June 12, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. We observed the reinforcing steel placed for the composite topping on the terrace level
at Gridlines 46-72/C-R. We observed the reinforcing steel for bar size, bar number, spacing,
clearance and splice lap. The reinforcing steel appeared to be placed in general accordance
with the project plans and specifications. Jeff with PCL was notified of our observations.
We observed J.D. Steel stressing the post-tension tendons for the terrace level deck and
second level deck. We measured the elongations, observed the gauge pressures and recorded
the calibrations. Jeff with PCL was notified of our observations and measurements.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
June 13, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. We observed reinforcing steel placed for footing 1215 at 28/E and footing 1103 at 36/A.
We also observed the reinforcing steel placed for shear wall #8 at B57.2-61.5 / BGGG.2 —
BEEE.8 and columns 407 at 52.3/MMM, 408 at 57.2/MMM, 409 at 65/MMM, 410 at 63.7/MMM.
We observed reinforcing steel for bar size, bar number, spacing, clearance, and splice lap. The
reinforcing steel appeared to be placed in general accordance with the project p►ans and
specifications. Jeff with PCL was notified of our observations.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
June 17, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. While on-site, we observed PCL placing reinforcing steel for footings 1241, 1242, 1244-
1246 at gridlines RG/R9-11, R11/RG-RJ and C.9, C10, C11 and C12. We observed the
reinforcing steel for bar size, bar number, spacing, clearance, and splice lap. We observed the
reinforcing steel touching the soils in footing 1245 and water in 1242. These issues were
addressed before the pour. The reinforcing steel appears to be placed in general accordance
with the project plans and specifications. Scott with PCL was notified of our results and
observations.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
June 18, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. While on-site, we observed the drilled epoxy bars at A/43 to 39 for the C.7 grade beam
the holes were cleaned with a brush and compressed air. We observed the reinforcing steel for
bar size, bar number, hole depth, and epoxy placement. The reinforcing steel appears to have
been placed in general accordance with he project specifications and manufacturers
specifications. Jeff with PCL was notified of our results.
Sincerely,
GROUND Engineering Consultants, Inc.
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
June 19, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. While on-site, we observed reinforcing steel placed for the composite topping for 2nd
level deck of the parking garage at 42/C-BEE.6. We observed the reinforcing steel for bar size,
bar number, spacing, clearance, and splice lap. The reinforcing steel appears to be placed in
general accordance with the project plans and specifications. Scott with PCL was notified of our
results and observations.
We also observed PCL placing reinforcing steel for spread footing C.7 at Gridline C-A/43-36.
We observed reinforcing steel for bar size, bar number, spacing, clearance, splice lap. The
reinforcing steel appeared to be placed in general accordance with the project plans and
specifications. Jeff with PCL was notified of our results and observations.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
June 20, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. While on-site, we observed the reinforcing steel repairs using epoxy for the spread
footing at Gridlines 34.5/A. We observed PCL placing reinforcing steel with epoxy for hole
depth, hole diameter, cleanliness, placement of epoxy. The holes were brushed out and
compressed air was used prior to placing the reinforcing steel. The reinforcing steel and epoxy
appears to be placed in general accordance with the project plans and specifications.
We observed reinforcing steel placed for spread footer C6 at Gridline C-A/56-49 for bar number,
bar size, spacing, clearance, splice lap. The reinforcing steel appears to be placed in general
accordance with the project plans and specifications. Jeff with PCL was notified of our
observations.
