List of Outstanding Discrepancies
Project Name: First Chair Employee Housing
Project No: 10-6522 Date 08-06-10
Client: Vail Resorts Development Co.
Address: P.O. Box 959
Avon, CO 81620
Attn: Mr. Kyle Griffith
Faxed to :
It is the responsibility of the contractor to notify GROUND once corrections have been made and to schedule re-
observations. The contractor should provide our office hard copies of any changes or approvals made by the
Structural Engineer of Record.
Date Item Outstanding Discrepancy Date Per Plan/
Re orted No. Acce ted Per RFI
07-08-10 1 Loose or missing bolts at Level 1 between Gridlines A g�6/2010 Per Plan
J/1-8.
07-08-10 2 Exposed slots at beam-to-beam and beam to clips at g�6/2010 Per Plan
Level 1, Gridlines J/5.4-8.
07-08-10 3 Undersized welds at L4x4x3/8 to embed at Level 1 at g�6/2010 Per Plan
Gridlines H.3/6-7.
07-08-10 4 GROUND is requesting WPS & WQTRs for AWS g�6/2010 Per Plan
D1.1 and D1.3 and WPS for H.A.S. from PSI.
07-12-10 5 Missing H.A.S. or H.A.S. failed bend test at Level 2 ��13/2010 Per Plan
deck at Gridlines A-E.3/1.3-5.4.
07-12-10 6 H.A.S. welded to bent plate at Level 2 at Gridlines g�6/2010 Per RFI #36
A/4.6-5.4, C.1-D.3/5.2, D.3-E.2/5.4 and D.3/4.6-5.2.
07-12-10 7 GROUND is requesting WPS & WQTRs for AWS g�6/2010 Per Plan
D1.4 from PSI.
Corporate Office Gypsum Office
41 Inverness Drive East PO Box 464
Englewood,CO 80112 Gypsum,CO 81637
Tel:(303)289 1989 Tel:(970)524 0720
Fax:(303)289 1686 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
VISUAL OBSERVATION REPORT
Project Name: First Chair Employee Housing Date: July 1, 2010
Project No: 10-6522 Report No: 1
Client: Vail Resorts Development Co.
Address: P.O. Box 959
Avon, CO 81620
Attn: Mr. Kyle Griffith
As requested, a representative of GROUND arrived at the project site to observe welded
connections of anchor bolts.
The following is a summary of our observations conducted on this date:
1) Observed welded connections of cut anchor bolts for column bases at the Ground
Level at Gridlines E.5/5 and E.6/4.6 and found them to be in general compiiance per
RFI #27.
Justin with R.A. Nelson was notified of our observations and received a copy of this report.
Submitted By:
GROUND Engineering Consultants, Inc.
Allen Barton
Field Representative
Grand Junction Office Corporate Office Gypsum Office
1008 3rd Avenue,Suite D 41 Inverness Drive East P.O. Box 464
Grand Junction,CO 81501 Englewood,CO 80112 Gypsum,CO 81637
P:(970)242-4300 P:(303)289-1989 P:(970)524-0720
F:(970)524-0721 F:(303)289-6742 F:(970)524-0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
VISUAL OBSERVATION REPORT
Project Name: First Chair Employee Housing Date: July 8, 2010
Project No: 10-6522 Report No: 2
Client: Vail Resorts Development Co.
Address: P.O. Box 959
Avon, CO 81620
Attn: Mr. Kyle Griffith
As requested, a representative of GROUND arrived at the project site to observe welded and
bolted connections.
The following is a summary of our observations conducted on this date:
1) Observed welded connections of L4x3x5/16x10" to embeds at Level 1 between
Gridlines A-J/1-1.3, J/1-1.8, B-C/4.6, E.2 & E.6/4.3-5 and found them to be in general
compliance per Detail 9/S4.07.
