HomeMy WebLinkAbout10-039 Daily Field Reports 57 to 62 REINFORCING STEEL (REBAR) OBSERVATION
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Lakewood—(303)989-1223
Grand Junction—(970)241-7700
To: Town of Vail Job No. 10-039 Date: ll/ll/10
Tom Kassmel,P.E.
Town Engineer Report#: 57A Sheet: 1 of 2
Department of Public Works/Transportation
1309 Elkhorn Drive
Vail,Colorado 81657
Project: Lionshead Transit Center,Vail, Colorado
Weather: ❑ Sunny � Cloudy ❑ Rain � Snow Temp: 30°F±
Reinforcing Steel (Rebar) Observations:
Type of Structure: (Wall, Grade Beam, Footin�, Slab-on-�rade, etc.): ECO Building Foundation Walls
Location of Observations: Gridlines A.0/61-8.0 and A.0-C.0/6.1
Sheet or Plan Number: S 100, 9/S 120, and 12/S 120
Meets Project Spec.
ECO Building Foundation Wall Rebar: Gridlines A.0/6.1-8.0 yes no
Horizontal: Size: #5 Spacing: 1'-4"o.c. at inside face � ❑
Horizontal: Size: #5 Spacing: 1'-4" o.c. at outside face � ❑
Vertical: Size: #5 Spacing: 1'-0"o.c. at inside face � ❑
Vertical: Size: #5 Spacing: 1'-4" o.c. at outside face � ❑
Corner bars: Size: #5 Spacing: 1'-4" o.c. each face at Gridlines A.0/6.1 � ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) no Length: ❑ ❑
Meets Project Spec.
ECO Building Foundation Wall Rebar: Gridlines A.0-C.0/6.1 yes no
Vertical: Size: #5 Spacing: 1'-0"o.c. at inside face � ❑
Vertical: Size: #5 Spacing: 1'-4" o.c. at outside face � ❑
Horizontal: Size: #5 Spacing: 1'-4"o.c. at inside face ❑ �
Horizontal: Size: #5 Spacing: 1'-4" o.c. at outside face ❑ �
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) no Length: ❑ ❑
Discrepancies/Remarks: Based on our observations, it is our opinion that the reinforcing steel (rebar) yes no
noted in this Daily Field Report has not been properly placed and has failed to meet project ❑ �
specifications.
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
REINFORCING STEEL (REBAR) OBSERVATION
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Lakewood—(303)989-1223
Grand Junction—(970)241-7700
To: Town of Vail Job No. 10-039 Date: ll/ll/10
Tom Kassmel,P.E.
Town Engineer Report#: 57B Sheet: 2 of 2
Department of Public Works/Transportation
1309 Elkhorn Drive
Vail,Colorado 81657
Project: Lionshead Transit Center,Vail, Colorado
Weather: ❑ Sunny � Cloudy ❑ Rain � Snow Temp: 30°F±
Reinforcing Steel (Rebar) Observations:
Type of Structure: (Wall, Grade Beam, Footin�, Slab-on-�rade, etc.): ECO Building Coluinn
Location of Observations: Gridlines B.0-C.0/2.0
Sheet or Plan Number: 5100 and 10/5311-CP1
Meets Project Spec.
ECO Building Column Rebar: Gridlines B.0-C.0/2.0 yes no
Vertical: Size: 16 - #8 Spacing: As per configuration � ❑
Ties: Size: #4 Spacing: 1'-0" o.c. � ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) no Length: ❑ ❑
Meets Project Spec.
Rebar: yes no
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) Length: ❑ ❑
Discrepancies/Remarks: Based on our observations, it is our opinion that the reinforcing steel (rebar) yes no
noted 'm this Daily Field Report has been properly placed and has met project specifications. � ❑
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
REINFORCING STEEL (REBAR) OBSERVATION
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Lakewood—(303)989-1223
Grand Junction—(970)241-7700
To: Town of Vail Job No. 10-039 Date: ll/12/10
Tom Kassmel,P.E.
