HomeMy WebLinkAboutB10-0168 special inspection January 11, 2011WESTERN STATES
INSPECTION
INSPECTION REPORT
8494 WHEATGRASS CIRCLE
PARKER, CO 80134
303 - 9578436
PAGE 1 OF 3
CLIENT BECK BUILDING COMPANY
PROJECT /JOB# B10-0168
DATE 1 -11 -11
HOURS OF SHIFT 10:00 AM To 4:00 PM
MILEAGETO 100 MILEAGE FROM 100
INSPECTOR ROBERT H. POLLOCK
ASSISTANT N/A
PER DIEM YES NO X
REMARKS:
CLIENT PO # ANGELOVICH - DUNN
CODE AWS D 1 .1 & D 1.3 / AISC /113C
SPECIFICATION PROJECT SPECS. / ASTM
DAY OF WEEK TUESDAY
TOTAL HOURS TODAY (6)
TOTAL MILEAGE 200
CLIENT REP. TOM SOLAWETZ
REPORT # AD - 03
`A - D U N N'
"725 FORREST RD.'
* VAIL, CO.`
1) TRAVEL TO PROJECT SITE, AS REQUESTED.
2) REVIEW APPROVED PROJECT SPECIFICATIONS & DRAWINGS AVAILABLE AT PROJECT SITE.
3) CONDUCT THE REQUIRED "STRUCTURAL STEEL & WELDING" SPECIAL INSPECTIONS FOR SHOP A ND /
FIELD APPLICATIONS.
4) CONDUCT SPECIAL INSPECTION OF HIGH STRENGTH BOLTING (ASTM A325 & / OR A490) AS REQU IRED.
55) SEE ATTACHED 'ERECTIO INSPECTIO R F D
AWS CWI # 10090331 ~ (CERTIFIED WELDING INSPECTOR)
ICC SPECIAL INSPECTOR # 878521 - S 1 & S2 - (STRUCTURAL WELDING & BOLTING)
SIGNATURE ROBERT H. POLLOCK N.
]CC SPECIAL INSPECTOR
WESTERN STATES
INSPECTION
STRUCTURAL STEEL
8494 WHEATGRASS CIRCLE
PARKER, CO 80134
303- 957 -8436
ERECTION INSPECTION REPORT
CLIENT BECK BUILDING COMPANY
PROJECT /JOB # B10-0168
DATE 1 -11 -11
HOURS OF SHIFT PG. 1 PM TO PG. 1 PM
MILEAGE TO PG. 1 MILEAGE FROM PG. 1
INSPECTOR ROBERT H. POLLOCK
ASSISTANT N/A
PER DIEM YES NO X
PAGE 2 OF - 3
CLIENT PO # ANGELOVICH - DUNN
CODE AWS D 1 .1 & D 1.3 / AISC / IBC
SPECIFICATION PROJECT SPECS. / ASTM
DAY OF WEEK TUESDAY
TOTAL HOURS TODAY PG. 1
TOTAL MILEAGE PG. 1
CLIENT REP. TOM SOLAWETZ
REPORT # AD - 03
ITEM
DESCRIPTION/ REMARKS
DISPOSITION
ACCEPTED
REJECTED
O.D. LIST
YEs /No
`ANGELOVICH - DUNN'
1
CONDUCT VISUAL INSPECTION OF WELDING REQUIRED AT
X
PREVIOUSLY IDENTIFIED CONNECTIONS HAVING MIS - ALIGNED
BOLT HOLES. CONNECTIONS HAVE BEEN WELDED AS PER DETAILS
ON SKETCHES PROVIDED. (SK7 & SK8, DATED 12-29-10)
(REF. WSI REPORT DATED 12-15-10, ITEM # 1 [A] )
2
CONDUCT VISUAL RE- INSPECTION OF BOLTED CONNECTIONS AT
X
ROOF TRUSSES. ALL BOLT HARDWARE HAS BEEN PROPERLY
INSTALLED.