2) Observed welded connections of '/4" bent plate to beam flange at Level 1 between
Gridlines J/1.8-8, E.2-J/7.8-8, E.2/5.4-7.8, A-E.2/5.4 and found them to be in general
compliance per Details 1/S4.07 and 12/S4.02.
3) Observed welded connections of L4x4x3/8 to embeds at Level 1 between Gridlines
E.2 & E.5/4.6-5, H.3-J/6-7 and H.3-J/6-7, B-C/4.6-5.4 and L6x4x3/8 to '/4" bent plate
at Gridlines E.2/5.4-7.8 and found them to be in general compliance per Details 3 &
12/S4.02 of the project plans.
4) Observed welded connections of HSS 6x4x1/2 to embed and to L4x3x3/16 at
elevator and stair core between Gridlines B-C/4.6-5.4, E.2-E.5/4.3-5 and found them
to be in general compliance per Detail 8/S4.07 of the project plans.
5) Observed bolted connections of beams and columns at Level 1 between Gridlines A-
J/1-8 and found them in non-compliance due to loose or missing bolts per project
plans and specifications. Discrepancy Item #1.
6) GROUND observed exposed slots at beam-to-beam and beam to clips bolted
connections at Gridlines J/5.4-8. Discrepancy Item #2.
Grand Junction Office Corporate Office Gypsum Office
1008 3rd Avenue,Suite D 41 Inverness Drive East P.O. Box 464
Grand Junction,CO 81501 Englewood,CO 80112 Gypsum,CO 81637
P:(970)242-4300 P:(303)289-1989 P:(970)524-0720
F:(970)524-0721 F:(303)289-6742 F:(970)524-0721
First Chair Employee Housing
Vail,Colorado
Page 2 of 2
7) GROUND observed undersized welds at L4x4x3/8 to embeds at Level 1 at Gridlines
H.3/6-7 per AWS D1.1, Table 6.1 and Detail 3/S4.02 of the project plans.
Discrepancy Item #3.
8) GROUND is requesting Welding Procedure Specification (WPS) and Welder
Qualification Test Records (WQTRs) for AWS D1.1 and D1.3 and WPS for H.A.S.
from PSI. Discrepancy Item #4.
Justin with R.A. Nelson was notified of our observations and received a copy of this report.
Submitted By:
GROUND Engineering Consultants, Inc.
Allen Barton
Field Representative
South Metro Office North Metro Office Gypsum Office
41 Inverness Drive East 7393 Dahlia Street, P.O. Box 464
Englewood,CO 80112-5412 Commerce City,CO 80022-1834 Gypsum,Colorado 81637
Tel:(303)289 1989 TeI:(303)289 1989 Tel:(970)524 0720
Fax: (303)289 1686 Fax:(303)289 6742 Fax:(970)524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
VISUAL OBSERVATION REPORT
Project Name: First Chair Employee Housing Date: July 12, 2010
Project No: 10-6522 Report No: 3
Client: Vail Resorts Development Co.
Address: P.O. Box 959
Avon, CO 81620
Attn: Mr. Kyle Griffith
As requested, a representative of GROUND arrived at the project site to observe are spot-
welds, Headed Anchor Studs (H.A.S.) and tek screws for Level 2 deck.
The following is a summary of our observations conducted on this date:
1) Observed are spot-welds/tek screws for Level 2 deck between Gridlines A-E.3/1.3-
5.4 and found them to be in general compliance with the project plans and
specifications.
2) Observed Headed Anchor Studs at Level 2 deck between Gridlines A-E.3/1.3-5.4
and found them to be in non-compliance due to missing H.A.S. and H.A.S. failing
bend test. Discrepancy Item #5.
3) GROUND observed H.A.S. automatically hand-welded to bent plate at Level 2 at
Gridlines A/4.6-5.4, C.1-D.3/5.2, D.3-E.2/5.4 and D.3/4.6-5.2. Per General Notes on
S1.00 of the project plans, headed anchor studs shall be welded directly to steel
beams. Discrepancy Item #6.
