HomeMy WebLinkAbout10-039 Daily Field Reports 74 to 79 SOIL COMPACTION TEST RESULTS
To: Town of Vail KOECHLEIN CONSULTING ENGINEERS, INC. Job No. 10-039 Date: 12/8/10
Tom Kassmel,P.E. Report#: 74A Sheet: 1 of 3
Geotechnical and Materials Engineers
Town Engineer Lalcewood-(303)989-1223 Subject: Fill Observation and Testine
Department of Public Works/Transportation Grand Junction-(970)241-7700 Interior and Exterior Slab-on-grade and
1309 Elkhorn Drive Foundation Wall Fill
Vail,Colorado 81657 ECO Building
Lionshead Transit Center
Vail,Colorado
Laborato Field
Depth Maximum Optimum
Test Location or Dry Moisture Dry Moisture Percent Pass/Fail Soil Type
No. Elevation Density Content Density Content Compaction
(feet) c� (%) c� (%)
221 Gridlines A.9/1.9 -6.5± 130.3 7.9 131.3 8.3 100 Pass Curve#1
SAND Gravell Sil
222 9'North of Gridlines A.0/1.0 -6.5± 130.3 7.9 127.2 10.3 98 Pass Curve#1
SAND Gravell Sil
223 Gridlines A.8/5.4 -13.0± 130.3 7.9 132.5 8.1 100 Pass Curve#1
SAND Gravell Sil
224 Gridlines A.4/3.7 -13.0± 130.3 7.9 131.8 9.1 100 Pass Curve#1
SAND Gravell Sil
225 8'North of Gridlines A.0/4.5 -13.0± 130.3 7.9 132.5 7.9 100 Pass Curve#1
SAND Gravell Sil
226 Gridlines A.7/3.6 -12.0± 131.1 7.7 126.0 8.0 96 Pass Ciuve#2
SAND Gravell Sil
227 5'North of Gridlines A.0/7.1 -13.5± 130.3 7.9 132.8 8.4 100 Pass Curve#1
SAND Gravell Sil
Weather: ❑ Sunny � Cloudy ❑ Rain ❑ Snow Temp: 17°-30°F± � Fill Tested Meets Specifications.
Specification Compaction&Material: 95%of Standard Proctor ASTM D 698, ❑ Fill Tested Does Not Meet Specifications as Indicated by Test Number(s)
+2%to-2%of Optimum Moisture Content and Should be Removed or Reworked.
Type and Number of Earth Moving Units: 2-Tracichoes, 1-Bobcat � Contractor Advised.
❑ Full Time Observation. � Part Time Observation.
Type and Number of Compaction Units: 1-Walk-behind, 1-Jumping jack Progress Report: Field engineer arrived on-site, as requested, to observe and test fill for
the interior and exterior slab-on-grade and foundation wall for the ECO Building. Test
Number of Passes: Varies Thickness of Lift: 8 inches results indicate that moisture and density tests performed at the noted locations have met
Method of Adding Moisture: None/Water truck for import project specifications.
This report presents opinions formed as a result of our observations and/or com�action testing of the fill during this visit.
We have relied on the coi�trac[ar to continue applying the recommended compactive effort and�noisture to the fill during
times when our observer is not observing operations. Tests are made of the fill only as believed necessary to calibrate our
observer's jud ment. Test data are not the sole basis for o i��ions on whether the fill meets s ecifications.
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
SOIL COMPACTION TEST RESULTS
To: Town of Vail KOECHLEIN CONSULTING ENGINEERS, INC. Job No. 10-039 Date: 12/8/10
Tom Kassmel,P.E. Report#: 74B Sheet: 2 of 3
Geotechnical and Materials Engineers
Town Engineer Lalcewood-(303)989-1223 Subject: Fill Observation and Testine
Department of Public Works/Transportation Grand Junction-(970)241-7700 Interior and Extcrior Slab-on-grade and
1309 Elkhorn Drive Exterior Foundation Wall Fill
Vail,Colorado 81657 ECO Building
Lionshead Transit Center
Vail,Colarado
Laborato Field
Depth Maximum Optimum
Test Location or Dry Moisture Dry Moisture Percent Pass/Fail Soil Type
No. Elevation Density Content Density Content Compaction
(feet) c� (%) c� (%)
228 Gridlines A.6/5.4 -ll.5± 131.1 7.7 132.8 9.2 100 Pass Curve#2
SAND Gravell Sil
229 Gridlines B.5/3.0 -12.5± 131.1 7.7 128.3 10.3 98 Pass Curve#2
SAND Gravell Sil
230 7'North of Gridlines A.0/5.7 -11.5± 131.1 7.7 132.9 7.9 100 Pass Curve#2
SAND Gravell Sil
231 Gridlines A.3/5.5 -11.0± 131.1 7.7 129.7 9.1 99 Pass Curve#2
SAND Gravell Sil
232 Gridlines A.6/4.1 -10.5± 131.1 7.7 133.9 7.7 100 Pass Curve#2
SAND Gravell Sil
233 Gridlines A.6/2.6 -6.0± 131.1 7.7 131.8 8.4 100 Pass Ciuve#2
SAND Gravell Sil
Weather: ❑ Sunn ❑ Cloud ❑ Rain ❑ Snow Tem : °F± � Fill Tested Meets Specifications.