Town Engineer Report#: 58 Sheet: 1 of 1
Department of Public Works/Transportation
1309 Elkhorn Drive
Vail,Colorado 81657
Project: Lionshead Transit Center,Vail, Colorado
Weather: � Sunny ❑ Cloudy ❑ Rain ❑ Snow Temp: 42°F±
Reinforcing Steel (Rebar) Observations:
Type of Structure: (Wall, Grade Beam, Footin�, Slab-on-�rade, etc.): ECO Building Foundation Wall
Location of Observations: Gridlines A.0-C.0/6.1
Sheet or Plan Number: S 100 and 12/S 120
Meets Project Spec.
ECO Building Foundation Wall Rebar: Gridlines A.0-C.0/6.1 yes no
Vertical: Size: #5 Spacing: 1'-0"o.c. inside face � ❑
Vertical: Size: #5 Spacing: 1'-4" o.c. outside face � ❑
Horizontal: Size: #5 Spacing: 1'-4"o.c. inside face � ❑
Horizontal: Size: #5 Spacing: 1'-4" o.c. outside face � ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) no Length: ❑ ❑
Meets Project Spec.
Rebar: yes no
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) Length: ❑ ❑
Discrepancies/Remarks: Based on our observations, it is our opinion that the reinforcing steel (rebar) yes no
noted 'm this Daily Field Report has been properly placed and has met project specifications. � ❑
Mike Brath Scott B. Myers, P.E.
Field Observer Reviewed By
REINFORCING STEEL (REBAR) OBSERVATION
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Lakewood—(303)989-1223
Grand Junction—(970)241-7700
To: Town of Vail Job No. 10-039 Date: ll/13/10
Tom Kassmel,P.E.
Town Engineer Report#: 59A Sheet: 1 of 4
Department of Public Works/Transportation
1309 Elkhorn Drive
Vail,Colorado 81657
Project: Lionshead Transit Center,Vail, Colorado
Weather: ❑ Sunny � Cloudy ❑ Rain � Snow Temp: 28°F±
Reinforcing Steel (Rebar) Observations:
Type of Structure: (Wall, Grade Beam, Footin�, Slab-on-�rade, etc.): Columns
Location of Observations: Gridlines B.0-C.0/1.0 and A.0/6.0
SheetorPlanNumber: 5100, 10/S3ll-CP1, 5101, and 10/5311-CP2
Meets Project Spec.
Column Rebar: Gridlines B.0-C.0/1.0 yes no
Vertical: Size: 16 - #8 Spacing: As per configuration � ❑
Ties: Size: #4 Spacing: 1'-0" o.c. � ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) no Length: ❑ ❑
Meets Project Spec.
Column Rebar: Gridlines A.0/6.0 yes no
Vertical: Size: 8 - #8 Spacing: As per configuration � ❑
Ties: Size: #4 Spacing: 1'-0" o.c. � ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) no Length: ❑ ❑
Discrepancies/Remarks: Based on our observations, it is our opinion that the reinforcing steel (rebar) yes no
noted 'm this Daily Field Report has been properly placed and has met project specifications. � ❑
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
REINFORCING STEEL (REBAR) OBSERVATION
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Lakewood—(303)989-1223
Grand Junction—(970)241-7700
To: Town of Vail Job No. 10-039 Date: ll/13/10
Tom Kassmel,P.E.
Town Engineer Report#: 59B Sheet: 2 of 4
Department of Public Works/Transportation
1309 Elkhorn Drive
Vail,Colorado 81657
Project: Lionshead Transit Center,Vail, Colorado
Weather: ❑ Sunny � Cloudy ❑ Rain � Snow Temp: 28°F±
Reinforcing Steel (Rebar) Observations:
Type of Structure: (Wall, Grade Beam, Footin�, Slab-on-�rade, etc.): Foundation Walls
Location of Observations: Gridlines C.0/6.0-8.0 and A.0-C.0/8.0
Sheet or Plan Number: S 100, 3/120-3, and 6/S 120
Meets Project Spec.
Foundation Wall Rebar: Gridlines C.0/6.0-8.0 yes no
Vertical: Size: #5 Spacing: 1'-4" o.c. outside face � ❑
Horizontal: Size: #5 Spacing: 1'-4" o.c. outside face � ❑
Vertical: Size: #5 Spacing: 1'-0"o.c. inside face � ❑
Horizontal: Size: #5 Spacing: 1'-0"o.c. inside face � ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) no Length: ❑ ❑
Meets Project Spec.