4) GROUND is requesting Welding Procedure Specification (WPS) and Welder
Qualification Test Records (WQTRs) for AWS D1.4 from PSI for welders reinforcing
steel to bent plate. Discrepancy Item #7.
Justin with R.A. Nelson was notified of our observations and received a copy of this report.
Submitted By:
GROUND Engineering Consultants, Inc.
Allen Barton
Field Representative
Grand Junction Office Corporate Office Gypsum Office
1008 3rd Avenue,Suite D 41 Inverness Drive East P.O. Box 464
Grand Junction,CO 81501 Englewood,CO 80112 Gypsum,CO 81637
P:(970)242-4300 P:(303)289-1989 P:(970)524-0720
F:(970)524-0721 F:(303)289-6742 F:(970)524-0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
VISUAL OBSERVATION REPORT
Project Name: First Chair Employee Housing Date: July 12, 2010
Project No: 10-6522 Report No: 4
Client: Vail Resorts Development Co.
Address: P.O. Box 959
Avon, CO 81620
Attn: Mr. Kyle Griffith
As requested, a representative of GROUND arrived at the project site to perform Ultrasonic (UT)
examinations of Complete Joint Penetration (CJP) welds.
The following is a summary of the observations perFormed on this date:
1) U.T. examinations were perFormed on the two CJP moment connections at Gridlines
A/2 on Level 2. They were found to be in general compliance with the project plans,
specifications and AWS D1.1-2008, Table 6.2. See the attached Ultrasonic
Examination Report for more information.
Justin with R.A. Nelson was notified of these observations and received a copy of this report.
Submitted By:
GROUND Engineering Consultants, Inc.
Austin Nicodemus
Field Representative
Grand Junction Office Corporate Office Gypsum Office
1008 3rd Avenue,Suite D 41 Inverness Drive East P.O. Box 464
Grand Junction,CO 81501 Englewood,CO 80112 Gypsum,CO 81637
P:(970)242-4300 P:(303)289-1989 P:(970)524-0720
F:(970)524-0721 F:(303)289-6742 F:(970)524-0721
CR�U�1In
ENGINEEFiING CDNSULTRNTS
Client Vail Resorts Development Co. Project: First Chair Employee Housing Weld Identification: CJP Moment Welds
P.O.Box 959 Job No.: 10-6522 Material Thickness: 3/8"
Avon,CO 81620 Weld Joint AWS: B-U4a and TC-U4a
Report No. 100712-1 Machine: OOCD23
Code and/or Specification AWS D1.1-2008 Transducer: OOVBN9
Attn Mr. Kyle Griffith Tested to: Table 6.2 Couplant: Ultragel II
Frequency: 2.25 MHz
Ultrasonic Examination Report
Decibels Defect
Line Defect Transducer Node Defect Reference Attenuate Defect Length Angular Depth From Distance Defect Remarks
# Number Angle Level Level Factor Rating Distance "A"Surface From From Evaluation
(Sound Path) "X" "Y" Part#
A/2 N/A 70 I/II N/A 48.5 N/A N/A N/A N/A N/A N/A N/A Com liant To fian e-east
A/2 N/A 70 I/II N/A 48.5 N/A N/A N/A N/A N/A N/A N/A Com liant Bottom flan e-east
A/2 N/A 70 I/II N/A 48.5 N/A N/A N/A N/A N/A N/A N/A Com liant To flan e-west
A/2 N/A 70 I/II N/A 48.5 N/A N/A N/A N/A N/A N/A N/A Com liant Bottom flan e-west
Notes: (1)`Use Node I or II
(2)In order to attain"Rating d": (a)with instruments with Gain Control.Use the formula:a-b-c=d,(b)with instruments with Attentuation Control.Use formula:b-a-c=d
(c)A+or-sign must accompany the"d"figure unless"d"is equal to zero
(3)Distance from X is used in describing the location of a weld discontinuity in a direction perpendicular to the weld reference line. Unless this figure is zero.
a+or-sign must accompany it.