(REF. WSI REPORT DATED 12-15-10, ITEM # 1 [BI)
3
CONDUCT VISUAL RE- INSPECTION OF BEAM COPES PREVIOUSLY
X
IDENTIFIED AS HAVING UNACCEPTABLE RADIUS. CORRECTIONS
HAVE BEEN MADE TO COMPLY WITH AISC CRITERIA.
(REF. WSI REPORT DATED 10-7-10, ITEM # 3 )
4
CERTIFCATE OF COMPLIANCE ATTACHED.
INFO.
AWS CWI # 10090331 - (CERTIFIED WELDING INSPECTOR)
ICC SPECIAL INSPECTOR # 878521 - S 1 & S2
(STRUCTURAL WELDING & BOLTING)
SIGNATURE ROBERT H. POLLOCK R ,
(ICC SPECIAL INSPECTOR)
3 oF3
8494 WHEATGRASS CIRCLE
W451 PARKER, CO 80134
303 - 9578436
WESTERN STATES
INSPECTION CO.
CERTIFICATE OF COMPLIANCE
DATE: JANUARY 1 1 , 201 1
CLIENT: BECK BUILDING CO. (B 1 0-0 1 68)
PROJECT: ANGELOVICH - DUNN REMODEL
INSPECTION: "STRUCTURAL STEEL & WELDING"
THIS IS TO CERTIFY THAT WESTERN STATES INSPECTION (WSI), TO THE BEST OF MY
KNOWLEDGE HAS COMPLIED WITH THE REQUIREMENTS OF THE PURCHASE AGREEMENT /ORDER
TO PROVIDE THE REQUIRED INSPECTION OF "STRUCTURAL STEEL & WELDING ". THE PROJECT
REFERENCED ABOVE SHALL BE CONSIDERED IN COMPLIANCE WITH ALL APPLICABLE GOVERNING
CODES, STANDARDS, SPECIFICATIONS AND WORKMANSHIP PROVISIONS, AS WELL AS THE
CONTRACT DOCUMENTS.
WESTERN STATES INSPECTION
ROBERT POLLOCK
ICC SPECIAL INSPECTOR
��( l (� I S' 6
.h p
0 4�10.
G<�bl tech
HEPWORTH - PAWLAK GEOTEGHNICAL
December 31, 2010
Michael Angelovich
3600B N. Capital of Texas Highway
Suite 350
li Ida: 7 � i
Austin, Texas 78746
(mangelo vi ch @npraust in. com)
Job No. 110 148A
Subject: Additional Observation of Underdrain Installation, Basement Addition to
Existing Residence, Lot 6A, Block 2, Filing 6, Vail Village, 725 Forest
Road, Vail, Colorado
Dear Mr. Angelovich:
As requested by Isaac Barela with Beck Builds, a representative of Hepworth - Pawlak
Geotechnical observed the underdrain installation as it continued at the subject site on
December 29, 2010 to evaluate compliance with the design. The findings of our
observations and recommendations are presented in this report.
We previously observed the partial foundation excavation for the basement addition
which included observation of the drain mat material behind the initial four new basement
wall areas (sequenced construction) and submitted our findings in a report dated June 10,
2010, Job No. 110 148A. The design for the underdrain system was provided in our
report dated October 8, 2010 under the above job number.
At the time of our December 29 site visit, the remaining basement wall areas had been
constructed and backfilled, but the basement floor slab has not been constructed.
During our visit, we observed the below basement floor slab piping to be in -place as
generally reconunended in our design. Some modifications to the piping layout from the
schematic alignment recommended in our report were needed per the contractor due to
footings and utilities. The piping was a minimum 1 foot below proposed floor slab
elevation and sloped to the sump in the mechanical room area. There were separate non -
perforated pipes below the floor slab area for drainage from the window well areas. We
also observed drain mat material extending from below all basement wall areas to the
edges of the adjacent new footings.
