HomeMy WebLinkAboutB12-0318 / B12-0319 OPEN HOLE REPORT039`
u Hepworth - Pawlak Geotechnical, Inc.
1—1
fn 5020 County Road 154
G4!��h 0tech Glenwood Springs, Colorado 81601
Phone: 970- 945 -7988
HEPWORTH - PAWLAK GEOTECHNICAL Fax: 970. 945 -8454
email: hpgeo@hpgeotech.com
September 27, 2012
Sunder, Inc.
Attn: John Sunderland
P. O. Box 1393
Edwards, Colorado 81632
jpsunderga vail.net
OCT 0 4 2012
1.yoP.M. V
TOWN OF VAIL
Job No. 112 252A
Subject: Subsoil Study for Foundation Design, Proposed Zuckerman Duplex,
Lot 3, Bighorn Subdivision Second Addition, 3807 Lupine Drive, Vail,
Colorado
Dear J P:
As requested, Hepworth - Pawlak Geotechnical, Inc. performed a subsoil study for design
of foundations at the subject site. The study was conducted in general accordance with
our agreement for geotechnical engineering services to Sunder, Inc. dated July 24, 2012.
The data obtained and our recommendations based on the proposed construction and
subsurface conditions encountered are presented in this report. We recently observed the
foundation excavation for a portion of the residence and submitted our findings, as well
as interim findings of our subsoil study, in a report dated September 17, 2012 under the
above job number. The rockfall assessment for the lot was presented in our report dated
May 30, 2012, Job No 112 134A.
Proposed Construction: The duplex will be a two story structure over a walkout
basement level with attached garages on the south side at the main level. Ground floors
will be slab -on- grade. Cut depths are expected to range between about 4 to 8 feet.
Foundation loadings for this type of construction are assumed to be relatively light and
typical of the proposed type of construction. Spread footings have been assumed for
foundation support of the building using an allowable soil bearing pressure of 2,000 psf.
If building conditions or foundation loadings are significantly different from those
described above,-we should be notified to re- evaluate the recommendations presented in
this report.
Site Conditions: The site was occupied by an existing older residence that was to be
removed for the new construction. The terrain is strongly sloping down to the north
towards Gore Creek which borders the north side of the lot. Vegetation consists of
landscape grasses and bushes with mature spruce trees.
Subsurface Conditions: The subsurface conditions at the site were evaluated by
excavating two exploratory pits at the locations shown on Figure 1. The logs of the pits
Parker 303 - 841 -7119 • Colorado Springs 719 - 633 -5562 • Silverthorne 970- 468 -1989
Sunder, Inc.
September 27, 2012
Page 2
are presented on Figure 2. The subsoils encountered in Pit 1, below about 4 feet of fill,
consisted of about 1 %2 feet of stiff, very sandy silty clay underlain by relatively dense,
slightly silty sandy gravel and cobbles with probable boulders. The subsoils encountered
in Pit 2, below about 1 foot of organic topsoil, consisted of about 5'/2 feet of medium
dense, clayey silty sand underlain by relatively dense, slightly silty sandy gravel and
cobbles with probable boulders. Results of swell - consolidation testing performed on
relatively undisturbed samples of the clay and sand soils, presented on Figure 3, indicate
moderate compressibility. Results of a gradation analysis performed on a sample of the
natural coarse granular soils (minus 3 inch fraction) obtained from Pit 1 are presented on
Figure 3. The laboratory testing is summarized in Table 1.
Free water was encountered n Pit 1 at a depth of about 7 feet and no free water was
encountered in Pit 2 at the time of excavation. The soils were moist to very moist
becoming wet with depth in Pit 1.
Foundation Recommendations: Considering the subsoil conditions encountered in the
exploratory pits and the nature of the proposed construction, we recommend spread
footings placed entirely on the undisturbed natural coarse granular soils designed for an
allowable bearing pressure of 2,000 psf for support of the proposed duplex. This may
require subexcavation of unsuitable soils down to below design bearing elevation.
Footings should be a minimum width of 16 inches for continuous walls and 2 feet for
columns. The existing fill, topsoil, fine grained clay and sand soils, and any loose
disturbed materials encountered at the foundation bearing level within the excavation
should be removed and the footing bearing level extended down to the undisturbed
natural coarse granular soils. Exterior footings should be provided with adequate soil
cover above their bearing elevations for frost protection. Placement of footings at least
48 inches below the exterior grade is typically used in this area. Continuous foundation
walls should be reinforced top and bottom to span local anomalies such as by assuming
an unsupported length of at least 10 feet. Foundation walls acting as retaining structures
should also be designed to resist a lateral earth pressure based on an equivalent fluid unit
weight of at least 50 pcf for the on -site soils as backfill. The backfill should not contain
vegetation, topsoil or oversized rocks.
