HomeMy WebLinkAboutB11-0328 comment letter
Date: 9/22/2011
Re: 610 Lionshead Circle B11-0328
Dear Mr. Hallenbeck,
RESPONSE INSTRUCTIONS
● Submit four complete sets of revised construction documents containing the requested information with all plan revision items clouded or otherwise identified.
● Please respond in writing to each comment with a response letter addressing each comment.
BUILDING COMMENTS
Architectural Comments:
Sheet A001
1. Provide cross-sectional details of the proposed handrails and guards. Reference sections 1012 and 1013 IBC.
2. Plans do not reflect a scale. Clarify compliance for the required intermediate handrail per section 1012.9 IBC. Provide details.
3. Plans do not reflect a scale. Clearly identify compliance for the rise and run of the proposed stair. Reference section 1009.4.2 IBC
4. Handrails are required on both sides of the stair. Reference section 1009.12 IBC
5. Plans do not appear to show compliance with section 1012.6 IBC. Please clarify on plans.
Structural Comments:
Sheet A001
1. Provide detail for the proposed columns showing compliance with section 1607.7 IBC.
Plumbing Comments:
NA
Mechanical Comments:
1. Provide plans for the proposed snowmelt system including sizing information as related to the additional load on the boiler system. Reference section 1201.2 IMC
Electrical Comments:
NA
PLANNING COMMENTS
Reviewed and accepted. Please note an additional review will be required if changes are made to address other department comments.
FIRE COMMENTS
Reviewed and accepted
PUBLIC WORKS COMMENTS
Approved with conditions
Sincerely,
Martin A. Haeberle
Chief Building Official