HomeMy WebLinkAboutB12-0382 GEOTECHNICAL REPORTKOECHLEIN CONSULTING ENGINEERS, INC.
GEOTECHNICAL AND MATERIALS ENGINEERS
GEOTECHNICAL REPORT
PROPOSED FORD PARK COMPLEX REDEVELOPMENT
580 SOUTH FRONTAGE ROAD EAST
VAIL, COLORADO
Job No. 09 -034
Prepared for:
Todd Oppenheimer _
Town of Vail
Department of Public Works D
1309 Elkhorn Drive
Vail, CO 81657 "I 2 1 2012
TOWN OF VAIL
September 10, 2009
DENVER: 12364 West Alameda Prkwy., Suite 115, Lakewood, CO 80228 (303) 989 -1223
GRAND JUNCTION. 52925 112 Rd* Suite 201 . Grand Junction, C081505(970)241-7700
AVON /SILVERTHORNE. (970) 949 -6009
31a -o38a
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
TABLE OF CONTENTS
SCOPE
I
EXECUTIVE SUMMARY
2
SITE CONDITIONS
5
PROPOSED CONSTRUCTION
6
SUBSURFACE EXPLORATION
7
SUBSURFACE CONDITIONS
8
RADON
10
MOLD
10
EXISTING FILL
11
GROUND WATER
12
EXCAVATIONS
13
SHORING
14
SEISMICITY
15
DEWATERING
15
CORROSION
17
FOUNDATIONS
18
SLABS -ON -GRADE
20
FOUNDATION DRAINAGE
22
LATERAL WALL LOADS
23
RETAINING WALL
24
SURFACE DRAINAGE
25
COMPACTED FILL
26
PAVEMENT DESIGN
27
Flexible Pavement Design
28
Rigid Pavement Design
29
Pavement Materials
30
Subgrade Stabilization
31
Construction Considerations
32
Drainaee
33
LIMITATIONS
33
September 10, 2009 KOECHLEIN CONSULTING ENGINEERS, INC.
Job No. 09 -034 Geotechnical and Materials Engineers
LIST OF FIGURES
VICINITY MAP
LOCATION OF EXPLORATORY BORING IN SOUTH AREA
LOCATIONS OF EXPLORATORY BORINGS IN NORTH AREA
LOGS OF EXPLORATORY BORINGS
LEGEND OF EXPLORATORY BORINGS
GRADATION TEST RESULTS
FOUNDATION EXCAVATION RECOMMENDATIONS
TYPICAL WALL DRAIN DETAIL
TRAPEZOIDAL LATERAL EARTH PRESSURE
TYPICAL RETAINING WALL DRAIN DETAIL
SUMMARY OF LABORATORY TEST RESULTS
PAVEMENT DESIGN CALCULATIONS
PAVEMENT CONSTRUCTION RECOMMENDATIONS
Fig. 1
Fig. 2
Fig.3
Figs. 4 and 5
Fig. 6
Figs. 7 thru 10
Fig. 11
Fig. 12
Fig. 13
Fig. 14
Table I
Appendix A
Appendix B
September 10, 2009 KOECHLEIN CONSULTING ENGINEERS, INC.
Job No. 09 -034 Geotechnical and Materials Engineers
SCOPE
This report presents the results of a subsurface exploration performed for the
proposed Ford Park Complex redevelopment project to be constructed at 580 South
Frontage Road East in Vail, Colorado. The approximate site location is shown on the
Vicinity Map, Fig. 1. The purpose of this report is to present the results of the subsurface
exploration at the subject site and to provide geotechnical recommendations for the
proposed construction.
This report includes descriptions of subsurface soil and ground water conditions
encountered in the exploratory borings, recommended foundation systems, allowable soil
bearing pressure, engineering soil properties, and recommended foundation design and
construction criteria. This report was prepared from data developed during our
subsurface exploration, laboratory testing, and our experience with similar projects and
subsurface conditions in the area.
At the time of our subsurface exploration, the locations of the proposed structures
within the site had not been fmalized. The recommendations presented in this report are
based on the construction of a multi -level parking structure and recreation center building
within the south and north site boundaries as indicated in the Location of Exploratory
Boring in South Area, Fig. 2 and Locations of Exploratory Borings in North Area, Fig. 3.
We should be contacted to review our recommendations when the final locations and
plans for the proposed parking garage and recreation center building have been
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
completed. A summary of our findings and conclusions is presented in the following
paragraphs.
EXECUTIVE SUMMARY
1. Subsurface conditions encountered in the exploratory borings TH -1 thru
TH -5 varied. The subsurface conditions encountered in exploratory boring
TH -1 consisted of 3 inches of asphalt underlain by a medium dense to very
dense, silty, sand and gravel with cobbles and scattered boulders to the
maximum depth explored of 20.0 feet. The subsurface conditions
encountered in exploratory borings TH -2 and TH -4 consisted of 2.5 to 6
inches of either asphalt or topsoil underlain by existing fill to varying
depths of 6.0 to 12.0 feet. The existing fill is characterized by a medium
dense to dense, gravelly sand with scattered cobbles and lenses of silty clay.
Below the existing fill the subsurface conditions consisted of natural,
medium dense to very dense, silty, sand and gravel with cobbles and
scattered boulders to the maximum depths explored of 40.0 feet. The
subsurface conditions encountered in boring TH -3 consisted of 6 inches of
topsoil underlain by existing fill. The existing fill is characterized by a
medium stiff, sandy clay to a depth of 4.0 feet. Below the existing fill the
subsurface conditions consisted of natural, medium dense to very dense,
silty, sand and gravel with cobbles and scattered boulders to the maximum
depth explored of 20.0 feet. The subsurface conditions encountered in
boring TH -5 consisted of 2 inches of topsoil underlain by medium dense to
dense, sandy silt to a depth of 4.0 feet. Below the silt, the subsurface
conditions consisted of a medium dense to very dense, silty, sand and
gravel with cobbles and scattered boulders to the maximum depth explored
of 40.0 feet. Refer to the SUBSURFACE CONDITIONS section of this
report for additional information.
2. At the time of drilling, ground water was encountered in boring TH -3 at a
depth of 9.0 feet. Ground water was not encountered during drilling in
borings TH -1, TH -2, TH -4, and TH -5 to the maximum depth explored of
20.0 feet in TH -1 and 40.0 feet in borings TH -2, TH -4, and TH -5. Refer
to the GROUND WATER section of this report for additional details.
2
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
3. Topsoil was encountered in borings TH -3 thru TH -5 to varying depths of 2
to 6 inches. Greater depths of topsoil could be encountered across the site.
All topsoil below areas of proposed construction should be removed.
Topsoil may be used in landscaped areas.
4. Asphalt was encountered in borings TH -1 and TH -2 to varying depths of
2.5 to 3 inches. Greater depths of asphalt could be encountered in paved
areas across the site. All asphalt in the area of the proposed construction
should be removed prior to the start of construction.
5. Existing fill was encountered in exploratory borings TH -2 thru TH -4 to
varying depths of 4.0 to 12.0 feet. However, greater depths of existing fill
could be encountered across the site. The existing fill encountered in
borings TH -2 and TH -4 is characterized by tan, brown, slightly moist to
moist, medium dense to dense, silty, gravelly sand with organics, scattered
cobbles, and lenses of silty clay. The existing fill encountered in boring
TH -3 is characterized by a dark brown, slightly moist, medium stiff, sandy
clay, with some gravel. Refer to the EXISTING FILL section of this
report for additional recommendations.
6. We anticipate that the subsurface conditions at the foundation elevation
for the proposed parking garage will consist of the natural sand and gravel.
It is our opinion that a spread footing foundation system constructed on the
sand and gravel will have a low risk of movement. We anticipate that the
subsurface conditions at the foundation elevation for the proposed
recreation center building could consist either of existing fill or the natural
sand and gravel. Due to the presence of existing fill at the foundation
elevation, special consideration should be taken into account when
selecting a foundation system for the proposed recreation center building.
Refer to the FOUNDATIONS section of this report for complete
recommendations.
7. We anticipate that the subsurface conditions at the proposed slabs -on-
grade elevation for the proposed parking garage will consist of the natural
sand and gravel. Slabs -on -grade constructed on the natural, sand and
gravel will have a very low risk of movement. We anticipate that the
subsurface conditions at the slab -on -grade elevation for the proposed
recreation center building could consist of either existing fill or the natural
sand and gravel. Due to the presence of existing fill at the slab -on -grade
elevation, special considerations will need to be taken into account. Refer
3
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
to the SLABS -ON -GRADE section of this report for complete
recommendations.
8. We anticipate excavation depths of up to 40 feet may be required for
construction of the proposed parking garage and 4 feet for the proposed
recreation center building. All cuts should be constructed as
recommended in this report in order to maintain the stability of the slopes
and sides of excavations. Refer to the EXCAVATIONS section of the
report for additional details.
9. Based on the subsurface conditions encountered in the exploratory borings
and depth of the anticipated excavations, we believe that heavy -duty
construction equipment may be necessary to complete the required
excavations.
