SUIVIMARY OF CONCRETE TEST RESULTS
Project: Lionshead Transit Center, Vail, Colorado
Location: ECO Building Driveway Curb & Gutter, Sampled at East End to Approximately 87 Feet West
Total Cubic Yards: 10
Supplier: Lafarge Ticket No: 85823782 Mix Design No: RMXDG45GD87
Slump: 4.50 inch(es) Air Content: 4.6 % Wet Unit Weight: 142.6 pcf
Concrete Temperature 69 °F Air Temperature: 71 °F
Test Date: 06/09/11 Time Test Taken: 12:14 PM
Design Strength: 4200 psi at 28 days Amount of Water Added at Site: 4 gallons
Remarks:
*Refer to ASTM C39/C39M-OS
Age (days) Total Load(lbs) Diameter(in.) Area (sq. in.) Compressive Stren�th(psi) Type of Fracture*
7 48066 4.02 12.69 3790 2