HomeMy WebLinkAboutB12-0367 GEOTECHNICAL INVESTIGATIONBla-oa(017
GEOTECHNICAL INVESTIGATION
PROPOSED RESIDENCE
LOT 6, JUNIPER LANE
BIGHORN SUBDIVISION
VAIL, COLORADO
Koechlein Consulting Engineers, Inc.
Consulting Geotechnical Engineers
12364 W. Alameda Pkwy • Suite 115 • Lakewood, CO 80228 -2845
LAKEWOOD AVON SILVERTHORNE
(303) 989 -1223 (970) 949 -6009 (970) 468 -6933
(303) 989 -0204 FAX (970) 949 -9223 FAX (970) 468 -6939 FAX
KOECHLEIN CONSULTING ENGINEERS, INC.
CONSULTING GEOTECHNICAL AND MATERIALS ENGINEERS
GEOTECHNICAL INVESTIGATION
PROPOSED RESIDENCE
LOT 6, JUNIPER LANE
BIGHORN SUBDIVISION
VAIL, COLORADO
Prepared for:
Greg Cummings
G & J Construction
5135 Main Gore Drive
Vail, Colorado 81657
Job No. 05 -172
October 24, 2005
DENVER: 12364 West Alameda Prkwy., Suite 115, Lakewood, CO 80228 (303) 989 -1223
AVON /SIL PER THORNE: (970) 949 -6009
October 24, 2005 KOECHLEIN CONSULTING ENGINEERS, INC.
Job No. 05 -172 Consulting
Geotechnical Engineers
'
TABLE OF CONTENTS
SCOPE
1
1
EXECUTIVE SUMMARY
SITE CONDITIONS
PROPOSED CONSTRUCTION
3
INVESTIGATION
4
SUBSURFACE CONDITIONS
RADON
5
5
MOLD
6
'
GROUND WATER
6
EXISTING FILL
6
EXCAVATIONS
7
'
FOUNDATIONS
8
SLABS -ON -GRADE
9
FOUNDATION DRAINAGE
11
LATERAL WALL LOADS
12
RETAINING WALLS
13
'
SURFACE DRAINAGE
13
IRRIGATION
14
COMPACTED FILL
15
LIMITATIONS
16
VICINITY MAP
Fig. 1
LOCATIONS OF EXPLORATORY TEST PITS
Fig. 2
'
LOGS OF EXPLORATORY TEST PITS
LEGEND OF EXPLORATORY TEST PITS
Fig. 3
Fig. 4
GRADATION ANALYSIS RESULTS
Fig. 5
'
TYPICAL WALL DRAIN DETAIL
Fig. 6
TYPICAL RETAINING WALL DRAIN DETAIL
Fig. 7
SUMMARY OF LABORATORY TEST RESULTS
Table I
October 24, 2005 KOECHLEIN CONSULTING ENGINEERS, INC
Job No. 05 -172 Consulting Geotechnical Engineers
SCOPE
This report presents the results of a geotechnical investigation for the proposed
residence to be constructed on Lot 6, Juniper Lane, Bighorn Subdivision in Vail,
Colorado. The approximate site location is shown on the Vicinity Map, Fig. 1. The
purpose of this investigation was to evaluate the subsurface conditions at the site and to
provide geotechnical recommendations for the proposed residence.
This report includes descriptions of subsurface soil and ground water conditions
encountered in the exploratory test pits, recommended foundation systems, and
recommended design and construction criteria. This report was prepared from data
developed during our field investigation and our experience with similar projects and
subsurface conditions in the area.
The recommendations presented in this report are based on a residence being
constructed at the approximate location indicated on the Locations of Exploratory Test
Pits, Fig. 2. We should be contacted by the contractor and/or owner to review our
recommendations when final plans for the residence have been completed. A summary of
our findings and conclusions is presented in the following paragraphs.
EXECUTIVE SUMMARY
1. The subsurface conditions encountered in the exploratory test pits varied.
Subsurface conditions encountered in exploratory test pit TP -1 consisted
of approximately 1.5 feet of topsoil overlying very dense sand and gravel
with cobbles and boulders to the maximum depth explored of 5.0 feet.
October 24, 2005 KOECHLEIN CONSULTING ENGINEERS, INC.