Floor Slabs: The natural on -site soils, exclusive of topsoil, are suitable to support lightly
loaded slab -on -grade construction. There could be some settlement of slabs underlain by
the fine grained soils. The fine grained soils could be removed and replaced with
compacted structural fill to reduce the settlement risk. To reduce the effects of some
differential movement, floor slabs should be separated from all bearing walls and
columns with expansion joints which allow unrestrained vertical movement. Floor slab
control joints should be used to reduce damage due to shrinkage cracking. The
requirements for joint spacing and slab reinforcement should be established by the
designer based on experience and the intended slab use. A minimum 4 inch layer of free -
draining gravel should be placed beneath basement level slabs to facilitate drainage. This
Job No. 112 252A
G95t~ ech
Sunder, Inc.
September 27, 2012
Page 3
material should consist of minus 2 inch aggregate with less than 50% passing the No. 4
sieve and less than 2% passing the No. 200 sieve.
All fill materials for support of floor slabs should be compacted to at least 95% of
maximum standard Proctor density at a moisture content near optimum. Required fill can
consist of the on -site granular soils devoid of topsoil and oversized rocks.
Underdrain System: Free water was encountered in one of our exploratory pits and it
has been our experience in that the area that groundwater level can rise seasonally or local
perched groundwater can develop during times of heavy precipitation or seasonal runoff.
Frozen ground during spring runoff can also create a perched condition. We recommend
below -grade construction, such as retaining walls, crawlspace and basement areas, be
protected from wetting and hydrostatic pressure buildup by an underdrain system.
The drains should consist of drainpipe placed in the bottom of the wall backfill
surrounded above the invert level with free - draining granular material. The drain should
be placed at each level of excavation and at least 1 foot below lowest adjacent finish
grade and sloped at a minimum 1 % to a suitable gravity outlet. Free - draining granular
material used in the underdrain system should contain less than 2% passing the No. 200
sieve, less than 50% passing the No. 4 sieve and have a maximum size of 2 inches. The
drain gravel backfill should be at least 11/2 feet deep and extend to above any seepage
level in the excavation cut level. The drain gravel should be separated from the on -site
soils with filter fabric such as Mirafi 140N.
Surface Drainage: The following drainage precautions should be observed during
construction and maintained at all times after the duplex has been completed:
1) Inundation of the foundation excavations and underslab areas should be
avoided during construction
2) Exterior backfill should be adjusted to near optimum moisture and
compacted to at least 95% of the maximum standard Proctor density in
pavement and slab areas and to at least 90% of the maximum standard
Proctor density in landscape areas. Free - draining wall backfill should be
capped with about 2 feet of the on -site, finer graded soils to reduce surface
water infiltration.
3) The ground surface surrounding the exterior of the building should be
sloped to drain away from the foundation in all directions. We
recommend a minimum slope of 6 inches in the first 10 feet in unpaved
areas and a minimum slope of 3 inches in the first 10 feet in pavement and
walkway areas.
4) Roof downspouts and drains should discharge well beyond the limits of all
backfill.
Excavation Observations: On September 14, we observed the foundation excavation for
the northwestern portion of the proposed building to evaluate the exposed soil bearing
Job No. 112 252A
G9&eCh
Sunder, Inc.
September 27, 2012
Page 4
conditions. As discussed in our September 17, 2012 letter, free water was encountered in
the excavation and dewatering and subexcavation and replacement of the coarse granular
soils with imported crushed rock was needed to achieve adequate bearing conditions.
We subsequently observed the remainder of the foundation excavation on September 17,
19 and 24, 2012. On September 17, we observed the northeast and eastern portion of the
excavation and found from about 1' /2 to 3 feet in depth of unsuitable soils below design
bearing elevation that were recommended to be removed to achieve adequate bearing. On
September 19, we observed the southeastern and southern portion of the excavation with
natural coarse granular soils encountered generally at design bearing elevation. At the
time of our September 24b site visit, the foundation excavation was essentially complete
and had been cut in multiple levels from about 3 to 8 feet below the adjacent ground
surface. The soils exposed in the bottom of the excavation consisted of relatively dense,
slightly silty sandy gravel and cobbles. No free water was encountered in these portions
of the excavation and the soils were moist to very moist.