Foundation Wall Rebar: Gridlines A.0-C.0/8.0 yes no
Vertical: Size: #5 Spacing: 1'-0"o.c. inside face � ❑
Vertical: Size: #5 Spacing: 1'-4" o.c. outside face � ❑
Horizontal: Size: #5 Spacing: 1'-4" o.c. each face � ❑
Corner bars: Size: #5 Spacing: 1'-4" o.c. each face � ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) no Length: ❑ ❑
Discrepancies/Remarks: Based on our observations, it is our opinion that the reinforcing steel (rebar) yes no
noted 'm this Daily Field Report has been properly placed and has met project specifications. � ❑
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
REINFORCING STEEL (REBAR) OBSERVATION
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Lakewood—(303)989-1223
Grand Junction—(970)241-7700
To: Town of Vail Job No. 10-039 Date: ll/13/10
Tom Kassmel,P.E.
Town Engineer Report#: 59C Sheet: 3 of 4
Department of Public Works/Transportation
1309 Elkhorn Drive
Vail,Colorado 81657
Project: Lionshead Transit Center,Vail, Colorado
Weather: ❑ Sunny � Cloudy ❑ Rain � Snow Temp: 28°F±
Reinforcing Steel (Rebar) Observations:
Type of Structure: (Wall, Grade Beam, Footin�, Slab-on-�rade, etc.): Foundation Wall
Location of Observations: Gridlines A.3-B.0/0.0 and B.0/0.0-1.0
Sheet or Plan Number: S 100 and 3/S 121
Meets Project Spec.
Foundation Wall Rebar: Gridlines yes no
Horizontal: Size: #5 Spacing: 1'-0" o.c. inside face � ❑
Vertical: Size: #5 Spacing: 1'-0"o.c. inside face � ❑
Horizontal: Size: #5 Spacing: 1'-4" o.c. outside face � ❑
Vertical: Size: #7 Spacing: 1'-0" o.c. outside face � ❑
Corner bars: Size: #5 Spacing: 1'-0" and 1'-4" o.c. to match horizontal � ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) no Length: ❑ ❑
Meets Project Spec.
Rebar: yes no
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) Length: ❑ ❑
Discrepancies/Remarks: Based on our observations, it is our opinion that the reinforcing steel (rebar) yes no
noted 'm this Daily Field Report has been properly placed and has met project specifications. � ❑
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
REINFORCING STEEL (REBAR) OBSERVATION
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Lakewood—(303)989-1223
Grand Junction—(970)241-7700
To: Town of Vail Job No. 10-039 Date: ll/13/10
Tom Kassmel,P.E.
Town Engineer Report#: 59D Sheet: 4 of 4
Department of Public Works/Transportation
1309 Elkhorn Drive
Vail,Colorado 81657
Project: Lionshead Transit Center,Vail, Colorado
Weather: ❑ Sunny � Cloudy ❑ Rain � Snow Temp: 28°F±
Reinforcing Steel (Rebar) Observations:
Type of Structure: (Wall, Grade Beam, Footin�, Slab-on-�rade, etc.): Foundation Walls
Location of Observations: Gridlines C.0/1.0-6.0, B.0-C.0/2.7, and B.0/2.7-3.4
Sheet or Plan Number: S 100, 3/S 121, and 6/S 121
Meets Project Spec.
Foundation Wall Rebar: Gridlines C.0/1.0-6.0 yes no
Horizontal: Size: #5 Spacing: 1'-0"o.c. inside face � ❑
Vertical: Size: #5 Spacing: 1'-0"o.c. inside face ❑ �
Horizontal: Size: #5 Spacing: 1'-4" o.c. outside face � ❑
Vertical: Size: #7 Spacing: 1'-0" o.c. outside face � ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) yes Length: 3'-2.5"at horizontal ❑ ❑
Meets Project Spec.