Job No. 05 -172 Consulting Geotechnical Engineers
Practical excavator refusal on a boulder was encountered at a depth of 5.0
feet. Subsurface conditions encountered in exploratory test pit TP -2
consisted of approximately 1.5 feet of topsoil overlying existing fill to a
depth of 5.5 feet. The existing fill consisted of medium dense, clayey,
gravelly sand. Underlying the existing fill to the maximum depth explored
of 8.0 feet, the subsurface conditions consisted of medium dense sand with
scattered gravel.
2. Topsoil and existing fill were encountered to a depth of 5.5 feet on this
site. Greater depths of topsoil and fill could be encountered in the areas of
the proposed construction. The topsoil and existing fill should be removed
from all construction areas prior to construction. The topsoil and existing
fill may be used in landscaping areas. Provided the existing fill is free of
deleterious material, it may be used as structural fill for this project. Refer
to the EXISTING FILL section of this report for additional details.
3. At the time of this investigation, ground water was not encountered in
either of the exploratory test pits to the maximum depth explored of 8.0
feet. However, this investigation was conducted during a dry time of year
and ground water could be encountered during construction at wetter times
of the year. Refer to the GROUND WATER section of this report for
further recommendations.
4. We anticipate that the subsurface conditions at the foundation elevations
for the proposed residence will consist of the natural sand and gravel or
the existing fill overlying natural sand. In our opinion, the natural sand
and gravel and/or natural sand will safely support a spread footing
foundation system for the proposed residence. Refer to the
FOUNDATIONS section of this report for complete recommendations.
5. Due to the presence of existing fill, special considerations should be taken
into account when constructing slabs -on -grade for the proposed residence.
Refer to the SLABS -ON -GRADE section of this report for complete
recommendations.
6. Open cuts and excavations require precautions as outlined in this report in
order to maintain the stability of slopes and sides of excavations. Refer to
the EXCAVATION section of the report for additional details.
2
October 24, 2005
Job No. 05 -] 72
KOECHLEIN CONSULTING ENGINEERS, INC.
Consulting Geotechnical Engineers
7. Because cobbles and boulders were encountered in the exploratory test
pits, heavy -duty excavation equipment may be required to complete the
required excavations.
8. Drainage around the proposed residence should be designed and
constructed to provide for rapid removal of surface runoff and avoid
concentration of water adjacent to foundation walls. Refer to the
SURFACE DRAINAGE section of this report for additional
recommendations.
9. The potential for radon gas is a concern in the area. Refer to the RADON
section of this report for additional recommendations
10. The potential for mold is a concern in new construction. Refer to the
MOLD section of this report for additional recommendations.
SITE CONDITIONS
The proposed residence will be constructed on Lot 6, Juniper Lane in the Bighorn
subdivision in Vail, Colorado. Currently the site is a vacant lot. The lot is bordered on
the northeast by Juniper Lane; on the southeast, southwest, and northwest by single
family residences. The topography of the lot slopes down to the northeast at a grade of
approximately 3 to 4 percent. Vegetation on the lot consists of grasses, weeds, and
several small bushes.
PROPOSED CONSTRUCTION
At the time of this investigation, no plans for the proposed residence were
available. However, based on a conversation with the owner, we understand that the
October 24, 2005 KOECHLEIN CONSULTING ENGINEERS, INC
Job No. 05 -172 Consulting Geotechnical Engineers
proposed residence will consist of a two -story, single family residence. No basement is
planned for the residence. We anticipate the residence will be of cast -in -place concrete
and wood frame construction with slab -on -grade floors. Access to the residence will be
from Juniper Lane. Maximum column and wall loads were assumed to be those normally
associated with residential construction.
INVESTIGATION
Subsurface conditions were investigated at this site on October 3, 2005 by
observing the excavation of two exploratory test pits with a mini- trackhoe at the
approximate locations shown on the Locations of Exploratory Test Pits, Fig. 2. An
engineer from our office was on site to observe the excavation of the exploratory test pits
and visually classify and document the subsurface soil and ground water conditions. A
description of the subsurface soils encountered in the exploratory test pits is shown on the
Logs of Exploratory Test Pits, Fig. 3; and on the Legend of Exploratory Test Pits, Fig. 4.
Representative soil samples obtained from the exploratory test pits were tested in
our laboratory in order to determine their natural moisture content and gradation
properties. The results of the laboratory tests are presented on the Logs of Exploratory,
Test Pits, Fig. 3; on the Gradation Test Results, Fig. 5; and in the Summary of Laboratory
Test Results, Table I.