The underdrain system appears to have been installed as generally recommended by us.
The modifications to the drain layout should not affect the drain performance and are
acceptable. The backfill of the pipe trenches and below the floor slab should consist of
the previously specified drain gravel. The drain mat material should continuously
l .li it`I' 'l' } 7•{ l i `} V4 l .i!�t rl !,�i `•� �,s �(�;�
1"A Jil J ll
Michael Angelovich
December 31, 2010
Page 2
connect with the underslab drain gravel. Filter fabric can be placed around the perorated
pipe sections and trench drain gravel backfill as needed. Other recommendations
presented in our previous report which are applicable should also be observed.
If you have any questions or need further assistance, please call our office.
Sincerely,
HEPWORTH — / PAAWLAK CAQT4jQINICAL, INC.
David A. Young, P. -216
DAY/ksw °sei5',S'"°.....•,•�, qq�
I0
cc: Beth Levine, Architect — bethOwbethlevinearchitect.com
Beck Building Company — Isaac Barela ( Isaac Dbeckbuilds.com
Beck Building Company — Tom Solawetz ( tomt(beckbuilds.com )
KRM Consultants - Tim Hennum ( tdh&krmconsultants.coin)
Job No. 110 148A
' gtech
January 21, 2011
Job Name: Materials Testing Services, 725
Forest Road, Anglovich -Dunn
Remodel, Vail, Colorado
Job Number: 10 -6591
Mr. Tom Solawetz
Anglovich /Dunn
c/o Beck Building Company
PO Box 4030
Vail, CO 81658
Attn: Mr. Solawetz
For the period ending January 15, 2011, representatives of GROUND Engineering were on site
to provide materials testing services and observations at times scheduled by the Contractor,
Subcontractor and /or Owner. The reports have been completed in the field on a daily basis as
work has been completed. The contractor has been notified of the testing results. This summary
report includes the observation reports as well as the materials test results.
Please do not hesitate to contact this office if you have any questions concerning these reports.
Sincerely,
GROUND ENGINEERING CONSULTANTS, INC.
Evan Kuhn, CET
SROUYL
ENGINEERING CCINSULTRNTS INC.
101A Airpark Dr., Unit 9, PO Box 464, Gypsum, CO 81637 Phone (970) 524 -0720 Fax (970) 524 -0721 www.groundeng.com
Office Locations: Englewood . Commerce City Loveland Granby Gypsum Grand Junction Casper, WY
725 Forest Road
Vail, Colorado
Observation Reports
Job #10 -6591 GROUND Engineering Consultants, Inc. period ending 111512011
GROUND
ENGINEERING CONSULTRNTS
October 4, 2010
Job Name: Materials Testing,
Anglovich -Dunn
Colorado
Job Number: 10 -6591
Mr. Tom Solawetz
Anglovich /Dunn
c/o Beck Building Company
PO Box 4030
Vail, CO 81658
Attn: Mr. Solawetz,
725 Forest Road,
Remodel, Vail,
As requested, a representative of GROUND visited the project to perform construction materials
testing. The footings had not been inspected by the City of Vail when we arrived. We waited
until 4:00 PM, at which point Ron with Hedrick Construction notified us that they would not be
able to get concrete today and would reschedule the pour for tomorrow.
Sincerely,
GROUND Engineering Consultants, Inc.
Stephen Buckeridge
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood, CO 80112 -5412 Commerce City, CO 80022 -1834 Gypsum, Colorado 81637
Tel: (303) 289 1989 Tel: (303) 289 1989 Tel: (970) 524 0720
Fax: (303) 289 1686 Fax: (303) 289 6742 Fax: (970) 524 0721
GROUND
ENGINEERING CONSULTRNTS
October 6, 2010
Job Name: Materials
Remodel;
Colorado
Job Number: 10 -6591
Mr. Tom Solawetz
Anglovich /Dunn
c/o Beck Building Company
PO Box 4030
Vail, CO 81658
Attn: Mr. Solawetz
Testing, Anglovich /Dunn
725 Forest Road, Vail,
As requested, a representative of GROUND visited the project to perform construction materials
testing. We collected concrete cylinders that were previously cast and returned them to our
office for future compressive strength testing. These results will be forwarded upon completion.