Specification Compaction&Material: 95%of Standard Proctor ASTM D 698, ❑ Fill Tested Does Not Meet Specifications as Indicated by Test Number(s)
+2%to-2%of Optimum Moisture Content and Should be Removed or Reworked.
Type and Number of Earth Moving Units: 2-Tracichoes, 1-Bobcat � Contractor Advised.
❑ Full Time Observation. � Part Time Observation.
Type and Number of Compaction Units: 1-Walk-behind, 1-Jumping jack Progress Report: See Sheet 1 of 3.
Number of Passes: Varies Thickness of Lift: 8 inches
Method of Adding Moisture: Water truck and hose assembly
This report�resents opinions fonned as a result of our observations and/or compaction testing of the fill during this visit.
We have relied on the coi�trac[ar to continue applying the recommended compactive effort and�noisture to the fill during
times when our observer is not observing operations. Tests are made of the fill only as believed necessary to calibrate our
observer's jud ment. Test data are not the sole basis for o i��ions on whether the fill meets s ecifications.
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
REINFORCING STEEL (REBAR) OBSERVATION
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Lakewood—(303)989-1223
Grand Junction—(970)241-7700
To: Town of Vail Job No. 10-039 Date: 12/8/10
Tom Kassmel,P.E.
Town Engineer Report#: 74C Sheet: 3 of 3
Department of Public Works/Transportation
1309 Elkhorn Drive
Vail,Colorado 81657
Project: Lionshead Transit Center,Vail, Colorado
Weather: ❑ Sunny ❑ Cloudy ❑ Rain ❑ Snow Temp: 43°F± in enclosed area
Reinforcing Steel (Rebar) Observations:
Type of Structure: (Wall, Grade Beam, Footin�, Slab-on-�rade, etc.): 2"`�to 3rd Level Stairs
Location of Observations: Gridlines E 1 to E-1.4, �A to E-A.2
Sheet or Plan Number: 5201, 1/5215, 2/5215, and 4/5215
Meets Project Spec.
2"d to 3rd Level Stairs Rebar: Gridlines E-1 to E-1.4, E-A to E-A.2 yes no
Top and bottom: Size: #6 Spacing: 1'-0"o.c. north to south � ❑
Top and bottom: Size: #4 Spacing: 1'-0" o.c. east to west � ❑
Dowels: Size: #5 Spacing: 0'-8" o.c. top and bottom for landing � ❑
Top and bottom: Size: #6 Spacing: 0'-8" east to west � ❑
Top and bottom: Size: #6 Spacing: 1'-0"o.c. north to south � ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) yes Length: 2'-11.5"North to Sou�h at Landing � ❑
Meets Project Spec.
Rebar: yes no
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) Length: ❑ ❑
Discrepancies/Remarks: Based on our observations, it is our opinion that the reinforcing steel (rebar) yes no
noted in this Daily Field Report has been properly placed and has met project specifications. � ❑
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
REPORT OF CONSTRUCTION ACTIVITIES
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Lakewood—(303)989-1223
Grand Junction—(970)241-7700
To: Town of Vail Job No. 10-039 Date: 12/9/10
Tom Kassmel,P.E.
Town Engineer Report#: 75A Sheet: 1 of 4
Department of Public Works/Transportation
1309 Elkhorn Drive
Vail,Colorado 81657
Project: Lionshead Transit Center,Vail, Colorado
Weather: ❑ Sunny � Cloudy ❑ Rain ❑ Snow Temp: 29° - 36°F±
Construction Activities/Observations: Field engineer arrived on site, as requested, to observe 3/4 inch rock placed
against the foundation wall between Gridlines B-GO-8 and E-A/E-9.8 to E-13 (S 101).
The contractor was in the process of placing approximately 11 feet of 3/4 inch rock in the area. The first lift was
approximately 1.5 feet. Field engineer informed fi�e contractor to place approximately 8 inch lifts unless a bigger
tamping plate was used. The 3/4 inch rocic below the electrical conduits were placed and compacted to approximately
28 inches from the bottom of the conduits. The remainder of the space will have loose 3/a inch rock, as it is not
accessible by tamping plate. Some flowfill will be placed, according to the contractar. The 3/4 inch rock that was
compacted was medium dense. Field engineer observed rock placement to a depth of approximately 5 feet.