We observed J.D. Steel placing reinforcing steel for footing 1228/F25 at Gridline M/28. We
observed the reinforcing steel for bar number, bar size, spacing, clearance, splice lap. The
reinforcing steel appears to be placed in general accordance with the project plans and
specifications. Jeff with PCL was notified of our observations.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
June 23, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. While on-site, we observed PCL placing reinforcing steel with epoxy for spread footings
D.18 at N-BJ6/21-23 and B27.4/D. We observed the reinforcing steel placed with epoxy for hole
depth, hole diameter, cleanliness, and placement of epoxy. The hole was cleaned with a brush
and compressed air prior to the placement of the epoxy. The reinforcing steel and epoxy
appears to be placed in general accordance with the project plans and specifications. Jeff with
PCL was notified of our observations.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
June 24, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. While on-site, we observed J.D. Steel placing reinforcing steel for footings 1235, 1234,
1236, and D19, D20, and shear walls southwest at 1228. We observed the reinforcing steel for
bar size, bar number, spacing, clearances, and splice lap. The reinforcing steel appears to be
placed in general accordance with the project plans and specifications. Jeff with PCL was
notified of our observations.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
June 25, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. While on-site, we observed J.D. Steel placing reinforcing steel for footings 1227, 1238,
1238, and columns 199, 200, 259, and 260. We observed the reinforcing steel for bar size, bar
number, spacing, clearances, and splice lap. We observed some clearance issues at Footer
1227, which was addressed promptly. The reinforcing steel appears to be in general
accordance with the project plans and specifications. Jeff with PCL was notified of our
observations.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
June 25, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. While on-site, we observed PCL placing reinforcing steel for plinth #199 at Gridline
B27.5/H. We observed the reinforcing steel for bar size, bar number, spacing, clearance, and
splice lap. The reinforcing steel appears to be in general accordance with the project plans and
specifications. Jeff with PCL was notified of our results and observations.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
June 26, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. While on-site, we observed reinforcing steel for footings 1240, 1243, and spread footer
D.24 and the composite topping for the parking structure at BZZ.9/B47.5-70. The reinforcing
steel was observed for bar size, bar number, spacing, clearance, and splice lap. The
reinforcing steel appears to be in general accordance with the project plans and specifications.
Jeff with PCL was notified of our observations.
We observed PCL placing reinforcing steel with epoxy along Gridlines R9/RJ for spread footer
D.24. We observed the steel placed with epoxy for hole depth, hole diameter, cleanliness, and
placement of epoxy. The holes were brushed and cleaned with compressed air prior to the
placement of the epoxy. The steel and epoxy appeared to be placed in general accordance
with the project plans and specifications. Jeff with PCL was notified of our observations.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
June 26, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. While on-site, we observed reinforcing steel placed for footing 1240 & 1243, and
spread footers D.24, D.25, plinths 189 & 200 and the composite topping for parking structure at
terrace level at W-BZZ.9/B475-72. The reinforcing steel was observed for bar size, bar number,
spacing, clearance, and splice lap. The reinforcing steel appears to be in general accordance
with the project plans and specifications. Jeff with PCL was notified of our observations.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
June 27, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. While on-site, we observed reinforcing steel placed for the 2nd level parking structure
composite topping at W-BZZZ.9/B47.5-70. We observed the reinforcing steel for bar size, bar
number, spacing, clearance, splice lap. We also observed the reinforcing steel placed for
footings 1237 and spread footing D.21 and D.22. Footing 1237 contained some standing water,
but this was removed before the pour. The reinforcing stee► for the topping slab and spread
footings appears to be placed in general accordance with the project plans and specifications.
Jeff with PCL was notified of our observations.
Jeff with PCL was notified of our observations.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
June 28, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. While on-site, we observed PCL placing reinforcing steel with epoxy along R9/RJ for
spread footers. We observed the reinforcing steel placed with epoxy for hole depth, hole
diameter, cleanliness, and placement of epoxy. The holes were cleaned with a brush and
compressed air prior to the placement of epoxy. The reinforcing steel and epoxy appeared to
be placed in general accordance with the project plans and specifications. We notified Jeff with
PCL of our observations.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
June 30, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. While on-site, we observed PCL placing reinforcing steel for Stem Wall at Footer 1238,
1240, and 1237. Also we observed the reinforcing steel in spread footer at 1240. We observed
the reinforcing steel for bar size, bar number, spacing, clearance, and lap splice. The
reinforcing steel appears to be placed in general accordance with the project plans and
specifications. Jeff with PCL was informed of our observations.
