stockpile
area to the immediate work area to be provided by others at no cost or backcharge
to B& Y Drilling, Inc.
• Concrete washout and trash disposal area to be provided by others.
H P
tE:�
HEPVVORTH-P.AWLAK GEOTECHNICaL
September 24, 2010
Frank Taplin
I505 Rising Glen Road
i �, � � �: �; �
_ ', -
,,a � � � ��
i�� � "; �;— — �_
;� . _ �,�� r
, . !: _t ' --, ,
Los Angeles, California 90069
Job No. 110 044A
Subject: Observation of Exploratoiy Pits, Proposed Residence, Lot 30, Block 7,
Vail Village First Filing, 115 Forest Road, Vail, Colorado
Dear Mr. Taplin:
As requested, a representative of Hepworth-Pawlak Geotechnical, Inc. observed
exploratory pits at the subject site on September 14, 2010 to evaluate the soils exposed for
foundation support. The findings of our observations and recommendations for the
foundation design are presented in this report. The services were performed in
accordance with our Proposal for Geotechnicul Services to you, dated March 3, 2010,
Proposal No. 034-10. We previously provided presumptive soil parameters for
foundation design in a report dated March 15, 2010 under the above Job Number.
Proposed Construction: The proposed residence will be a 4 level structure located on
the site in roughly the same location as the existing residence. The lowest (recreation)
level floor elevation will be at 8203'-6" and the upper (garagelauto court) elevation will
be at 8235'-0". Ground floor at the recreation level will be slab-on-grade and the garage
floor will be structural above a combination of crawlspace and basement storage. The
auto court and driveway will consist of structural slabs. We understand that the driveway
will be elevated above the finished ground surface. Spread footings sized for an
allowable soil bearing pressure of 2,500 psf, as recommended in our previous report, will
support the proposed structure. A permanent soil nail wall will be constructed at the
uphill side of the recreation and living levels, along building grid lines 6 and 7.
Subsurface Conditions: At the time of our site visit, the existing residence and
foundation had been removed and an access trail and pad had been rough graded on the
site. Two exploratory pits were excavated in the proposed building footprint. The
subsoils exposed in the south pit (Pit 1) consisted of 7 feet of inedium dense clayey sand
and gravel with rock fiagments up to about 18 inches in size overlying weathered to hard
claystone shale bedrock down to the pit depth of 9 feet, or about elevation 8208 feet
(provided). The subsoils exposed in the west pit (Pit 2) consisted of inediuin dense
clayey sand and gravel down to the bottom pit depth of 11 feet, or about elevation 8 t96
feet (provided). Results of swell-consolidation testing performed on samples of the
matrix soils taken from the pits, shown on Figure l, indicate low to moderate
compressibility under conditions of loading and wetting. The results of a gradation
analysis perforined on a sample of the coarse natural granular soils (minus 3 inch
i , � , , �, . � �
Frank Taplin
September 24, 2010
Page 2
fraction} obtainerl from Pit 1 are presented on Figure 2. No free water was encountered in
the pits and the soils and bedrock were slightly moist to moist.
Recommendations: Considering the conditions exposed in the explaratory pits and the
nature of ihe proposed constniction, spread footings ptaced on the vndis#urbed natural
granular soil designed for an a]lowable soil bearing pressure of2,500 psf should be
adequate for suppart of the proposed foundation. The matrix portion ofthe soils tends io
compress under load and there could be sonae post-cor�struct2on d.i�erential settlement of
the fouttdation, especially between continuous footings and isolated pads (such as for the
elevated driveway), The underlying bedrock is reiatively incompressible and the
magnitude of pote�ntial foundation settlement will depend on the depth of soil below the
footing and the load on the footing. We can eva.luate the settlement potential when
foundation loads have been developed.
Faotings beat'ing entirely on bedrock can be sized for an allowable bearing pressure of
4,000 psf. There could be some differential settlement between footings bearing on the
natural soils and foatings beari,ng on bedrock. Footings should be a minimunn vvidth of 16
inches for continuous walls and 2 feet for columns. All existing fill, topsoil and loose and
distwrbed soils and bedrock fragments in footing areas should be removed and the bearing
1evel extended down to the undisturbed natural soils or bedrock. The bearing soils shouId
be protected against frost and concrete should not be placed on frozen soils. Extezior
footings should be provided with adequate soil cover above their bearing elevations for
frost protection. Continuous foundation walls should be reinforced. top and bottorn to
span local anomalies such as by assuming az� unsupported length of at Ieast 12 feet.
Foundation wa11s acting as retaining structures up to about 12 feet tall should also be
designed to resist a lateral earth pressure based on an equivalent fluid unit weight of at
least 50 pcf for on-site soil as backfill. Cantilevered retaining structures whzch are
separate from the zesidence and can be expected to deflect sufficiently to mobilize the fu11
active earth pressur$ condition should be designed for a lateral earth pressure computed
on ihe basis of an equivalent fluid unit weigl�t of at least 40 pcf for backfill consisting of
the on-site granular soils or 35 pcf for zmpc�rted crushed screened rock. A perimeter
fowndation drain should be provided to pxevent temporazy buildup of hydrostaric pressure
behind the uphill foundation and retaining vva]ls, and soil nail walls, and prevent wetting
of the lower levels. Structural fill placed within floor slab areas can consist of the on--site
predominantly granular soils or suitable imported granular soil (such as road base)
compacted ta at least 95% of standaxd Proctar density (SPD) at a znoisture content near
optimum. Backfill placed around the structure should be compacted to at least 90°/a SPD
and the surface graded to prevent ponding within at least 10 feet ofthe building. The
existing retaining wall at the south (uphill} side of the lot should be underpinned if
excavation for the new foundations will be performeci within an envelope defined as a
line extended down from the edge ofthe footing at I lzorizontai to 1 verticaI. It appears
feasible to underpin the existing retaining wa11 conventionaliy by extending the bearing
level down to an adec�uate elevation or can be done with micropiles.
Job No. 110 044A
Ce'ic�rt�Cf'�
Frank Taplin
September 24, 2010
Page 3
Limitations: The recommendations submitted in this letter are based on our observation
of the soils exposed within the exploratory pit excavations and do not include subsurface
exploration to evaluate the subsurface conditions within the loaded depth of foundation
influence. This study is based on the assumption that soils beneath the footings have
equal or better support than those exposed. The risk of foundation movement may be
greater than indicated in this report because of possible variations in the subsurface
conditions. In order to reveal the nature and extent of variations in the subsurface
conditions below the excavation, drilling would be required, It is possible the data
obtained by subsurface exploration could change the recommendations contained in this
letter. Our services do not include determining the presence, prevention or possibility of
mold or other biological contaminants (MOBC) developing in the future. If the client is
concerned about MOBC, then a professional in this special field of practice should be
consulted.
If you have any questions or need further assistance, please call our office.
Sincerely,
HEPWORTH — PA
Trevor L. Knell, P
Rev. by: DAY
TLK/ksw
�L ICAL, INC.
oQPo�' i:E�/S�F
'�,�..���` `�
:Q
�~ 3846J r:
90 �. Q� 24 -!o .- ��,�
�
FsS�ONAI �N�\�
Attachments Figure 1— Swell-Consolidation Test Results
Figure 2— Gradation Test Results
cc: Beck Building Company — Attn: Terry Bond (terry an,beckbuilds com)
Job No, l 10 044A
G�c�tecn
' , Moisture Content = 13.7 percerrt
' ' Dry Density = 114 pcf
Sample of: Clayey Sand with Gravel
From: Pit 1 at 6 Feet
0
�
z 1 ' : : '
O :
� i No movement
� 2 upon wetting
a :
� ' '
O , �; '
3 '�,
: , ' ' , ,
0.1 1.0 10 100
APPLIED PRESSURE ( ksf )
0
�
v
Z 1
O
�
�
o�[ 2
a
�
O
U 3
0.1
' , Moisture Content = 16.5 percent
, � Dry Density = 111 pcf
� -200 = 26 percent
' Sample of: Clayey Sand
From: Pit 2 at 10 Feet
! No movement '
upon wetting :
1.0 10
APPLIED PRESSURE ( ksf )
�
110 044A I C�jeCj'1 I SWELL-CONSOLIDATION TEST RESULTS ( FIGURE 1
-=PWO�'H �AWLAK G=�?= �iiNi�L
, . � .
- ..
, �..�
- . . �.
,
��
. � ,,
►
� �
P
. . ./�
�� :,
�
, .� , .
�
� �
�, �
:�
.,
�
,.
�
.0�1 .002 .ODS .009 .019 .037 .WI .150 .90p .60p 7.1B 2.36 4.75 9.5125 19.0 37S 782 ��52 ffi3
DIAMETER OF PARTICLES IN MILLIMETERS
CUY TO SIIT � ��'
COBBLEs
FlNE MEOHINI CpMSE FlNE COARSE
Gravel 43 % Sand 35 % Silt and Ciay 22 9'0
Liquid Limit XX % Plasticity Index XX °�6
Sample of: Clayey Sand and Gravel with Cobbles From: Pit 1 at 5 to 7 Feet
110 044A
�:PS�`a-=Fw1t�(
GRADATION TEST RESULTS I FIGURE 2
�
�
�.