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
SOIL COMPACTION TEST RESULTS
To: Town of Vail KOECHLEIN CONSULTING ENGINEERS, INC. Job No. 10-039 Date: 12/9/10
Tom Kassmel,P.E. Report#: 75B Sheet: 2 of 4
Geotechnical and Materials Engineers
Town Engineer Lalcewood-(303)989-1223 Subject: Fill Observation and Testine
Department of Public Works/Transportation Grand Junction-(970)241-7700 Interiar Slab-on-grade and Grade Beam Fill
1309 Elkhorn Drive ECO Building
Vail,Colorado 81657 Lionshead Transit Center
Vail,Colorado
LaboraYo Field
Depth MaJCimum Optimum
Test Location or Dry Moisture Dry Moisture Percent Pass/Fail Soil Type
No. Elevation Density Content Density Content Compaction
(feet) cf� (%) cfl (%)
234 Gridlines A.6/2.0(grade beam) -2.5± 131.1 7.7 132.7 7.4 100 Pass Curve#2
SAND Gravell Sil
235 Gridlines A.3/1.0(grade beam) -2.0-E- 131.1 7.7 124.0 9.6 95 Fail Curve#2
SAND Gravell Sil
236 Gridlines A.0/0.5(grade beam) Grade± 131.1 7.7 1331 8.3 100 Pass Curve#2
SAND Gravell Sil
237 Retest of Test#235(grade beam) -2.0-E- 131.1 7.7 131.4 7.9 100 Pass Curve#2
SAND Gravell Sil
238 Gridlines A.9/2.0(grade beam) -2.0± 131.1 7.7 133.3 6.5 100 Pass Curve#2
SAND Gravell Sil
239 Gridlines A.9/1.0(grade beam) -1.5-f- 131.1 7.7 134.3 8.5 100 Pass Curve#2
SAND Gravell Sil
240 Gridlines A.4/0.7(slab-on-grade) -2.0± 131.1 7.7 126.7 8.3 97 Pass Curve#2
SAND Gravell Sil
Weather: ❑ Sum� ❑ Cloud ❑ Rain ❑ Snow Tem : °F± � Fill Tested Meets Specifications.
Specification Compaction&Material: 95%(slab-on-grade)or 98%(grade beams)of ❑ Fill Tested Does Not Meet Specifications as Indicated by Test Number(s)
Standard Proctor ASTM D 698,+2%to-2%of Optimum Moisture Content and Should be Removed or Reworked.
Type and Number of Earth Moving Units: 1-Tracichoe, 1-Bobcat � Contractor Advised.
❑ Full Time Observation. � Part Time Observation.
Type and Number of Compaction Units: 1-Jumping jack, 1-Walk-behind Progress Report: Field engineer arrived on-site, as requested, to observe and test fill for
the interior slab-on-grade and grade beams for the ECO Building. Test results indicate that
Number of Passes: Varies Thickness of Lift: 8 inches moisture and density tests performed at the noted locations have met project
Method of Adding Moisture: Water truck and hose assembly specifications.
This report presents opinions formed as a result of our obseivations and/or compaction testing of the fill during this visit.
We have relied m�the contractar to continue applying the recommended compactive effbrt and moisture to the fill duri�g
times wl�en our observer is not observing operations. Tests are made of the fill only as believed necessary to calibrate our
observer's jud ment. Test data are not the sole basis for o i�ions on whether the fill meets s ecificatio�s.
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
SOIL COMPACTION TEST RESULTS
To: Town of Vail KOECHLEIN CONSULTING ENGINEERS, INC. Job No. 10-039 Date: 12/9/10
Tom Kassmel,P.E. Report#: 75C Sheet: 3 of 4
Geotechnical and Materials Engineers
Town Engineer Lalcewood—(303)989-1223 Subject: Fill Observation and Testine
Department of Public Works/Transportation Grand Junction—(970)241-7700 Interiar Slab-on-grade and Grade Beam Fill
1309 Elkhorn Drive ECO Building
Vail,Colorado 81657 Lionshead Transit Center
Vail,Colorado
LaboraYo Field
Depth MaJCimum Optimum
Test Location or Dry Moisture Dry Moisture Percent Pass/Fail Soil Type
No. Elevation Density Content Density Content Compaction
(feet) cf� (%) cfl (%)
241 Gridlines A.6/5.7(slab-on-grade) -9.5± 131.1 7.7 126.1 9.7 96 Pass Curve#2
SAND Gravell Sil
242 Gridlines A.4/3.7(slab-on-grade) -9.0-�- 131.1 7.7 124.6 101 95 Pass Curve#2
SAND Gravell Sil
243 Gridlines A.5/4.6(slab-on-grade) -8.0± 131.1 7.7 130.0 7.6 99 Pass Curve#2
SAND Gravell Sil
244 Gridlines B.0/4.0(grade beam) -8.0-�- 131.1 7.7 129.2 7.8 99 Pass Curve#2
SAND Gravell Sil
245 Gridlines A.8/2A(grade beam) Grade± 131.1 7.7 133.8 7.3 100 Pass Curve#2
SAND Gravell Sil
246 Gridlines A.6/1.0(grade beam) Grade± 131.1 7.7 134.9 6.2 100 Pass Curve#2
SAND Gravell Sil
Weather: ❑ Sunny � Cloudy ❑ Rain ❑ Snow Temp: 29°-56°°F± � Fill Tested Meets Specifications.