We observed PCL placing flow fill around the footers 1240-1246. It is our understanding that
PCL elected to use fiow fill because of a near by electrical trench and ground water issues.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
July 1, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. While on-site, we observed PCL placing reinforcing steel with epoxy for the Mechanical
Pads 12 and 13 at 72/H-R. We observed the reinforcing steel placed with epoxy for hole depth,
hole diameter, cleanliness, and placement of epoxy. The holes were brushed and cleaned with
compressed air prior to the placement of the epoxy. The reinforcing steel and epoxy appears to
be placed in general accordance with the project plans and specifications. Jeff with PCL was
notified of our observations.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
July 2, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. We observed reinforcing steel for the Terrace Level composite topping for parking
structure at Gridlines BTT.9-BEE.6/56-70. We observed the reinforcing steel for bar size, bar
number, spacing, clearance, and splice lap. The steel appears to be placed in general
accordance with the project plans and specifications. Jeff with PCL was notified of our results.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
July 8, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. We observed PCL placing reinforcing steel for footings 1028 at B40.3/BMMM.4, 1034
at B40.3/BEEE.8, 1059 at B40.3/BTT.9. We observed the reinforcing steel for bar size, bar
number, spacing, clearance, and splice lap. The reinforcing steel appears to be placed in
general accordance with the project plans and specifications. Jeff with PCL was notified of our
observations.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
July 9, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. We observed PCL placing reinforcing steel for footings 1060 at SS/40, and 1062 at
BTT.9/34. We observed the reinforcing steel for bar size, bar number, spacing, clearance, and
splice lap. Footing 1060 had some clearance issues which will be addressed before the pour.
The reinforcing steel appears to be placed in general accordance with the project plans and
specifications. Jeff with PCL was notified of our observations.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
July 10, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. We observed PCL placing reinforcing steel for footings 1033 at BZZ.9 and 1061 at
34/SS. We observed the reinforcing steel for bar size, bar number, spacing, clearance, and
splice lap. Footings 1061 had clearance issues which were addressed promptly. The
reinforcing steel appears to be placed in general accordance with the project plans and
specifications. Jeff with PCL was notified of our observations.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
July 11, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. We observed PCL placing reinforcing steel for footings 1031 at 34/BZZE.8 and 1032 at
34/BAAA.2. We observed the reinforcing steel for bar size, bar number, spacing, clearance,
and splice lap. The reinforcing steel appears to be placed in general accordance with he project
plans and specifications.
Also we observed PCL placing reinforcing steel with epoxy along 70/BPP.9. We observed the
reinforcing steel placed with epoxy for hole depth, hole diameter, cleanliness, and placement of
epoxy. The holes were brushed and compressed air was used prior to the placement of the
epoxy. The reinforcing steel and epoxy appears to be placed in general accordance with the
plans and specifications. Jeff with PCL was notified of our observations.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
July 15, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. We observed the reinforcing steel placed for slab on grade at M-P/66-70. We observed
the reinforcing steel for bar size, bar number, spacing, cleanliness, and splice lap. The
reinforcing steel appears to be placed in general accordance with the plans and specifications
Also we observed PCL placing reinforcing steel with epoxy along spread footers B.6 at
BSSS.3/B42 and for the mechanical pads 12 and 13 at 69/P-Y. We observed the reinforcing
steel placed with epoxy for hole depth, hole diameter, cleanliness, placement of epoxy. The
reinforcing steel and epoxy appears to be placed in general accordance with the plans and
specifications. Jeff with PCL was notified of our observations.
We observed PCL placing reinforcing steel for footing B.6 at BSSS.3/B35, 1029 at
B34.5/BSSS.3, 1030 at B34.5/BNNN.8, 1104 at B34.5/BNNN.8, and 1169 at B29.5/BEEE.8.