,�
A
L_J
��
�
Ta " '
lin
Res�
den
p ce
115 Forest Road
Vail, Colorado
Permanent Ground Nail Wall
1. Cover
2. General Notes
3.
4.
Approximate Wall Location
Elevation View
APPROVED
,�� �� "� Community Developrr^^t �`�=aartment
- 9'�: [3uilding Safety 4nd i•;� ;. � � S°rvices
IU•. -
�n^' . ��-._-.._:id�cl tduil�ing Code/Int�;�._ ... . �:ial
G�.�� ��' �� c�. -^:?. Tie issuance or gran: �` ;�.all
nc; be con�.rG�d to be a permit for, or �n appro��.l .`, .-_ -.:��n of
any of the provis;on:, of this ccde or of 2ny other orc:,-��_ ..:'�
jurisdicticn. Permits presuming to give authority to v'e'.�:� �_, c.� �cel the
provisions cf this code or cther ordinances of the juris4:�:i�� c.` =:! nct be
valid. The issuan�e of a permit based on const�4�:;c� :'�^_"' f,_^- �nd
other data she!I rot prevent the building official frc-.� rc�:'� ...,, •.,�
Correctien cf er�ers in the construction documentJ 4��� G.i�..� l..�la. The
building c`:Tic;;:l i� c:!so authorized to prevent occu�.:^cy c° u�� cf a
Structur^ �.� '? :� '��i v.olation cf this code or cf any c:l,.ar c� d:nances of
this juri�c'.c.;:,, � � � I
DATE: / � � � �
pLANS EXAMINER:
5. Ground Nail Wall - Typical Cross Section
6. Ground Nail Wall - Details
� Yeh and Associates, Inc. D8�
Consulting Geotechnical Engineers
170 Mel Ray Road Glenwood Springs, CO 81601
Phone: (970) 384-1500 Fa�c: (970) 384-1501
Sheet Revision
Revision/Issue
Designed For:
Checked by B&Y Drilling, Ine,
���t N��:
210-158
n�� by:
Checked by:
RDJ Date: Project:
September 23, 2010
RDJ
���n af Vail
� �R�`�.��
� � E�.,,�.: � v
K � �S/ t
!`
� ;
�
�
�
1�
�: , ; ,� �.
'„ � • � � �;,-i�',
�
' �f o � s���� r��:`1
� , �:
3a '�� f i3�,�1 �. �-
;•.,.�
�:.•9
Cover
I Sheet Number:
Taplin Residence 1 of 6
;,
i I�
j�'
1.0 Ground Nail Wall Materials
1.1 Ground nails - Grade 75 threadbar or equivalent in accordance with ASTM A615, and galvanized or epoxy-coated in
accordance with ASTM A153.
fy=75,000 psi
1.2 Grout - Grout may be neat-cement or with sand, with Type II cement in accordance with ASTM C150. Water-cement
ratio should be between 0.4 and 0.6.
f�c=1,500 psi minimum 3 day
f�c=3,000 psi minimum 28 day
1.3 End hardware - Nuts and washers shall be in accordance with ground nail manufacturer's recommendations. Bearing
plate shall be in accordance with ASTM A36, Grade 36.
1.4 Shotcrete - Shotcrete mix shall consist of Type II cement in accordance with ASTM C150, potable water and normal
weight aggregate in accordance with ASTM C33. Admixtures, if used, should be non-corrosive to steel.
f'c=4,000 psi (28-day strength)
1.5 Welded wire mesh shall be in accordance with ASTM A185.
1.6 Walers and vertical bearing bars shall be in accordance with ASTM A615.
fy=60,000 psi
1.7 Strip drains consist of 12" wide dimpled cores wrapped in geotextile. The compressive strength of the core should
be at least 20 psi when tested in accordance with ASTM D1621, and it's in-plane flow capacity should be at least
10 gpm/ft when tested in accordance with ASTM D4716.
1.8 Centralizers should be plastic that will provide free passage of grout and attached to the nails in accordance with the
manufacturer s recommendations.
2.0 Ground Nail Wall Construction Sequence
2.1 Excavate one lift to a maximum depth of five feet.
2.2 Install ground nails at the locations and to the lengths shown on the plans. Ground nail location may vary by up to
6". Tremie the grout from the bottom of the hole up.
2.3 Install strip drains, welded wire mesh, walers and bearing bars as shown on the drawings. Use chairs to hold the
welded wire mesh away from the soil as necessary.
2.4 Install shotcrete to the minimum thickness shown on the drawings and to attain the minimum coverages specified
herein. Give special attention to filling the void in the borehole above the grout line. Cold weather protection measures
may be necessary.
2.5 Install the ground nail end hardware after the minimum inside coverage specified herein has been attained. While the
shotcrete is still wet, embed the plate into the shotcrete surface until there is no void behind the plate.
Handtighten the nut. Install remainder of shotcrete over end hardware to minimum specified thickness
and minimum outside cover as specified herein.
2.6 Once the grout and shotcrete have attained 80% of their specific strengths, repeat 2.1-2.5 to the bottom of the
wa I I.
2.7 At the bottom lift, complete strip drains to daylight as shown on the drawings.
� Yeh and Associates, Inc. Da�
Consulting Geotechnical Engineers
170 Mel Ray Road Glenwood Springs, CO 81601
Phone: (970) 384-1500 Fax: (970) 384-1501
;et Revision
Revision/Issue
3.0 Ground Nail Wall Design Parameters
3.1 The ground nail wall has been designed in general accordance with procedures contained in the FWHA "Manual
for Design and Construction Monitoring of Soil Nail Walls", Report No. FHWA-SA-96-069R.
3.2 The following strength parameters walls were assumed for the subsoils based on the "Presumptive Soil
Parameters for Foundation Design, Proposed Improvements, 115 Forest Road, Vail, Colorado" by HP Geotech,
Inc., Project No. 110 044A, dated March 15, 2010.
Sand and Gravel Soils
� c y qult
(deg) (psf) (pcf) (psi)
30 150 125 27
An experienced geotechnical engineer should verify the above design parameters during construction.
3.3 Groundwater level was assumed to be below the base of the wall.
3.4 Factors of safety
Global - FS > 1.5
Nail Tension Strength Factor -�N = 0.55
Nail Pullout Resistance Factor -�Q = 0.50
Nail Head Strength Factor -�F = 0.67
3.5 Surcharge loading
No surcharge loading was assumed.
3.6 Corrosivity was assumed to be low.
4.0 Special Notes
4.1 Wall geometry used in design was based on information provided by REI Sructural, Inc. plans dated 09.02.10.
42 At least one verification test shall be perFormed on a ground nail to verify the contractors
installation method and nail pull-out resistance in accordance with FHWA-SA-96-069R.
4.3 Ground nail verification and proof testing shall be performed in accordance with FHWA-SA-96-069R.
4.4 This design is valid only for B&Y Drilling at the subject site.
4.5 The ground nail wall may be redesigned at the discretion of Yeh and Associates based on verification test
results.
4.6 Yeh and Associates is not responsible for maintaining slope stability above and below the ground nail wall
during construction.
4.7 The contractors are responsible for field locating all nearby utilities. Conflicting utilities may require ground nail
wall redesign, at Yeh and Associates' discretion.
4.8 Yeh and Associates is not responsible for quality control, quality assurance, changed conditions, problems
resulting from improper construction techniques, or construction site safety. j %
4.9 Yeh and Associates is not responsible for wall layout. � ���
/ � � �-
�� - '� � � � �_ , ��`� _
� �����, o
Designed For:
Checked by B&Y Drilling, Inc.
Project Number:
210-158
v�� by:
Checked by:
RDJ Date: Project:
September 23, 2010
RDJ
General Notes
Sheet Number:
Taplin Residence 2 of 6
� row
� � ezora
TOF.
�f
ti8 p9$ 1E'-0 7-1P
_ .__ .__ - - _- ._ .
B-71S T.BI�!' 7'.31? 25J]E' 1]'-�iT 3'-]3�C
TOW � iOF. � � � — ��
TO.W. 07W'-1P B18B'-d �
E2Df.10' rl � �_ _ _�___ � TOW
. _...— --------------� �,v _ _:.-_-- - — -
TOF. ' TOF.
eisva I � � eieea• � �
TOW -
ems-a I i Tow rof j 1 row. cos. ` =
rar j e�''�' - esaas I � °�'$ esove
-- ----� -- -- ---- _a
ylOP"B .. _ ..._'__- _ _ - _
' _ ____ _____ _ ___ _ _ __ � _ __ _ _ '
- _-' f I TOW.
.ow. i � r-- ---- J .oF �
—+�ro�osed Ground Nail Wall �$ i j °17�,"' : $
e�,?d � i ' i i�4ax H= 15 feet) � '
I I � T.ow
TOF. / ' L_ N�l17E1M
� Y cow. � I I aa�re _— � �_ . __ _
- ��W� � TOF TOf T.OW. iOF. l � t�r
- e��e-r � j � �'$ � emoiu - apra � � r.ow. g
rof T0W ToF row. � � � etanz - e
T.OW. I I 9101'8 TO.W. �
ean'-01M _ � � % !�'8_, eaore 02�$_ _ °�z � I wnurrvE so�^
� I _____J���� L____J
_ _ - - _ _
� � � i ,aW .oF -- -- — —_ _
� ,.oW �
a � i �-0W I I � �g T0s - em�-0iK ��ow. �ow � �wR3fi tor � ez�ra_enioae
' � - T[14-P RLASTER a
a p
^' a L _ DTG'-01M R3f-61 �
�. __ �_ ____
._ __ ....-w. TOW.
