July 31st, 2006
To whom it may concern,
This is a reminder to all parties that the Town of Vail, per title 8 -1 -26 of the Town Municipal Code, will be
requiring an asphalt mill and overlay of Vail Rd. from the roundabout to and thru the W. Meadow Drive
intersection. The cost of this work shall be paid for thru a cost share agreement between all effected parties and
based on the length and area of disturbance.
Currently the projects that are expected to contribute to this asphalt overlay are:
-Eagle River Water and Sanitation District's joint utility project (2005)
-Vail Plaza Hotel's Vail Rd widening and storm sewer projects (2005, 2006 & Future)
-Four Seasons' Spraddle Creek realignment project and streetscape improvements (2005 & Future)
-Town of Vail Street reconstruction project along South lane just north of intersection (Future)
It is anticipated that the asphalt overlay project will occur once all work within Vail Rd. is complete, which at
this point will be contingent on Four Season's streetscape improvements along Vail Rd.
If you have any questions regarding this matter please contact me at 479 -2235.
Sincerely,
Thomas E. Kassmel,
Town Engineer
Town of Vail
cc: Linn Schorr, ERWSD
Chuck McDonald, Shaw Construction (Vail Plaza. Hotel)
David Brooks, John Hardy Group (Four Seasons)
Leonard Sandoval, Town of Vail