RE: Vail's Front Door—Eacavation Permit
Dear Tom,
Pursuant to our conversation earlier today, Hyder Construdion Inc. hereby recognizes that until
such time that executed tie back agreements between Vail Resorts Development Company and
the South Lodge Tower and Vail Resorts Development Company and The Lodge at Vail, no
work related to demolitioq excavation and shoring adjacent to these properties will take place.
According to Vail Resorts Development Company the aforementioned agreements are imminent.
Hyder Construction will submit these agreements to the Town of Vail for approval prior to
commencing work related to the excavation adjacent to these two properties.
Additiona.11y, in response to the Site Staging&Access Plan dated,May 22, 2006, Hyder
Construction will maintain access to the previously designated delivery zone adjacent to Chair
One until such time as either the improvements north of the Chute are completed and The Chute
open to through tr�c or Vail Road is open to cocrtinuous tr�c.
Sincerely,
Doug Thompso
Project Executive