10. Due to the anticipated depth of excavation for the proposed parking
garage, we anticipate that a temporary shoring system may be necessary
for the proposed construction. Refer to the SHORING section of this
report for additional details
11. Laboratory tests were conducted on soil samples to determine their
corrosive potential in order to evaluate any potential impact on
construction activities. Refer to the CORROSION section of this report
for additional information.
12. Drainage around the proposed parking garage and recreation center
building should be designed and constructed to provide for rapid removal
of surface runoff and avoid concentration of water adjacent to foundation
walls. Refer to the SURFACE DRAINAGE section of this report for
additional recommendations.
13. The potential for radon gas is a concern in the area. Refer to the RADON
section of this report for additional recommendations.
14. The potential for mold is a concern in new construction. Refer to the
MOLD section of this report for additional recommendations.
15. Based on the subsurface soil profile, this site has a seismic site
classification of Site Class C. Refer to the SEISMICITY section of this
report for additional details.
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
16. Laboratory testing on the subgrade samples in borings TH -1 and TH -2 to a
depth of 5.0 feet indicate that the soils classify as A -1 -a and A -1 -b soils in
accordance with the AASHTO classification system. The pavement
designs presented in this report are based on the subgrade soils classifying
as A -1 -b soils
17. Pavement thickness design recommendations for the proposed parking lots
are presented in the PAVEMENT DESIGN section and in Appendix A of
this report.
18. Pavement construction recommendations are presented in the
CONSTRUCTION CONSIDERATIONS section of this report and in
Appendix B.
SITE CONDITIONS
The subject site is located at 580 South Frontage Road East in Vail, Colorado
which is currently occupied by the existing Ford Park Complex. The existing Ford Park
Complex consists of asphalt parking lots, concrete pathways, athletic fields, a concession
stand, tennis courts, playgrounds, gardens, and an amphitheater. The existing structures
are single -story in height with no below grade levels. Buildings are of wood frame and
cast -in -place construction with slab -on -grade floors. The northern portion of the park is
bordered to the north by South Frontage Road East, to the east and south by Gore Creek,
and to the west by residential structures. The southern portion of the park is bordered to
the north by Vail Valley Drive, to the east and south by the Vail Golf Club golf course,
and to the west by Pinos Del Norte. At the time of our subsurface exploration the specific
locations for the proposed parking garage and recreation center building had not been
5
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
determined. Overall site topography is gently rolling with a slope down towards the
south at an approximate grade of 5 percent. However, the topography changes along the
southern side of the north improvement area to a steep slope down towards Gore Creek at
an approximate grade of 10 to 25 percent. The existing parking lots are constructed of
asphalt pavement. Vegetation on -site consists of cut grasses within the athletic fields
with tall pine and aspen trees in the adjacent landscaped areas.
PROPOSED CONSTRUCTION
We understand that the proposed project consists of the construction of a parking
garage and recreation center building as well as the pavement of parking lots within the
existing Ford Park Complex in Vail, Colorado. Prior to the start of our subsurface
exploration a site plan showing the location of the requested exploratory borings was
provided by the Town of Vail. At the time of our subsurface exploration, locations for
the proposed structures had not been determined.
We anticipate that the proposed parking garage will consist of a multi -level
structure with up to three levels of above grade and three levels of below grade parking.
The proposed parking garage will most likely consist of cast -in -place and pre -cast
concrete construction with slab -on -grade floors at the lowest level. We anticipate that
excavations up to 40 feet in depth may be necessary for construction of the proposed
Ce
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
parking garage. Due to the potential for deep excavation cuts both temporary and /or
permanent shoring systems may be necessary.
We anticipate that the proposed recreation center building will consist of a
structure with up to two- stories above grade and no below grade levels. The proposed
recreation center building will be of cast -in -place concrete and wood frame construction
with slab -on -grade floors. Excavations up to 4 feet in depth will likely be necessary for
the construction of the proposed recreation center building. However, if the proposed
recreation center building is constructed in the area of existing fill, excavation depths may
be as deep as 12 feet.
SUBSURFACE EXPLORATION
Subsurface conditions were explored at this site on August 18, 19, and 20, 2009
by drilling a total of five exploratory borings (TH -1 thru TH -5). Exploratory borings TH-
1, TH -2, TH -4, and TH -5 were drilled using an air rotary percussion down -hole hammer
mounted on a tracked drill rig at the approximate locations shown on the Location of
Exploratory Boring in South Area, Fig. 2 and on the Locations of Exploratory Borings in
North Area, Fig. 3. Boring TH -3 was drilled with a 4 -inch diameter continuous flight
power auger mounted on a tracked drill rig at the approximate location shown on the
Locations of Exploratory Borings in North Area, Fig. 3.
7
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
An engineer from our office was on site during the subsurface exploration to
supervise the drilling of the exploratory borings and to visually classify and document the
subsurface soils and ground water conditions. Graphical logs of the subsurface
conditions encountered within the exploratory borings are presented on the Logs of
Exploratory Borings, Figs. 4 and 5; and on the Legend of Exploratory Borings, Fig. 6.
Soil samples obtained from the exploratory borings were visually classified and
select samples were tested in our laboratory to determine their natural moisture content,
natural dry density, gradation properties, Atterberg limits, and corrosive potential.
Results of the laboratory testing are presented on the Logs of Exploratory Borings, Figs. 4
and 5; on the Gradation Test Results, Figs. 7 thru 10; and on the Summary of Laboratory
Test Results, Table I.
SUBSURFACE CONDITIONS
Subsurface conditions encountered in exploratory borings TH -1 thru TH -5 varied.
The subsurface conditions encountered in exploratory boring TH -1 consisted of 3 inches
of asphalt underlain by a brown, slightly moist to wet, medium dense to very dense, silty,
sand and gravel with cobbles and scattered boulders to the maximum depth explored of
20.0 feet. The subsurface conditions encountered in exploratory borings TH -2 and TH -4
consisted of 2.5 to 6 inches of either asphalt or topsoil underlain by existing fill to varying
depths of 6.0 to 12.0 feet. The existing fill is characterized by a tan, brown, slightly moist
E
September 10, 2009 KOECALEIN CONSULTING ENGINEERS, INC.
Job No. 09 -034 Geotechnical and Materials Engineers
to moist, medium dense to dense, silty, gravelly sand with organics, scattered cobbles,
and lenses of silty clay. Below the existing fill the subsurface conditions consisted of a
natural, brown, slightly moist to wet, medium dense to very dense, silty, sand and gravel
with cobbles and scattered boulders to the maximum depths explored of 40.0 feet. The
subsurface conditions encountered in boring TH -3 consisted of 6 inches of topsoil
underlain by existing fill. The existing fill is characterized by a dark brown, slightly
moist, medium stiff, sandy clay, with some gravel to a depth of 4.0 feet. Below the
existing fill the subsurface conditions consisted of a natural, brown, slightly moist to wet,
medium dense to very dense, silty, sand and gravel with cobbles and scattered boulders to
the maximum depth explored of 20.0 feet. The subsurface conditions encountered in TH-
5 consisted of 2 inches of topsoil underlain by a brown, dry to slightly moist, medium
dense to dense, sandy silt with scattered gravels and cobbles to a depth of 4.0 feet. Below
the silt, the subsurface conditions consisted of a brown, slightly moist to wet, medium
dense to very dense, silty, sand and gravel with cobbles and scattered boulders to the
maximum depth explored of 40.0 feet.
At the time of drilling, ground water was encountered in boring TH -3 at a depth of
9.0 feet. Ground water was not encountered during drilling in borings TH -1, TH -2, TH -4,
and TH -5 to the maximum depth explored of 20.0 feet in TH -1 and 40.0 feet in borings
TH -2, TH -4, and TH -5.
0j
September 10, 2009 KOECHLEIN CONSULTING ENGINEERS, INC.
Job No. 09 -034 Geotechnical and Materials Engineers
RADON
In recent years, radon gas has become a concern. Radon gas is a colorless,
odorless gas that is produced by the decay of minerals in soil and rock. The potential for
radon gas in the subsurface strata is likely. Since the proposed parking garage could be
constructed with up to three levels of below grade parking, the risk of radon gas for this
structure is high. We suggest that all below grade levels be designed with ventilation for
these areas.
Because the proposed recreation center will likely be constructed with no below
grade levels, the risk for radon gas for this structure is low. However, if plans change and
below grade levels are added, we recommend all below grade levels be designed with
ventilation for these areas.
MOLD
Mold has become a concern with new construction. Mold tends to develop in
dark or damp areas such as below grade levels, under floor spaces, or bathrooms.
Recommendations for the prevention, remediation, and /or mitigation of mold is outside
the scope of this report. We recommend that the owner contact a Professional Industrial
Hygienist for recommendations for the prevention, remediation, and /or mitigation of
mold.
10
September 10, 2009 KOECHLEIN CONSULTING ENGINEERS, INC.