.. -- TOF _ -_-..__.-T __�._ _
--Q), I BTlT$ -..��� _ -
�8Z0-0T \ �I � ITOF. tOF. l216'-�_ lYLCR i0F � TOW.
.. T�� _•. _�1T= E71V.P TOW ( I TOF l27B�P rJ �l744I
I I �p� T0� I I TOW.
ez�T O.W. � � � A7E'$ I � Ct164"� \� K771'd .-
' I I ! TOF ��� _�� I� 9t
� � � �r°w. ?ow
�+ -� TOF � / �-P TOf. I I Et9'O $
� TOW. TO.F I 1.OW
N19-0'
-�� � � i dTl6' P �f I r � ��a - 9R0[E
�'� TOF. �f� ��- TOF. I X TOn, RUSIER
� eav'� — _. ema � � ez+rs p
tow T.or. row L1 I r.o.w cow. g
-°2��\, em.a ezo�a .�e 1 I ¢c•.ir uzra �� uars
� TOF. TO.W.
� 87l9'JI 8��"»� TOF T.OW.
I ` ,.b� �� TOW. � I !Z9'.9
u.�� � � L t t7A7-0' T.O.F. �'d TOW
I ��__ a¢. � �� ` ETd'-P TOF !7!r-B
�` �_�_ ��__ _ TOW. TOW
'I __ I � __ B7RV � d77T�6 Aifi'-0`
I _� A ���� - �
���
� TOW
' I I ��� nb+ 7iV
' �� � SO.GSf00P ��
— __ � —�
��� �� i0F �
_ R7' B
0 M N H� ` .oF: '- �
�� ; ;
.of.
��� , .
� Yeh and Associates, Inc. De�
Consulting Geotechnical Engineers
170 Mel Ray Road Glenwood Springs, CO 81601
Phone: (970) 384-1500 Fax: (970) 384-1501
T�W
,�.aa
NJL
�r
20 � 1� 20
SCALE� 1" = 20'
. ��
'LT
O�'OOD � ���}. �`�,� .
� f� � �
s �R�
���' u° U ����� �/°�•_�
v •
i ` � � /,y�,/'� 2�'�
, �'. / : ��.
.
o•. .
. .
������-- °� �•����o m�• ����
�s�,�� ° -��
Notes:
1. Based plan and building layout from provided by REI
Structural, Inc. plans dated 09.02.10.
2. The proposed wall location is approximate and may vary
based on field conditions.
3. The ground nail wall shall be contained entirely within
property boundaries.
4. This drawing should not be used for wall or building layout.
Sheet Revision Designed For:
Revision/Issue Checked by B&Y Drilling� Il1C.
Pro,jecc Number:
210-158
vrawn by: � J Date: rroject:
Checked by: � J September 23, 2010
Approximate Wall Location
Sheet Number:
Taplin Residence 3 of 6
MAXIMUM REINFORCEMENT REINFORCEMENT HORIZONTAL VERTICAL
WALL HEIGHT LENGTH SPACING SPACING
(DH) B'°`R (RL) (SH) (SV)
15 �� #B GRADE 75 ALL SEE SHEEf 4 5 FEEf 5 FEEf
THREAD BAR
SHOTCR
VEF
DEi
TOP OF WALL
EL. = 8217' � W
3' MAX
SV
DESIGN HEIGHT=DH
VARIES
MAXIMUM=15' sv
.. �.
sy �,: `ti
,.y • .
; : .
,,'.
a wvc . � � r
.`� '•1'
BOTTOM OF WALL ��•
AT BOF
VOID
MAINTAINI
FOUNDATII
GROUNO
� Yeh and Associates, Inc. Da`�
Consulting Geotechnical Engineers
170 Mel Ray Road Glenwood Springs, CO 81601
Phone: (970) 384-1500 Fax: (970) 384-1501
STRIP DRAINS SHALL BE 12—INCHES WIDE �"�
PLACED 10' ON CENTER AND SHALL
NOT EXTEND WITHIN 18—INCHES OF TOP OF SHOTCREfE
SHOTCREfE
15 degrees "`�
DAYLIGHT STRIP DRAINS OR PIPED �
WfTH 4" SCH. 40 TO OUTFALL
(SLOT 4" PIPE AND INSERT DR,41N
STRIP AT EVERY LOCATION)
�ei icevision
Revision/Issue
Designed For:
Checked by B&Y Drilling, Inc.
Project Number:
210-158
Drawn by: � J Date: Project:
Checked by: � J September 23, 2010
;^�0 RE���, :
� �Y`��� b 14 .
� 3 �.:� � -
f ��� �„. . P� Aa.CY �!i`
S''�� � • � � aX � a/� F-�'
• �
.�:��. 23���
DRAWING NOT TO SCALE
Ground Nail Wall
Typical Cross Section
Sheet Number:
Taplin Residence 5 of 6
VERTICAL
BEARING BARS (2)
�5 O 6" OC, 30" LONG
(OR EQUIVALENT)
MESH OVERLAP �
MIN 2 GRIDS
WELDED
WIRE FABRIC
4"x4"—W4.OxW4.0
SHOTCRETE
REINFORCEMENT
FRONT VIEW
r— 8��� FIELD INSTALI
�
8"
NAII HOLE DIAMETER = BAR DIAMETER + 1/4"
BEARING PLATE
FRONT VIEW
—i f--a/4"
BEARING PLATE
SIDE VIEW
EPDXY COATED �8 ALL '
HORIZONTAL
BEARING BARS (2), CONTINUOUS
�5 O 6" OC (OR EQUIVALENT)
BEARING PLATE
2 IN. (MIN.) COVER
STEEL 81
HEX N
SHOTCRETE OR CIP CONCRETE
GROUND NAIL CROSS
SECTION A—A'
� Yeh and Associates, Inc.
Consulting Geotechnical Engineers
170 Mel Ray Road Glenwood Springs, CO 81601
Phone: (970) 384-1500 Fax: (970) 384-1501
Sheet Revision
Date Revision/Issue
SHOTCRETE FACING
r�TA� NAIL DRILLEp NAIL
BAR L cu..,...
GROUND NAIL DETAIL
NOT TO SCALE
BEARING PLATE
2 IN. (MIN.) COVER
HEX Nl
4"x4"—W4.Ox1
WELDED WIRE FABRIC
CENTRALIZER O MAX. 10 FT. O.C. AND
PROVIDE CENTRAIJZERS WITHIN 2 FT
FROM THE TOP AND BOTTOM Of DRILLHOLE
EPDXY COATED �8 ALL THREAD BAR
4 IN. (MIN.)
MINIMUM CLEAR
SHOTCRETE FACING
(MINIMUTA 28—DAY COMPRESSIVE STRENGTH 4000 PSI)
2— N0. 5 VERTICAL BARS (OR EQUIVALENT)
— N0. 5 WALER BARS (OR EQUIVALENT)
�—SHOTCRETE OR NAIL GROUT
STEEL BAR WITH CENTRALIZERS (ALL THREADBAR ONLY)
NAIL GROUT
:�
CENTRAUZER • � �N (d►IN.
1 THREADBAR ONLY) �
/ ,7 � y �..: �' e.
GEOCOMPOSITE DRAIN STRIP � - �,E
SEE NOTES FOR REQUIREMENTS. {� �'/r�-� '%, ��� �`�
�' L :6� ��J� � �:
�: �° �3 / C �:
. � � e .�
s �P �' ,
FINISHED WALL SECTION '-'����'eq� ��'�`
NOT TO SCALE
Designed For:
Checked by B&Y Drilling, Inc.
Project Number:
210-158
�� by� � J Date: Project:
Checked by: � J September 23, 2010
Ground Nail Wall Details
Sheet Number:
Taplin Residence 6 of 6
��+� �� ��` � � �
`�s �.� � , �
, � , �� . �
9. y_ a� v6�* L �.
��. $ �.; . '� y
� - � �s F '�
.� ` �
M �Y::
�
. `�
���' �
��'`�.
��
�.. �;
t.ic�u� una..
' ��� +
����::, r„ x' � ,a� �*' � .
� � ������ �` �i
�` ����� ,: "
a3�� �t,. y,"�
� '" __ : ;� ,� � 1 .
,, TRANSMITTAL FORM
�.
�� 3� ia ��� a:� �7 �� � �.;.y, �` ,,° �. Y �„,�r :§'�% -;�
� �
,y ��� � +� .._ 7'i
�f�,� i�'i`�ri��nrt�,`��.� -- men� ;
;:75 South Fro�r�tag�` E�a�� �
Vail„�Q.lo�� p� 8#���
�' � � �
� �efi�,� .9�Q-47� ���2�;�,
�
� ` � �� ¢k` �Faicz;,9?���9��� �
a��Ek�:� v+iVll�n? �3��t��?��C� ',
_d t
en����v�e�vv,����d�rn�t ��
� �
w� � � � ° � � ,� �� �.