4
October 24, 2005
Job No. 05 -172
SUBSURFACE CONDITIONS
KOECHLEM CONSULTING ENGINEERS, INC
Consulting Geotechnical Engineers
The subsurface conditions encountered in the exploratory test pits varied. The
subsurface conditions encountered in exploratory test pit TP -1 consisted of approximately
1.5 feet of topsoil overlying red - brown, dry, very dense sand and gravel with cobbles and
boulders to the maximum depth explored of 5.0 feet. Practical excavator refusal on a
boulder occurred at a depth of 5.0 feet. The subsurface conditions encountered in
exploratory test pit TP -2 consisted of approximately 1.5 feet of topsoil overlying existing
fill to a depth of 5.5 feet. The existing fill consisted of dark brown, slightly moist,
medium dense, clayey, gravelly sand. Underlying the existing fill to the maximum depth
explored of 8.0 feet, the subsurface conditions consisted of red - brown, moist, medium
dense sand with scattered gravel.
At the time of this investigation no ground water was encountered in either of the
exploratory test pit to the maximum depth explored of 8.0 feet.
is s6►I
In recent years, radon gas has become a concern. Radon gas is a colorless,
odorless gas that is produced by the decay of minerals in soil and rock. The potential for
radon gas in the subsurface strata is likely. Because no below grade areas are planned for
the proposed residence ventilation for below grade areas will not be necessary. However,
if plans change, we recommend that below grade areas be constructed with ventilation.
5
October 24, 2005 KOECHLEIN CONSULTING ENGINEERS, INC.
Job No. 05 -172 Consulting Geotechnical Engineers
MOLD
Mold tends to grow in areas that are dark and damp, such as bathrooms,
crawlspaces or other below grade areas. Recommendations for mold prevention,
mitigation, or remediation are outside the scope of this investigation. We recommend
that the contractor and /or owner contact a professional Industrial Hygienist to provide
specific recommendations for the prevention and /or remediation of mold.
GROUND WATER
At the time of this investigation no ground water was encountered in either of the
exploratory test pits to the maximum depth explored of 8.0 feet. However, this
investigation was performed during a dry time of year. During wetter times of the year
ground water may be encountered. If ground water is encountered during excavation for
the proposed residence, we should be contacted immediately to provide recommendations
on how to control the ground water.
EXISTING FILL
Existing fill was encountered to a depth of 5.5 feet in exploratory test pit TP -2.
Greater amounts of fill may be encountered across the site. The existing fill consisted of
dark brown, slightly moist, medium dense clayey, gravelly sand. Because we anticipate
el
October 24, 2005 KOECHLEIN CONSULTING ENGINEERS, INC
Job No. 05 -172 Consulting Geotechnical Engineers
that the existing fill was not placed in a controlled manner, all existing fill should be
removed from construction areas prior to beginning construction. The existing fill may
be used as structural fill for this project provided it is free from deleterious material such
as organics, trash, and construction debris.
EXCAVATIONS
We anticipate that excavations up to 5.5 feet in depth may be required to remove
the existing fill. However, greater amounts of fill may be encountered across the site,
resulting in excavations deeper than 5.5 feet.
Care needs to be exercised during construction so that the excavation slopes
remain stable. The subsurface soils, which consisted of the existing fill, natural sand and
gravel with cobbles and boulders, and natural sand classify as Type C soils in accordance
with OSHA regulations. OSHA regulations should be followed in all excavations and
cuts.
Because cobbles and boulders were encountered in the exploratory test pits, it is
our opinion that heavy -duty construction equipment may be required to complete the
necessary excavations.
Up to 1.5 feet of topsoil was encountered in the exploratory test pits. Greater
depths of topsoil could be encountered throughout the site. All topsoil beneath the
proposed construction should be removed. The topsoil may be used in landscape areas.
7
October 24, 2005 KOECHLEIN CONSULTING ENGINEERS, INC.
Job No. 05 -172 Consulting Geotechnical Engineers
FOUNDATIONS
We anticipate that the subsurface soils at the foundation elevations for the
proposed residence will consist of the existing fill and natural sand and gravel with
cobbles and boulders. The existing fill is not suitable for the construction of foundations
and must be removed prior to the construction of foundations to expose the underlying
natural sand. In our opinion, the proposed residence may be supported by a spread
footing foundation system bearing on the natural sand and gravel with cobbles and
boulders or natural sand. We recommend that the spread footing foundation system be
designed and constructed to meet the following criteria:
1. Footings should be supported by the undisturbed, natural sand and gravel
with cobbles and boulders; natural sand; or properly moisture conditioned
and compacted structural fill, as described below in Items 5, 8, and 9.
