HomeMy WebLinkAbout10-039 Daily Field Reports 12 13 SOIL COMPACTION TEST RESULTS
To: Town of Vail KOECHLEIN CONSULTING ENGINEERS, INC. Job No. 10-039 Date: 9/7/10
Tom Kassmel,P.E. Report#: 12 Sheet: 1 of 1
Geotechnical and Materials Engineers
Town Engineer Lalcewood—(303)989-1223 Subject: Fill Observation and Testine
Department of Public Works/Transportation Grand Junction—(970)241-7700 Sanitary Sewer Line
1309 Elkhorn Drive South of Existing Frontage Road
Vail,Colorado 81657 Lionshead Transit Center
Vail,Colorado
LaboraYo Field
Depth MaJCimum Optimum
Test Location or Dry Moisture Dry Moisture Percent Pass/Fail Soil Type
No. Elevation Density Content Density Content Compaction
(feet) cf� (%) cfl (%)
30 Sta.00+50 Grade± 130.3 7.9 131.3 6.2 100 Pass Curve#1
SAND Gravell Sil
31 Sta. 1+00 Grade± 130.3 7.9 130.8 6.5 100 Pass Curve#1
SAND Gravell Sil
Weather: � Sum� ❑ Cloud ❑ Rain ❑ Snow Tem : 70°F± � Fill Tested Meets Specifications.
Specification Compaction&Material: 100%of Standard Proctor AASHTO T 99, ❑ Fill Tested Does Not Meet Specifications as Indicated by Test Number(s)
+2%to-2%of Optimum Moisture Content and Should be Removed or Reworked.
Type and Number of Earth Moving Units: 1-Loader, 1-Trackhoe � Contractor Advised.
❑ Full Time Observation. � Part Time Observation.
Type and Number of Compaction Units: 1-Walk-behind Wacker Progress Report: Field engineer arrived on-site,as requested,to observe and test backfill
far the sanitary sewer line south of the existing Frontage Road. Test results indicate that
Number of Passes: Varies Thickness of Lift: 8 inches moisture and density tests performed at the noted locations have met project
Method of Adding Moisture: N/A specifications.
Tl�is re�ort presents opinions formed as a result of our observations and/or compaction testing of tl�e fill during this visit.
We have relied on the contractor to continue applying the recommended compactive effort and moisture to the fill during
times when our observer is not observing operations. Tests are made of the fill only as believed necessary to calibrate our
observer's jud ment Test data are not the sole basis for o inio��s on whether the fill meets s ecifications.
Mike Brath Scott B. Myers, P.E.
Field Observer Reviewed By
REPORT OF CONSTRUCTION ACTIVITIES
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Lakewood—(303)989-1223
Grand Junction—(970)241-7700
To: Town of Vail Job No. 10-039 Date: 9/8/10
Tom Kassmel,P.E.
Town Engineer Report#: 13A Sheet: 1 of 2
Department of Public Works/Transportation
1309 Elkhorn Drive
Vail,Colorado 81657
Project: Lionshead Transit Center,Vail, Colorado
Weather: ❑ Sunny � Cloudy ❑ Rain ❑ Snow Temp: 70°F±
Construction Activities/Observations: Engineer arrived on site, as requested, to observe the installation of the
micropiles along the west side of the existing parking garage. The pile group consists of 3 piles which are located
approxirriately 6 feet west of Gridline �1. No micropiles were installed at the time of our observation due to site
conditions inconsistent with the assumed design conditions and criteria presented in the plan documents. Engineer met
with B&Y Drilling and FCI, Inc. to discuss the required changes to the micropile specifications.
Engineer deternvned that, due to the presence of approximately 18 feet of wall backf'ill in the area of the micropiles,the
minimum depth of the 3 piles from existing grade may be no less than 43 feet to achieve the 25 feet of penetration into
native soils as outlined by Yeh and Associates.
Engineer also determined that the minimum length for the micropiles to be installed for the proposed pedestrian bridge
will need to be extended due to the presence of existing fill. The six piles located north of Gridline �1 and between
Gridlines �1 and �3 will need to be a minimum length of 50 feet to achieve the required 30 feet of penetration into
native soils. This is due to the presence of approximately 20 feet of foundation wall backfill adjacent to the lowest level
of the parking garage. The micropiles located north of Gridline E-A and between Gridlines E 3 and E-4 will need to be
a minimum of 35 feet in length to account for approximately 5 feet of additional utility fill at surface elevation. Engineer
will return to site tomorrow to continue observation.
Katie Shaw Scott B. Myers, P.E.
Field Observer Reviewed By
SOIL COMPACTION TEST RESULTS
To: Town of Vail KOECHLEIN CONSULTING ENGINEERS, INC. Job No. 10-039 Date: 9/8/10
Tom Kassmel,P.E. Report#: 13B Sheet: 2 of 2
Geotechnical and Materials Engineers
Town Engineer Subject: Fill Obs�rvation and Testine
Lalcewood—(303)989-1223
Department of Public Works/Transpartation Grand Junction—(970)241-7700 Storm Sewer Line and Manhole Backfill
1309 Elkhorn Drive Lionshead Transit Center
Vail,Colorado 81657 Vail,Colorado
Laborato Field
Depth Mauimum Optimum
Test Location or Dry Moisture Dry Moisture Percent Pass/Fail Soil Type
No. Elevation Density Content Density Content Compaction
(feet) cfj (%) c� (%)
32 Storm Sewer Line: Sta.00+92 -4.0± 130.3 7.9 129.9 6.8 100 Pass Curve#1
SAND Gravell Sil
33 Storm Sewer Line: Sta. 1+02 -3.0± 130.3 7.9 130.0 6.6 100 Pass Curve#1
SAND Gravell Sil
34 Storm Sewer Line: Sta. 1+12 -2.0± 130.3 7.9 131.2 6.0 100 Pass Curve#1
SAND Gravell Sil
35 Manhole: Sta.00+00,west side -3.0± 130.3 7.9 131.0 6.2 100 Pass Curve#1
SAND Gravell Sil
Weather: ❑ Sunn � Cloud ❑ Rain ❑ Snow Tem : 68°F± � Fill Tested Meets Specifications.
Specification Compaction&Material: 100%of Standard Proctor AASHTO T 99, ❑ Fill Tested Does Not Meet Specifications as Indicated by Test Number(s)
+2%to-2°/o of Optimum Moisture Content and Should be Removed or Reworked.
Type and Number of Earth Moving Units: 1-Trackhoe � Contractor Advised.
❑ Full Time Observation. � Part Time Observation.
Type and Number of Compaction Units: 1-Walk-behind Wacker Progress Report: Field engineer arrived on-site,as requested,to observe and test backfill
far the storm sewer line and manhole. Test results indicate that moisture and density tests
Number of Passes: Varies Thickness of Lift: 8 inches performed at the noted locations have met project specifications.
Method of Adding Moisture: N/A
This report prosents opinions formed as a result of our observations and/or compaction testing of the fill during this visit.
We have relied o��the contractor to continue applying the recommended compactive effort and moistu�e to the fill during
times when our observer is not observing operations. Tests are made of the fill only as belicved necessary to calibrate our
observer's jud ment. Test data are not tl�e sole basis for o inions on whether the fill meets s ecificatious.
Mike Brath Scott B. Myers, P.E.
Field Observer Reviewed By