HomeMy WebLinkAbout10-039 Discrepancies thru 10-22-10 LIONSHEAD TRANSIT CENTER
DISCREPANCY LIST FOR KCE JOB NO. 10-039
PROPOSED LIONSHEAD TRANSIT CENTER, VAIL, COLORADO
IN AN EFFORT TO IMPROVE OUR SERVICES AND THE COMMUNICATION BETWEEN TEAM MEMBERS,WE WILL BE PROVIDING THE
FOLLOWING DISCREPANCY LIST. THIS LiST WILL INCLUDE ANY DISCREPANCiES IDENTIFIED IN OUR FIELD REPORTS THRU THE
LATEST REViEWED FiELD REPORT. CONCRETE AND GROUT DISCREPANCIES WILL ONLY BE NOTED FOR CONCRETE OR GROUT THAT
DOES NOT MEET THE 28 DAY STRENGTH REQUIREMENTS. THE DISCREPANCY LiST WILL BE UPDATED ON A WEEKLY BASIS(DAILY
FOR CONCRETE)AND WILL BE SENT OUT EVERY WEEK. IF YOU HAVE ANY QUESTIONS,PLEASE CALL.
KCE JOB NO.10-039 10/22/10 SHEET 1 OF 7
LIONSHEAD TRANSIT CENTER
EXCAVATION OBSERVATIONS-DISCREPANCIES
Date Daily Report No. Discrepancy I.ocation Resolved(y/n) Resolution Date
None to date
KCE JOB NO.10-039 10/22/10 SHEET 2 OF 7
LIONSHEAD TRANSIT CENTER
SOIL COMPACTION,OTHER OBSERVATIONS-DISCREPANCIES
Date Daily Report No. Discrepancy Location Resolved(y/n) Resolution Date
08/]7/l0 1 Low densities Tests 1 and 2 08/26/10
09/29/10 26A Low densities Test 69 y 09/30/l0
10/02/10 29 Failed Proof-roll Sta.4+40 to 5+59
10/06/10 32A Low densities Tests 86 and 87 y 10/07/10
10/09/10 34A Low densit Test 94
10/]0/10 35 Low density Test 96(Re-test of Test 94)
10/1 I/10 36A Fill in base of excavafion FCO Buildin -Gridlines A.0-C.0/8.0 10/20/10
10/15/10 40A Fill in base of excavation ECO Building-Gridlines A.0-C.0/8.0 y 10/20/]0
KCE JOB NO.10-039 10/22/10 SHEET 3 OF 7
LIONSHEAD TRANSIT CENTER
REINFORCING STEEL(REBAR)-DiSCREPANCIES
Date Daily Report No. Discrepancy Location Resolved(y/n) Resolution Date
09/28/l0 25C Rebar laced does not match detail on 6/S210 Gridlines E-1.5 Yo E-3.0/E-A 10/]8/10
10/21/10 44C Rebar laced does not match detail o��9/5215 Leve12-U er landing
KCE JOB NO.10-039 10/22/10 SHEET 4 OF 7
LIONSHEAD TRANSIT CENTER
MASONRY OBSERVATIONS-DISCREPANCIES
Date Daily Report No. Discrepancy I.ocation Resolved(y/n) Resolution Date
None to date
KCE JOB NO.10-039 10/22/10 SHEET 5 OF 7
LIONSHEAD TRANSIT CENTER
CONCRETE DISCREPANCIES
Did Concrete meet 28 day Compressive Did Concrete meet 28 day Compressive
Cast Date Discrepancy Item Cast Approximate I.ocation Strength(yes/no) Strength at 56 days(yes/no)
None to date
KCE JOB NO.10-039 10/22/10 SHEET 6 OF 7
LIONSHEAD TRANSIT CENTER
ASPAALT DISCREPANCIES
Date Daily Report No. Discrepancy Location Resolved(y/n) Resolution Date
None to date
KCE JOB NO.10-039 10/22/10 SHEET 7 OF 7