HomeMy WebLinkAboutRoad Improvement Letter 010710OVAKU
TOWN Department of Public Works & Transportation
1309 Elkhorn Drive
Vail, CO 81657
970-479-2158
Fax: 970-479-2166
wuw. vailgov. com
January 7, 2010
Vail Development 09 LLC
Attention: Michael M. Rossi, PE, LEED AP
Dear Mike,
The Vail Development 09 LLC is currently under contract with Hyder Construction for the construction of
the Four Seasons and adjacent road improvements in Vail. The Town has determined the need to install
additional concrete pan, curb and storm sewer along the South Frontage Road in conjunction with your
work. The Town requests that the Vail Development 09 LLC complete the Town concrete/storm sewer
work for the Town of Vail thru Vail Development's 09 LLC contract with Hyder Construction in
accordance with the change order as presented by Hyder Construction as attached.
The Town agrees to reimburse Vail Development 09 LLC for the above referenced work within 30 days of
invoice from Vail Development 09 LLC. The Town will provide all construction inspection, design and
surveying for the above referenced work. The total estimated cost of work is $68,788.00. The Town will
issue a separate Public Way permit to Hyder Construction for this work to ensure all Town specifications
are followed and that the required two year warranty will be between the contractor and the Town.
Please acknowledge acceptance of this agreement by signing. If you have any questions please call Tom
Kassmel at 479-2235.
Greg Hall Date
Town of Vail
Director of Public Works
Michael M. Rossi, PE, LEED AP
Authorized Project Representative
Vail Development 09 LLC
1/7/10
HYDER BID ESTIMATE
co~sriz.c-rloti Iv<-.
,PROJECT: SOUTH FRONTAGE ROAD - VAIL COLORADO
Work for Town of Vail
CODE CATEGORY
012010 Project Management
TY
20
NIT
HR
N PRICE
$ 85.00
OTAL PRICE
$ 1,700.00
012020
Supervision
40
HR
$ 65.00
$ 2,600.00
012020
Misc. GC Expenses - Company Vehicle, Diem, Reproducibles
1
LS
$ 500.00
$ 500.00
010510
Surveying
1
LS
$ 1,250.00
$ 1,250.00
015550
Traffic Control
1
LS
$ 5,503.00
$ 5,503.00
015810
Winter Conditions
1
LS
$ 2,342.00
$ 2,342.00
023001
B+B - Excavation, sub prep, storm sewer, backfill and paving
1
LS
$ 27,318.00
$ 27,318.00
023001
B+B - Excavation - Added 2x2 inlet per TOV direction
1
LS
$ 1,924.00
$ 1,924.00
027510
Concrete Flatwork
1
LS
$ 19,861.00
$ 19,861.00
044001
Paver sidewalk tie in
1
LS
$ 1,000.00
$ 19000.00
Landscaping-(Excluded)
$ -
$ -
Snowmelt - (Excluded)
$ -
$ -
Electrical - (Excluded)
$ -
$ -
$ -
CDOT Bond
1.4
%
$ 896.00
Fee
6
%
$ 3,894.00
$ -
IN-HOUSE ESTIM
ATED CO
NSTRU
CTION COST:
$ 68,788.00
ALTERNATES
None $
TOV Frontage Road Costs 2009.11.20.x1sx/Budget Estimate CO backup sheet 1 11/20/2009
1
i
P.O.Box 4sru
•
Ilk-
Eagle, CO 81631
x
y
Ph. 970-3/-'8-17,34
c
Fax 970-328-1735
Item Price Summary Report
Project Name:
TOV Work For South Frontage Road
Customer.
Town Of Vail
Improvements
Job Number:
Billing Address:
75 S. Frontage Rd West
Bid As:
GC
Vail, CO 81657
Estimator.
Mpettit
Phone:
479-2160
Project Address:
Contact:
Tom Kassmel
Completion Date:
Description
Job Cost ID Bid Quantity
UM
Unit Bid Price
Total Bid Price
1 - 01 - Erosion Control(inlet Protection)
1.00
LS
$400.00
$400.00
2 - 02 -Demo Existing Pan, Sawcut & Remove
1.00
LS
$6,073.00
$6,073.00
Asphalt, Remove Pavers
D
3 - 03 - Type 13 Inlet(North)
1.00
EACH
$2,025.00
$2,025.00
4
4 - 04 -12" CMP(2 Locations)
28.00
LF
$111.50
$3,122.00
D
5 - 05 - Relocate CATV Pedestal
1.00
EACH
$897.33
$897.33
i Da
6 - 06 - Prep For 4' Pan
1,220.00
SF
$3.10
$3,782.00
i
7 - 07 - Prep For Concrete Apron/new
285.00
SF
$3.55
$1,011.75
Pavers/replace Old Pavers
!