�.�" a' •".Y_ . r. r ��:�
Revisio� Submittals:
1. "Field Set" of approved plans MUST accompany revisions.
2. No further inspections wil! be performed until the revisions are approved & the peRnit is re-issued.
3. Fees for reviewing revisions are $55.00 per hour (2 hour minimum), and are due upon issuance.
Permit #(s) informa6on applies to: Attention: () Revisions
_ � ; �� N` ��P�' [ }Response to py rrection Letter
� J 1N� attached co of correction letter
( ) Deferred Submittal
���i-��i���.�% �er
Project Street Address:
"� FD 2G3?` �O A"�
(Number) (Street) (Suite #)
Building/Complex Name:
Contact Infortnation:
Company. g�G� QU�IDIMG CoMPA�N',
Company Address: �• �• Q� � � � 3 a
�ity: vM L state: �_ z�P: 8 l 6 SS
Contact Name: �� C2-RY 1� o N 1�
Contact Phone: Q 7O •� 7�O • J�3 65J
E-Mail " l�2f�Y Ca �EGkQV�Ll�S. Go�_
Revised ADDITIONAL Valuations (Labor 8� Materials)
(DO NOT include original valuation)
Building
Plumbing:
Electrical:
$
$
$
Mechanical: $
Total: �
Description / List of Changes:
J� l.l� 3 a.0 A�t`1 �,.� s��o�►
� cwr t � f ��N �Ng -l�o -�i f
.fiior�.�.�� G� ' Ltrr�
`,,: � -r�E G� �Nb P�M ; � .
�
,�
(use additional sheet if necessary)
Date Received:
p ���o��
NOV 10 2010
OF VAIL
oz-J�-io
�
HEPWORTH-PAWC.AK GEOTECNNICAL
5020 County Road 154
Glenwood Springs, CO 89601
Phone: 970-945-T988
Fax: 970-945-8454
hnaeoCa?hpqeotech.com
SHOTCRETE CORE TEST REPORT
Frank Taplin
1505 Rising Glen Road
West Hollywood, California 90069
Job No: 110 044A
Project: Taplin Residence, 115 Forest Road, Vail, Colorado
Placement Location: Permanent Ground Nail Wall, 2nd Row Facing
LAB SAMPLE PREPARATION
Age When Cored: 7 days End Preparation:
Dafe Piaced: 10-99-10
Page: 1 of 9
Saw cut
Specified Strength at 28 Days: 4000 psi
Distribution:
Beck Building Company (terrvtc�beckbuilds.com)
Con#ractor Cast Trevor L. Kneil, P.E.
Fiefd Observer Reviewed By
. •
� �
�
HEPWORTH-PAWLAK GEOTECHNICAL
CONSTRUCTION ACTIVITY REPORT
Client: Frank Tapiin
1505 Rising Glen Road
West Hollywood, California 90069
5020 County Road 154
Glenwood Springs, CO 81601
Phone: 970-945-7988
Fax: 970-94�8454
hpgeo aQhpgeotech.com
Job No.: 170 044A Day: Friday
Date: '10129/10
Page: 1 of 1
Project: Tapiin Residence, 115 Farest Road, Vaif, Colorado
Weather: Ciear, caim, dry Temperature: 50°F at 11:00 am
Contractors Construction Activities: B8�Y Drilling installed ground nails #47 (re-drill), #45, #44, #25,
#43, #42, #41, #40A, #21, #22, #23 and #24 (see atEached nail
layout ior numbering}.
Equipment in Use: BD 70QE air-track dril! rig, grout plant, air compressor
HP Geotech's Site Activities: Observed drilling of ground nails #45, #44, #25, #43, #42, #41,
#40A, #21, #22, #23 and #24. Prepared bars were instalied in
completed borings and grouted, except nails #29, #22 and #23.
Nail instaflation abserved this date appeared to be in
substantial accardance with the design drawings (Yeh �
Associates, dated 9/23/10), provideci.
Nail #45 and #47 were dritled and installed prior to our arrival to
the site today. Bars were observed to extend about 6 to 8
inches out from the front face of the reinforcing steel.
The drill rig was down for re�airs most af the morning.
Verbal Communication: B�Y Drilling stated they woutd complete the soil nailing on
Monday, (11/1/1 U).
distribution:
Beck Building Company -- Attn: Terry Bond (terry@beckbuilds.com)
Louis Eller SET
Field Technician
8230-------.—
�..�:.,� �,.....�--
8220 — — —
.-.
w
a�
w
c
° 8210 — — —
>
m
w
----------- 8230
8200 --------------
— — — 8220
.-.
m
°,�'
...
----8210 °
m
>
m
w
------------------8200
8190 ---------------------------------- 8t90
NAIL LENGTH SCHEDULE
• 20 feet
��Yeh and Associates, Inc.
ConsUldng Gootechnical Engineers
170 Mel Ray Road Glenwood Springs, CO 81601
Phone: (970) 3641500 Fax: (97D) 384-1501
f
;.CL t(BVlslo� �+�.ir•�r.
u„�.�w�,,,� � s,. Is.�v uriniag, mc.
PnijaA Numbv:
2I0.758
thewn 6y: RDJ ��' Rolen:
�� tiY � J Septcmhv 23, 2020
SCALEt HOR[ZONTAL L' = 10'
VERTICAL 1' = 10'
Elevation View
SActtNipnba:
Tspl[n Rcsidrnce 4 of 6
� �
�
HEPWORTH - PAWLAK GEOTECHNICAL
CONSTRUCTION ACTIVITY REPORT
Client: Frank Taplin
1505 Rising Glen Road
West Hollywood, California 90069
5020 County Road 154
Glenwood Springs, CO 81601
Phone: 97Q-945-7988
Fax: 970-945-8454
hpgeo@hpgeotech.com
Job No.: 110 044A Day:
Date:
Page
Project: Taptin Residence, 915 Forest Road, Vaif, Colorado
Wednesday
1 '!l3/10
1 of '!
Weather: Ciear, calm, dry Temperature: 30°F af 9:95 am
Contractor's Construction Activities: Yeh and Associates performed a'pull test' on 2 test nails
installed along the bottom row of the permanent ground nail
wall. B�Y Driliing assisted with the testing.
Equipment in Use: Testing Equipment
HP Geotech's Site Activities: Observed 'pull test' on test nai[ located betwean nails #49 and
#50. We left the site prior to testing the second test nail.
The test nail at the first row was abandoned and not tested.
Verbal Communication: Keith with Yeh and Associa#es indicated that preliminary test
results appear adequate. Test results will be forwarded to Terry
Bond with Beck Building Company and then provided to us for
review.
distribution:
Beck Building Company — Attn: Terry Bond {terry@beckbuitds.com)
Trevor L. Knell, P.E.
Fiefd Technician
8230------
8220 — — —
�
.,
a�
�
._..
c
° 8210 — — —
>
m
w
8200 ------------
— — — 8230
— — — 8220
�
a�'i
r-
c
— — — 8210 °
�
>
m
w
--------�--------------8200
819d------------------------- �—�--.� 8190
NAIL lENGTH SCHEDiJLE
• 20 feet
��Yeh and Associates, Inc.
Consuldng Geotechnicai Fngineers
170 Mel Ray Road Glenwood Springs, CO 81601
Phonr: (970)384-IS00 Fa�c: {470)384-2501
n,�;��i r•�:
BS:Y Driliing, lae.
Rqcx Nmahcr.
ziatss
Dnwn by. g��.
RDJ Yml�:
�� �,. � J Scptember 23, 2010
SCALE= HORIZONTAL l' = 10'
VERT[CAL C = 10'
Elevation View
Shc�1 Numbx:
Taplin Rasidence 4 of b
� �
�
HEPWORiH-PAWLAK GEOTECHNICAL
CQNSTRUCTION AC�TIVITY REPORT
Client: Frank Tapfin
1505 Rising Glen Road
West HoHywood, Califomia 90069
Job No.: 1't0 044A
Project: Taplin Residence, 115 Forest Roacl, Vail, Colorado
5020 County Road 154
Glenwood Springs, CO 8160't
Phone: 970-945-7988
Fax: 970-945-8454
hpgeo@hpgeotech.com
Day: Monday
Date: 11/1/10
Page: 1 of 1
Weather: Clear, calm, dry Temperature: 45°F at 11:00 am
Contractor's Canstruction Activities: B&Y Drilling installed ground nails �#1, #2, #3, and #4, and
completed nails #21, #22 and #23 (see attached nail layout for
numbering).
Equipment in Use: BD 700E air track drill rig, grout pEant, air campressor
HP Geotech's Site Activities: Observed drilling of ground nails #1,#2, #3, and #4. Prepared �
bars were installed in completed borings and grouted. Nails
#21, #22 and #23 were grouted.
Nail installation observed this date appeared to be in
substantial accordance with the design drawings (Yeh &
Associates, dated 9/23/'[O}, provided.