I 2. We recommend wall and column footings be designed for a maximum
allowable soil bearing pressure of 3,000 psf.
3. Spread footings constructed on the natural sand and gravel with cobbles
and boulders or natural sand could experience up to 0.5 inch of differential
movement between foundation elements. Because the soils are granular,
' we anticipate that the majority of the differential settlement will occur
during construction.
' 4. Wall footings and foundation walls should be designed to span a distance
of at least 10.0 feet in order to account for anomalies in the soil or fill.
5. Foundation wall backfill should not be considered for support of load
bearing footings. Footings should be stepped and supported by undisturbed
natural soils and should not be constructed on foundation wall backfill.
Foundation walls or grade beams should be designed to span across an
excavation backfill zone and should not be constructed with footings
twithin this zone.
i 1 8
r
October 24, 2005
Job No. 05 -172
KOECHLEIN CONSULTING ENGINEERS, INC.
Consulting Geotechnical Engineers
6. The base of the exterior footings should be established at a minimum depth
below the exterior ground surface, as required by the local building code.
We believe that the depth for frost protection in the local building code in
this area is 4.0 feet.
7. Column footings should have a minimum dimension of 24 inches square
and continuous wall footings should have a minimum width of 16 inches.
Footing widths may be greater to accommodate structural design loads.
8. We anticipate that cobbles and boulders will be encountered at the
foundation elevation. Removal of the cobbles and boulders may result in
depressions and rough bottoms in the excavation. The resulting
depressions can be backfilled with compacted backfill or lean concrete.
Refer to the COMPACTED FILL section of this report for backfill
requirements.
9. Fill should be placed and compacted as outlined in the COMPACTED
FILL section of this report. We recommend that a representative of our
office observe and test the placement and compaction of each lift of
structural fill used in foundation construction. It has been our experience
that without engineering quality control, inappropriate construction
techniques occur which result in poor foundation performance.
10. We recommend that a representative of our office observe the completed
foundation excavation. Variations from the conditions described in this
report, which were not indicated by our test pits, can occur. The
representative can observe the excavation to evaluate the exposed
subsurface conditions.
SLABS -ON -GRADE
Based on subsurface conditions encountered in our exploratory test pits, we
anticipate that the subsurface conditions at the approximate floor slab and exterior slab-
on -grade elevations consist of either topsoil, existing fill or the natural sand and gravel.
0
October 24, 2005
Job No. 05 -172
KOECHLEIN CONSULTING ENGINEERS, INC.
Consulting Geotechnicol Engineers
The topsoil is not suitable for the construction of slabs -on -grade and must be removed
from all construction areas prior to the beginning of construction. Slabs -on -grade
constructed on the existing fill could experience up to 1.0 inch of movement. If the
owner is willing to accept the risk of slab movement, then slabs -on -grade may be
constructed on the existing fill. If the owner would like to reduce the risk of slab
movement, we recommend that all of the existing fill be removed and replaced with
properly moisture conditioned and compacted, non - expansive structural fill. In our
opinion, slabs -on -grade may be constructed on the natural sand and gravel with cobbles
and boulders with a low risk of movement. We recommend the following precautions for
the construction of slab -on -grade floors at this site.
1. If the owner is willing to take the risk of slab movement, slabs -on -grade
may be constructed on the existing fill. If the owner would like to reduce
the risk of slab movement, all of the existing fill should be removed and
replaced with properly moisture conditioned and compacted structural fill.
Slabs -on -grade may also be constructed on the natural sand and gravel with
cobbles and boulders.
2. Slabs should be separated from exterior walls and interior bearing
members. Vertical movement of the slabs should not be restricted.
I Exterior slabs should be separated from the residence. These slabs should
be reinforced to function as independent units. Movement of these slabs
should not be transmitted directly to the foundations or walls of the
residence.
4. Frequent control joints should be provided in all slabs to reduce problems
associated with shrinkage of the concrete.
5. Structural fill should be placed and compacted as outlined in the
COMPACTED FILL section of this report. We recommend that a
10
October 24, 2005 KOECHLEIN CONSULTING ENGINEERS, INC.
Job No. 05 -172 Consulting Geotechnicnl Engineers
representative of our office observe and test the placement and compaction
of structural fill used in slab -on -grade construction. It has been our
experience that without engineering quality control, inappropriate
construction techniques can occur which result in poor slab performance.