Foundation Wall Rebar: Gridlines B.0-C.0/2.7 and B.0/2.7-3.4 yes no
Horizontal: Size: #5 Spacing: 1'-4" o.c. each face � ❑
Vertical: Size: #5 Spacing: 1'-0" o.c. each face � ❑
Corner bars: Size: #5 Spacing: 1'-4" o.c. each face � ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) no Length: ❑ ❑
Discrepancies/Remarks: Based on our observations, it is our opinion that the reinforcing steel (rebar) yes no
noted in this Daily Field Report has not been properly placed and has failed to meet project ❑ �
specifications.
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
REINFORCING STEEL (REBAR) OBSERVATION
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Lakewood—(303)989-1223
Grand Junction—(970)241-7700
To: Town of Vail Job No. 10-039 Date: ll/15/10
Tom Kassmel,P.E.
Town Engineer Report#: 60A Sheet: 1 of 2
Department of Public Works/Transportation
1309 Elkhorn Drive
Vail,Colorado 81657
Project: Lionshead Transit Center,Vail, Colorado
Weather: ❑ Sunny � Cloudy ❑ Rain ❑ Snow Temp: 28°F±
Reinforcing Steel (Rebar) Observations:
Type of Structure: (Wall, Grade Beam, Footin�, Slab-on-�rade, etc.): ECO Building Foundation Walls
Location of Observations: Gridlines C.0/1.0-6.0, A.0-B.0/3.4, and A.2/5.5-6.1
Sheet or Plan Number: S 100, 3/S 121, and 6/5312
Meets Project Spec.
ECO Building Foundation Wall Rebar: Gridlines C.0/1.0-6.0 yes no
Horizontal: Size: #5 Spacing: 1'-0"o.c. inside face � ❑
Vertical: Size: #5 Spacing: 1'-0"o.c. inside face � ❑
Horizontal: Size: #5 Spacing: 1'-4" o.c. outside face � ❑
Vertical: Size: #7 Spacing: 1'-0" o.c. outside face � ❑
Corner bars: Size: #5 Spacing: 1'-0"o.c. inside face � ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) yes Length: 3'-2.5" at horizontal � ❑
Meets Project Spec.
ECO Building Foundation Walls Rebar: Gridlines A.0-B.0/3.4 and A.2/5.5-6.1 yes no
Vertical: Size: #5 Spacing: 1'-0" o.c. � ❑
Horizontal: Size: #5 Spacing: 1'-0" o.c. � ❑
Corner bars: Size: #5 Spacing: 1'-0" o.c. � ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) yes Length: 3'-1.0"at horizontal � ❑
Discrepancies/Remarks: Based on our observations, it is our opinion that the reinforcing steel (rebar) yes no
noted in this Daily Field Report has been properly placed and has met project specifications. � ❑
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
REINFORCING STEEL (REBAR) OBSERVATION
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Lakewood—(303)989-1223
Grand Junction—(970)241-7700
To: Town of Vail Job No. 10-039 Date: ll/15/10
Tom Kassmel,P.E.
Town Engineer Report#: 60B Sheet: 2 of 2
Department of Public Works/Transportation
1309 Elkhorn Drive
Vail,Colorado 81657
Project: Lionshead Transit Center,Vail, Colorado
Weather: ❑ Sunny � Cloudy ❑ Rain ❑ Snow Temp: 28°F±
Reinforcing Steel (Rebar) Observations:
Type of Structure: (Wall, Grade Beam, Footin�, Slab-on-�rade, etc.): ECO Building Foundation wall openings
Location of Observations: Gridlines C.0/6.0-6.5 and B.0-C.0/8.0 from Mid-height to Top of Wall
Sheet or Plan Number: S 100 and 5300-12
Meets Project Spec.
ECO Building Foundation Wall Openings Rebal': Gridlines C.0/6.0-6.5 and B.0-C.0/8.0 from Mid-height to Top of Wall yeS ri0
Around opening: Size: #5 Spacing: Add '/z number of bars plus 1 at 0'-3" � ❑
o.c.
Corner bars: Size: 2 - #5 Spacing: At corners, observed � ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) no Length: ❑ ❑
Meets Project Spec.
