HomeMy WebLinkAbout10-039 Daily Field Reports 22 to 24 REPORT OF CONSTRUCTION ACTIVITIES
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Lakewood—(303)989-1223
Grand Junction—(970)241-7700
To: Town of Vail Job No. 10-039 Date: 9/23/10
Tom Kassmel,P.E.
Town Engineer Report#: 22 Sheet: 1 of 1
Department of Public Works/Transportation
1309 Elkhorn Drive
Vail,Colorado 81657
Project: Lionshead Transit Center,Vail, Colorado
Weather: � Sunny ❑ Cloudy ❑ Rain ❑ Snow Temp: 80°F±
Construction Activities/Observations: Field engineer arrived on site, as requested,to observe a proof-roll.
The proof-roll was cancelled on site. Therefore,no observations of a proof-roll were performed during this site visit.
Mike Brath Scott B. Myers, P.E.
Field Observer Reviewed By
REPORT OF CONSTRUCTION ACTIVITIES
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Lakewood—(303)989-1223
Grand Junction—(970)241-7700
To: Town of Vail Job No. 10-039 Date: 9/24/10
Tom Kassmel,P.E.
Town Engineer Report#: 23A Sheet: 1 of 4
Department of Public Works/Transportation
1309 Elkhorn Drive
Vail,Colorado 81657
Project: Lionshead Transit Center,Vail, Colorado
Weather: � Sunny ❑ Cloudy ❑ Rain ❑ Snow Temp: 70°F±
Construction Activities/Observations: Field engineer arrived on site, as requested, to meet with FCI and the Town
of Vail and to observe the concrete wall-on-grade failure on the west side of the existing parking garage for the
pedestrian walkway.
The concrete wall-on-grade is approxirnately 1 foot thick and extends along the west side of the existing parking
garage. At the time of our observation, a 10 foot section of the wall had been removed. The wall is being supported by
e�sting fill. The depth of the e�sting fill varies but could be up to 15 feet.
Engineer advised that, in order to reduce the risk of movement, the fill below the area of construction would need to be
stabilized. Engineer discussed stabilization options including micro-piles and compaction grouting. Engineer suggested
that if the wall is to be reconstructed, that it be redesigned to include footings, so that if future movement occurs, the
wall may be stabilized by compaction grouting.
Katie Shaw Scott B. Myers, P.E.
Field Observer Reviewed By
REPORT OF CONSTRUCTION ACTIVITIES
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Lakewood—(303)989-1223
Grand Junction—(970)241-7700
To: Town of Vail Job No. 10-039 Date: 9/24/10
Tom Kassmel,P.E.
Town Engineer Report#: 23B Sheet: 2 of 4
Department of Public Works/Transportation
1309 Elkhorn Drive
Vail,Colorado 81657
Project: Lionshead Transit Center,Vail, Colorado
Weather: � Sunny ❑ Cloudy ❑ Rain ❑ Snow Temp: 78°F±
Construction Activities/Observations: Field engineer arrived on site, as requested, to observe the proof-roll on the
eastbound lane of the proposed frontage road from Sta. 6+50 to Sta. 11+00.
The material exposed in the subgrade consisted of a silty sand with gravel and small cobbles. The proof-roll was
performed using a fully loaded water truck.
At the time of this observation, field engineer observed moderate rutting and pumping of the material at appro�mately
Sta. 7+00, Sta. 8+25, Sta. 8+75, Sta. 9+50, and Sta. 10+25. These areas varied in lineal feet from 5 to 15 feet.
Based on our observations, it is our opinion that these areas need to be stabilized priar to placement of recycled asphalt
or base course. The subgrade soils may be stabilized by removing the pumping soils to a depth of 8 inches, placing a
Mirafi HP370 ar Mirafi 600X geotextile in the base of the excavation and then placing and compacting granular soils to
subgrade elevation. The granular soils may consist of 1 to 3 inch minus gravel or Class 5 or 6 base course material.
Mike Brath Scott B. Myers, P.E.
Field Observer Reviewed By
REINFORCING STEEL (REBAR) OBSERVATION
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Lakewood—(303)989-1223
Grand Junction—(970)241-7700
To: Town of Vail Job No. 10-039 Date: 9/24/10
Tom Kassmel,P.E.
Town Engineer Report#: 23C Sheet: 3 of 4
Department of Public Works/Transportation
1309 Elkhorn Drive
Vail,Colorado 81657
Project: Lionshead Transit Center,Vail, Colorado
Weather: � Sunny ❑ Cloudy ❑ Rain ❑ Snow Temp: 78°F±
Reinforcing Steel (Rebar) Observations:
Type of Structure: (Wall, Grade Beam, Footin�, Slab-on-�rade, etc.): Grade Beams
Location of Observations: Gridlines E-A.0/E-1.5 to E-3.5 and E-3.5 to E-4
Sheet or Plan Number: 5210, 5312
Meets Project Spec.
Grade Beams Rebar: Gridlines E A.0/E-1.5 to E-3.5 yes no
Horizontal: Size: 4 - #7 Spacing: Continuous, top and bottom � ❑
Horizontal: Size: 3 - #4 Spacing. Continuous, each side � ❑
Stirrups: Size: #4 Spacing: 1'-0" o.c. � ❑
Vertical: Size: 4 - #6 Spacing: From piles � ❑
Ties: Size: #3 Spacing: 0'-6" o.c. � ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) no Length: � ❑
Meets Project Spec.