FOUNDATION DRAINAGE
Surface water, especially that originating from snowmelt, tends to flow through
relatively permeable backfill typically found adjacent to foundations. The water that
flows through the fill collects on the surface of relatively impermeable soils occurring at
the foundation elevation. Both this surface water and possible ground water can cause
wet or moist below grade conditions after construction.
Because no below grade areas are planned for the proposed residence, it is our
opinion that a foundation drain will not be necessary. However, if plans change and
below grade areas are constructed for the residence, we recommend the installation of a
drain along the below grade foundation walls. The drain should consist of a 4 -inch
diameter perforated pipe encased in free draining gravel and a manufactured wall drain.
The gravel should have a maximum size of 1.5 inches and have a maximum of 3 percent
passing the No. 200 sieve. The drain should be sloped so that water flows to a sump
where the water can be removed by pumping, or to a positive gravity outlet.
Recommended details for a typical foundation wall drain are presented in the Typical
Wall Drain Detail, Fig. 6.
October 24, 2005
Job No. 05 -172
LATERAL WALL LOADS
KOECHLEIN CONSULTING ENGINEERS, INC
Consulting Geotechnical Engineers
We do not anticipate the construction of walls that will require lateral earth loads
for design. However, if plans change, we have provided the following information.
Lateral earth pressures depend on the type of backfill and the height and type of wall.
Walls that are free to rotate sufficiently to mobilize the strength of the backfill should be
designed to resist the "active" earth pressure condition. Walls that are restrained should
be designed to resist the "at rest" earth pressure condition. Below grade foundation walls
are typically restrained. The following table presents the lateral wall pressures that may
be assumed for design.
Earth Pressure Condition
Equivalent Fluid Pressure
(pcf)
Active
40
At -rest
50
Passive
300
Notes:
1. Equivalent fluid pressures are for a horizontal backfill condition with no hydrostatic
pressures or live loads.
2. A coefficient of friction of 0.4 may be used at the base of spread footings to resist
lateral loads.
Backfill placed behind or adjacent to foundation walls and retaining walls should
be placed and compacted as recommended in the COMPACTED FILL section of this
report. All foundation walls must be properly braced before placing and compacting
backfill. Placement and compaction of the fill should be observed and tested by a
representative of our office.
12
October 24, 2005
Job No. 05 -172
RETAINING WALLS
KOECHLEIN CONSULTING ENGINEERS, INC.
Consulting Geotechnical Engineers
Although we do not anticipate that retaining walls will be constructed as part of
the development of the site. If plans change, foundations for retaining walls may be
designed and constructed as outlined in the FOUNDATIONS section of this report.
Lateral earth loads for retaining wall designs are presented in the LATERAL WALL
LOADS section of this report. In order to reduce the possibility of developing hydrostatic
pressures behind retaining walls, a drain should be constructed adjacent to the wall. The
drain may consist of a manufactured drain system and gravel. The gravel should have a
maximum size of 1.5 inches and have a maximum of 3 percent passing the No. 200 sieve.
The manufactured drain should extend from the bottom of the retaining wall to within 2
feet of subgrade elevation. The water can be drained by a perforated pipe with collection
of the water at the bottom of the wall leading to a positive gravity outlet. A typical detail
for a retaining wall drain is presented in the Typical Retaining Wall Drain Detail, Fig. 7.
SURFACE DRAINAGE
Reducing the wetting of structural soils can be achieved by carefully planned and
maintained surface drainage. We recommend the following precautions be observed
during construction and maintained at all times after the residence is completed.
1. Wetting or drying of the open excavations should be minimized during
construction.
13
October 24, 2005
Job No. 05 -172
KOECHLEIN CONSULTING ENGINEERS, INC.
Consulting Geotechnica[ Engineers
2. All surface water should be directed away from the top and sides of the
excavations during construction.
3. The ground surface surrounding the exterior of the residence should be
sloped to drain away from the structure in all directions. We recommend a
slope of at least 12 inches in the first 10 feet.
4. Hardscape (concrete and asphalt) should be sloped to drain away from the
residence. We recommend a slope of at least 2 percent for all hardscape
adjacent to the residence.
5. Backfill, especially around foundation walls, should be placed and
compacted as recommended in the COMPACTED FILL section of this
report.
6. Roof drains should discharge at least 10 feet away from foundation walls
with drainage directed away from the residence.
7. Surface drainage for this site should be designed by a Professional Civil
Engineer.
IRRIGATION
Irrigation systems installed next to foundation walls or sidewalks could cause
consolidation of backfill below and adjacent to these areas. This can result in settling of
exterior steps, patios and /or sidewalks if they are constructed on these soils. We
recommend the following precautions be followed:
1. Do not install an irrigation system next to foundation walls. The irrigation
system should be at least 10 feet away from the residence.
