Date:June 9, 2011
Re: 1916 Gore Creek/ B11-0139
Dear Gies Architects,
RESPONSE INSTRUCTIONS
● Submit four complete sets of revised construction documents containing the requested information with all plan revision items clouded or otherwise identified.
● Please respond in writing to each comment with a response letter addressing each comment.
BUILDING COMMENTS
Architectural Comments:
General
1. All plans to have “ Not for Construction” removed from them
Sheet A4.2
1. Snow fencing to be designed by the structural engineer per section 1510.7 IBC as amended by the Town Code.
Sheet A4.4
1. Provide u values on window/ door schedules showing compliance with the IECC.
Structural Comments:
Sheet S3.1
1. Plans to reflect the required special inspections per section 1704.1.1 IBC.
2. Submit a completed special inspection agreement available at the Town of Vail web page. www.vailgov.com.
Plumbing Comments:
Reviewed and accepted
Mechanical Comments:
General
1. Show location of proposed and existing equipment per Town of Vail submittal requirements
2. Indicate boiler efficiency on plans per Town of Vail submittal requirements.
Electrical Comments
General
1. Provide load calculations per Town of Vail submittal requirements.
2. Annotate on plans the required high efficacy per the IECC.
3. Show location of electrical service and panel boards per Town of Vail submittal requirements.
PLANNING COMMENTS
Reviewed and accepted
FIRE COMMENTS
Reviewed and accepted
PUBLIC WORKS COMMENTS
PProvide stamped details/calcs for tiered boulder wall per Town Code.
RRevocable permit required for private improvements located in the Town Right of Way
Sincerely,
Martin A. Haeberle
Chief Building Official