Job No. 09 -034 Geotechnical and Materials Engineers
EXISTING FILL
Existing fill was encountered in exploratory borings TH -2 thru TH -4 to varying
depths of 4.0 to 12.0 feet. However, greater depths of existing fill could be encountered
across the site. The existing fill encountered in borings TH -2 and TH -4 is characterized
by tan, brown, slightly moist to moist, medium dense to dense, silty, gravelly sand with
scattered cobbles and lenses of silty clay. The existing fill encountered in boring TH -3 is
characterized by a dark brown, slightly moist, medium stiff, sandy clay, with scattered
gravels and cobbles.
All existing fill should be removed and replaced with properly moisture
conditioned and compacted new structural fill where new structures will be constructed.
Due to the necessary depth of the excavation for the proposed parking garage, we
anticipate that all existing fill will be removed in the initial excavation and will not likely
influence the construction of the proposed parking garage. However, the presence of
existing fill could influence the construction of the proposed recreation center building.
The final location of the proposed recreation building should be carefully selected to an
area with the least amount of existing fill. When the final location the proposed
recreation center building is determined, an additional site specific subsurface exploration
could be performed in order to better define the limits of the existing fill within the final
location.
11
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
We anticipate that the existing, gravelly sand fill may be used as structural fill
for this project. However, we do not recommend that that the existing, silty clay fill be
used as structural fill for this area. The existing, silty clay fill may be placed in
landscaped areas. Existing fill should be evaluated by a representative of our office prior
to its use to determine placement criteria as structural fill. Refer to the COMPACTED
FILL section of this report for additional recommendations.
GROUND WATER
At the time of drilling, ground water was encountered in boring TH -3 at a depth of
9.0 feet. Ground water was not encountered during drilling in borings TH -1, TH -2, TH -4,
and TH -5 to the maximum depth explored of 20.0 feet in TH -1 and 40.0 feet in borings
TH -2, TH -4, and TH -5. Based on the encountered ground water conditions, the
anticipated excavation depths, and depending upon where the proposed structures are
constructed across the site, it is possible that ground water could adversely affect the
construction of the proposed parking garage. However, we do not anticipate that ground
water will adversely affect the construction of the proposed recreation center building. If
ground water is encountered during construction, both temporary and permanent
dewatering may be necessary. Refer to the DEWATERING section of this report for
additional information.
12
September 10, 2009 KOECHLEIN CONSULTING ENGINEERS, INC.
Job No. 09 -034 Geotechnical and Materials Engineers
EXCAVATIONS
We anticipate that excavation depths of up to 40 feet could be necessary for
construction of the proposed parking garage, while excavations of up to 4 feet will be
necessary for construction of the proposed recreation center building. However, if the
proposed recreation center building is constructed in the area of existing fill, excavation
depths may be as deep as 12 feet. Based on the subsurface conditions encountered in the
exploratory borings, it is our opinion that heavy -duty excavation equipment will be
necessary to complete the required excavations.
Care needs to be exercised during construction so that the excavation slopes
remain stable. In our opinion, the existing fill, natural silt, and natural sand and gravel
above the water table classify as Type B soils in accordance with OSHA classifications.
The existing fill, natural silt, and natural sand and gravel below the water table classify as
Type C soils in accordance with OSHA regulations. OSHA regulations should be
followed in any excavations or cuts.
Existing fill was encountered at this site to varying depths of 4.0 to 12.0 feet.
Greater depths of existing fill could be encountered across the site. All existing fill
located below areas of construction should be removed. If necessary these areas may be
brought back to finished grade with properly moisture conditioned and compacted new
structural fill as outlined in the COMPACTED FILL section of this report.
Asphalt and topsoil was encountered to varying depths of 2 to 6 inches. Greater
13
September 10, 2009 KOECHLEIN CONSULTING ENGINEERS, INC.
Job No. 09 -034 Geotechnical and Materials Engineers
amounts of asphalt and topsoil could be encountered across the site. All asphalt and
topsoil located below areas of construction should be removed prior to the start of
construction. Topsoil may be used in landscaped areas.
SHORING
Based on the proposed construction, we anticipate that the parking garage will
require excavations of up to 40 feet in depth. While the location of the proposed parking
garage had not been finalized at the time of the issue of this report, we anticipate that the
construction of the garage could be influenced by existing structures and athletic fields
across the Ford Park Complex. Due to the depth of excavation and close proximity of
utilities, roadways, and existing structures, it may not be possible to slope all of the
excavation sides as required by OSHA regulations. Therefore, a temporary shoring
system may be necessary. The ability to complete the excavation within the site
constraints and the need for a shoring system including the type of system should be
evaluated during the design phase of the project. Due to the constant evolution of shoring
systems, we recommend a contractor specializing in shoring be contacted to provide
applicable shoring system alternatives and associated design and construction criteria. If
requested, we can assist the owner in selecting an appropriate shoring system after a
shoring contractor has been contacted.
14
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSUL TING ENGINEERS, INC.
Geotechnical and Materials Engineers
The subsurface conditions encountered across the Ford Park Complex site
consisted of existing sand fill, existing clay fill, natural silt, and natural sand and gravel.
Engineering properties of the soils are based on visual observation and laboratory testing
that was conducted. The following table outlines engineering properties of the soils that
may be used in design of the proposed shoring system.
Soil Type
Y
(c
(degrees)
C
(psf)
FILL, Sand
120
35
0
FILL, Clay
105
0
200
SILT
115
30
0
SAND and GRAVEL
135
35
0
SEISMICITY
The subsurface soil and ground water conditions encountered within the
exploratory borings indicate that the soil profile classifies as a very dense soil and soft
rock profile. Based on this classification and the International Building Code (IBC), it is
our opinion that the subject site has a seismic site classification of Site Class C.
DEWATERING
At the time of drilling ground water was encountered in boring TH -3 at a depth of
9.0 feet. Groundwater was not encountered during drilling in borings TH -1, TH -2, TH -4,
and TH -5 to the maximum depth explored of 20.0 feet in TH -1 and 40.0 feet in borings
TH -2, TH -4, and TH -5. Ground water in mountain terrain typically travels in more
15
September 10, 2009 KOECHLEIN CONSULTING ENGINEERS, INC.
Job No. 09 -034 Geotechnical and Materials Engineers
permeable layers of soil. Therefore, ground water may be encountered at various
elevations across the site. During wetter times of the year, ground water may be
encountered at higher elevations. If construction begins after July 15'', it is our opinion,
less ground water may be encountered.
Based on the proposed construction, excavations for the proposed parking garage
could be up to 40 feet below the current ground surface elevation, while excavations for
the proposed recreation center building will be approximately 4 below the ground surface
elevation. Because ground water was encountered in the exploratory borings above the
proposed excavation depths for the proposed parking garage, we anticipate that both
temporary and permanent dewatering systems will be necessary.
Temporary dewatering methods that have worked in this area to control the
ground water have consisted of either shallow trenches or interceptor trenches. Shallow
trenches can be constructed in the footing excavations adjacent to the proposed footings
and can be sloped to a sump pit where the water can be removed by pumping.
Due to the potential for shallow ground water and the required depth of
excavation for the proposed parking garage, permanent dewatering will be required for
the construction of the proposed parking garage. The permanent dewatering system
should consist of an underslab drain in conjunction with foundation wall drains. These
two systems could be combined and sloped to a sump pit where the water can be removed
by pumping. Because the water will require pumping, we recommend that the permanent
16
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
dewatering system be designed with redundant pumps and possibly with backup power.
The underslab drain may consist of a series of lateral and collection pipes sloped to the
sump pit, while the foundation wall drains may consist of a manufactured wall drain and
collection pipes sloped to a sump pit. A professional Civil Engineer or Dewatering
Consultant should be contacted to layout the underslab drains, foundation wall drains and
sump pit locations. If requested, we can assist the dewatering system designer.
CORROSION
Laboratory tests were conducted on soil samples to determine the corrosive
potential of the on -site soils and to evaluate any potential impact on construction
activities. Conductivity, resistivity, pH, as well as soluble chloride and sulfate testing
was conducted on the sand and gravel and the sandy silt.
The sand and gravel at a depth of 14.0 feet had a resistivity of 4,300 Ohm-
centimeters, a pH of 7.0, water soluble chloride concentration of 14.0 ppm, and soluble
sulfate concentration of 0 ppm. The sandy silt at 0.2 - 4.0 feet had a resistivity of 5,800
Ohm- centimeters, a pH of 7.1, water soluble chloride concentration of 4.8 ppm, and
soluble sulfate concentration of 0 ppm. The results of these tests are presented in the
Results of the Summary of Laboratory Test Results, Table I.
Chloride concentrations greater than or equal to 500 ppm, sulfate concentrations
greater than or equal to 2000 ppm, a pH of less than 5.5, and a resistivity of 1,000 Ohm-
17
September 10, 2009 KOECHLEIN CONSULTING ENGINEERS, INC.
Job No. 09 -034 Geotechnical and Materials Engineers
centimeter or less indicate a high corrosion potential. Based on the laboratory test results,
the sand and gravel and sandy silt have a negligible corrosive potential. In our opinion,
no special cement requirements will be required for concrete elements that come in
contact with the on -site soils.
