HomeMy WebLinkAboutB12-0306 CR1Department of Community Development
75 South Frontage Road
TOWN OF VAlL � Z Vail, co 816
Tel: 970 - 479 -2128
- = - www.vailgov.com
Development Review Coordinator
TRANSMITTAL FORM
Revision Submittals:
1. "Field Set" of approved plans MUST accompany revisions.
2. No further inspections will be performed until the revisions are approved & the permit is re- issued.
3. Fees for reviewing revisions are $55.00 per hour (2 hour minimum), and are due upon issuance.
Permit #(s) information applies to: Attention: XRevisions
Response to Correction Letter
D, _attached copy of correction letter
( ) Deferred Submittal
( ) Other
Project Street Address:
( 0 41t- C;'4lnf-m. .
(Number) (Street) (Suite #)
Building /Complex Name:
Contractor Information
Business Name: JA- 12 e C P
Business Address:
City
State: Zip:
Contact Name:
Contact Phone:
Contact E -Mail:
I hereby acknowledge that I have read this application, filled out
in full the information required, completed an accurate plot plan,
and state that all the information as required is correct. I agree to
comply with the information and plot plan, to comply with all Town
ordinances and state laws, and to build this structure according
to the town's zoning and subdivision codes, design review ap-
p ved, Inte ational B1 ilding and Residential Codes and other
or ' ances o the To;y applicable thereto.
Owner /Owner's Roresentativ- Signature (Required)
Applicant I
Applicant Name: �
Applicant Phone: 1 l C l 1 1
Applicant E -Mail: �Az 6 fl% t/ h,(,/Q, ,
For Office Use Only:
Fee Paid:
Received From:
Cash Check # _
CC: Visa / MC Last 4 CC #
Auth #
exp. date:
Description / List of Cha / nges � : .,
ZI
IPA, 0 (A,
,f
(use additional sheet if necessary)
Revised ADDITIONAL Valuations (Labor & Materials)
(DO NOT include original valuation)
Building:
Plumbing: $
Electrical: $
Mechanical: $ \�
Total: $
Date Received:
p �c��od� O
JUL 27 2012
TOWN OF VAIL
Date: 7/25/2012
Re: B 12 -0306
Dear Ms. Gowie Response is by the architect of record, R. Duane Piper, Colorado lic. #
C -1953 on July 27, 2012.
RESPONSE INSTRUCTIONS
• Submit two complete sets of revised construction documents containing the
requested information with all plan revision items clouded or otherwise identified.
• Please respond in writing to each comment with a response letter addressing each
comment.
BUILDING COM MENTS
Architectural Comments:
Sheet Al. I
1. Plans indicate a proposed boulder retaining wall. Clarify height of the retaining wall. If 4
feet or taller a design by a licensed engineer is required to be submitted. Reference Town of
Vail amendments to the building code.
36" Sht. A -1.1 has been revised to indicate that boulder retaining wall will not exceed
2. Plans to include: Building code and edition work designed to. Sht. A -].1 now indicates
that the governing code is IBC and IRC 2009.
Sheet A2.1
1. What is the proposed height above grade for the deck? If by deck, reference is being
made to top of existing plywoodJioor sheathing, the dimension is 12"
2. Plans do not include stair, handrail, and guard details. Please provide showing
compliance with the building code No stairs existing in new wor /�
3. Annotate on plans CO detectors to be provided throughout the home per the IRC CO
detectors were installed in 2009 as per the new IRC regulations.
Structural Comments: To comments involving structure, the wood foundation wall does
not act as a be; ing wall. The wall is a thermal barrier between the outside and the crawl
space. Existing structure is a concrete foundation wall on the north end and a
combination of concrete wall, cone. pier and WF stl. beam on the south end plus a
midspan WF stl. beam bearing on a concrete pier and wall. Manufactured 12" I joists
span north to south half the distance of the structure. All of this work was done under a
previous permit sometime in the 1980's.
Sheet A3.1
1. Provide plans showing compliance with section 1807.4 IBC 2009 edition for wood
foundation walls
2. Plans to reflect the design loads to include bearing pressures, lateral soil loads ( concrete
slurry), live and dead loads for all structural elements. Reference section 1603 IBC The
thermal barrier wall is stablized by
concrete slurry and the bottom and a thrust block at the top from moving inward. The
counter load is compacted earth on the outside.
3. Bearing pressures and soil verification at the foundation base. Plans show gravel?
Provide a structural analysis of this proposed design. Reference section 1604.4 IBC
4. Indicate special inspections required per section 1704.1.1 1 suggest that this is a minor
construction effort and does not require special inspection. Just the same, I'm contracted
by the owner to review and observe construction.
Plumbing Comments:
NA
Mechanical Comments:
NA
Electrical Comments:
NA
PLANNING COMMENTS
Reviewed and accepted
FIRE COMMENTS
NA
PUBLIC WORKS COMMENTS
NA
Sincerely,
Martin A. Haeberle
Chief Building Official