Sincerely,
GROUND Engineering Consultants, Inc.
Stephen Buckeridge
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood, CO 80112 -5412 Commerce City, CO 80022 -1834 Gypsum, Colorado 81637
Tel: (303) 289 1989 Tel: (303) 289 1989 Tel: (970) 524 0720
Fax: (303) 289 1686 Fax: (303) 289 6742 Fax: (970) 524 0721
GROUND
ENGINEERING CONSULTRNTS
October 18, 2010
Job Name: Materials Testing, Anglovich /Dunn
Remodel; 725 Forest Road, Vail,
Colorado
Job Number: 10 -6591
Mr. Tom Solawetz
Anglovich /Dunn
c/o Beck Building Company
PO Box 4030
Vail, CO 81658
Attn: Mr. Solawetz
As requested, a representative of GROUND visited the project to perform construction materials
testing. We observed holes drilled into the existing southeast foundation wall for the south stair,
drilled by Hedrick Construction. We observed the holes for depth, diameter and general
cleanliness. The holes appeared to be relatively clean and in general compliance with the site
specifications for depth and diameter.
Isaac with Beck was informed of our observations.
Sincerely,
GROUND Engineering Consultants, Inc.
Kevin McClure
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood, CO 80112 -5412 Commerce City, CO 80022 -1834 Gypsum, Colorado 81637
Tel: (303) 289 1989 Tel: (303) 289 1989 Tel: (970) 524 0720
Fax: (303) 289 1686 Fax: (303) 289 6742 Fax: (970) 524 0721
GROUND
ENGINEERING CONSULTFINTS
November 2, 2010
Job Name: Materials Testing, Anglovich /Dunn
Remodel; 725 Forest Road, Vail,
Colorado
Job Number: 10 -6591
Mr. Tom Solawetz
Anglovich /Dunn
c/o Beck Building Company
PO Box 4030
Vail, CO 81658
Attn: Mr. Solawetz
As requested, a representative of GROUND visited the project to perform construction materials
testing. We observed holes drilled by Hedrick into the existing foundation walls for the south
window well and north foundation wall extension. We observed the holes for depth, diameter
and overall cleanliness. The holes appeared to be in general compliance with the site
specifications of 6" depth for #5 dowels as well as the epoxy manufacturers recommendations
of Hilty HY 150.
Isaac with Beck was informed of our observations.
Sincerely,
GROUND Engineering Consultants, Inc.
Kevin McClure
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood, CO 80112 -5412 Commerce City, CO 80022 -1834 Gypsum, Colorado 81637
Tel: (303) 289 1989 Tel: (303) 289 1989 Tel: (970) 524 0720
Fax: (303) 289 1686 Fax: (303) 289 6742 Fax: (970) 524 0721
GROUND
ENGINEERING CONSULTRNTS
November 2, 2010
Job Name: Materials
Remodel;
Colorado
Job Number: 10 -6591
Mr. Tom Solawetz
Anglovich /Dunn
c/o Beck Building Company
PO Box 4030
Vail, CO 81658
Attn: Mr. Solawetz
Testing, Anglovich /Dunn
725 Forest Road, Vail,
As requested, a representative of GROUND visited the project to perform construction materials
testing. We observed Hedrick Construction had drilled holes into the existing foundation walls
for the dowels to be placed for the northeast and south window wells. We observed the drilled
holes for size, spacing, depth and general cleanliness. We observed Hedrick Construction
placing Hilti Hit -Hy 150 max epoxy and #5 reinforcing dowels into the drilled holes at the
previously described locations. Based on our observations, the drilled holes, epoxy and
reinforcing dowels appeared to have been constructed in general conformance with the project
plans and site specifications.