Nails were drilled and insialled prior to our arrival to the site
ioday. Bars were observed to extend about 6 to 8 inches out
from the front face of ihe reinforcing steel.
Naii #2 was about 16 inches short of drilled depth.
Verbal Communicatian:
disMbution:
Beck 8uitding Company — Attn: Terry Bond (terry@beckbu[Ids.com)
Louis Eller SET
Field Technician
8230-----------------
Inscde Comer�
Outside Corner—�
8220 -----------
�
a�
w
v
C
° 8210 ----
W
_'m �w
azoo --------.__
----------------_.�-- 823d
�----8220
m
w
...
c
— — — 8290 °
>
m
w
-------------------------8200
8190---------------
---------------- g190
��Yeh and Associates, Inc.
Consulting Geotechnioal F_ngineers
170 Mel Ruy Rcxid Gtenwood Springs, CO S 1601
Phouer (970) 3841500 Far: (970) 384-1501
NAIL LENGTH SCHEDULE
• 20 feet
na;�.it r,+r.
B&i' UrflliaQ, lnc.
Roia+Nvmt�u:
210.159
Draxn h :
Y RBJ �0k: Pmy;ct:
�� � September 23, 2010
RDJ
SCALE� HpRIZONTAL L' = 10'
VERTICAL I' = 10'
Elevation View
Taplin RcsEdence sM�`�N��
4of6
0
HP
�
HEPWORTH-PAWLAK GEOTECHNICAL
CONSTRUCTION ACTIVITY REPQRT
Client: Frank Taplin
1505 Rising Glen Road
West Hollywood, California 90069
5020 County Road 954
Glenwood Springs, CO 8164'[
Phone: 970•945-7988
Fax:970-945-8454
hpgeo@hpgeotech.com
Job No.: 110 044A Day: Wednesday
Date: 9/29/10
Page: 1 of 1
Project: Taplin Residence, 115 Farest Road, Vail, Colorado
Weather: Clear, calm, dry Temperature: 50°F at 8:10 am
Contractor's Construction Activities: Idle
Equipment in Use: None
HP Geotech's Site Activities: Observed reinforcing steei for �rst row of ground nails at
proposed permanent ground nail wall, building Grid Lines fi, 7
and E. The wall was designed by Yeh and Associates, Inc. and
design drawings (Yeh and Associates, Project Number 290-158,
dated September 23, 2010) were provided by Beck Building
Company for our use. The wall will E�e contructed by B8�Y
Drilling, Inc. The watl is proposed to have a maximum height of
'15 feet. A total of 58 nails are proposed to be instafled in 3 rows
of 20, 20 and 18, top to botto�n, respectivety.
Excavation for the firs# row of nails and erectian of reinforcing
steel had been performed prior to our arrival to the site, bu#
ground nails had not been installed. The west wing wall portion
was not excavated. The soils exposed along the cut face
consisted of existing fill and natura[ granular soils. Existing
footings were observed in the area of nails #9 and #90 (see
at�ached nail layaut for numbering). Nails #1 through #�4 are
located in the area of the rough graded access ramp into the
site and were not prepared for nail installation. Nail #18 will be
installed with west wing wall nai(s #99 and #20 at a tater date.
We understand that a thin "flash" coat of shotcrete will be
applied to the cut face prior to installing t�e ground naits in
order to prevent ravelling of the cut #ace.
Reinforcement steel observed between nails #5 and #17
appeared to be in substantial conformance with the details
shown on Sheet 6 of 6 of the design drawings with the
following exceptions noted below.
1. Welded wire fabric was partially erected around the existing
footings which protruded out from the excavated face and
rebar was not observed at nails #9 and #10.
2. Verticat bars consisted of No. 4 rebar spraced at
approximately 4 1/2" o.c. The grade of the rebar is not known.
cant...
3. Horizontal walers consisted of No. 4 rebar spaced at
approximately 4 9/2" o.c. ihe grade of the rebar is not known.
No splice overlap was specified on the design drawings, but
typical(y measured between 27 and 29 inches in length.
Verbal Communication: We informed Terry Bond with Beck Building Company of our
observations and deviatians from the design drawings noted
above.
The ground nail wal! engineer of record (Richard Johnson with
Yeh and Associates) accepted the rebar spacing as
constructed verbally in a tefephone conversation conducted in
the job trailer while on-site. The engineer also verified #hat the
"flash" coat application was a typicat construction technique
and was acceptable at this site. The engineer was not aware af
the rebar size discrepancy and staied that he would investigate
the matter.
Mr. Bond informed us the earthwork contractor would be on-
site later in the day to sawcut the protruding footing and B&Y
wouid complete steel rein%rcement erection the foliawing day.
He also requested a follow-up site visit #o observe the
compteted work.
distribution:
Beck Building Company—Attn: Terry Bond {terry@beckbuilds.com)
Trevor L. Knell, P.E.
Field Technician
8230---.--�_.._
�i'1c1!'�C rnrnnr -_ �� i�
8220 --- — --
�
.°'
�
° 8210 — — —
ca
N
W
^'----------- 8230
8220
w
�
c
— — — 821� �
ld
m
w
8200 ---------------.—
----------------82Q0
8'i90 -----------------
------------�----- 8190
NAIL LENGTH SCHEDULE
• 20 feet
��Yeh and Associates, Inc.
Consulting Geotechnical Engineers
! 70 �1e1 Ray Road Glenwood Springs, CO 81601
Phonr: (970) 384-1500 Fax: (970) 3841,501
Dea�l Fr.
BStY Drllling, Int.
P�cttNiunl+er.
310-158
Lkawn hy: Ddr.
RDJ pn�Jca:
��� M,. � J Septembcr 23, 2010
SCALE� HORIZONTAL t' = 10'
VERTICAL 1' = ip'
Elevation View
TaptiaRssidmce gh"�NW"e`r
4 0[ 6
,
H�
�
HEPWORTH-PAWL,AK GEOTECHNiCAL
CONSTRUCTION ACTIVITY REPORT
Client: Frank Taplin
1505 Rising Glen Road
West Hollywood, Caiifornia 90069
Job No.: 110 Q44A
Project Taplin Residence, 115 Forest Road, Vail, Colorado
5020 County Road 15�1
Glenwoad Springs, CO 81609
Phone:9i0-945-7988
Fax: 970-945-8454
hpgeo@hpgeotech.com
Day_ Friday
Date: 10/1110
Page: 1 of 1
Weather: Clear, ca[m, dry Temperature: 45°F at 8:30 am
Contractar's Construction Activities: B8�Y Drilling was preparing to appty "flash" coat between
ground nails #5 and #17 (see attached nail layout for
numbering) a# proposed lower leve[, permanent ground nail
waU.
Equipment in Use: Nane
HP Geotech's Site Activities: Observed completed reinforcing steel erection at first row of
ground nails as a foilow-up to our 9129110 site visit. Reinforcing
stee) observed between ground nails #5 and #17 appeared to
be in substantial conformance with the details shown on Sheet
6 of 6 of the design drawings.
Rebar sizing had been corrected from No. 4 to No. 5 since our
9/29/10 site visit.
Application of the "flash" coat wiU be per#ormed later today.
Verbal Communication: We informed Terry Bond with Beck Building Company of our
observations.
disfribution:
Beck Building Company — Attn: Terry Bond (terry@beckbuilds.com)
Trevor L. Knell, P.E.
Field Technician
8230 — — ---
� ' Inside Corne�--=} `— —
Outside Corner--,
$220 ------------
Y
�
�I
�
� 8210 — —
co
a'�
w
8240 ------^..--.,—.�.—
— — — — — --- — __._ ._ _. _ —. _ —,. 8230
--`—'----8220
�
V�
c
-- — 8210 °
>
d
`w
�..�.—.�--..�—�_�.--,—_.._.-8200
8190-----------_..---�
----------------- 8190
��Yeh and Associates, Tuc.
Gonsttlsing Geotechnical Engineers
170 Me! Ray Road Glenwood Springs, CO 81601
Phour: (970} 384I500 Fax: (970) 384-1501
NAIL LENGTH BCHEDULE
• 20 feet
nr�i�c,t r•oc
B�Y DriUing, Ina
rrojax Nwnbcr.
210-158
ur.ur nY
RDd De1c Projar.
a+od�oa a�: �Ptembcr 23, 2010
RAJ
SCALE: H�RIZONTAL t' _ !0'
VERTICAL 1' = 10'
Elevation View
Taplin Residence �KNumLcr,
4of6
►
H�
�
HEPWORTH - PAWLAK GEOiECHNICAL
CONSTRUCTION ACTIVITY REPORT
Client: Frank Taplin
9505 Rising Glen Road
West Hollywood, California 90069
Job No.: 110 044A
Project Taplin Residence, 115 Forest Road, Vail, Colorado
502Q County Road 154
Glenwooc! Springs, CO 81B41
Phone: 970-945-7988
Fax:870-945-8454
hpgeo@hpgeotech.com
Day: Tuesday
Date: 10l519 0
Page: 1 of 1
Weather: Clear, calm, dry Temperature: 68°F at 11:00 am
Contractor's Construction Activities: B&Y Drilling installed ground naits #7 through #17 and a test
nail (see attached nail tayout for numbering).
