David Brooks
Four Seasons Vail
Re: the easement agreement, I have made changes and sent them to Art
Abplanalp for his review and counsel. Obviously we cannot do anything
with the agreement until we have seen the exhibits.
If we had the fire exit promised, we would shovel it. Gravel, which was
supposed to be only a stop-gap, is very difficult to shovel. I believe
Mike McGee wants to see a viable exit. You have had a full year to
address the pathway from the north exit.
The fencing Jim Heid installed did not have to be there and should come
out. What was needed was a barrier between our property and the
construction zone, and that is now leaning into the path and needs to be
moved to an upright position.
As this has material effect on our property and our operations, I wish
to be included, along with Tom Saalfed, in any discussions with Mike
McGee, not just told the outcome of your negotiations.
Gwen
David Brooks wrote:
Hope your thanksgiving weekend went well.
I was wondering if you have been able to review the easement
document that TJ's lawyer sent to you?. We would like to try and get
the language squared away as soon as possible. You said you might get
to it this past weekend. any progress?
Also, Mike McGee sent me a note that he had talked with you
about the north exit from the 1st floor being cleared of snow. I
realize that the sidewalk is not poured yet as I was hoping that Layton
would have been on site by now and would have been able to complete that
work. As it is, they are now just getting on site.
If the sidewalk were poured, how would you have handled the snow
removal? Because the sidewalk is not concrete but stone, I realize it
might cost more to handle the removal. We would be willing to pay the
additional cost of removal over the cost to remove the snow from a
concrete sidewalk.
Do you think this would be something that we can work out?
I believe that the stakes and fencing could be removed as the
grass that borders the walk path is in place. I will talk with McGee
about this before we finalize how to handle the snow removal.
David W. Brooks
Sr. Project Manager
The John Hardy Group, Inc.
The Centre Building
5180 Roswell Road
Atlanta, GA 30342
Phone # 404-256-8800 Ext. 105
Fax # 404-256-8810
Cell # 404-931-6584
E-mail dbrooks@jhgi.com
This e-mail and any attachments may contain confidential and
privileged information. If you are not the intended recipient, please
notify the sender immediately by return e-mail, delete this e-mail and
destroy any copies. Any dissemination or use of this information by a
person other than the intended recipient is unauthorized and may be
illegal.
RE:THEEASEMENTAGREEMENT,IHAVEMADECHANGESANDSENTTHEMTOARTABPLANALPFORHISREVIEWANDCOUNSELOBVIOUSLYWECA
<!DOCTYPE html PUBLIC "-//W3C//DTD HTML 4.01 Transitional//EN">
<html>
<head>
<meta content="text/html;charset=ISO-8859-1" http-equiv="Content-Type">
<title></title>
</head>
<body bgcolor="#ffffff" text="#000000">
Re: the easement agreement, I have made changes and sent them to Art
Abplanalp for his review and counsel. Obviously we cannot do anything
with the agreement until we have seen the exhibits.<br>
<br>
If we had the fire exit promised, we would shovel it. Gravel, which
was supposed to be only a stop-gap, is very difficult to shovel. I
believe Mike McGee wants to see a viable exit. You have had a full
year to address the pathway from the north exit. <br>
<br>
The fencing Jim Heid installed did not have to be there and should come
out. What was needed was a barrier between our property and the
construction zone, and that is now leaning into the path and needs to
be moved to an upright position. <br>
<br>
As this has material effect on our property and our operations, I wish
to be included, along with Tom Saalfed, in any discussions with Mike
McGee, not just told the outcome of your negotiations. <br>
<br>
Gwen<br>
<br>
David Brooks wrote:<br>
<blockquote cite="mid000601c71339$7e6e9b30$6601a8c0@jhgi.com"
type="cite">
<meta http-equiv="Content-Type" content="text/html; ">
<meta content="MSHTML 6.00.2900.2995" name="GENERATOR">
<style></style>
<div><font face="Arial" size="2">Hope your thanksgiving weekend went
well.</font></div>
<div> </div>
<div><font face="Arial" size="2">I was wondering if you have been
able to review the easement document that TJ's lawyer sent to you?. We
would like to try and get the language squared away as soon as
possible. You said you might get to it this past weekend. any
progress?</font></div>
<div> </div>
<div><font face="Arial" size="2">Also, Mike McGee sent me a note that
he had talked with you about the north exit from the 1st floor being
cleared of snow. I realize that the sidewalk is not poured yet as I
was hoping that Layton would have been on site by now and would have
been able to complete that work. As it is, they are now just getting
on site.</font></div>
<div> </div>
<div><font face="Arial" size="2">If the sidewalk were poured, how
would you have handled the snow removal? Because the sidewalk is not
concrete but stone, I realize it might cost more to handle the
removal. We would be willing to pay the additional cost of removal
over the cost to remove the snow from a concrete sidewalk.</font></div>
<div> </div>
<div><font face="Arial" size="2">Do you think this would be something
that we can work out?</font></div>
<div> </div>
<div><font face="Arial" size="2">I believe that the stakes and
fencing could be removed as the grass that borders the walk path is in
place. I will talk with McGee about this before we finalize how to
handle the snow removal.</font></div>
<div> </div>
<div><font face="Arial" size="2">David W. Brooks<br>
Sr. Project Manager<br>
The John Hardy Group, Inc.<br>
The Centre Building<br>
5180 Roswell Road<br>
Atlanta, GA 30342<br>
Phone # 404-256-8800 Ext. 105<br>
Fax # 404-256-8810<br>
Cell # 404-931-6584<br>
E-mail <a href="mailto:dbrooks@jhgi.com">dbrooks@jhgi.com</a></font></div>
<!--[object_id=#jhgi.com#]--><font size="2"><font color="#0000ff"
face="Tahoma" size="1">
<p><font color="#000000">This e-mail and any attachments may contain
confidential and privileged information. If you are not the intended
recipient, please notify the sender immediately by return e-mail,
delete this e-mail and destroy any copies. Any dissemination or use of
this information by a person other than the intended recipient is
unauthorized and may be illegal.</font> </p>
</font></font></blockquote>
</body>
</html>
David Brooks
NGW
dbrooks@jhgi.com
dbrooks@jhgi.com
David Brooks