2. Irrigation heads should be pointed away from the residence or in a manner
that does not allow the spray to come within 5 feet of the residence.
14
5. Control valve boxes, for automatic irrigation systems, should be located at
least 10 feet away from the structure and periodically checked for leaks
and flooding.
COMPACTED FILL
Structural fill for this project may consist of the existing fill free of deleterious
material; the natural sand and gravel with cobbles and boulders; the natural sand; or
approved imported, non - expansive fill. Deleterious material consists of materials such as
organics, construction debris and trash. The imported fill may consist of non - expansive
silty or clayey sands or gravels with up to 30 percent passing the No. 200 sieve and a
maximum plasticity index of 10. No cobbles or boulders larger than 6 inches should be
placed in fill areas. Fill areas should be stripped of all vegetation, existing fill, and
topsoil; scarified; and then compacted. Topsoil may be used in landscape areas. Fill
should be placed in thin loose lifts and moisture conditioned and compacted to the
recommended compaction shown in the following table. Recommended compaction
varies for the given use of the fill.
15
October 24, 2005 KOECHLEIN CONSULTING ENGINEERS, INC
Job No. 05 -172 Consulting Geotechnical Engineers
3. The landscape around the irrigation system should be sloped so that no
ponding occurs at the irrigation heads.
4. Install landscaping geotextile fabrics to inhibit growth of weeds and to
allow normal moisture evaporation. We do not recommend the use of a
plastic membrane to inhibit the growth of weeds.
5. Control valve boxes, for automatic irrigation systems, should be located at
least 10 feet away from the structure and periodically checked for leaks
and flooding.
COMPACTED FILL
Structural fill for this project may consist of the existing fill free of deleterious
material; the natural sand and gravel with cobbles and boulders; the natural sand; or
approved imported, non - expansive fill. Deleterious material consists of materials such as
organics, construction debris and trash. The imported fill may consist of non - expansive
silty or clayey sands or gravels with up to 30 percent passing the No. 200 sieve and a
maximum plasticity index of 10. No cobbles or boulders larger than 6 inches should be
placed in fill areas. Fill areas should be stripped of all vegetation, existing fill, and
topsoil; scarified; and then compacted. Topsoil may be used in landscape areas. Fill
should be placed in thin loose lifts and moisture conditioned and compacted to the
recommended compaction shown in the following table. Recommended compaction
varies for the given use of the fill.
15
October 24, 2005
Job No. 05 -172
KOECHLEIN CONSULTING ENGINEERS, INC.
Consulting Geotechnical Engineers
Use of Fill
Recommended Compaction
Percentage of the Standard
Proctor Maximum Dry Density
(ASTM D -698)
Percentage of the Modified
Proctor Maximum Dry Density
(ASTM D -1557)
Below Structure Foundations
98
95
Below Slab -On -Grade Floors
95
90
Utility Trench Backfill
95
90
Backfill (Non- Structural)
90
90
Notes:
1. For clay soils the moisture content should be 0 to +3 percent of the optimum moisture content.
2. For granular soils the moisture content should be —2 to +2 of the optimum moisture content.
We recommend the contractor and /or owner contact us so that a representative
from our office can observe and test the placement and compaction of each lift of
structural fill placed. Fill placed behind retaining walls and below foundations, slab -on-
grade floors, and exterior slabs -on -grade is considered structural. It has been our
experience that without engineering quality control, inappropriate construction techniques
can occur which result in poor foundation and slab perfonnance.
LIMITATIONS
Although the exploratory test pits were located to obtain a reasonably accurate
determination of subsurface conditions, variations in the subsurface conditions are always
possible. Any variations that exist beneath the site generally become evident during
construction of the foundation for the residence. Therefore, we must be contacted by the
contractor and /or owner so that a representative of our office can observe the completed
16
October 24, 2005 KOECHLEIN CONSULTING ENGINEERS, INC.
Job No. 05 -172 Consulting Geotechnical Engineers
excavations and foundation construction to confirm that the soils are as indicated by the
exploratory test pits and to verify our foundation and floor slab recommendations.
The placement and compaction of fill, as well as installation of foundations,
should also be observed and tested. The design criteria and subsurface data presented in
this report are valid for 3 years, provided that a representative from our office observes
the site at that time and confirms that the site conditions are similar to the conditions
presented in the SITE CONDITIONS section of this report and that the recommendations
presented in this report are still applicable. We recommend that final plans and
specifications for proposed construction be submitted to our office for study, prior to the
beginning of construction, to determine compliance with the recommendations presented
in this report.