8 - 08 - Remove /replace Existing Signs
9.00
EACH
$315.00
$2,835.00
i3o
9 - 09 - Demo Concrete /asphalt @Bank
1.00
IS
$3,645.00
$3,645.00
&
10 -10 - Prep For Curb At Bank Island
38.00
LF
$13.40
$509.20
0a
11 - 11 - Prep Base(8')
267.00
SF
$3.60
$961.20
fl
12 -12 - 7" Asphalt
267.00
SF
$7.70
$2,055.90
Pay Items Total:
$27,317.38
8/27/2009 5:32:38 PM Page 1 of 1
~(JNI~RUCTION, INC.
-11 0 R
FIELD WORK ORDER 0 6
Project _ Uy SSG ~ s HCI Job No. Z/>x1;1' Date: 0y
Subcontractor: --Cu;V~-~ t nit
Reason For Work: .4U ~u Gi/1 t- j~,L)5Lq-(t 2- k 7_ J,ti/ 44
Will other subcontractors be impacted by this work? YES NO JJ
Description Of Work To Be Performed: - t 2 z ICS
Estimated Man Hours To Complete This Work:
Labor Category Rate Hours r
Labor Category { ~.Z Rate Hours
Labor Category Rate Hours
Labor Category Rate Hours
TOTAL MAN HOURS
Estimated Materials And/Or Equipment To Complete This Work:
Description Quantity Description Quantity
, AAb -50 /YI ~,v, G l Li'/a l T
2-
Estimated cost to complete this work here in is J :z- 3, ,rf 7
Subcontractor Representative:
F
The work is authorized to proceed as stated herein, not to exceed the amount stated above.
The work is subject to the review and approval of the Hyder Construction Inc. Project Manager.
Please see comments below.
Hyder Construction Inc. Representative Date z?47
COMMENTS:
White Copy: Hyder Construction Inc. Office
Pink Copy: Superintendent
Yellow Copy: Owner, Architect or Subcontractor
543 Santa Fe Drive • Denver, Colorado 80204 • (303) 825-1313 • FAX (303) 825-3223 0 Email: info ash dcrinc.corn • Website: www.h derinc_com
B "RFC
EXCAVATMG
Oldcastle SW Group, INC.
dba B&B Excavating
U &B
rXCAVAnNG
P.O. Box 4870
Eagle, CO 81631
-
f~~ ro3
970-328-1734/970-328-1735(fax.;
Daily Extra Work Report
Job Number 201902
Job Name Four Seasons
Work Date 9/24/2009
Customer Name Hyder Construction
Description of Work Supply
and install 2x2 inlet north side of Frontage Road Per Chad @ TOV.
Inlet to tie in 18" cmp at driveway
to 12" cmp to the east.
LABOR
General Labor
Operator/Laborer
Foreman
Supervisor
EQUIPMENT
JD-50 Mini Excavator
SUBCONTRACTORS QTY
Hourly
rate
Hours
Extended
amount
$ 48.00
17
$ 816.00
$ 58.00
4
$ 232.00
$ 60.00
$ -
$ 68.00
$ -
Total labor cost
$1,048.00
Hourly
rate
Hours
Extended
amount
$ 103.00
2
$ 206.00
$ -
Total equipment
cost
$ 206.00
Unit
Unit Price
Extended
amount
each
$ 617.98
$ 617.98
Subtotal
$ 617.98
Tax 8.4%
$ 51.91
Total material cost
$ 669.89
Unit
Unit Price
Extended
amount
$ -
Total subcontractor
cost
$ -
Total this report
$1,923.89
A signature by both parties is an agreement that the above is complete and correct.
Contracting Party Date
B&B Representative Date
Scott Miller
From: Jody Kenney [Jody@peakland.net]
Sent: Tuesday, September 29, 2009 1:35 PM
To: Scott Miller
Subject: TOV1Four Seasons Frontage Rd. work...
Good afternoon. Here is the information you requested. Steve said he's 4 days into the road work for both
aspects (TOV portion and Four Season) He said he will have another day or so out there. That would put the
field portion to $5400. Office time so far has been 4 hours for the town portion and probably an additional 4
forthcoming which is about $720. Total of $6120. Please let me know if you have any questions or comments.
71anks!
Jody Kenney
Peak Land Consultants, Inc.
1000 Lions Ridge Loop
Vail, CO 81657
Phone: (970) 476-8644
Fax: (970) 476-8616
Email: JodvnPeakland.net
IPRZ
M%K WO CONSI LTAN-M, INC.