FOUNDATIONS
While the final locations of the proposed parking garage and recreation center
building have not been determined, based on the subsurface exploration and the proposed
construction, we anticipate that the material at the foundation elevation for the proposed
parking garage will consist of the natural sand and gravel. The material at the foundation
elevation for the proposed recreation center building will consist either of existing clay
fill, sand fill, or natural sand and gravel. It is our opinion that spread footings constructed
on the natural sand and gravel or properly moisture treated and compacted structural fill
will have a low risk of movement. Spread footings constructed on the existing fill will
have a high risk of movement. We do not recommend that spread footings be constructed
on the existing fill. If the owner would like to construct the proposed structures in areas
of existing fill, we recommend that all existing fill below the proposed construction be
removed and, if necessary, replaced with properly moisture treated and compacted
structural fill. We recommend that spread footings at these sites be designed and
constructed to meet the following criteria:
IN
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Spread footings should be supported by either the natural sand and gravel
or properly moisture conditioned and compacted non - expansive structural
fill.
2. Footings at depths less than 20 feet from the current ground surface may
be designed for a maximum allowable soil bearing pressure of 4,000 psf.
Footings at depths greater than 20 feet from the current ground surface
may be designed for a maximum allowable soil bearing pressure of 6,000
psf.
Existing fill was encountered to varying depths of 4.0 to 12.0 feet in
exploratory borings TH -2 thru TH -4. Greater depths of existing fill could
be encountered across the site. Topsoil and asphalt was encountered to
varying depths of 2 to 6 inches in the exploratory borings. Greater depths
of topsoil and asphalt could be encountered across the site. Any topsoil,
asphalt, and all existing fill must be removed in order to expose the natural
soils. If necessary, properly moisture conditioned and compacted non-
expansive structural fill may be placed beneath the proposed foundations.
Refer to the COMPACTED FILL section of this report for structural fill
requirements.
4. Spread footings constructed on the natural sand and gravel or properly
moisture conditioned and compacted structural fill should experience less
than 0.5 inch of differential movement between foundation elements.
Because the soils are granular, we anticipate that the majority of the
settlement will occur during construction.
Continuous foundation systems should be designed to span a distance of at
least 10 feet in order to account for anomalies in the soil or fill.
6. Compacted structural fill placed beneath spread footings should extend at
a 1 to 1 (Horizontal to Vertical) slope from the outside edge of the
footings. Excavation recommendations beneath spread footings are shown
in the Foundation Excavation Recommendations, Fig. 11.
7. The base of the exterior footings should be established at a minimum
depth below the exterior ground surface, as required by the local building
code. We believe that the depth for frost protection in the local building
code in this area is 40 inches.
19
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
8. Column footings should have a minimum dimension of 24 inches square
and continuous wall footings should have a minimum width of 16 inches.
Footing widths may be greater to accommodate structural design loads.
9. Pockets or layers of soft soils or existing fill may be encountered in the
bottom of the completed footing excavations. These materials should be
removed to expose the undisturbed natural sand and gravel. The
foundations should be constructed on the natural sand and gravel or new
structural fill. Refer to the COMPACTED FILL section of this report for
backfill requirements.
10. Structural fill should be placed and compacted as outlined in the
COMPACTED FILL section of this report. We recommend that a
representative of our office observe and test the compaction of structural
fill used in foundation construction during the placement process. It has
been our experience that without engineering quality control, inappropriate
construction techniques can occur which result in unsatisfactory
foundation performance.
11. A representative from our office must observe the completed foundation
excavations. Variations from the conditions described in this report,
which were not indicated by the borings, can occur. The representative
can observe the excavations to evaluate the exposed subsurface conditions.
SLABS -ON -GRADE
While the final locations of the proposed parking garage and recreation center
building have not been determined, based on the subsurface exploration and the proposed
construction, we anticipate that the subsurface conditions at the approximate slab -on-
grade elevation for the proposed parking garage should consist of the natural sand and
gravel while the conditions at the approximate slab -on -grade elevation for the proposed
recreation center building could consist of either topsoil, asphalt, existing fill, or natural
sand and gravel. It is our opinion that slabs -on -grade could be constructed on the natural,
20
September 10, 2009
Job No. 09 -034
XOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
sand and gravel with a very low risk of movement. Slabs -on -grade constructed on the
existing fill will have a high risk of movement. We do not recommend that slabs -on-
grade be constructed on the existing fill. We recommend the following precautions for
the construction of slabs -on -grade at these sites:
1. Slabs -on -grade may be constructed on the natural sand and gravel or
properly moisture conditioned and compacted structural fill with a very
low risk of movement.
2. Existing fill was encountered in exploratory borings TH -2 thru TH -4 to
varying depths of 4.0 to 12.0 feet. Greater depths of existing fill could be
encountered across the site. All existing fill should be removed and, if
necessary, replaced with properly moisture treated and compacted
structural fill. Refer to the COMPACTED FILL section of this report for
structural fill requirements.
3. Topsoil and asphalt was encountered to varying depths of 2 to 6 inches in
the exploratory borings. Greater depths of topsoil and asphalt could be
encountered across the site. All topsoil and asphalt should be removed
from below slabs -on -grade.
4. Slabs -on -grade may be designed using a modulus of subgrade reaction of
150 psi.
5. Slabs should be separated from exterior walls and interior bearing
members. Vertical movement of the slab should not be restricted.
6. Exterior slabs should be separated from the parking garage and the
recreation center building. These slabs should be reinforced to function as
independent units. Movement of these slabs should not be transmitted
directly to the foundations or walls of these structures.
7. Frequent control joints should be provided in all slabs to reduce problems
associated with shrinkage of the concrete.
8. Structural fill beneath slabs -on -grade may consist of the existing sand fill,
natural sand and gravel, or approved imported, non - expansive fill.
21
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Structural fill should be placed and compacted as outlined in the
COMPACTED FILL section of this report. We recommend that a
representative of our office observe and test the placement and compaction
of each lift of structural fill used in slab -on -grade construction. It has been
our experience that without engineering quality control, inappropriate
construction techniques can occur which results in unsatisfactory slab
performance.
FOUNDATION DRAINAGE
Surface water tends to flow through relatively permeable backfill typically found
adjacent to foundations. The water that flows through the fill collects on the surface of
relatively impermeable soils occurring at the foundation elevation. Both this surface
water and possible ground water can cause wet or moist below grade conditions after
construction. It is our understanding that the proposed recreation center building will not
be constructed with below grade levels. Provided no below grade levels or crawl spaces
are constructed, it is our opinion that a foundation drain will not be necessary for the
proposed recreation center building. However, due to the depth of the excavation for the
proposed parking garage we anticipate that below grade walls will be constructed,
therefore, we recommend the installation of an exterior drain along the below grade
foundation walls of the proposed parking garage.
The foundation drain for the below grade area of the proposed parking garage may
consist of a manufactured wall drain and gravel. The gravel should have a maximum size
of 1.5 inches and a maximum of 3 percent passing the No. 200 sieve. Screened aggregate
22
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
will be satisfactory for the drainage layer. The manufactured drain should extend from
the bottom of the retaining wall to within 2 feet of subgrade elevation. The water can be
drained by a perforated pipe with collection of water at the bottom of the wall leading to a
sump pit where water can be pumped out. Recommended details for typical foundation
wall drains are presented in the Typical Wall Drain Detail, Fig. 12.
LATERAL WALL LOADS
Based on the proposed construction we anticipate that the parking garage will be
constructed with below grade walls that will require lateral earth pressures for design.
Lateral earth pressures depend on the type of backfill and the height and type of wall.
Walls, which are free to rotate sufficiently to mobilize the strength of the backfill, should
be designed to resist the "active" earth pressure condition. Walls that are restrained
should be designed to resist the "at rest" earth pressure condition. The following table
presents the lateral wall pressures that may be assumed for design with on -site soils for
walls less than 15 feet in height.
23
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Earth Pressure Condition
Equivalent Fluid Pressure
( cf)
Active
40
At -rest
60
Passive
300
Notes:
1. Equivalent fluid pressures are for a horizontal backfill condition with no hydrostatic
pressures or live loads.
2. A coefficient of friction of 0.5 may be used at the base of footings to resist lateral wall
loads.
Walls greater than 15 feet in height that are braced may be designed using the lateral earth
pressure diagram presented in the Trapezoidal Lateral Earth Pressure (Braced Walls —
Dewatered), Fig. 13 of this report.
RETAINING WALL
Based on the proposed depth of excavation for the proposed parking garage, we
anticipate that retaining walls will be constructed as part of the development of the site.
Foundations for retaining walls may be designed and constructed as outlined in the
FOUNDATIONS section of this report. Lateral earth loads for retaining wall designs are
presented in the LATERAL WALL LOADS section of this report. In order to reduce the
possibility of developing hydrostatic pressures behind retaining walls, a drain should be
constructed adjacent to the wall. The drain may consist of a manufactured drain system
and gravel. The gravel should have a maximum size of 1.5 inches and have a maximum
of 3 percent passing the No. 200 sieve. Screened aggregate will be satisfactory for the
drainage layer. The manufactured drain should extend from the bottom of the retaining
24
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
wall to within 2 feet of subgrade elevation. The water can be drained by a perforated pipe
with collection of the water at the bottom of the wall leading to a positive gravity outlet.