Isaac with Beck was informed of today's observations.
Sincerely,
GROUND Engineering Consultants, Inc.
Jon Noble
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood, CO 80112 -5412 Commerce City, CO 80022 -1834 Gypsum, Colorado 81637
Tel: (303) 289 1989 Tel: (303) 289 1989 Tel: (970) 524 0720
Fax: (303) 289 1686 Fax: (303) 289 6742 Fax: (970) 524 0721
GROUND
ENGINEERING CONSULTRNTS
November 2, 2010
Job Name: Materials Testing, Anglovich /Dunn
Remodel; 725 Forest Road, Vail,
Colorado
Job Number: 10 -6591
Mr. Tom Solawetz
Anglovich /Dunn
c/o Beck Building Company
PO Box 4030
Vail, CO 81658
Attn: Mr. Solawetz
As requested, a representative of GROUND visited the project to perform construction materials
testing. We collected concrete cylinders that were previously cast and returned them to our
office for future compressive strength testing. These results will be forwarded upon completion.
Sincerely,
GROUND Engineering Consultants, Inc.
Jon Noble
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood, CO 80112 -5412 Commerce City, CO 80022 -1834 Gypsum, Colorado 81637
Tel: (303) 289 1989 Tel: (303) 289 1989 Tel: (970) 524 0720
Fax: (303) 289 1686 Fax: (303) 289 6742 Fax: (970) 524 0721
725 Forest Road
Vail, Colorado
Concrete
Compressive Strength and Field Test Results
Job #10 -6591 GROUND Engineering Consultants, Inc. period ending 1/1512011
GROUND
ENGINEERING CONSULTRNTS
CONCRETE FIELD PROPERTIES AND
COMPRESSIVE STRENGTH TEST RESULTS
Report Number
1
Job Name
725 Forest Road, Anglovich -Dunn Remodel
Job Number
10 -6591
Report Date
October 5, 2010
Client:
Anglovich -Dunn C/O Beck Building Inc.
Address:
PO Box 4030
Vail, Colorado 81658
Attn:
Mr Tom Solawetz
On the date specified above, Ground Engineering Consultants, Inc (GROUND) was requested to provide materials testing services for this project on sampled concrete. GROUND
performed testing in general accordance with the frequencies required and / or as requested by the contractor or onsite representative of the owner. The following information includes
related site observations for the concrete placement and to the best of our knowledge including information from site representatives. As we provide periodic services on most projects
and may not be onsite during the entire concrete placement, the contractor should be consulted for precise details. This report includes the results of the tests we performed and our
observations, however, it is the responsibility of the contractor to perform construction and provide materials that meet the project plans and specifications
Placement Date: 10/05/10 Specifications
Concrete Placed By: Hedrick Construction Required Strength (psi) 3000
Concrete Supplier / Mix ID: LaFarge /RMXZP40GF87 Slump Range (in.)
Total Cubic Yards Placed: 51/2 Air Range ( %)
Weather / Temperature Overcast/60's Temperature ( °F) 50-90
Placement Location: Footings for Basement Addition
Methods Employed: Tailgate to Pump Truck
Test Sample Location
Truck No.
Ticket No.
Batch Time
Test Time
Slump or
Spread (in.)
Air Content
( %)
Concrete
Temp: °F
Unit Weight
(pcf)
Water Added
(gallons)
Footing at NE comer of basement addition
4780640
85909218
3:05PM
3:45PM
41/2
4.1
70
138.4
11/02/10
Test Age
7
28
Type of Fracture
T5
T5
Notification of field test results:
Isaac with
Beck
Compressive Strength Results (ASTM C39)
86060
Cylinder Diameter (in.)
4.00
4.00
Cross Secional Area (sq in.)