Specification Compaction&Material: 95%(slab-on-grade)or 98%(grade beams)of ❑ Fill Tested Does Not Meet Specifications as Indicated by Test Number(s)
Standard Proctor ASTM D 698,+2%to-2%of Optimum Moisture Content and Should be Removed or Reworked.
Type and Number of Earth Moving Units: 1-Tracichoe, 1-Bobcat � Contractor Advised.
❑ Full Time Observation. � Part Time Observation.
Type and Number of Compaction Units: 1-Walk-behind, 1-Jumping jack Progress Report: See Sheet 2 of 4.
Number of Passes: Varies Thickness of Lift: 8 inches
Method of Adding Moisture: Water truck and hose assembly
This report presents opinions formed as a result of our obseivations and/or compaction testing of the fill during this visit.
We have relied m�the contractar to continue applying the recommended compactive effbrt and moisture to the fill duri�g
times wl�en our observer is not observing operations. Tests are made of the fill only as belicved necessary to calibrate our
observer's jud ment. Test data are not the sole basis for o i�ions on whether the fill meets s ecificatio�s.
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
REINFORCING STEEL (REBAR) OBSERVATION
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Lakewood—(303)989-1223
Grand Junction—(970)241-7700
To: Town of Vail Job No. 10-039 Date: 12/9/10
Tom Kassmel,P.E.
Town Engineer Report#: 75D Sheet: 4 of 4
Department of Public Works/Transportation
1309 Elkhorn Drive
Vail,Colorado 81657
Project: Lionshead Transit Center,Vail, Colorado
Weather: ❑ Sunny ❑ Cloudy ❑ Rain ❑ Snow Temp: 54°F± in enclosed area
Reinforcing Steel (Rebar) Observations:
Type of Structure: (Wall, Grade Beam, Footin�, Slab-on-�rade, etc.): 2°d to 3�d Le�e�sta�rS,Land�ng Topp�ng and steps
Location of Observations: Gridlines E A to E-A.3, E-18.7 to E-19
Sheet or Plan Number: 5204 and 9/5316
Meets Project Spec.
2°d to 3`d Level Stairs,Landing Topping Relj�I': Grid]1rieS E 1�t0 E-l�.3, E-1 g.� t0 E-I9 yeS ri0
and Steps
Dowels: Size: #4 Spacing: 1'-0" each corner � ❑
Nosing bars: Size: #4 Spacing: Each corner � ❑
Bottom: Size: #4 Spacing: 1'-6"o.c. each way, each comer � ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) yes Length: 2'-8.5"at landing � ❑
Meets Project Spec.
Rebar: yes no
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) Length: ❑ ❑
Discrepancies/Remarks: Based on our observations, it is our opinion that the reinforcing steel (rebar) yes no
noted in this Daily Field Report has been properly placed and has met project specifications. � ❑
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
SOIL COMPACTION TEST RESULTS
To: Town of Vail KOECHLEIN CONSULTING ENGINEERS, INC. Job No. 10-039 Date: 12/10/10
Tom Kassmel,P.E. Report#: 76A Sheet: 1 of 2
Geotechnical and Materials Engineers
Town Engineer Lalcewood-(303)989-1223 Subject: Fill Observation and Testine
Department of Public Works/Transportation Grand Junction-(970)241-7700 Interiar Slab-on-grade and Grade Beam Fill
1309 Elkhorn Drive ECO Building
Vail,Colorado 81657 Lionshead Transit Center
Vail,Colorado
LaboraYo Field
Depth MaJCimum Optimum
Test Location or Dry Moisture Dry Moisture Percent Pass/Fail Soil Type
No. Elevation Density Content Density Content Compaction
(feet) cf� (%) cfl (%)
247 Gridlines B.0/3.7(slab-on-grade) -7.5± 131.1 7.7 128.5 8.1 98 Pass Curve#2
SAND Gravell Sil
248 Gridlines A.6/09(slab-on-grade) Grade± 131.1 7.7 133.5 5.7 100 Pass Curve#2
SAND Gravell Sil
249 Gridlines A.8/2.4(slab-on-grade) Grade± 131.1 7.7 132.8 6.8 100 Pass Curve#2
SAND Gravell Sil
250 Gridlines A.9/4.0(grade beam) -5.0-E- 131.1 7.7 131.2 7.3 100 Pass Curve#2
SAND Gravell Sil
251 Gridlines A.7/5.0(grade beam) -5.5± 131.1 7.7 130.5 9.1 100 Pass Curve#2
SAND Gravell Sil
252 Gridlines A.6/3.6(slab-on-grade) -3.0-E- 131.1 7.7 129.7 6.6 99 Pass Curve#2
SAND Gravell Sil
253 Gridlines A.6/5.6(slab-on-grade) -3.0± 131.1 7.7 131.7 9.1 100 Pass Curve#2
SAND Gravell Sil
Weather: ❑ Sum� � Cloud ❑ Rain ❑ Snow Tem : 31°F± � Fill Tested Meets Specifications.