A typical detail for a retaining wall drain is presented in the Typical Retaining Wall Drain
Detail, Fig. 14.
SURFACE DRAINAGE
Reducing the wetting of structural soils and the potential of developing
hydrostatic pressure behind below grade walls can be achieved by carefully planned and
maintained surface drainage. We recommend the following precautions be observed
during construction and maintained at all times after the proposed construction has been
completed.
1. Wetting or drying of the open excavations should be minimized during
construction.
2. All surface water should be directed away from the top and sides of the
excavations during construction.
3. The ground surface surrounding the exterior of the proposed structures
should be sloped to drain away from the structures in all directions. We
recommend a slope of at least 12 inches in the first 10 feet in landscaped
areas.
4. Hardscape (concrete and asphalt) should be sloped to drain away from the
structures. We recommend a slope of at least 2 percent for all hardscape
within 10 feet of the structures.
5. Backfill, especially around foundation walls, should be placed and
compacted as recommended in the COMPACTED FILL section of this
report.
25
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
6. Roof drains should discharge at least 10 feet away from foundation walls
with drainage directed away from the structures.
7. Surface drainage for this site should be designed by a Professional Civil
Engineer.
COMPACTED FILL
Structural fill for this project may consist of the existing sand fill free of
deleterious material, the natural sand and gravel, or approved imported, non - expansive
structural fill. A representative of our office should evaluate the condition of the existing
fill during to construction to verify its suitability as structural fill. Topsoil and the
existing clay fill are not suitable for use as structural fill and should be removed prior to
construction. The topsoil and existing clay fill may be used in landscape areas. Imported
fill may consist of non - expansive silty or clayey sands or gravels with up to 30 percent
passing the No. 200 sieve with a maximum plasticity index of 10. No cobbles larger than
10 inches should be placed in fill areas. Fill areas should be stripped of all vegetation,
topsoil, and existing fill, and then scarified. Fill should be placed and compacted in thin
loose lifts, moisture conditioned and compacted to the recommended compaction shown
in the following table. The recommended compaction varies for the given use of the fill.
26
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Use of Fill
Recommended Compaction
Percentage of the Standard
Proctor Maximum Dry
Density
(ASTM D -698)
Percentage of the Modified
Proctor Maximum Dry
Density
(ASTM D -1557)
Below Structure Foundations
98
95
Below Slabs -on -Grade
95
90
Utility Trench Backfill
95
90
Pavement Sub grade
95 (AASHTO T -99
90 (AASHTO T -180)
Base Course
98 (AASHTO T -99)
95 (AASHTO T -180)
Backfill (Non - Structural)
90
1 90
Note :
1. For granular soils, the moisture content should be —2 to +2 percent of the optimum
moisture content.
We recommend that a representative of our office observe and test the placement
and compaction of each lift placed for structural fill. Fill placed below foundations,
slabs -on- grade, retaining walls, and pavement sections is considered structural. It has
been our experience that without engineering quality control, inappropriate construction
techniques can occur which result in unsatisfactory foundation, slab -on- grade, retaining
wall, and pavement performance.
PAVEMENT DESIGN
As part of the redevelopment of this site, we anticipate that parking lots will be
constructed adjacent to the athletic fields in the general vicinity of the existing parking
lots. We anticipate that both flexible pavement and rigid pavement may be used for the
construction of the proposed parking lots. It is recommended that rigid pavement be used
27
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
in high traffic areas such as entrances or where heavy vehicles (fire trucks and trash
trucks) turn or maneuver. The following sections present design assumptions,
recommended flexible pavement sections, and recommended rigid pavement sections.
Flexible Pavement Design
The design of the flexible pavement sections was based upon an
Equivalent Daily Load Application (EDLA), laboratory test results, and the
Colorado Department of Transportation Pavement Design Manual. Design
calculations for the parking lots were based on engineering soil characteristics
from soil samples encountered in exploratory borings TH -1 and TH -2 to a depth
of 5.0 feet. The subsurface conditions encountered in exploratory boring TH -1
consisted of 3 inches of asphalt underlain by brown, slightly moist to wet, medium
dense to very dense, silty, sand and gravel with cobbles and scattered boulders to a
depth of 5 feet. The subsurface conditions encountered in boring TH -2 consisted
of 2.5 inches of asphalt underlain by a tan, brown, slightly moist to moist, medium
dense to dense, silty, sand and gravel with organics, scattered cobbles, and lenses
of silty clay to a depth of 5 feet.
Laboratory test results indicated that the soils encountered within
exploratory boring TH -1, to a depth of 5.0 feet, classify as A -1 -a soils, as defined
by the AASHTO classification system. The soils encountered within exploratory
28
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
boring TH -2, to a depth of 5.0 feet, classify as A -1 -b soils. The pavement section
designs presented in this report are based on the subgrade soils classifying as A -1-
b soils. This soil type was assumed to have an Hveem Stabilometer R -value of
50. The R -value was estimated from the AASHTO classification of the soil. An
EDLA was taken as 10 for traffic and parking areas. Flexible pavement sections
for the subject side are shown in the following table.
Full Depth
Asphalt (inches)
Asphalt + Base Course
(inches)
5.0
4.0+6.0
Flexible pavement design values and calculations are presented in the
Pavement Design Calculations, Appendix A.
Rigid Pavement Design
A rigid pavement section was designed using an EDLA value of 10 as
used in the flexible pavement design. The subgrade soils were assumed to have a
modulus of subgrade reaction of 150 psi /in. The rigid pavement design is based
on the working stress of the concrete, which is assumed to be 650 psi. The
Colorado Department of Transportation Pavement Design Manual, along with the
above mentioned design values, was used to determine a rigid pavement section.
The rigid pavement design resulted in a design section of 5.0 inches of concrete.
29
September 10, 2009
Job No. 09 -034
Pavement Materials
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
The design of a pavement system is as much a function of the paving
materials as the support characteristics of the subgrade. The quality of the
construction materials is reflected by the structural coefficients used in the design
calculations. If the pavement system is constructed of inferior materials, the life
and serviceability will be substantially reduced.
The asphalt component of the pavement is designed assuming at least
1,800 pounds Marshall stability (strength coefficient of 0.44). Normally, an
asphalt aggregate should be relatively impermeable to moisture and should be
designed as a well - graded mix. The oil content and voids ratio also need to be
determined to verify compliance with the mix design. We recommend a job mix
design be performed and periodic checks be made to verify compliance with the
specifications for this project.
All asphalt should be compacted to between 92 and 96 percent of the
maximum theoretical density. During asphalt placement, joints between asphalt
rows should be feathered such that the surface water is shed from the asphalt
surface. For a more thorough description of our pavement construction
recommendations, please refer to Appendix B.
30
September 10, 2009
Job No. 09 -034
Subgrade Stabilization
KOECHLEIN CONSUL TING ENGINEERS, INC.
Geotechnical and Materials Engineers
Based on our subsurface exploration, it is possible that existing fill could
be encountered during the construction of the proposed parking lots. Pavements
constructed on existing fill may experience a shortened life expectancy.
Movement of the pavement may result in cracking, high and low spots, and other
distress. Repair of high and low spots and cracking in the pavements should be
expected if pavements are constructed on the existing fill. If the owner is willing
to accept the risk of premature deterioration of the pavements, then the flexible
pavements may be constructed on the existing fill.
If the owner would like to reduce the risk of early pavement deterioration
due to the existing fill, we recommend that 3.0 feet of the existing fill be removed
and replaced with a non - expansive structural fill. Construction of pavements on
properly moisture conditioned and compacted non - expansive fill should
experience a typical life expectancy, provided proper maintenance is provided. If
fill is required to obtain the final pavement subgrade elevation, the fill should
consist of non - expansive material and be moisture treated and compacted as
recommended in the COMPACTED FILL section of this report.
31
September 10, 2009
Job No. 09 -034
Construction Considerations
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
Major utilities, such as water and sewer, are usually placed beneath
pavements during construction. If utilities are installed, the trench backfill should
be observed, tested, and approved prior to paving. Careful attention should be
paid to compaction of curb lines and around manholes.
Excavation of completed pavements for utility construction and repair can
destroy the integrity of the pavement and result in a severe decrease in
serviceability. To restore the pavement to its original serviceability, careful
control of backfill compaction and repaving is necessary. If utilities are to be
installed beneath the proposed access drive or parking lot, the utilities should be
installed, tested, and approved prior to paving.
We do not anticipate that construction of the proposed parking lots will
take place during cold weather. However, if plans change, caution should be
employed when constructing during freezing times of the year. Construction on
frozen subgrade soils may result in damage to the pavement. When the subgrade
thaws, premature pavement failure may occur. Pavement or fill should be placed
on unfrozen or frost -free subgrade soils. Frozen subgrade soils should be allowed
to thaw or be removed and replaced to prevent future problems caused by the
frozen subgrade. For a more thorough description of our pavement construction
recommendations, please refer to Appendix B.