17
October 24, 2005
Job No. 05-172
KOECHLEIN CONSULTING ENGINEERS, INC.
Consulting Geotechnicnl Engineers
We appreciate the opportunity to provide this service. If we can be of further
assistance in discussing the contents of this report or in analysis of the proposed residence
from a geotechnical viewpoint, please contact our office.
KOECHLEIN CONSULTING ENGINEERS, INC.
Richard M. Wenzel III, P.E.
Project Engineer
Reviewed by:
4 0;4� -4
William H. Koechlein, P.E.
President
(4 copies sent)
18
i
1
1
JOB NO. 05-172
VICINITY MAP
KOECHLEIN CONSULTING ENGINEERS, INC.
Consulting Geotechnical Engineers
SITE
NOT TO SCALE
FIG. 1
KOECHLEIN CONSULTING ENGINEERS, INC.
Consulting Geotechnical Engineers
LOT 5
I LOCATIONS OF EXPLORATORY TEST PITS
IJOB NO. 05 -172 FIG.2
TP -1
8545 EL. 8543.2
. �pQ
D:d
8540 o °a
oaa WC =2
-200 =5
8535
8530
I—
w
w
u_ 8525
z
O
1=
Q
w
W 8520
8515
8510
8505
JOB NO. 05 -172
KOECHLEIN CONSULTING ENGINEERS, INC.
Consulting Geotechnical Engineers
TP -2
EL. 8540.9
-200 =8
LOGS OF EXPLORATORY TEST PITS
8545
8540
8535
8530
m
r
m
8525 <
D
O
z
m
m
8520 --1
8515
8510
8505
FIG. 3
KOECHLEIN CONSULTING ENGINEERS, INC.
Consulting Geotechnical Engineers
LEGEND:
TOPSOIL
p Q:: SAND and GRAVEL with Cobbles and Boulders,
Dry, Very dense, Red - brown.
FILL, Sand, Clayey, Gravelly, Slightly moist,
Medium dense, Dark brown.
SAND, Scattered gravel, Moist, Medium dense,
Red - brown.
T REFUSAL. Indicates practical excavator refusal
on a boulder.
BULK SAMPLE. Obtained from excavation spoils.
Notes:
1. Exploratory test pits were excavated on October 3, 2005 using a rubber - tracked mini - trackhoe
2. No free ground water was encountered at the time of excavation in either of the exploratory test pits to the maximum
depth explored of 8.0 feet.
3. The Test Pit Logs are subject to the explanations, limitations, and conclusions as contained in this report.
4. Laboratory Test Results:
WC - Indicates natural moisture ( %)
-200- Indicates percent passing the No. 200 sieve ( %)
5. Approximate elevations were measured with a Stanley Compulevel Elevation Measurement System using the piece
of No. 5 rebar near the northwest property corner as a benchmark. Based on the site survey map provided by the
owner, the elevation of the benchmark is 8549.4.
LEGEND OF EXPLORATORY TEST PITS
JOB NO. 05 -172 FIG. 4
KOECHLEIN CONSULTING ENGINEERS
1 314 112 1,318 .10 tjO 930 92 960 0100 #140 9200
100 0
0 10
8
10
20
70
20
30
Z
M
60
U)
30 -v
z
U)
40
m
<
M
Q
6
<
z
i
40
z
50
50
50
z
50 X
Z
M
ui
m
U
40
i:
40
W
I
60
60
Z
M0
CL
I
Z
M
30
it0
-
30
7
70
20
80
10
20
90
0
80
100
200 100 10 1 0.1 0.01 0.001
DIAMETER OF PARTICLE IN MM
COBBLES GRAVEL
SAND
SILT
CLAY
Sample of
Source
SAND and GRAVEL
TP-1 Sample No. Elev./Depth 4.0 feet
GRAVEL 46 % SAND 49 %
SILT & CLAY 5 % LIQUD LIMIT %
PLASTICITY INDEX %
12 l,31811 m .110 'j0 VT30 90 *60 9100 *140 00
100 7 0
0 10
8
20
70
30
Z
M
60
U)
40
m
<
z
50
50
z
M
ui
40
60
Z
M
30
70
20
80
10
90
1100
200 100 10 1 0.1 0.01 0.001
DIAMETER OF PARTICLE IN MM
COBBLES
GRAVEL SAND
SILT CLAY
Sample of
Source
TP-2
SAND
Sample No. Elev./Depth 7.0 feet
GRAVEL 5 % SAND 87 %
SILT & CLAY 8 % LIQUID LIMIT %
PLASTICITY INDEX %
GRADATION TEST RESULTS
Job No. 05-172 FIG. 5
CLAYEY BACKFILL 10 -
COMPACTED BACKFILL
EDGE OF EXCAVATION
(EXCAVATE AS PER
OSHA REGULATIONS)
MANUFACTURED
WALL DRAIN
FILTER FABRIC
GRAVEL -
12"
KOECHLEIN CONSULTING ENGINEERS, INC.