Grade Beams Rebar: Gridlines E 3.5 to E-4 yes no
Horizontal: Size: 3 - #7 Spacing. Top and bottom continuous � ❑
Horizontal: Size: 3 - #4 Spacing: Each side continuous � ❑
Stirrups: Size: #4 Spacing: 1'-0" o.c. � ❑
Vertical: Size: #5 Spacing: 1'-0" o.c. � ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) no Length: � ❑
Discrepancies/Remarks: Based on our observations, it is our opinion that the reinforcing steel (rebar) yes no
noted in this Daily Field Report has been properly placed and has met project specifications. � ❑
Mike Brath Scott B. Myers, P.E.
Field Observer Reviewed By
REINFORCING STEEL (REBAR) OBSERVATION
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Lakewood—(303)989-1223
Grand Junction—(970)241-7700
To: Town of Vail Job No. 10-039 Date: 9/24/10
Tom Kassmel,P.E.
Town Engineer Report#: 23D Sheet: 4 of 4
Department of Public Works/Transportation
1309 Elkhorn Drive
Vail,Colorado 81657
Project: Lionshead Transit Center,Vail, Colorado
Weather: � Sunny ❑ Cloudy ❑ Rain ❑ Snow Temp: 78°F±
Reinforcing Steel (Rebar) Observations:
Type of Structure: (Wall, Grade Beam, Footin�, Slab-on-�rade, etc.): Footing Keyway
Location of Observations: Gridlines E E.3/E-0 to E-1
Sheet or Plan Number: 5200 and 5213-5
Meets Project Spec.
Footing Keyway Rebar: Gridlines E E.3/E-0 to E-1 yes no
Horizontal: Size: 2 - #5 Spacing: Bottom � ❑
Horizontal: Size: 4 - #5 Spacing: As per plans � ❑
Vertical: Size: #9 Spacing: 1'-0" o.c. � ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) yes Length: 3'-0" � ❑
Meets Project Spec.
Rebar: yes no
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) Length: ❑ ❑
Discrepancies/Remarks: Based on our observations, it is our opinion that the reinforcing steel (rebar) yes no
noted 'm this Daily Field Report has been properly placed and has met project specifications. � ❑
Mike Brath Scott B. Myers, P.E.
Field Observer Reviewed By
SOIL COMPACTION TEST RESULTS
To: Town of Vail KOECHLEIN CONSULTING ENGINEERS, INC. Job No. 10-039 Date: 9/24/10
Tom Kassmel,P.E. Report#: 24 Sheet: 1 of 1
Geotechnical and Materials Engineers
Town Engineer Lalcewood—(303)989-1223 Subject: Fill Observation and Testine
Department of Public Works/Transportation Grand Junction—(970)241-7700 Sidewalk Subgrade and
1309 Elkhorn Drive Sanitary Scwer Line Backfill
Vail,Colorado 81657 Lionshead Transit Center
Vail,Colorado
LaboraYo Field
Depth MaJCimum Optimum
Test Location or Dry Moisture Dry Moisture Percent Pass/Fail Soil Type
No. Elevation Density Content Density Content Compaction
(feet) cf� (%) cfl (%)
54 Sidewalk: Sta.00+50 Grade± 142.5 5.6 136.0 4.1 95 Pass Proctor by Others
G sum Pit-3/a"ABC
55 Sanitary Sewer Line: Sta. 1+60 -5.0-f- 130.3 7.9 129.7 6.5 100 Pass Curve#1
SAND Gravell Sil
56 Sanitary Sewer Line: Sta.2+00 -3.0± 130.3 7.9 1301 6.2 100 Pass Curve#1
SAND Gravell Sil
57 Sanitary Sewer Line: Sta.2+25 -1.0-�- 130.3 7.9 130.4 6.0 100 Pass Curve#1
SAND Gravell Sil
Weather: � Sum� ❑ Cloud ❑ Rain ❑ Snow Tem : 70°F± � Fill Tested Meets Specifications.
Specification Compaction&Material: Sidewalk: 95%of Modified Proctor ASTM D ❑ Fill Tested Does Not Meet Specifications as Indicated by Test Number(s)
1557,+2%to-2°/o of Optimum Moisture Content. Sanitarv Sewer Line: 100%of Standard and Should be Removed or Reworked.
Proctor AASHTO T 99,+2°/a to-2%of Optimum Moisture Content.
Type and Number of Earth Moving Units: 1-Tracichoe � Contractor Advised.
❑ Full Time Observation. � Part Time Observation.
Type and Number of Compaction Units: 1-Vibe Skid Plate Progress Report: Field engineer arrived on-site, as requested, to observe and test
sidewalk sLibgrade and sanitary sewer line backfill. Test results indicate that moisture and
Number of Passes: Varies Thickness of Lift: 8 inches densiry tests performed at the noted locations have met project specifications.
Method of Adding Moisture: N/A
This re�ort presents opinions formed as a result of our observations and/or compaction testing of the fill during this visit.
We have relied o��the contrac[or to continue applying the recommended compactive effort and moisture to the fill during
times when our observer is not observing operations. Tests are made of the fill only as believed necessary to calibrate our
observer's jud ment. Test data are not tlie sole basis fir o inions on whether the till meets s ecificatious.
Mike Brath Scott B. Myers, P.E.
Field Observer Reviewed By