12.57
12.57
Maximum Load
64860
86670
Compressive Strength (psi)
5160
6900
Test Date
10/12/10
11/02/10
Test Age
7
28
Type of Fracture
T5
T5
and Ron with Hedrick Construction
Cylinders Cast from ticket: 85909218
4.00
4.00
12.57
12.57
86060
88410
6850
7040
11/02/10
11/02/10
28
28
T5
T5
Lab ID 1896
Additional Comments As requested, we arrivewd on site for a scheduled 3:OOPM pour. The concrete did not arrive until approximately 3:40PM. Field Technician Jon Noble
Corporate Office
41 Inverness Dr East
Englewood, CO 80112
Tel:(303)289 1989
Fax:(303)289 1686
Offices: Denver, Loveland, Western Slope, Granby
Gypsum Office
P.O Box 464
Gypsum CO 81637
Tel:(970) 524 0720
Fax:(970) 524 0721
GROUND
ENGINEERING CONSULTFiNTS
CONCRETE FIELD PROPERTIES AND
COMPRESSIVE STRENGTH TEST RESULTS
Job Name
725 Forest Road, Anglovich -Dunn Remodel
Job Number
10 -6591
Client:
Anglovich -Dunn C/O Beck Building Inc.
Address:
PO Box 4030
Vail, Colorado 81658
Report Number Report Date Attn:
2 November 8, 2010 Mr Tom Solawetz
On the date specified above, Ground Engineering Consultants, Inc (GROUND) was requested to provide materials testing services for this project on sampled concrete. GROUND
performed testing in general accordance with the frequencies required and / or as requested by the contractor or onsite representative of the owner. The following information includes
related site observations for the concrete placement and to the best of our knowledge including information from site representatives. As we provide periodic services on most projects
and may not be onsite during the entire concrete placement, the contractor should be consulted for precise details. This report includes the results of the tests we performed and our
observations, however, it is the responsibility of the contractor to perform construction and provide materials that meet the project plans and specifications
Placement Date: 11/08/10 Specifications
Concrete Placed By: Hedrick Construction Required Strength (psi) 3000
Concrete Supplier / Mix ID: B &B/37512691 Slump Range (in.)
Total Cubic Yards Placed: 10 Air Range ( %)
Weather / Temperature Partly Cloudy /50's Temperature ( °F) 50-90
Placement Location: Basement Walls in NW corner of Addition, Footer in SW corner of Addition
Methods Employed: Pump Truck, Vibration, Hand Finish
Test Sample Location
Truck No.
Ticket No.
Batch Time
Test Time
Slump or
Spread (in.)
Air Content
( %)
Concrete
Temp: °F
Unit Weight
(pcf)
Water Added
(gallons)
Basement Wall, T E of NW comer
6038
B2136128
12:45PM
1:30PM
5
7.0
68
135.4
Maximum Load
50860
64520
73990
74680
Compressive Strength (psi)
4050
5130
5890
5940
Test Date
11/15/10
12/06/10
12/06/10
12/06/10
Test Age
7
28
28
28
Type of Fracture
T5
T5
T5
T5
Additional Comments
Field Technician Jon Noble
Notification of field test results:
Isaac with
Beck
Compressive Strenqth Results (ASTM C39)
Cylinders Cast from ticket: B2136128 Lab ID 2011
Cylinder Diameter (in.)
4.00
4.00
4.00
4.00
Cross Secional Area (sq in.)
12.57
12.57
12.57
12.57
Maximum Load
50860
64520
73990
74680
Compressive Strength (psi)
4050
5130
5890
5940
Test Date
11/15/10
12/06/10
12/06/10
12/06/10
Test Age
7
28
28
28
Type of Fracture
T5
T5
T5
T5
Additional Comments
Field Technician Jon Noble
Corporate Office
41 Inverness Dr East
Englewood, CO 80112
Tel:(303)289 1989
Fax:(303)289 1686
Offices: Denver, Loveland, Western Slope, Granby
Gypsum Office
P.O Box 464
Gypsum CO 81637
Tel:(970) 524 0720
Fax:(970) 524 0721