32
September 10, 2009 KOECHLEIN CONSULTING ENGINEERS, INC.
Job No. 09 -034 Geotechnical and Materials Engineers
Drainage
The primary cause of saturated subgrade soils and early pavement
deterioration is water infiltration into the pavement system. The addition of
moisture usually results in softening of the subgrade, potential frost heave, and the
eventual failure of the pavement section. In order to reduce the risk of water
infiltration below the pavement section and potential frost heave, we recommend
that a surface drainage system be designed, constructed, and maintained in order
to provide rapid removal of surface runoff. The design cross -slope should be
maintained. If curb and gutter is installed, seals should be provided between curb
and pavement and all joints to reduce moisture infiltration.
LIMITATIONS
Although the exploratory borings were located to obtain a reasonably accurate
determination of foundation and subgrade conditions, variations in the subsurface
conditions are always possible. Any variations that exist beneath the site generally
become evident during excavations for the proposed structures. Therefore, we should be
contacted by the contractor and/or owner so that a representative of our office can observe
the completed excavation to confirm that the soils are as indicated by the exploratory
33
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
borings and to verify our foundation and slab -on -grade design and construction
recommendations.
The placement and compaction of fill, as well as installation of foundations,
should also be observed and tested. The design criteria and subsurface data presented in
this report are valid for 3 years provided that a representative from our office observes the
site at that time and confirms that the site conditions are similar to the conditions
presented in the SITE CONDTIONS section of this report and that the recommendations
presented in this report are still applicable. We recommend that fmal plans and
specifications for proposed construction be submitted to our office for study, prior to
beginning construction, to determine compliance with the recommendations presented
Routine maintenance, such as sealing and repair of cracks annually and overlays at
5 to 10 year intervals, is generally necessary to achieve long -term life of a pavement
system. In addition, positive drainage must be maintained at all times in order to reduce
the risk of pavement failure.
34
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
We appreciate the opportunity to provide this service. If we can be of further
service in discussing the contents of this report or in the analyses of the proposed
structures from a geotechnical viewpoint, please contact our office.
KOECHLEIN CONSULTING ENGINEERS, INC.
Jessica E. Street, E.I.
Staff Engineer
Reviewed by:
Scott B. Myers, P.E.
Senior Engineer
(4 copies sent)
35
�i
L
r
(Generated by MapQuest on 8/26/09)
NOT TO SCALE
R;vt__
NORTH AREA
VICINITY MAP
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
al
SOUTH AREA
JOB NO. 09 -034 FIG. 1
t in= 100ft
JOB NO. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
v
L /
\ ATHLETIC FIELD
Q)
EXISTING
RESTROOM
BUILDING
LOCATION OF EXPLORATORY BORING IN SOUTH AREA
FIG. 2
= m
•c
K,
W
W W
Z=u
U2
Z m
W p
02
Z y
f C
J N
7
H q
Z C
OL
U V
= O
W m
2U
U
W
O
Y
Q
w
Q
O
z
z
V
z
EE
Q
m
}
O
Q
O
J
CL
x
w
U-
0
cn
z
O
a
U
O
J
25
30
35
W1
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
TH -3
APP.EL. 8235
0
9/12
WC =28
D D =92
o LL =46
Q :-
�. P1 =17 5
23/12
d:
R�
�:
ti 50/6
bQ•:
-200=14 10
50/5
LOGS OF EXPLORATORY BORINGS
15
v
m
T
20
m
m
25
30
35
Ell
JOB NO. 09-034 FIG. 4
TH -1
N Q-
TH -2
APP.
EL.
8229 APP.
EL. 8246
0
CL =14.0
�'
SS =O
Q
WC =4
PH =7.0
w
a
- 200 =12
RES =4300
W
C3:
OD'd
LL =NL
O
.
LX
P1 =NP
20
d
50/9
2�' o:
50/7
o:
WC =3
o
o�
50/11
DD =118
44/18
5
y �3
bra
- 200 =22
2019
LL =NL
a
P1 =NP
� c3:
b
50/11
17/18
10
! Q�:
25
30
35
W1
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
TH -3
APP.EL. 8235
0
9/12
WC =28
D D =92
o LL =46
Q :-
�. P1 =17 5
23/12
d:
R�
�:
ti 50/6
bQ•:
-200=14 10
50/5
LOGS OF EXPLORATORY BORINGS
15
v
m
T
20
m
m
25
30
35
Ell
JOB NO. 09-034 FIG. 4
N Q-
34/12
15 rd
o
WC =5
�p
CL =14.0
�'
SS =O
PH =7.0
w
a
o
RES =4300
W
C3:
OD'd
O
.
20
d
50/9
(L
o:
WC =3
o
DD =118
- 200 =22
25
30
35
W1
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
TH -3
APP.EL. 8235
0
9/12
WC =28
D D =92
o LL =46
Q :-
�. P1 =17 5
23/12
d:
R�
�:
ti 50/6
bQ•:
-200=14 10
50/5
LOGS OF EXPLORATORY BORINGS
15
v
m
T
20
m
m
25
30
35
Ell
JOB NO. 09-034 FIG. 4
TH -4
APP.EL. 8216
0
15
w
w
u_
= 20
a
w
0
25
30
KOECHLEIN CONSULTING ENGINEERS, INC.
20/12
5
Qd
s
WC =7
APP. EL. 8218
DD =104
►_' o, :
- 200 =21
A �3:
q �}.
50/9
9da
0o
r io
Q�
SS =O
►0
18/12
10
15
w
w
u_
= 20
a
w
0
25
30
KOECHLEIN CONSULTING ENGINEERS, INC.
50/7
Geotechnical and Materials Engineers
Qd
s
WC =5
APP. EL. 8218
DD =103
►_' o, :
- 200 =11
35
40
50/3
10
15
v
m
20 =
m
m
50/6
WC =6 25
DD =103
- 200 =13
30
35
40
LOGS OF EXPLORATORY BORINGS
JOB NO. 09-034 FIG. 5
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
TH -5
APP. EL. 8218
0
WC =4
q �}.
50/9
0o
CL =4.8 5
Q�
SS =O
e
PH =7.1
�3
RES =5800
50/3
10
15
v
m
20 =
m
m
50/6
WC =6 25
DD =103
- 200 =13
30
35
40
LOGS OF EXPLORATORY BORINGS
JOB NO. 09-034 FIG. 5
LEGEND:
■ ASPHALT
SAND and GRAVEL, Silty, Cobbles, Scattered
boulders, Slightly moist to wet, Medium dense to very
dense, Brown.
FILL, Sand, Gravelly, Silty, Scattered cobbles,
Lenses of silty clay, Organics, Slightly moist to moist,
Medium dense to dense, Tan, Brown.
® TOPSOIL
FILL, Clay, Sandy, Some gravel, Slightly moist,
Medium stiff, Dark brown.
FMSILT, Sandy, Scattered gravels and cobbles, Dry to
slightly moist, Medium dense to dense, Brown.
WATER. Indicates depth of water encountered while
drilling.
BULK SAMPLE. Obtained from percussion down -
hole hammer cuttings.
a CALIFORNIA DRIVE SAMPLE. The symbol 50/7
indicates that 50 blows of a 140 pound hammer
falling 30 inches were required to drive a 2.5 inch
O.D. sampler 7 inches.
Notes:
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
' SPLIT SPOON DRIVE SAMPLE. The symbol
50/11 indicates that 50 blows of a 140 pound
hammer falling 30 inches were required to drive a 2.0
inch O.D. sampler 11 inches.
1. The exploratory borings were drilled on August 18, 19, and 20, 2009. Exploratory boring TH -3 was drilled using a 4 -inch
diameter continuous flight power auger mounted on a tracked drill rig. Exploratory borings TH -1, TH -2, TH -4, and TH -5 were
drilled using a percussion down -hole hammer technique.
2. Ground water was encountered at the time of drilling in exploratory boring TH -3 at a depth of 9.0 feet. Ground water was not
encountered in exploratory boring TH -1 to the maximum depth of 20.0 feet, and in borings TH -2, TH -4, and TH -5 to the
maximum depth explored of 40.0 feet.
3. The Logs of Exploratory Borings are subject to the explanations, limitations, and conclusions as contained in this report.
4. Laboratory Test Results:
WC -
Indicates natural moisture ( %)
DD -
Indicates dry density (pcf)
-200-
Indicates percent passing the No. 200 sieve ( %)
LL -
Indicates liquid limit ( %)
PI -
Indicates plasticity index ( %)
CL-
Indicates water soluble chloride concentration (ppm)
Ss-
Indicates soluble sulfate concentration (ppm)
pH -
Indicates pH
RES -
Indicates resistivity (OHM -cm)
5. Approximate elevations for exploratory borings are based on interpreting the elevations after locating the exploratory borings
on the topographic maps provided by the Town of Vail.