(4)Distance from Y is used in describing the location of a weld discontinuity in a direction parallel to the weld reference line. This figure is attained by measuring
the distance from"Y"end of the weld to the beginning of said discontinuity.
(5)Make separate report following repairs.
Ilnspected by: Austin Nicodemus, Level II I
Corporate Office Gypsum Office
41 Inverness Drive East PO Box 464
Englewood,CO 50112 Gypsum,CO 81637
P:303 289 1989 P:970 524 0720
F:303-289•6742 F:970 524 0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
VISUAL OBSERVATION REPORT
Project Name: First Chair Employee Housing Date: July 13, 2010
Project No: 10-6522 Report No: 5
Client: Vail Resorts Development Co.
Address: P.O. Box 959
Avon, CO 81620
Attn: Mr. Kyle Griffith
As requested, a representative of GROUND arrived at the project site to observe are spot-
welds, H.A.S. and tek screws for Level 2 deck and to re-observe outstanding Discrepancy
Items.
The following is a summary of our observations and re-observations conducted on this date:
1) Observed Headed Anchor Studs (H.A.S.), are spot-welds and tek screws for Level 2
deck between Gridlines E.3-J/1-8 and found them to be in general compliance with
the project plans and specifications.
2) Observed welded connections of #5x3'-0" to '/4" bent plate at Level 2 between
Gridlines J/2-8, E.2-J/7.8-8, E.2/5.4-7.8 and C-E.2/5.4 and found them to be in
general compliance per Details 1/S4.02, 5/S4.03, 4/S4.07 and 6/S4.06 of the project
plans.
3) Re-observed Discrepancy Item #5. This item is now in general compliance with the
project plans.
Mike with R.A. Nelson was notified of our observations, re-observations and received a copy of
this report.
Submitted By:
GROUND Engineering Consultants, Inc.
Allen Barton
Field Representative
Grand Junction Office Corporate Office Gypsum Office
1008 3rd Avenue,Suite D 41 Inverness Drive East P.O. Box 464
Grand Junction,CO 81501 Englewood,CO 80112 Gypsum,CO 81637
P:(970)242-4300 P:(303)289-1989 P:(970)524-0720
F:(970)524-0721 F:(303)289-6742 F:(970)524-0721
CRDU�IIn
ENGINEERING CDNSULTRNTS
VISUAL OBSERVATION REPORT
Project Name: First Chair Employee Housing Date: August 6, 2010
Project No: 10-6522 Report No: 6
Client: Vail Resorts Development Co.
Address: P.O. Box 959
Avon, CO 81620
Attn: Mr. Kyle Griffith
As requested, a representative of GROUND arrived at the project site to re-observe outstanding
Discrepancy Items.
The following is a summary of our re-observations conducted on this date:
1) Re-observed Discrepancy Items 1, 2 and 3. These items are now in general
compliance with the project plans, specifications and AWS D1.1 Table 6.1.
2) GROUND received WPS and WQTR for AWS D1.1,WQTR for D1.4 and WQTRs for
AWS D1.3. GROUND is requesting WPS #PSI-420 and WPS #PSI-1103A before
Discrepancy Items 4 and 7 are in compliance.
3) Re-observed Discrepancy Item #6. This item is now in general compliance with RFI
#36.
Justin with R.A. Nelson was notified of our re-observations and received a copy of this report
and updated Discrepancy List.
Submitted By:
GROUND Engineering Consultants, Inc.
Allen Barton
Field Representative
Grand Junction Office Corporate Office Gypsum Office
1008 3rd Avenue,Suite D 41 Inverness Drive East P.O. Box 464
Grand Junction,CO 81501 Englewood,CO 80112 Gypsum,CO 81637
P:(970)242-4300 P:(303)289-1989 P:(970)524-0720
F:(970)524-0721 F:(303)289-6742 F:(970)524-0721