Equipment in Use: BD 700E air-track drill rig, grout ptan#, air compressor
HP Geotech's Site Activities: �bserved insiatlation of ground nails #7 through #17 and a test
nail between nails #12 and #13. Grout tubes were attached to
the bars with duct tape. Grout consisted of Quikrete Type I/ll
p(aced in drill hvles after inserting prepared bars. Nails were
installed in substantial accordance with the design drawings
(Yeh & Associates, dated 9/23/10), provided.
Verbal Cammunication: We informed Terry Bond with Beck Building Company of our
observations.
distribution:
Beck 8uitding Company — Attn: Terry Bond (terry@beckbuilds.com)
Louis Eller, SET
Field Technician
8230-----------.
I nside
Outside Comer—.
8220 ----------
a�
�
�
�
� 8210 — — —
m
>
a�
w
ier--� ^--'--'"------.�—�_� 8230
`---'�--8220
.^
a�
w
c
— — — 8210 .°
m
>
m
`w
8200 ---------------
----------------8200
819p-----------------
--------------____ g190
��Yeh and Associates Inc.
Consulting Geotechnical Engineers
170 Me1 Ray Rood Glenwaod Springs, CO 8 f 601
Phone: (970) 384-1500 Fax: (970) 384-1501
NAtL LENGTH SCHEDULE
• 20 feet
o«��a r•��: —
B&Y Drilliag, [nc.
'rolccC Nunl�cr.
TIO•158
[kawr hy: RD7 Date: PruJca:
��� nY � J September 23, 20I0
SCALE= HOR[ZONTAL l' = 10'
VERT[CAL 1' = i0'
Elevation View
TaplinResidcnce ��N1tl"b°`
4of6
H�
�
HEPWORTH - PAWLAK GEOTECHNICAL
CONSTRUCTION ACTIVITY REPORT
Client: Frank Taplin
1505 Rising Gten Road
West Hollywood, Catifamia 90069
Job No.: 110 044A
Project: Taplin Residence, 915 forest Road, Vail, Colorado
5020 County Road 154
Glenwood Springs, GO 81601
Phone: 970-945-7988
Fax: 970-945-8454
hpgeo aQhpgeotech.com
Day: Friday
Date: 1018/10
Page: 1 of 1
Weather: Clear, calm, dry Temperature: 65°F at 12:30 pm
Contracto�'s Consiruction Activities: B8�Y Dritling was preparing to appfy "flash" coat between
ground nails #18 and #Z0, and #26 and #37 (see attached nail
layout for numbering) at proposed permanent ground nail wall.
Equipment in Use:
HP Geotech's Si#e AcUvities:
None
Observed reinforcing steel for �rst row, west wing wa(! and
second row of ground nails at proposed permanen# ground nail
wall.
Excavation for the first row, west wing walf and second row of
nails and ereciion of reinforcing steel had been performed priar
to our arriva) to the site, bufi ground nails had not been
installed. Nails #18 through #20 were abserved to descend in
eievation with ihe existing grounc! slope. The soils exposed
along the cut face consisted mainly of natural granular soils
wi#h weathered beclrock near the bottom of the cut #ace at fhe
west side. We understand that a thin "flash" coat of shotcrete
will be applied to the cut face prior to installing the ground
nails in order to prevent ravelling of the cu# face.
Reinforcing steel abserved between nails #18 and #20, and #26
and #37 appeared to be in substantial canformance with #he
details shown on Sheet 6 of 6 0# the design drawings.
Nails #21 through #25 are located in the area of the rough
graded access ramp into the site ancf cauld not be prepared for
nail installation.
Nails #38 through #40 will be insta[led with the third row of
naits.
Verbal Communication: We informed Terry Bond (via telephane) with Beck Building
Company of our observations.
distribution:
Beck Building Company — Attn: 7erry 8ond (terry@beckbuilds.com)
Trevor l.. Knell, P.E.
8230---------
Inside
Outside Corner-
8220 ----�--�—
m
w
�
C
� $2 � � -- — ---
>
N
W
6200 — — — —
---------------- 8230
-----8220
B ?O �
1 • p�
�
�— � � — _` 82 � � ;�
N
N
W
`----------------------------8200
8190----------------
---------^�—,.—_.,— 8190
��Yeh and Associates, Inc.
Consu?ting Geoiechnical Engineers
170 Met Ray Road Glenwood Sprincs, CQ 81601
Phonr: (970) 384-I500 Fax: (970} 384-1501
NAIL LENG7H SCHEDULE
• 20 feet
n�.;�ra r�r
Bdcl' nrillia�, inc.
zio-iss
w.� tiy:
RDd �°" Projcst:
�.�m �,. � J Septcmbcr 23, 20I0
SCA�E� HOR[ZONTAL 1' = 10'
VERT[CAL 1' = 10'
Elevation View
T�plin Residencc �YN��
4 0[ 6
l
�
T �
� �
t�°'�i'�
HEPWORTH - PAWLAK GEOTECHNfCAi
CONSTRUCTtON ACTIVITY REPORT
Client: Frank Taplin
1505 Rising Gfen Road
West Hoilywood, California 90069
Job No.: 110 d44A
Project: Tapfin Residence, 115 Forest Road, Vail, Colorado
5020 County Road 154
Glenwood Springs, CO 81601
Phone: 970-9457988
F2rx: 970-945-8454
hpgeo@hpgeotech.com
Day: Monday
Date: 10/11/90
Page: 7 of '!
Weather: Clear, catm, dry Tempera#ure: 58°F at 11:00 am
Contractors Construc#ion Activities: B&Y Drilling installed ground nails #5, #fi, #18 through #20 and
#26 through #37 (see attached nail layout for numbering).
Equipment in Use: BD 700E air-track dril! rig, grout plant, air compressor
HP Geotech's Site Activities: Observed installation of ground nails #5, #6, #18 through #20
and #26 through #37. Grout tubes were attached to the bars
with duct tape. Grout consisted of Quikrete Type 1/tl ptaced in
drill holes after inserting prepared bars. A bar was not be
placed at nai! #27 because of contact with nail #26. Nai[s were
installed in substantial accordance with the design drawings
(Yeh & Associates, dated 9/23110), provided.
Verbal Communication: None
distribution:
Beck Building Company -- Attn: Terry Bond (terry@beckbuilds.comj
Louis Efler, SET
Field Technician
8230---------
InsideComer—� ^--'---�---------- 8230
Outside Corner---,
Strip Drains
8220 ------.._—�—_. -- —
� ------
� — ^ — — — ` — 8220
� ♦ � • • • � • � � 11 1 13 74 15 1B 17 16 79 20
v �
r � • • • • � • • • p�
0 21 � � 24 ❑�` 28 27 28 29 a 31 32 33 j� � .,n., �� �
� 82�� —� — — ^ —i
a�i a, � s� � �� � — — — 82'10 °
w ❑ 42 43 ��� 4 4°° S' b2 0 0 � 0 37 0 >
. . . . . . . . . . 4 .. �,
8200 -----------------
-----------------8200
8190------------.^�_
------------------ 8190
NAIL LENGTH SCHEDULE
• 20 feet
��Yeh and Associates, Inc.
ConsuRing Geotechnical 8ngineers
t70 Mel Ray Road Glenwood Springs, CO S160i
Phone: (970) 384-i S00 Fsuc: (970) 384-1501
:CC iCCV1S20n D<+q;nedF�r.
u�.wom�we ��yy BScY Drilling, iac.
PmJat NwnLcr;
ziaiss
�� �� RDJ �`' Pmjcct:
�� M,. � 3cptembcr 23, 2010
SCALE� NORIZ�NTAL 1' = IO`
VERTICAL F' � 10'
Elevation View
Taplin RcsldCrtce �1D1''�Nwnh�r,
4 0{'6
.
�
H�
�
HEPWORTH-PAWLAK GEOTECHNICAL
CONSTRUCTION ACTIVITY REPORT
Client: Frank Taplin
7505 Rising Glen Road
West Hailywood, California 90069
Job No.: 190 044A
Project: Taplin Residence, 115 Forest Road, Vail, Colorado
5Q20 County Road 954
Glenwood Springs, CO 816Q1
Phone: 976-945-7988
Fax: 970-945-8454
h p g eo@tipgeotech. com
Day: Tuesday
Date: 10/19/14
Page: 9 of 1
Weather: Clear, calm, dry Temperature: 45°F at 8:20 am
Contractor's Construction Activities: B&Y Drilling was preparing to apply "fiash" coat between
ground nails #38 and #40, and #44 and #58 (see attached nail
layout for numbering) at proposed permanent graund nail wall.
Equipment in Use: None
HP Geotech's Site Activities: Observed reinforcing steel for second raw, west wing wall and
third row of ground nails at proposed permanent ground nail
wall.
Excavation for #he second row, west wing walt and third row of
nails, and erection of reinforcing s#eel had been per�ormed
prior to our arrival to the site, but ground nails had not been
installed. Nails #38 through #44 were observed to slightty
descend in elevation with the existing ground slope. The soils
exposed along the cut face consisied of naturaf granular soils
on the east half and weathered fo competent bedrock on the
west haff. We understand that a thin "flash" coat of shotcrete
will be applied to the cut face prior to instalfing the ground
nails in order to prevent ravelting of the cut face.