LEGEND OF EXPLORATORY BORINGS
JOB NO. 09 -048 FIG. 6
KOECHLEIN CONSULTING ENGINEERS
100 0
90
90
10
80
10
80
20
70
20
0
70
O
30
z
30
z
m
co
m
�
so
40
40 m
<a
40 m
z
F so
1— so
50 M
z
w
so �
z
M
40
m
D
(f
D
40
0
w
a
80
W
a
60
z
m
z
m
30
v
30
70
70
20
20
80
80
10
10
90
0
90
0
1100
200 100 10 1 0.1 0.01 0.001
DIAMETER OF PARTICLE IN MM
100
COBBLES
200 100 10 1 0.1 0.01 0.001
SAND
SILT
DIAMETER OF PARTICLE IN MM
COBBLES
GRAVEL
SAND
SILT
CLAY
Sample of SAND, Gravelly, Some silt GRAVEL 39 % SAND 49 %
Source TH -1 Sample No. Elev. /Depth 0.3 -5.0 feet SILT & CLAY 12 % LIQUID LIMIT NL %
PLASTICITY INDEX NP %
a'
100 0
90
10
80
20
70
O
30
z
m
�
so
40 m
1— so
so �
z
m
D
40
0
w
a
60
z
m
30
70
20
80
10
90
0
1100
200 100 10 1 0.1 0.01 0.001
DIAMETER OF PARTICLE IN MM
COBBLES
GRAVEL
SAND
SILT
CLAY
Sample of FILL, Sand, Gravelly, Silty GRAVEL 27 % SAND 54 %
Source TH -2 Sample No. Elev. /Depth 4.0 feet SILT & CLAY 19 % LIQUID LIMIT NL %
PLASTICITY INDEX NP %
GRADATION TEST RESULTS
Job No. 09 -034 FIG. 7
KOECHLEIN CONSULTING ENGINEERS
100 0
10
90
80
20
30
70
(7
z
30
70
Z
60
m
�
40
i 60
u
a
�
40
N
a
a
M
�
50
1.- 50
w
m
z
-i
50
50
Wm
;0
60 D
E 40
w
a
,
60 D
40
�
w
0
z
m
p
70
30
z
m
70 p
30
80
20
80
20
10
90
10
-
1
90
p
0
77-
100
100
200 100 10 1 0.1 0.01 0.001
DIAMETER OF PARTICLE IN MM
COBBLES
GRAVEL
COBBLES
GRAVEL
SAND
SILT
CLAY
Sample of SAND, Gravelly, Silty GRAVEL 14 % SAND 64 %
Source TH -2 Sample No. Elev. /Depth 20.0 feet SILT & CLAY 22 % LIQUID LIMIT %
PLASTICITY INDEX %
#143 #200
100 0
10
90
80
20
30
70
(7
z
m
�
40
i 60
u
a
M
�
50
1.- 50
w
;0
60 D
E 40
w
a
z
m
p
70
30
80
20
10
-
1
90
p
77-
100
__
200 100 10 1 0.1 0.01 0.001
DIAMETER OF PARTICLE IN MM
COBBLES
GRAVEL
SAND
SILT
CLAY
Sample of SAND, Gravelly, Silty GRAVEL 20
Source TH -3 Sample No. Elev. /Depth 9.0 feet SILT & CLAY 14
PLASTICITY INDEX
GRADATION TEST RESULTS
• SAND 66 %
• LIQUID LIMIT %
Job No. 09 -034 FIG. 8
KOECHLEIN CONSULTING ENGINEERS
100 0
90
10
10
80
80
20
20
70
C7
70
30
z
CO
30
z
m
;U
so
a
m
6o
�
40 n
Z
ao m
<a
--I
50
50
Z
w
z
50
M
m
40
50
z
LU
D
m
60
W
a
*C
D
40
�
W
a
Z
m
60
Z
M
v
30
70
30
20
70
80
20
10
80
90
0
10
H
Li
100
200 100 10 1 0.1 0.01 0.001
DIAMETER OF PARTICLE IN MM
COBBLES
GRAVEL
SAND
SILT
CLAY
Sample of FILL, Sand and gravel, Silty GRAVEL 39 % SAND 40 %
Source TH -4 Sample No. Elev. /Depth 4.0 feet SILT & CLAY 21 % LIQUID LIMIT %
PLASTICITY INDEX %
100 0
90
10
80
20
70
30
z
m
6o
�
ao m
<a
z
50
50
z
LU
m
D
40
�
W
a
60
Z
M
30
70
20
80
10
H
Li
90
0
too
200 100 10 1 0.1 0.01 0.001
DIAMETER OF PARTICLE IN MM
COBBLES
GRAVEL
SAND
SILT
CLAY
Sample of SAND, Gravelly, Some silt GRAVEL 36
Source TH -4 Sample No. Elev. /Depth 30.0 feet SILT & CLAY 11
PLASTICITY INDEX
GRADATION TEST RESULTS
• SAND 53 %
• LIQUID LIMIT %
Job No. 09 -034 FIG. 9
KOECHLEIN CONSULTING ENGINEERS
100 0
10
90
80
20
30
70
(7
z
60
m
;0
40 M
z
50
1.- 50
w
D
of 40
w
a
60 z
m
70 p
30
80
20
10
90
p
100
200 100 10 1 0.1 0.01 0.001
DIAMETER OF PARTICLE IN MM
COBBLES
GRAVEL
SAND
SILT
CLAY
Sample of SAND, Gravelly, Some silt GRAVEL 41 % SAND 46 %
Source TH -5 Sample No. Elev. /Depth 24.0 feet SILT & CLAY 13 % LIQUID LIMIT %
PLASTICITY INDEX %
Sample of
Source
Sample No. Elev. /Depth
GRAVEL % SAND %
SILT & CLAY % LIQUID LIMIT %
PLASTICITY INDEX %
GRADATION TEST RESULTS
Job No. 09 -034 FIG. 10
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
CONCRETE FOOTING
'�
is
1 1
EXISTING 1 EXISTING
FILL COMPACTED FILL \ FILL
(SEE REPORT FOR
COMPACTION RECOMMENDATIONS)
-
=1 I I -1 I I -1 I I-1 I I -1 11= -
-1 I 1 =1 I I =11 I- FIRM NATURAL SOIL
EDGE OF EXCAVATION
(EXCAVATE AS PER
OSHA REGULATIONS)
FOUNDATION EXCAVATION RECOMMENDATIONS
JOB NO. 09 -034 FIG. 11
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
CLAYEY BACKFILL 10 -
COMPACTED BACKFILL 11 Y BELOW GRADE WALL
EDGE OF EXCAVATION
(EXCAVATE AS PER
OSHA REGULATIONS)
MANUFACTURED
WALL DRAIN
FILTER FABRIC
GRAVEL
12"
PERFORATED PIPE
NOTES:
WATERPROOFING
OR DAMPPROOFING
`PLASTIC SHEETING
12" MIN.
1. DRAIN SHOULD BE AT LEAST 12 INCHES BELOW TOP OF FOOTING AT THE
HIGHEST POINT AND SLOPE DOWNWARD TO A POSITIVE GRAVITY OUTLET OR
TO A SUMP WHERE WATER CAN BE REMOVED BY PUMPING.
2. EXCAVATIONS ADJACENT TO FOOTINGS SHOULD BE CUT AT A 1 TO 1
(HORIZONTAL TO VERTICAL) OR FLATTER SLOPE FROM THE BOTTOM OF THE
FOOTINGS. EXCAVATIONS ADJACENT TO FOOTINGS SHOULD NOT BE CUT
VERTICALLY.
3. THE DRAIN SHOULD BE LAID ON A SLOPE RANGING BETWEEN 1/8 INCH AND
1/4 INCH DROP PER FOOT OF DRAIN.
4. GRAVEL SPECIFICATIONS: WASHED 1.5 INCH TO NO. 4 GRAVEL WITH LESS
THAN 3% PASSING THE NO. 200 SIEVE.
5. THE BELOW GRADE CONCRETE FOUNDATION WALLS SHOULD BE
PROTECTED FROM MOISTURE INFILTRATION BY APPLYING A SPRAYED ON
MASTIC WATERPROOFING, DAMPPROOFING, OR AN EQUIVALENT PROTECTION
METHOD.
TYPICAL WALL DRAIN DETAIL
JOB NO. 09 -034 FIG. 12
FLOOR
NOTES:
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
EARTH
PRESSURE
--- 45H
0.2 H
0. iH
f 0.2 H
I
1. THIS PRESSURE DIAGRAM IS APPLICABLE FOR BRACED WALLS THAT ARE
GREATER THAN 15 FEET IN HEIGHT WITH NO HYDROSTATIC PRESSURE.
2. THE PRESENCE OF A FLOOR SYSTEM IN BELOW GRADE LEVELS CREATES
A BRACED EXCAVATION CONDITION.
3. THE BELOW GRADE WALLS SHOULD BE PROTECTED FROM MOISTURE
INFILTRATION BY APPLYING A SPRAYED ON MASTIC WATERPROOFING OR
AN EQUIVALENT PROTECTION METHOD.