Specification Compaction&Material: 95%(slab-on-grade)or 98%(grade beams)of ❑ Fill Tested Does Not Meet Specifications as Indicated by Test Number(s)
Standard Proctor ASTM D 698,+2%to-2%of Optimum Moisture Content and Should be Removed or Reworked.
Type and Number of Earth Moving Units: 1-Tracichoe, 1-Bobcat � Contractor Advised.
❑ Full Time Observation. � Part Time Observation.
Type and Number of Compaction Units: 1-Walk-behind, 1-7umping jack Progress Report: Field engineer arrived on-site, as requested, to observe and test fill for
the interior slab-on-grade and grade beams for the ECO Building. Test results indicate that
Number of Passes: Varies Thickness of Lift: 8 inches moisture and density tests performed at the noted locations have met project
Method of Adding Moisture: Water truck and hose assembly specifications.
This report presents opinions formed as a result of our obseivations and/or compaction testing of the fill during this visit.
We have relied m�the contractar to continue applying the recommended compactive effbrt and moisture to the fill duri�g
times wl�en our observer is not observing operations. Tests are made of the fill only as believed necessary to calibrate our
observer's jud ment. Test data are not the sole basis for o i�ions on whether the fill meets s ecificatio�s.
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
REINFORCING STEEL (REBAR) OBSERVATION
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Lakewood—(303)989-1223
Grand Junction—(970)241-7700
To: Town of Vail Job No. 10-039 Date: 12/10/10
Tom Kassmel,P.E.
Town Engineer Report#: 76B Sheet: 2 of 2
Department of Public Works/Transportation
1309 Elkhorn Drive
Vail,Colorado 81657
Project: Lionshead Transit Center,Vail, Colorado
Weather: ❑ Sunny ❑ Cloudy ❑ Rain ❑ Snow Temp: 44°F± in enclosed area
Reinforcing Steel (Rebar) Observations:
Type of Structure: (Wall, Grade Beam, Footin�, Slab-on-�rade, etc.): Northeast Stairs,Leve12 to 3,Landing
Topping and Steps
Location of Observations: Gridlines E A to E-A.3, E-1 to E-1.3
Sheet or Plan Number: 5201 and 9/5316
Meets Project Spec.
Northeast Stairs,Level 2 to 3,Landing Rebar: Grldllnes E A to E-A.3, E-1 to E-1.3 yes no
Topping and Steps
Dowels: Size: #4 Spacing: 1'-0" each corner � ❑
Nosing: Size: #4 Spacing: Each corner � ❑
Bottom: Size: #4 Spacing: 1'-6" o.c. each way, each comer � ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) yes Length: 2'-2"at landing � ❑
Meets Project Spec.
Rebar: yes no
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) Length: ❑ ❑
Discrepancies/Remarks: Based on our observations, it is our opinion that the reinforcing steel (rebar) yes no
noted in this Daily Field Report has been properly placed and has met project specifications. � ❑
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
REPORT OF CONSTRUCTION ACTIVITIES
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Lakewood—(303)989-1223
Grand Junction—(970)241-7700
To: Town of Vail Job No. 10-039 Date: 12/ll/10
Tom Kassmel,P.E.
Town Engineer Report#: 77 Sheet: 1 of 1
Department of Public Works/Transportation
1309 Elkhorn Drive
Vail,Colorado 81657
Project: Lionshead Transit Center,Vail, Colorado
Weather: ❑ Sunny � Cloudy ❑ Rain ❑ Snow Temp: 35°F±
Construction Activities/Observations: Field engineer was en route to the site, as requested, to perform moisture
and density testing for the fill placement for the ECO Building.
While field engineer was en route to the site, the contractor called him and informed him that the day's testing was
cancelled due to excessive traffic on the road and at Vail.
Therefore,no moisture and density testing was performed this day.