Rebar: yes no
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) Length: ❑ ❑
Discrepancies/Remarks: Based on our observations, it is our opinion that the reinforcing steel (rebar) yes no
noted in this Daily Field Report has been properly placed and has met project specifications. � ❑
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
REPORT OF CONSTRUCTION ACTIVITIES
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Lakewood—(303)989-1223
Grand Junction—(970)241-7700
To: Town of Vail Job No. 10-039 Date: ll/16/10
Tom Kassmel,P.E.
Town Engineer Report#: 61A Sheet: 1 of 3
Department of Public Works/Transportation
1309 Elkhorn Drive
Vail,Colorado 81657
Project: Lionshead Transit Center,Vail, Colorado
Weather: ❑ Sunny � Cloudy ❑ Rain � Snow Temp: 27°F±
Construction Activities/Observations: Field engineer arrived on site, as requested,to observe waterproofmg for the
snow storage retaining wall 14'-6"to 30'-3"west of Gridline E-1/E-B.1 to E-D.S.
Field engineer observed that the waterproofing was in place on the interior of the wall from the north to the south end
and to approximately 6.25"from the top of the wall.
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
SOIL COMPACTION TEST RESULTS
To: Town of Vail KOECHLEIN CONSULTING ENGINEERS, INC. Job No. 10-039 Date: ll/16/10
Tom Kassmel,P.E. Report#: 61B Sheet: 2 of 3
Geotechnical and Materials Engineers
Town Engineer Subject: Fill Observation and Testine
Department of Public Works/Transpartation Lalcewood-(303)989-1223 Snow Starage Slab-on-grade Backfill
1309 Elkhorn Drive Grand Junction-(970)241-7700 Lionshead Transit Center
Vail,Colorado 81657 Vail,Colorado
Laborato Field
Depth Mauimum Optimum
Test Location or Dry Moisture Dry Moisture Percent Pass/Fail Soil Type
No. Elevation Density Content Density Content Compaction
(feet) cfj (%) c� (%)
194 21'West of Gridlines�1/E-D.4 -L0± 130.3 7.9 128.1 9.0 98 Fail Curve#1
SAND Gravell Sil
195 18'West of Gridlines&1/E-E.5 -2.0± 130.3 7.9 123.8 101 95 Fail Curve#1
SAND Gravell Sil
196 27'West of Gridlines�1/E-B.6 -3.0± 130.3 7.9 126.2 10.0 97 Fail Curve#1
SAND Gravell Sil
197 Retest of Test#194 -1.0± 130.3 7.9 129.7 9.6 100 Pass Curve#1
SAND Gravell Sil
198 Retest of Test#195 -2.0± 130.3 7.9 131.1 10.3 100 Pass Curve#1
SAND Gravell Sil
199 Retest of Test#196 -3.0± 130.3 7.9 130.7 10.5 100 Pass Curve#1
SAND Gravell Sil
Weather: ❑ Sunn � Cloud ❑ Rain � Snow Tem : 26°F± � Fill Tested Meets Specifications.
Specification Compaction&Material: 100%of Standard Proctor AASHTO T 99,+2°/o ❑ Fill Tested Does Not Meet Specifications as Indicated by Test Number(s)
to-2°/o of Optimum Moisture Content and Should be Removed or Reworked.
Type and Number of Earth Moving Units: 1-Trackhoe � Contractor Advised.
❑ Full Time Observation. � Part Time Observation.
Type and Number of Compaction Units: 1-Walk-behind Progress Report: Field engineer arrived on-site, as requested, to observe and test snow
storage slab-on-grade bacicfill 14'-6" to 30'-3" west of Gridline �1/E-B.1 to E�D.S. The
Number of Passes: Varies Thickness of Lift: Unknown failing area was further compacted. Test results indicate that moisture and density tests
Method of Adding Moisture: None performed at the noted locations have inet project specificarions.
This report presents opinions formed as a rosult of our observations and/or compaction testing of the fill during this visit.
We have relied on the co��tractar to continue applying the recommended compactive effort and moisture to the fill during
times when our obscrver is not observing operations. Tests are made of the fill only as believed necessary ro calibrate our
observer's'ud ment. Test data are not the sole basis for o inions on whether the fill meets s ecifications.