Consulting Geotechnical Engineers
BELOW GRADE WALL
WATERPROOFING
OR DAMPPROOFING
� PLASTIC SHEETING
F- --r-
PERFORATED PIPE 12" MIN.
NOTES:
1. DRAIN SHOULD BE AT LEAST 12 INCHES BELOW TOP OF FOOTING AT THE
HIGHEST POINT AND SLOPE DOWNWARD TO A POSITIVE GRAVITY OUTLET OR
TO A SUMP WHERE WATER CAN BE REMOVED BY PUMPING.
2. EXCAVATIONS ADJACENT TO FOOTINGS SHOULD BE CUT AT A 1 TO 1
(HORIZONTAL TO VERTICAL) OR FLATTER SLOPE FROM THE BOTTOM OF THE
FOOTINGS. EXCAVATIONS ADJACENT TO FOOTINGS SHOULD NOT BE CUT
VERTICALLY.
3. THE DRAIN SHOULD BE LAID ON A SLOPE RANGING BETWEEN 1/8 INCH AND
1/4 INCH DROP PER FOOT OF DRAIN.
4. GRAVEL SPECIFICATIONS: 1.5 INCH TO NO. 4 GRAVEL WITH LESS THAN 3 %
PASSING THE NO. 200 SIEVE.
5. THE BELOW GRADE CONCRETE FOUNDATION WALLS SHOULD BE
PROTECTED FROM MOISTURE INFILTRATION BY APPLYING A SPRAYED ON
MASTIC WATERPROOFING, DAMPPROOFING, OR AN EQUIVALENT PROTECTION
METHOD.
TYPICAL WALL DRAIN DETAIL
JOB NO. 05 -172 FIG. 6
CLAYEY BACKFILL 10
-11ElI -
- iii —ii
F A COMPACTED BACKFILL
EDGE OF EXCAVATION
(EXCAVATE AS PER
OSHA REGULATIONS)
FILTER FA
G
PERFORATED PIPE
`►N11944
KOECHLEIN CONSULTING ENGINEERS, INC.
Consulting Geotechnical Engineers
MANUFACTURED
WALL DRAIN
- RETAINING WALL
WATERPROOFING
OR DAMPPROOFING
1. DRAIN SHOULD BE SLOPED DOWNWARD TO A POSITIVE GRAVITY OUTLET
OR TO A SUMP WHERE WATER CAN BE REMOVED BY PUMPING.
2. THE DRAIN SHOULD BE LAID ON A SLOPE RANGING BETWEEN 1/8 INCH AND
1/4 INCH DROP PER FOOT OF DRAIN.
3. GRAVEL SPECIFICATIONS: 1.5 INCH TO NO. 4 GRAVEL WITH LESS THAN 3
PASSING THE NO. 200 SIEVE.
4. THE BELOW GRADE CONCRETE RETAINING WALLS SHOULD BE
PROTECTED FROM MOISTURE INFILTRATION BY APPLYING A SPRAYED ON
MASTIC WATERPROOFING, DAMPPROOFING, OR AN EQUIVALENT PROTECTION
METHOD.
TYPICAL RETAINING WALL DRAIN DETAIL
JOB NO. 05 -172 FIG. 7
C/]
O
0
0
p
C
U
z
C6
W
W
z_
U
z
W
(
V
z
J
z
O
U
Z_
W
J
U
w
O
Y
c�
r`
0
O
z
m
0
C.
�
v
z
O
J_
J
z
s
U-�oo
U3°
C7 o
w
F- p
w
n
a
z
¢oo
Z � U
w -
w -
Q p
w
J
-
N
O
-
U
z
C6
W
W
z_
U
z
W
(
V
z
J
z
O
U
Z_
W
J
U
w
O
Y
c�
r`
0
O
z
m
0