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
SOIL COMPACTION TEST RESULTS
To: Town of Vail KOECHLEIN CONSULTING ENGINEERS, ING Job No. ]0-039 Date: 12/13/10
Tom Kassmel,P.E. Geotechnical and Materials Engineers Report#: 78A Sheet: 1 of 2
Town Engineer Subject: Fill Observation and Testint
Department of Public Works/Transportation Lakewood-(303)989-1223 Interior Slab-on-grade,Retaining Wall
1309 Elkhorn Drive Grand Junction-(970)241-7700 Footing Pad,and Foundation Wall Fill
Vail,Colorado 81657 ECO Building
Lionshead Transit Center
Vail,Colorado
Laboratory Field
Depth Ma�mum Optimum
Test Location or Dry Moisture Dry Moisture Percent Pass/Fail Soil Type
No. Elevation Density Content Density Content Compaction
(feet) ( c� (%) ( c� (%)
254 Gridlincs A.3/5.7(slab-on-grade) -0.5± 1311 7.7 133.0 7.7 100 Pass Curve#2
SAND Gravell Sil
255 Gridlines A.1/3.6(slab-on-grade) -2.0± 131.1 7.7 124.0 7.8 95 Pass Curve#2
SAND Gravell Sil
256 5'-9"East of Gridlines A.7/8A(retaining -5.0± 1311 7.7 133.8 6.7 100 Pass Curve#2
wall footin ad SAND Gravell Sil
257 2'East of Gridlines B.4/8.0(retaining wall -5.0± 131.1 7.7 1291 9.1 98 Pass Curve#2
footin ad SAND Gravell Sil
258 12'East of Gridlines B.0/8.0(retaining wall -4.0± 1311 7.7 130.4 9.4 99 Pass Curve#2
footin ad SAND Gravell Sil
259 6'East of Gridlines A.8/8.0(retaining wall -2.0± 131.1 7.7 129.0 8.5 98 Pass Curve#2
footin ad SAND Gravell Sil
260 10'East of Gridlines B.2/8.0(retaining wall -1.0± 1311 7.7 125.1 7.9 95 Fail Curve#2
footin ad SAND Gravell Sil
Weather: � Sunny ❑ Cloudy ❑ Rain ❑ Snow Temp: 26°-48°F± � Fill Tested Meets Specifications.
Specification Compaction&Material: 95%(slab-on-grade and foundation wall)or 98% ❑ Fill Tested Does Not Meet Specifications as Indicated by Test Number(s)
(retaining wall footing pad)of Standard Proctor ASTM D 698,+2%to-2%of Optimum and Should be Removed or Reworked.
Moisture Content
Type and Number of Earth Moving Units: 2-Trackhoes, 1-Bobcat � Contractor Advised.
❑ Full Time Observation. � Part Time Observation.
Type and Number of Compaction UniYs: 1-Walk-behind Progress Report: Field engineer arrived on-site, as requested,to observe and test the fill
for the interior slab-on-grade,retaining wall footing pad,and foundation walls far the ECO
Number of Passes: Varies Thickness of Lift: 8 inches Building. Test results indicate that moishire and density tests performed at the noted
Method of Adding Moisture: Water truck and hose assembly locations have met project speci�carions.
This report presen[s opinions formed as a result of our observations and/or compaction[esting of the fill d�ring this visiC.
We have relied on the contractor to continue applying the recommended compactive effort and moisture to the fill during
times when our observer is not'observing operations. Tests are made of the fill onLy as beLieved necessary to calibrate our
observer's'ud ment. Test data are not the sole basis for o inions on whetherthe fill meets s ecifications.
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
SOIL COMPACTION TEST RESULTS
To: Town of Vail KOECHLEIN CONSULTING ENGINEERS, ING Job No. ]0-039 Date: 12/13/10
Tom Kassmel,P.E. Report#: 78B Sheet: 2 of 2
Geotechnical and Materials Engineers
Town Engineer Subject: Fill Observation and Testint
Department of Public Works/Transportation Lakewood—(303)989-1223 Interior Slab-on-grade,Retaining Wall
1309 Elkhorn Drive Grand Junction—(970)241-7700 Footing Pad,and Foundation Wall Fill
Vail,Colorado 81657 ECO Building
Lionshead Transit Center
Vail,Colorado
Laboratory Field
Depth Ma�mum Optimum
Test Location or Dry Moisture Dry Moisture Percent Pass/Fail Soil Type
No. Elevation Density Content Density Content Compaction
(feet) ( c� (%) ( c� (%)
261 2.5' East of Gridlines A.6/8.0(foundation -11.0± 1311 7.7 129.8 8.2 99 Pass Curve#2
walls SAND Gravell Sil
262 Retest of Tcst#260(retaining wall footing -1.0± 131.1 7.7 133.0 6.8 100 Pass Curve#2
ad SAND Gravell Sil
263 5'North of Gridlines A.0/7.4(foundation -8.0± 1311 7.7 132.0 6.7 100 Pass Curve#2
walls SAND Gravell Sil
264 7'East of Gridlines B.6/8.0(retaining wall Grade± 131.1 7.7 130.2 8.2 99 Pass Curve#2
footin ad SAND Gravell Sil
Weather: � Sunny ❑ Cloudy ❑ Rain ❑ Snow Temp: 26°-48°F± � Fill Tested Meets Specifications.