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
REINFORCING STEEL (REBAR) OBSERVATION
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Lakewood—(303)989-1223
Grand Junction—(970)241-7700
To: Town of Vail Job No. 10-039 Date: ll/16/10
Tom Kassmel,P.E.
Town Engineer Report#: 61C Sheet: 3 of 3
Department of Public Works/Transportation
1309 Elkhorn Drive
Vail,Colorado 81657
Project: Lionshead Transit Center,Vail, Colorado
Weather: ❑ Sunny � Cloudy ❑ Rain � Snow Temp: 26°F±
Reinforcing Steel (Rebar) Observations:
Type of Structure: (Wall, Grade Beam, Footin�, Slab-on-�rade, etc.): North and South Cantilever ltetaining wall
Caps at Southwest Parking Entrance
Location of Observations: Gridline E-1 to 61'-2.5"West, on Gridlines E-E.2 and E-E.7
Sheet or Plan Number: 5200, 5/5213, 11/5213, and 9/5319
Meets Project Spec.
Re�2ffill1g�J�7�CapS Relj�2': Gridline E-1 to 61'-2.5"West,on Gridlines E-E.2 and E-E.7 yeS T10
Bottom: Size: 3 - #5 Spacing: Continuous � ❑
Dowels: Size: #4 Spacing: 1'-0"o.c., altemating directions � ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) yes Length: 14'-4" � ❑
Meets Project Spec.
Rebar: yes no
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) Length: ❑ ❑
Discrepancies/Remarks: Based on our observations, it is our opinion that the reinforcing steel (rebar) yes no
noted in this Daily Field Report has been properly placed and has met project specifications. � ❑
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
SOIL COMPACTION TEST RESULTS
To: Town of Vail KOECHLEIN CONSULTING ENGINEERS, INC. Job No. 10-039 Date: ll/17/10
Tom Kassmel,P.E. Report#: 62 Sheet: 1 of 1
Geotechnical and Materials Engineers
Town Engineer Subject: Fill Observation and Testine
Department of Public Works/Transpartation Lalcewood—(303)989-1223 Snow Starage Slab-on-grade Backfill
1309 Elkhorn Drive Grand Junction—(970)241-7700 Lionshead Transit Center
Vail,Colorado 81657 Vail,Colorado
Laborato Field
Depth Mauimum Optimum
Test Location or Dry Moisture Dry Moisture Percent Pass/Fail Soil Type
No. Elevation Density Content Density Content Compaction
(feet) cfj (%) c� (%)
200 18'West of Gridlines�1/E-B.3 -2.0± 130.3 7.9 124.6 11.1 96 Fail Curve#1
(moisture) SAND Gravell Sil
201 26'West of Gridlines&1/E-C -0.5± 130.3 7.9 124.8 ll.3 96 Fail Curve#1
(moisture) SAND Gravell Sil
202 21' West of Gridlines E-1/E-D.2 Grade± 130.3 7.9 120.9 12.1 93 Fail Curve#1
SAND Gravell Sil
Weather: ❑ Sunn � Cloud ❑ Rain ❑ Snow Tem : 32°F± ❑ Fill TestedMeets Specifications.
Specification Compaction&Material: 95%of Standard Proctor AASHTO T 99,+2%to � Fill Tested Does Not Meet Specifications as Indicated by Test Number(s)
-2%of Optimum Moisture Content 200,201,and 202,and Should be Removed or Reworked.
Type and Number of Earth Moving Units: 1-Trackhoe � Contractor Advised.
❑ Full Time Observation. � Part Time Observation.
Type and Number of Compaction Units: 1-Walk-behind Progress Report: Field engineer arrived on-site, as requested, to observe and test snow
storage slab-on-grade backfill. Test results indicate that moisture and density tests
Number of Passes: Varies Thickness of Lift: Unknown performed at the noted locations have failed to meet project specifications.
Method of Adding Moisture: None
This report prosents opinions formed as a result of our observations and/or compaction testing of the fill during this visit.
We have relied on the contractor to continue applying the recommended compactive effort and moisture to tlie fill during
times when our observer is not observing operations. Tests are made of the fill only as beli�ved necessary to calibrate our
observer's jud ment Test data are not the sole basis for o inions on whether the fill meets s ecifications.
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By