Reinforcing steei observed between nails #38 and #40, and #44
and #58 appeared to be in substantial conformance with the
details shown on Sheet 6 of 6 of the design drawings.
Nails #41 through #43 are located in the area of the rough
graded access ramp into fhe site and could not be prepared for
nail installaiion.
Yerbal Comrnunication: We infvrmed Terry Bond with Beck Building Company of our
observations.
distribution:
Beck Building Company — Attn: Terry Bond (terry@beckbuitds.com)
Trevor L. Kneli, P.E.
Field Technician
8230 — — --. .— .— — � —
Insid r�..,o.. —�.—^---------
Outside Corner-
8220 ----------�—
�
s
� • • • • �s—
� 8210 --- 21 �p � p�
W41 4�2 43 q I
— — ~ — — 8230
� — — — 8220
m
�
---82'!0 °
>
m
W
s2ao ------------
-------------z_�---�.—s2oa
8190-------------------------------8190
NAIL LENG7H SCHEDULE
• 20 feet
��Yeh and Associaies, Tnc.
Consulring Geotechnicat Bngineers
170 Mei Ray Road Glenwood 5prings, CO 81601
Phone: (970) 384-1500 Fax: (970) 384-1501
SCA�E� HpR[ZaNTQL 1' _ !0'
VERT[CAL 1' = t0'
�CI1Ce.V1610� Duai�tF<r.
k�.+�a�n.,.A �y yy B&1' DNIIinR, Ina
P�N�� Elevation View
210-158
lkownby. Da�q
RDJ Pmjea: shcc� xum6cr.
�y,�;� yY Septcmbcr 23.2010 Taplin Rcs�deucc 4 oC 6
RDJ
.
� �
HEPWORTH-PAWLAK GEOTECHNtCAL
CONS7RUCTlON ACTIVITY REPORT
Client: Frank Taptin
1505 Rising Glen Road
West HoHywood, California 90069
5020 County Road 154
Glenwood Springs, CO 81641
Phone: 97U-945-7988
Fax: 970-945-8454
hpgeo@hpgeotech.com
Job No.: 110 044A Day: Thursday
Date: 10I21/10
Page: 1 of 1
Project: Taplin Residence, 115 Forest Road, Vail, Colorado
Weafher: Ciear, calm, dry Temperature: 45°F at 9:14 am
Contractor's Constructian Activities: BB�Y Drilting installed ground nai�s #27, #46, #48 through #57
and 2 test nails (see attached nait layout for numbering).
Equipment in Use: BD 700E air-track drill rig, grout plant, air cflmpressor
HP Geotech's Site Activities: Observed drilling of ground nails #27 and #46 through #49.
Prepared bars were installed in completed borings and
grouted, except nail #47 where 10' of drill steel was lost in the
borehole during drilling. The 6orehole for nail #47 was grouted
and will be re-drilled at a later date.
Nail installation observed this date appeared to be in
substantial accordance with the ciesign drawings (Yeh 8�
Associates, dated 9/23/10), provided.
Nai[s #50 through #57 were drilled and grouted on 10/20/10
after we had left the site and the drifl rig been repaired. The test
nails were drilled and installed prior to our arrival to the site
today. Bars were observed to extend about 6 to 8 inches out
from the front face of the reinforcing steel. Test nails were
installed between nails # 49 and #50, and #40 and #58.
Picked up a shotcreie panel prepared by B&Y Drilling and
delivered it our laboratory for strength testing.
Verbal Communication: Terry Bond with Beck Building Company provided us with the
upcoming project schedute prior to him leaving the siie.
distribution:
Beck Building Company — Attn: Terry Bond (terry@beckbuilds.com)
Trevor L. Knell, P.E.
Fieid Technician
8230---------------------.__.._--
Inside Corner--` — — — — — — $230
Outside Corner--,
Strip Drains
822Q ---------- --
--------- --------8220
:..
� 3 B ! 4 15 18 77 78 19 20
v • • • • • � r • • � • • • • I • • • • • �
•� 82 �i Q --- — ^ �—� � � _� � � � � � � � _�___33 � � 3�-- � 3`, _ ` _ 82 � fl �
W � � � � � � �T � � � � � 0 � � � � � N
� W
8200 -----------------------.`—�
------8200
8190------------_..--�.--____.--�—
--------8190
NAIL LENGTH SCHEDULE
� 20 feet
��Yeh and Associates. Inc.
Consulting Geotechnicel Fngineers
170 Mel Ray Road Glenwood Springs, CO 81601
Phone: (970) 3841500 Fax: (970) 384-1501
i
0
SCALE� HORIZONTAL 1' = 10'
VERTICAL 1' = 10'
Dc,yxw,� x�r. —
BSrY Drlllia� inc.
PmjtttNunM1Cx: Elevation View
210-158
lkarn h :
y �f Date: p�� SIicClNUmbc':
�� SeptemAer 23, 2010 Taplia Res3drnce q of 6
� RDJ
� �
�
HEPWORTH-PAWLAK GEOTECHNICAL
CONSTRUCTION ACTIVITY REPORT
Client: Frank Taplin
1505 Rising Glen Road
West Hollywood, Califomia 900fi9
5020 County Road 154
Glenwood Springs, CO 81601
Phnne: 97Q-945-7988
Fax: 970-945-8454
hpgeo@hpgeatech.com
Job No.: 110 044A Day: Wednesday
Date: 9 0I20/10
Page: 1 of 1
Project Taplin Residence, 115 Forest Road, Vail, Colorado
Weather: Clear, calm, dry Temperature: 40°F at 9:20 am
Contrdctor's Construction Activifies: B&Y Drilling instalted ground naits #38 through #40, part of #57 and
#58 (see attached naiE layout for numbering).
Equipment in Use: BD 700E air-track dritl rig, grout planf, air compressor
HP Geotech's Site Activities: Observed drilling of ground nails #38, #58 and part of #5T. Drllling
ceased after about 15 feet ai nail #57 after a hydrauiic line ruptured.
Prepared bars were installed in nails #38 and #58. No grouting was
performed and we left the site at 11:30 am while repairs were made to
the dritl rig.
N�il installation observed this date appeared to be in substantial
accoMance with the design drawings (Yeh � Associates, dated
9/23/70), provided.
Nails #39 and #40 were drilled and bars instafled prlor ta our arrival to
the site. Bars were observed to extend about 6 to 8 inches aut from
the frontface of reinforcing steel.
Verba( Communication: Terry Bond with Beck Building Company was informed of our
observatins and the dri(iing progress. He informed us that drilling
would like[y resume the following day after repairs were made to the
drill rig.
We discussed completion vf nail #27 (see 10/1111Q report) with
Richard Johnson with Yeh $ Associates via te[ephone. He informed
us ihai it was acceptable to re-drill hole provided it remained centered
between the reinforcing steel and avoided contact with completed nait
#26.
We also discussed our concern about hydraulic fluid whlch had
sprayed on a portion of the completed wal! after the hydrau(ic line
rupture and it's potential effect on aciherence of the final shotcrete
coat on the third row "flash" coating. Mr. Johnson stated that he had
observed similar conditions on a previous job and was not aware of
any methods for removing the hydraulic fluid and did not note any
adverse effects after applying the final coat of shotcrete in ihat case.
distribution:
Beck Buitding Company — Attn: Terry Bond {terry@beckbuiids.com)
Trevor L, Knell, P.E,
Field Technician
8230 — — — —
8220 — — —
.-.
w
N
w
C
� $2�� _'_-
>
a�
w
----�— ----------- --- 8230
— — — 8220
m
�
C
----8210 °
m
>
m
w
8200 ----------------------------------8200
8190-------------------------------8190
NAIL LENGTH SCHEDULE
� 20 feef
��Yeh and Associates, Inc.
Consulting Geotechnical Fngineers
170 Mel Aay Rood Glenwood Springs, CO 8 i 601
Phonr: (970) 384-I500 Fax: (910) 384-1501
♦ _
�C[ KCV1S101] 1kyp�fF�r.
ke.uew� �k�M. BfiYDrininR,rac.
ProjR.lNumhcr
220-i58
INuYT by.
RD7 �°1O' Prnjcd:
c��� � Septemher 23, 2010
RDJ
SCALE� HORIZONTAL 1' = iQ'
VERTICAL 1' = 10'
Bievation View
ShxlNum6cr.
Taplln RCxldeott 4 of6
H�
�
HEPWORTH - PAWLAK GEOTECHN[CAL
CfJNSTRUCTION ACTiVITY REP�RT
Client: Frank Taplin
1505 Rising Gten Road
West Hallywood, California 90Q89
5020 County Road 754
Glenwood Springs, C� 81601
Phone: 970-945-7988
Fax: 970-945-8454
hpgeo@hpgeotech.com
Job No.: 110 044A Day: Tuesday
Date: 10l26/10
Page: 1 of 1
Project: Taplin Residence, 175 Forest Road, Vail, Colorado
Weather: Cloudy, light breeze, light snow Temperature: 30°F at 12:24 pm
Contractor's Construction Activities: B�Y Drilling was preparing to appty "flash" coat between ground
nails #9 and #4, #29 and #25, and #40A and #43 (see attached nail
tayout for numbering) at proposed permanent ground nail wall.