4. THE LATERAL EARTH PRESSURE DIAGRAM ASSUMES THAT THE WALLS
ARE PROPERLY DRAINED AND NO HYDROSTATIC PRESSURE CAN DEVELOP
AGAINST THE WALLS.
TRAPEZOIDAL LATERAL EARTH PRESSURE
(BRACED WALLS - DEWATERED)
JOB NO. OM34 FIG. 13
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
CLAYEY 7:7111=11 10
MANUFACTURED
— ■ WALL DRAIN
EDGE OF EXCAVATION
(EXCAVATE AS PER
OSHA REGULATIONS)
FILTER
COMPACTED BACKFILL 11 1,,— RETAINING WALL
L
PERFORATED PIPE
i 101 "MIS
WATERPROOFING/
DAMPPROOFING
1. DRAIN SHOULD BE SLOPED DOWNWARD TO A POSITIVE GRAVITY OUTLET
OR TO A SUMP WHERE WATER CAN BE REMOVED BY PUMPING.
2. THE DRAIN SHOULD BE LAID ON A SLOPE RANGING BETWEEN 1/8 INCH AND
1/4 INCH DROP PER FOOT OF DRAIN.
3. GRAVEL SPECIFICATIONS: WASHED 1.5 INCH TO NO. 4 GRAVEL WITH LESS
THAN 3% PASSING THE NO. 200 SIEVE.
4. THE BELOW GRADE CONCRETE RETAINING WALLS SHOULD BE
PROTECTED FROM MOISTURE INFILTRATION BY APPLYING A SPRAYED ON
MASTIC WATERPROOFING /DAMPPROOFING OR AN EQUIVALENT PROTECTION
METHOD.
TYPICAL RETAINING WALL DRAIN DETAIL
JOB NO. 09 -034 FIG. 14
H
a
E-�
W
H
W
W
W
Q
a
w
O
C6
of
w
w
z
z
w
IIIIIIIIIIIIIII
�II�I
111�9i
■II�111111�
II
■IIIIIIIIIIIIIIII
C6
of
w
w
z
z
w
September 10, 2009
Job No. 09 -034
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
APPENDIX A
PAVEMENT DESIGN CALCULATIONS
FLEXIBLE PAVEMENT DESIGN DATA
DESIGN DATA
Traffic Load - EDLA
= 10
Traffic Load - 18 kip ESAL's
= 7,300
Design Life
= 20
Subgrade Soil Classification
= A -1 -b
Assumed "R" Value
= 50
Soil Support Value - S,
= 7.0
Resilient Modulus - MR (psi)
= 13,168
Reliability - R ( %)
= 90
Serviceability Index - SI
= 2.5
Serviceability Loss - PSI
= 2.0
Overall Deviation - So
= 0.44
DESIGN CALCULATION RESULTS
Based on the following equation:
log,o(18k ESAL) = ZRxS,,+9.36xlogio(SN +1) -0.20
+log,o( PSI /(4.2- 1.5))/(0.4 +( 1094 /(SN +1)5'19)) +2.32xlog,AMR) - 8.07
Structural Number - SN = 1.8
PAVEMENT THICKNESS DESIGN EQUATION
SN = C,D, +C2D2m2
where
C, = Strength Coefficient - Asphalt = 0.44
1112 = Drainage Coefficient = 1.0
D, = Depth of Asphalt (inches)
D2 = Depth of Roadbase (inches)
PAVEMENT THICKNESS RESULTS
Full Depth Asphalt
D, = 5.0 inches
Asphalt + Aggregate Base Course
D, (Asphalt) = 4.0 inches
D2 (Aggregate Base Course) = 6.0 inches
JOB NO. 09 -034 FIG. A -1
RIGID PAVEMENT DESIGN DATA
DESIGN DATA
Traffic Load - EDLA
= 10
Traffic Load - 18 kip ESAL's
= 7,300
Design Life
= 20
Subgrade Soil Classification
= A -1 -b
Assumed Modulus of Subgrade Reaction - k (psi /in)
= 150
Modulus of Rupture - S'c (psi)
= 650
Modulus of Elasticity - Ec (psi)
= 3,400,000
Drainage Coefficient - Cd
= 1.0
Load Transfer Coefficient - J
= 4.2
Reliability - R ( %)
= 90
Serviceability Index - SI
= 2.0
Overall Deviation - So
= 0.34
DESIGN CALCULATION RESULTS
Based on the following equation:
loglo(18k ESAL) = ZRxS,,+7.35xloglo(D +1) -0.60 +logio(PSI/(4.5-
1.5))/(1.0 +(1.624x 107) /(D +l )8'46)) +(4.22- 0.32xp,)x(log,o[(Sc' xCDx(Do.7s_
1.132))/((2l 5.63xJx(D0.75- (18.42 /(E,/k)0z5))))]
PAVEMENT THICKNESS RESULTS
Rigid Pavement Thickness
D = 5.0 inches
JOB NO. 09 -034 FIG. A -2
September 10, 2009
Job No. 09 -034
APPENDIX B
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
PAVEMENT CONSTRUCTION RECOMMENDATIONS
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
FLEXIBLE PAVEMENT CONSTRUCTION RECOMMENDATIONS
Experience has shown that construction methods can have a significant influence on the life and
serviceability of a pavement system. We recommend the proposed pavement be constructed in the
following manner:
Where the subgrade soils do not satisfy the compaction requirements, they should be
scarified, moisture treated, and recompacted. Soils should be compacted as specified in the
COMPACTED FILL section of this report.
2. Utility trenches and all subsequently placed fill should be properly compacted and tested
prior to paving. Fill should be compacted as specified in the COMPACTED FILL section
of this report.
3. After final subgrade elevation has been reached and the subgrade compacted, the area
should be proof - rolled with a heavy pneumatic tired vehicle (i.e., a loaded 10 -wheel dump
truck). Subgrade that is pumping or deforming excessively should be removed and
replaced.
4. If areas of soft or wet subgrade are encountered, the material should be overexcavated and
replaced. Suitable structural fill may be used. Where extensively soft, yielding subgrade is
encountered, we recommend the excavation be inspected by a representative of our office.
5. Aggregate base course should be laid in loose lifts not exceeding 6.0 inches, moisture
treated to within 2.0 percent of the optimum moisture content, and compacted as specified
in the COMPACTED FILL section of this report.
6. The aggregate base course may consist of processed recycled asphalt. The recycled asphalt
base course should meet the gradation requirements of CDOT Class 5 or Class 6 base
course. The recycled asphalt base should be laid in loose lifts not exceeding 6.0 inches,
moisture treated and compacted as specified in the COMPACTED FILL section of this
report.
7. Asphaltic concrete should be plant -mixed material. Superpave material should be
compacted to between 92 and 96 percent of the maximum theoretical density and other
asphalt material to at least 95 percent of the maximum Marshall value.
The subgrade preparation and the placement and compaction of all pavement layers should
be observed and tested. Compaction criteria should be met prior to the placement of the
next paving lift.
JOB NO. 09 -034 FIG. B -1
KOECHLEIN CONSULTING ENGINEERS, INC.
Geotechnical and Materials Engineers
RIGID PAVEMENT CONSTRUCTION RECOMMENDATIONS
Rigid pavement sections are not as sensitive to subgrade support characteristics as flexible
pavement. Due to the strength of the concrete, wheel loads from traffic are distributed over a large area
and the resulting subgrade stresses are relatively low. The critical factors influencing the performance of a
rigid pavement are the strength and quality of the concrete, and the uniformity of the subgrade. We
recommend subgrade preparation and construction of the rigid pavement section be completed in
accordance with the following recommendations.
1. Where the subgrade soils do not satisfy the compaction requirements, they should be
scarified, moisture treated, and compacted. Soils should be compacted as specified in the
COMPACTED FILL section of this report.
2. Utility trenches and all subsequently placed fill should be properly compacted and tested
prior to paving. Fill should be compacted as specified in the COMPACTED FILL section
of this report.
3. The resulting subgrade should be checked for uniformity and all soft or yielding materials
should be replaced prior to paving. This should be done by proof - rolling with a heavy
pneumatic tired vehicle (i.e., a loaded 10 -wheel dump truck). Concrete should not be
placed on soft, spongy, frozen, or otherwise unsuitable subgrade.
4. Subgrade should be kept moist prior to paving.
5. Curing procedures should protect the concrete against moisture loss, rapid temperature
change, freezing, and mechanical injury for at least 3 days after placement. Traffic should
not be allowed on the pavement for at least one week.
6. A white, liquid membrane curing compound, applied at the rate recommended by the
manufacturer, should be used.
7. Construction joints, including longitudinal joints and transverse joints, should be formed
during construction or should be sawed shortly after the concrete has begun to set, but prior
to uncontrolled cracking. All joints should be sealed.
8. Construction control and inspection should be carried out during the subgrade preparation
and paving procedures. Concrete should be carefully monitored for quality control.
JOB NO. 09-034 FIG. B -2