HomeMy WebLinkAboutMiddle Creek Affordable Housing 2003.PDF /
l f `� __ \
�s��
1 ,
1Vliddle Creek TCO
General Conditions
• During the TCO all construction matenal will be inside 1 of the 2 fenced
Construction matenal areas
• These areas will be properly signed"Construction personnel only"
• All construction personnel will be required to wear hard hats These will
-- be required both for safety(per Shaw safety requirements) and so that
• Shaw management is able to readily identify construction workers from
the public.
• Shaw personnel will inspect construction fence daily, both inside the
buildmg and outside, to mamtam safety, secunty, and the cleanest
appearance possible
Construction and Resident parking -
• Construction parkmg will be behmd fence in the garage, surface
parking north of"A"buildmg, or at the ELC only.
• Resident parkmg will be m all open parking spaces in buildmg
"C" covered parkmg
Interior/Exterior Work
Exterior
1 Work to be done m exit passages whether remedial or otherwise
will occur between the hours of 9 00 AM and 4 00 PM Monday
through Friday
+, 2 All work to be done m these areas will be done with the proper
cautionary signage and public protection in place
\ 3 As work progresses towards unit completion in the highlighted
\ "Saddle bag"unrts. It will be necessary to move fixtures,
4
�
� �
- �
✓ -_ -
a� �
,
, appliances, material, ETC, into these units. This will be scheduled
through Shaw The same signage required in item#2 will be
utilized, and matenal will be stocked by floor only.
4. Work remaimng in these areas consists of the following•
1 Mmor stucco and pamt touch up
2 Cleanmg
3 Movmg necessary matenal to saddlebags to finish mterior
umt work
Interior
North, southeast, and south saddlebags are complete through
drywall The work that still needs to be done is the following
1. Tape and texture
2 Pamt
3 Casework and tnm
4. Mep tnm
5. Carpet/Vmyl
6. Hardware/accessories
7. Appliances
�.- � , �.r
� �'�'..Ir 1 -- " ' _
,/
� !
1 1
Fire Alarm Remediation
The following list is the order in which the units will be prepared and inspected for fire
department approval
• The apartments will be done three at a time
• In each apartment there will be 2-3 electricians, a person to patch drywall, and a
representative from Middle Creek Apartments
• The fire alarm devices will be mstalled ��o��� �
� ��� ` � L r �
• The alarms will be pretested with the doors on �i� ��,,P�
• Doors will be removed until the alarm can be tested by the fire department
• A test will then be scheduled with fire department by pods
• Doors will be remstalled for this test
• After the alarms are certified by the fire department doors will remain in place