Equipment in Use:
HP Geotech's Site Activities:
None
06served reinforcing steel for remaining ground naiis at east end and
east wing wall at proposed permanent grounct nail wall.
Excavation for the easi end and east wing wall, and erection of
reinforcing steel had been perFormed prior to our arrival to the site,
but ground nails had not been installed. Nails #9 through #4were
observed to slightly descend in elevation with the existing ground
slope. Nail #40A was added east of nai! #40 of the third row. The soifs
exposed along the cut face consisted of existing fill soiis overlying
natural granular soils. We unde�stand that a thin "flash" coat of
shotcrete wiU be applied to the cut face prior to instatling the ground
nails in order to prevent ravelling of the cut face.
Reinforcing steel observed between nails #1 and #4, #21 and #25, and
#40A and #43 appeared to be 9n substantial conformance with the
details shown on Sheet 6 of 6 of the design drawings,
Some patches of snow were observed on the cut face, and the soils
expased appeared thawed and free af frost.
Verbal CommunicatiOn: We informed Justin Yenter with B&Y Drilling of our observations. He
informed us that he blow any snow off of #he cut face prior to
applying shotcrete and cover the area with construction blankets
when completed. Also, he informed us that drilling would be delayed
until the excavator could widen the excavation for drill rig access.
distribution:
Beck Building Company — Attn: Terry Bond (terry@becKbuilds.com)
Trevar L. Knell, P.E.
Field Technician
8230--------------------=-------
inside Corner
Uutsids Comer
Strip Drains
8220 ---------- -- ---------- --
.:
� 3 4 6 7 8 9 1 3 1 15 SB 17
� • � • • � • � • 1 � • • • • � •
� 82 � fl--- 21 a � z4 � Q 2T 28 � 35 Q 33 � 35 � 37
j —� � �— � �—
� OA 1 � � � � q❑g � 4B 49 Q 51 52 � � 55 SB
� • • � • � � � � • � • � • • •
82�� ------------------^--------....—
------ 8230
----8220
� w
_ — _ 82�0 �
N
N
W
-----8200
8190 --------------------------------- 8190
NAIL LENGTH SCMEbULE
• 20 feet
��Yeh aqd Associates, Inc.
Consulting Geotechnioal Fngineers
170 Mel Ray Road Glenwood Springs, CO 81641
Yhonr: (970) 384-1500 Fax: (970) 384-1501
• ' .
SCALE� HORIZONTAL 1' = 10'
VERTICAL 1' = LO'
n�.;i,�� r•��:
B&1' Drilling, inc.
PnqcaN�nhcr; E�BV$iIOIl v10W
210-159
u�.�.m nr RDJ °aic� rMia�: sn� N�
a�.�ed ny. � J �ptcmbcr 23, 2010 'CapNn Rcsidcncc 4 of 6
�'
HP
�
HEPWORTH-PAWLAK GEOTECHNICAL
5020 County Road 154
Glenwood Springs, CO 81601
Phone: 970-945-7988
Fax: 970-945-8454
hpgeo@hpgeotech.com
CONCRETE TEST REPORT � lb °
Frank Taplin Job No.
1505 Rising Glen Road Date Cast:
Los Angeles, California 90069 Revised*
Sheet:
Project: Taplin Residence, 115 Forest Road, Vail, Colorado
Placement Location: Walls, Lines 4.5 - 1
Supplier: B&B Time Batched
Truck No: 6042 Time Arrived:
Ticket No: Time Placed:
Mix Design: 36012474
Method of Placement: Pump
110 044A
01-21-11
1of1
6 ;�
L J�
9:46 am Load Size (Yds): 9
11:20 am Yds Delivered: 9
11:30 am Yds Ordered: 27
Sample Point: Truck discharge
Time Sampled: 11:35 am Slump: 2 3/< inches
Air Temp: 28° Air Content: 7.6 %
Concrete Temp: 74° Wet Unit Wt: 142.1 pcf
Water Added: 10 gallons added by pump operator
Communication: The Contractor was informed of field test results.
Time Cylinders Cast: 11:45 am
Initial Cure: 3 days on site Field Storage: Heated Job Trailer
Date Stripped: 01-24-11
� Compressive Strength Data
2010
Compressive 2g Da
Lab A9e Date Load Diameter Area Y
Number Days Ibs. in. �nz Strength (psi) Avg. (psi}
028A 7 01-28-11 38,600 4.01 12.63 3060
0286 28 02-18-11 53,400 4.01 12.63 4230
4230
028C 28 02-18-11 53,400 4.01 12.63 4230
028D 56 03-18-11
Specified Strength: 3000 psi at 28 days
Notes: *Specified strength revised to 3000 psi, original issued test report stated 4000 psi.
Distribution:
Frank Taplin (franktaalin(a�amail.com)
Terry Bond-Beck Buitders terrvan.beckbuilds.com
Justin Orgill James Parker, PG, EIT
Field Technician Reviewed By
HP
�
HEPWORTH-PAWLAK GEOTECHNICAL
5020 County Road 154
Glenwood Springs, CO 81601
Phone: 970-945-7988
Fax:970-945-8454
hpgeo@hpgeotech.com
CONCRETE TEST REPORT
Frank Taplin � � Job No. 110 044A
1505 Rising Glen Road Date Cast: 01-26-11
Los Angeles, California 90069
Sheet: 1 of 1
Project: Taplin Residence, 115 Forest Road, Vail, Colorado
Placement Location: Walls; Lines 4.5 - 7
Supplier: B8�B Time Batched
Truck No: 6003 Time Arrived:
Ticket No: B2136324 Time Placed:
Mix Design: 36012477
Method of Placement: Pump
9:48 am Load Size (Yds): 10
11:15 am Yds Delivered: 10
11:40 am Yds Ordered: 67
Sample Point: Truck discharge
Time Sampled: 11:44 am Slump: 4 1/2 inches
Air Temp: 32° Air Content: 5.4 %
Concrete Temp: 70° Wet Unit Wt: 144.2 pcf
Water Added: 25 gallons added by supplier
Communication: The Supplier was informed of field test results.
Time Cylinders Cast: 11:54 am
Initial Cure: 24 hrs on site Field Storage: Trailer
Date Stripped: 01-27-11 Cyt Temp at Pick Up: 62° Min/Max: 62°/72°
Compressive Strength Data
2010
Lab Age Load Diameter Area Compressive 2g Day
Date
Number �ays Ibs. in. inZ Strength (psi) Avg. (psi)
035A 7 02-02-11 56,200 4.01 12.63 4450
035B 28 02-23-11 70,OOU 4.01 12.63 5540
5480
035C 28 02-23-11 68,600 4.01 12.63 5430
035D 56 03-23-11
Specified Strength: 3000 psi at 28 days
Notes:
Distribution:
Frank Taplin (franktaqlin(u)qmail.comj
Terry Bond-Beck Builders terrvCc�beckbuilds.com
Justin Orgill James Parker, PG, EIT
Field Technician Reviewed By
HP
�
HEPWORTH-PAWLAK GEOTECHNICAL
5020 County Road 154
Glenwood 5prings, CO 81601
Phone: 970-945-7988
Fax: 970-945-8454
hpgeo@hpgeotech.com
CONCRETE TEST REPORT
Frank Taplin Job No. 110 044A
1505 Rising Glen Road Date Cast: 12-29-10
Los Angeles, California 90069
Sheet: 1 of 1
Project: Taplin Residence, 115 Forest Road, Vail, Colorado
Placement Location: Building Perimeter and Pad Footings
Supplier: B8�B Time Batched: 8:58 am Load Size (Yds):
Truck No: 6003 Time Arrived: 10:50 am Yds Delivered:
Ticket No: 62136296 Time Placed: 11:00 am Yds Ordered:
Mix Design: Win 3 Master Exterior
Method of Placement: Pump Sample Point: Truck discharge
Time Sampled: 11:10 am Slump: 4 3/. inches
Air Temp: 18° Air Content: 5.0%
Concrete Temp: 72° Wet Unit Wt: 138.9 pcf
Water Added: 10 gallons added by contractor
Communication: The Contractor was informed of field test results.
Time Cylinders Cast: 11:20 am
Initial Cure: 5 days on site Field Storage: Heated job trailer
Date Stripped: 01-03-11
10
10
32
Compressive Strength Data
2010
Lab Age Load Diameter Area Compressive 2g Day
Date
Number Days Ibs. in. in2 Strength (psi) qy9_ (psi)
984A 7 01-05-11 31,000 4.01 12.63 2450
984B 28 01-26-11 43,800 4.01 12.63 3470
3360
984C 28 01-26-11 41,200 4.01 12.63 3260
984D 56 02-23-11 53,800 4.01 12.63 4260
I
Specified Strength: 3000 psi at 28 days
Notes:
Distribution:
Frank Taplin (franktaplin(a�gmail.com)
Terry Bond-Beck Building Company (terrvCa�beckbuilds.com)
Buzz Taplin (buzztaalin(�comcast.net)
James Parker Thomas J. Westhoff, CET
Field Technician Reviewed By