Specification Compaction&Material: 95%(slab-on-grade and foundation wall)or 98% ❑ Fill Tested Does Not Meet Specifications as Indicated by Test Number(s)
(retaining wall footing pad)of Standard Proctor ASTM D 698,+2%to-2%of Optimum and Should be Removed or Reworked.
Moisture Content
Type and Number of Earth Moving Units: 2-Trackhoes, 1-Bobcat � Contractor Advised.
❑ Full Time Observation. � Part Time Observation.
Type and Number of Compaction UniYs: 1-Walk-behind Progress Report: See Sheet 1 of 2.
Number of Passes: Varies Thickness of Lift: 8 inches
Method of Adding Moisture: Water truck with hose assembly
This report presenCS opinions formed as a res�lt of our observations and/or compaction testing of the fill during this visiC.
We have relied on the contractm to continue applying the recommended compactive effort and moisture to the fill during
times when our observer is not observing operations. Tests are made of the FiLI only as believed necessary to caLibrate our
obseiver's'ud�ment. Test data are not the sole basis for o inions on whether the fill meets s ecifications.
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
SOIL COMPACTION TEST RESULTS
To: Town of Vail KOECHLEIN CONSULTING ENGINEERS, INC. Job No. 10-039 Date: 12/14/10
Tom Kassmel,P.E. Report#: 79A Sheet: 1 of 3
Geotechnical and Materials Engineers
Town Engineer Lalcewood-(303)989-1223 Subject: Fill Obs�rvation and Testine
Department of Public Works/Transpartation Grand Junction-(970)241-7700 Foundation Wall and Interior Slab-on-
1309 Elkhorn Drive grade Fill
Vail,Colorado 81657 ECO Building
Lionshead Transit Center
Vail,Colarado
Laborato Field
Depth Maximum Optimum
Test Location or Dry Moisture Dry Moisture Percent Pass/Fail Soil Type
No. Elevation Density Content Density Content Compaction
(feet) c� (%) c� (%)
265 9'North and 9'East of Gridlines A.0/8.0 -10.0± 131.1 7.7 127.7 8.7 97 Pass Curve#2
foundation wall SAND Gravell Sil
266 4.5' East of Gridlines A.0/8A(foundation -10.0± 131.1 7.7 125.7 7.6 96 Pass Curve#2
wall SAND Gravell Sil
267 Gridlines B.0/6.5(slab-on-grade) -7.5± 131.1 7.7 131.2 9.3 100 Pass Curve#2
SAND Gravell Sil
268 Gridlines A.8/7.7(slab-on-grade) -7.5± 131.1 7.7 125.7 9.6 96 Pass Curve#2
SAND Gravell Sil
269 Gridlines A.3/7.8(slab-on-grade) -6.0± 131.1 7.7 122.7 9.7 94 Fail Curve#2
SAND Gravell Sil
270 Gridlines A.5/7.2(slab-on-grade) -6.0± 131.1 7.7 123.1 10.7 94 Fail Ciuve#2
SAND Gravell Sil
271 Retest of Test#269(slab-on-grade) -6.0± 131.1 7.7 125.0 10.3 95 Pass Curve#2
SAND Gravell Sil
Weather: ❑ Sunny � Cloudy ❑ Rain ❑ Snow Temp: 31°-38°F± � Fill Tested Meets Specifications.
Specification Compaction&Material: 95%of Standard Proctor ASTM D 698, ❑ Fill Tested Does Not Meet Specifications as Indicated by Test Number(s)
+2%to-2%of Optimum Moisture Content and Should be Removed or Reworked.
Type and Number of Earth Moving Units: 1-Trackhoe, 1-Bobcat � Contractor Advised.
❑ Full Time Observation. � Part Time Observation.
Type and Number of Compaction Units: 1-Walk-behind Progress Report: Field engineer arrived on-site, as requested,to observe and test fill for
the foundation wall and the interior slab-on-grade far the ECO Building. Test results
Number of Passes: Varies Thickness of Lift: 8 inches indicate that moisture and density tests performed at the noted locations have met project
Method of Adding Moisture: Water truck and hose assembly specifications.
This re�ort presents opinions formed as a result of our observations and/or compaction testing of the fill during this visit.
We have relied on tlie coi�trac[ar to continue applying the recommended compactive effort and�noisture to the fill during
times when our observer is not observing operations. Tests are made of the fill only as believed necessary to calibrate our
observer's jud ment. Test data are not the sole basis for o i��ions on whether the fill meets s ecificatim�s.