We observed the reinforcing steel for bar size, bar number, spacing, clearance, and splice lap.
The reinforcing steel and epoxy appears to be placed in general accordance with the plans and
specifications. Jeff with PCL was notified of our observations.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
July 16, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. We observed the reinforcing steel placed for footing 1168 at B29.5/BAAA.2 and 1170 at
B29.5/BTT.9. We observed the reinforcing steel for bar size, bar number, spacing, clearance,
and splice lap. The reinforcing steel at 1170 had clearance issues but was addressed. The
reinforcing steel appeared to be placed in general accordance with the project plans and
specifications.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
July 18, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. We observed the reinforcing steel for slab on grade at pour 3 at 65/E#-BTT.9 and pour
2A at BTT.-BAAA.2/48. We observed the reinforcing steel for specified bar size, bar number,
spacing, clearances and splice lengths. The reinforcing steel appears to be placed in general
accordance with the project plans and specifications.
Also we observed reinforcing steel for footings 1105 at 27.8/BSSS.4, 1167 at B25.8/BAAA.2,
1173 at B25.8/BTT.9, and Spread Footer B.7 at BSSS.4/27-34. The reinforcing steel appears to
be placed in general accordance with the project plans and specifications. Jeff with PCL was
notified of our observations.
We observed reinforcing steel with epoxy at Spread Footer B.7 at BSSS.4/27-34. We observed
the reinforcing steel placed with epoxy for hole depth, diameter, cleanliness, and placement of
epoxy. The holes were brushed out and blown with compressed air prior to the epoxy. The
reinforcing steel and epoxy appears to be placed in general accordance with the project plans
and specifications. Jeff with PCL was notified of our observations.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
July 22, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. We observed PCL placing reinforcing steel for S.O.G. at pour 3, Mechanical Room.
We observed the reinforcing steel for specified sizes, bar number, spacing and splice lengths.
The reinforcing steel appears to be placed in general accordance with the project plans and
specifications. Jeff with PCL was notified of our observations.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
July 23, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. We observed PCL placing reinforcing steel for footings 1106 at B25.8/BNNN.4, and
1166 at B25.8/BEEE.8. We observed the reinforcing steel for bar size, bar number, spacing,
clearance, and splice lap. The reinforcing steel appears to be placed in general accordance
with the project plans and specifications.
Also we observed reinforcing steel placed with epoxy at Spread Footer 1105 at 27.8/BSSS.3.
We observed the reinforcing steel placed with epoxy for hole depth, hole diameter, cleanliness,
and placement of epoxy. The holes were brushed out and compressed air was used prior to the
placement of epoxy. The reinforcing steel with epoxy appears to be placed in general
accordance with the project plans and specifications. Jeff with PCL was notified of our
observations.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
July 24, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. We observed PCL placing reinforcing steel for S.O.G. at 48-63/W-C and for footer B.8
at BSSS.3/B25.8 and 1107 at 23/BSSS.3 and 1165 at 23/BEEE.8. We observed the reinforcing
steel for bar size, bar number, spacing, clearance and splice lengths. The reinforcing steel
appears to be placed in general accordance with the project plans and specifications. Jeff with
PCL was notified of our observations.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
July 25, 2008
Job Name: Materials Testing, Ritz Carlton
Residences, Vail, Colorado
Job Number: 08-6502
Mr. Dave Williams
Vail Resorts Development Company
953 S. Frontage Rd. West, Suite 215
Vail, Colorado 81657
Attn: Mr. Williams,
As requested, a representative of GROUND visited the project to perForm construction materials
testing. We observed PCL placing reinforcing steel for Footer 1165 at B23.4/BAAA.2. We
observed the reinforcing steel for bar size, bar number, clearance, spacing, and splice lengths.
The reinforcing steel appears to be placed in general accordance with the project plans and
specifications. Jeff with PCL was notified of our observations.
Sincerely,
GROUND Engineering Consultants, Inc.
James Ford
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721