The information contained in this message is confidential and intended only for the use of the individual or entity named above, and may be privileged. Any unauthorized
review, use, disclosure, or distribution is prohibited. Ifyou are not the intended recipient, please reply to the sender immediately, staling that you have received the message
in error, then please delete this e-mail. Thank you.
Proposed Change Order
To: Scott Miller Number: 50-3.1
Hyder Construction Job: 50-013081 Four Seasons
543 Sante Fe Drive Date: 9/29/09
Denver, CC 80204
Ph: (970)476-2813 Fax: (970)476-2820
Description: 18"x8" curb and 4' pan on Frontage Road
THE
Gallegos
CORPORATK0N
R~kl:u Sdutiorn fw` Di~Gncti.c A o)nu
Vail
Po Box 821
Vail Colorado 01658
970.926.3737 Phone
970.926.3727 Fax
1. Furnish and install 75 lineal feet of 8"x18" curb in front of the bank on the South Frontage Road $4,348.
Information for bidding curb was received by conversation with Chad Salli of the Town of Vail on 9124/09.
2. Furnish and install 1,520 square feet of W concrete street pan on North side of South Frontage Road = $14,331.
3. Furnish and install an additional 136 square feet of W concrete street pan not shown on plans = $1,282.
Additional street pan takes place at driveway entrance on West side and around drop inlet.
The total amount of this change is .......$19,861.00
If you have any questions, please contact me at (970)926-3737.
Submitted by: Herb Samson
Gallegos Corporation
Cc:
Approved by:
Date:
Page 1 of 1
Scott Miller
From:
Kirk Knowles [Kirk@ywsss.com]
Sent:
Wednesday, October 07, 2009 6:28 AM
To:
Scott Miller
Cc:
Robynn Moore
Subject:
f=irst week's traffic control costs
Scott,
Per our phone conversation, the following is the first week's (9121/09 to 9/26/09) billing for the Four Seasons project in
Vail.
1 - Mobilization and Traffic Control Plans $1,500.00
5- Traffic Control Management Days ($600.00) $3,000.00
137- Flagging Hours ($26.70) $3,657.90
5- Equipment Rental Days ($55.00) $275.00
Total = $8,432.90
If you have any questions or need further information contact me at 970-263-4520 or 970-260-3377.
Thank you.
Kirk Knowles
loW, D F VAIJ
kk,.r,f f OC OF Far--074rx P-0.
3
'PAY3
OF
M ac~ewr
3
DAYS
OF
3
9A`!3
0r-
Gtir~/1(~ML^~t
t CC, ~01& A g 1SO0
Z 7 ern) (D4'-(~c$ZU0 = U Z I C Z
At1.76t- 955 IPAr = 165
y l2 ?
~ow^' Gl' VA (L_ W°a.,- - ~A~~ plak-kc,Nc. Anz
D AY Or aNUGrMryvr G~ 90~ A4) = 'Goo
OF FLA~, /NG 2 ( t7 A~
AY Or-
707 t- (5503
1
THE GALLEGOS CORPORATION
11111111113111- 11131SHEET
JOB NAME
T&MNO.
JOB #
LABOR
Pate
Name
HOURS
WORKED
RATE
TOTAL
.
, ao
,
~~F F Ln3cti G Row 6~~~n'.~J
?yA? C`+tFS V +v /0
v
JOV co
APPROVED BY:
CE3
TOTAL LABOR ~j0 72 -
t ~1 C-~
TOTAL MATERIALS ~J V
C116
TOTAL LABOR AND MATERIALS O
OVERHEAD
PROFIT ( )
c
TOTAL
el- - r' A - 7 i _ - / /~1 I % /71 _ I
THE GALLEGOS CORPORATION
TIME & MATERIAL WORKSHEET
JOB NAME F^C, ~r S~g
JOB # So ► s.p_$I_
T & M NO. DATE 2 a, /o e,
DESCRIPTION OF WORK
t' r D - T fig G _ G L ~ ♦ 'i~ ~I11 ~L.~__~~ p '4t ~ [1 Ib
LABOR
Date
Name
HOURS
WORKED
RATE
TOTAL
j
3
Gr c. X\ c- e, Lr%
IBS:
J
Tr%TAl 1 A--- T
APPROVED BY:
FOR OWNER
FOR GENERAL CONTRACTOR
FOR THE GALLEGOS CORPORATION
TOTAL LABOR '*Oe
TOTAL MATERIALS I . Z B O
TOTAL LABOR AND MATERIALS $ I i X18 S J
OVERHEAD -o
PROFIT
TOTAL I~ gaSJ