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
SOIL COMPACTION TEST RESULTS
To: Town of Vail KOECHLEIN CONSULTING ENGINEERS, INC. Job No. 10-039 Date: 12/14/10
Tom Kassmel,P.E. Report#: 79B Sheet: 2 of 3
Geotechnical and Materials Engineers
Town Engineer Lalcewood—(303)989-1223 Subject: Fill Observation and Testine
Department of Public Works/Transpartation Grand Junction—(970)241-7700 Foundation Wall and Interiar Slab-on-
1309 Elkhorn Drive grade Fill
Vail,Colorado 81657 ECO Building
Lionshead Transit Center
Vail,Colarado
Laborato Field
Depth Maximum Optimum
Test Location or Dry Moisture Dry Moisture Percent Pass/Fail Soil Type
No. Elevation Density Content Density Content Compaction
(feet) c� (%) c� (%)
272 Retest of Test#270 -6.0± 131.1 7.7 1241 10.4 95 Pass Curve#2
SAND Gravell Sil
273 Gridlines A.4/6.7 -4.5± 131.1 7.7 124.7 101 95 Pass Curve#2
SAND Gravell Sil
274 Gridlines A.7/7.6 -4.5± 131.1 7.7 128.8 9.0 98 Pass Curve#2
SAND Gravell Sil
275 Gridlines A.5/6.5 -3.0± 131.1 7.7 127.4 9.1 97 Pass Curve#2
SAND Gravell Sil
276 Gridlines B.6/7.8 -3.0± 131.1 7.7 125.3 9.8 96 Pass Curve#2
SAND Gravell Sil
Weather: ❑ Sunn � Cloud ❑ Rain ❑ Snow Temp: 31°-38°F± � Fill Tested Meets Specifications.
Specification Compaction&Material: 95%of Standard Proctar ASTM D 698, ❑ Fill Tested Does Not Meet Specifications as Indicated by Test Number(s)
+2%to-2%of Optimum Moisture Content and Should be Removed or Reworked.
Type and Number of Earth Moving Units: 1-Trackhoe, 1-Bobcat � Contractor Advised.
❑ Full Time Observation. � Part Time Observation.
Type and Number of Compaction Units: 1-Walk-behind Progress Report: See Sheet 1 of 3.
Number of Passes: Varies Thickness of Lift: 8 inches
Method of Adding Moisture: Water truck and hose assembly
This report presents opinions formed as a result of our observations and/or compaction testing of the fill during this visit.
We have relied on the coi�trac[ar to continue applying the recommended compactive effort and�noisture to the fill during
times when our observer is not observing operetions. Tests are made of the fill only as believed necessary to calibrate our
observer's jud ment. Test data are not the sole basis for o i��ions on whether the fill meets s ecifications.
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By
REINFORCING STEEL (REBAR) OBSERVATION
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Lakewood—(303)989-1223
Grand Junction—(970)241-7700
To: Town of Vail Job No. 10-039 Date: 12/14/10
Tom Kassmel,P.E.
Town Engineer Report#: 79C Sheet: 3 of 3
Department of Public Works/Transportation
1309 Elkhorn Drive
Vail,Colorado 81657
Project: Lionshead Transit Center,Vail, Colorado
Weather: ❑ Sunny � Cloudy ❑ Rain ❑ Snow Temp: 31°F±
Reinforcing Steel (Rebar) Observations:
Type of Structure: (Wall, Grade Beam, Footin�, Slab-on-�rade, etc.): Northeasc sta�r curbs and Norcheasc sta�r De�k
Apron Topping
Locatlon of Observatlons: Gridlines E-18.7/E-A to E-A.3, E-A.3/E-18 9 to E-19, and E-A.3 to E-A.4, �18.7 to �19
Sheet or Plan Number: 5203, 5204, 4/5316, and 4/5211
Meets Project Spec.
Northeast Stair Curbs Rebar: Gridlines E-18.7/E-A to E-A.3 and E-A.3/E-18.9 to E-19 yes no
Dowels: Size: #4 Spacing: 1'-4" o.c. - U bars - epoxied � ❑
Top of U bars Size: 2 - #4 Spacing: Continuous � ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) no Length: ❑ ❑
Meets Project Spec.
Nartheast Stair Deck Apron Topping RebaT: GTldllnes �A.3 to E-A.4, E-1 8.7 to E-19 yes no
Bottom: Size: #4 Spacing: 1'-6"o.c. each way � ❑
Dowels: Size: #4 Spacing: 1'-0" o.c. over double T's—epoxied � ❑
Extra dowels: Size: #4 Spacing: 1'-4" o.c. at perimeter � ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Size: Spacing: ❑ ❑
Splices:(yes/no) no Length: ❑ ❑
Discrepancies/Remarks: Based on our observations, it is our opinion that the reinforcing steel (rebar) yes no
noted in this Daily Field Report has been properly placed and has met project specifications. � ❑
Don Sneed Scott B. Myers, P.E.
Field Observer Reviewed By