The coarse granular soil conditions exposed in the excavation are consistent with those
previously encountered on the site and suitable for support of spread footings designed
for the recommended allowable bearing pressure of 2,000 psf. Loose and disturbed soils
should be removed in the footing areas to expose the undisturbed natural coarse granular
soils. The water seepage into the excavation should continue to be collected and diverted
away from the footing areas and any softened soils and mud removed before concrete
placement. Other recommendations presented in the preceding reports which are
applicable should also be observed.
Limitations: This study has been conducted in accordance with generally accepted
geotechnical engineering principles and practices in this area at this time. We make no
warranty either express or implied. The conclusions and recommendations submitted in
this report are based upon the data obtained from the exploratory pits excavated at the
locations indicated on Figure 1 and to the depths shown on Figure 2, the proposed type of
construction, and our experience in the area. Our services do not include determining the
presence, prevention or possibility of mold or other biological contaminants (MOBC)
developing in the future. If the client is concerned about MOBC, then a professional in
this special field of practice should be consulted. Our findings include interpolation and
extrapolation of the subsurface conditions identified at the exploratory pits and variations
in the subsurface conditions may not become evident until excavation is performed. If
conditions encountered during construction appear different from those described in this
report, we should be notified at once so re- evaluation of the recommendations may be
made.
This report has been prepared for the exclusive use by our client for design purposes. We
are not responsible for technical interpretations by others of our information. As the
project evolves, we should provide continued consultation and field services during
construction to review and monitor the implementation of our recommendations, and to
Job No. 112 252A
G99tL-Ch
Sunder, Inc.
September 27, 2012
Page 5
verify that the recommendations have been appropriately interpreted. Significant design
changes may require additional analysis or modifications to the recommendations
presented herein. We recommend on -site observation of excavations and foundation
bearing strata and testing of structural fill by a representative of the geotechnical
engineer.
If you have any questions or if we may be of further assistance, please let us know.
Respectfully Submitted,
HEPWORTH - PAWLAK 6�' ICAL, INC.
itl IFjj/
f A. •
•
David A. Young, P. IS .�
�i 32216
Reviewed by: �ir,S. •.....•••• �``e�
Steven L. Pawlak, P.E.
DAY/ksw
attachments Figure 1, Locations of Exploratory Pits
Figure 2, Logs of Exploratory Pits
Figure 3, Swell- Consolidation Test Results
Figure 4, Gradation Test Results
Table 1, Summary of Laboratory Test Results
Job No. 112 252A
Gg to
\ \
PIT 1
\\
LOT 4 � � \ •
\
LOWE LEVEL % -'r
x
f f '
-
.,. PIT 2
,APPROXIMATE SCALE:
30
J LOT 2
T,
112 252A I teCrn I LOCATIONS OF EXPLORATORY PITS I FIGURE 1
HEPWORTH- PAWLAK GEOTECHNICAL
10 10
LEGEND:
®FILL; about 1 foot of organic sandy silty clay over
sandy silty clay, medium stiff, moist, brown to
dark brown.
CLAY (CL); silty, very sandy, stiff, very moist,
brown, low to medium plasticity.
0§0 GRAVEL and COBBLES (GM -GP); probale
boulders, sandy, slightly silty, dense, moist to
wet with depth in Pit 1, brown.
TOPSOIL; organic sandy silty clay, moist, dark
brown.
SAND (SC); clayey, silty, medium dense, moist
to very moist, brown, slightly porous, low to
medium plasticity.
2" Diameter hand driven liner sample.
Disturbed bulk sample.
_ J
Free water depth measured in the pit at the time of excavation.
NOTES:
1. Exploratory pits were excavated on July 27, 2012 with a John Deere 35D mini- excavator.
2. Locations of exploratory pits were measured approximately by pacing from features shown on the site plan
provided.
3. Elevations of exploratory pits were obtained by interpolation between contours shown on the site plan provided. The
logs of exploratory pits are drawn to depth.
4. The exploratory pit locations and elevations should be considered accurate only to the degree implied by the method
used.
5. The lines between materials shown on the exploratory pit logs represent the approximate boundaries between
material types and transitions may be gradual.
6. Water level readings shown on the logs were made at the time and under the conditions indicated. No free water
wsa encountered in Pit 2. Fluctuations in water level may occur with time.
7. Laboratory Testing Results:
WC = Water Content ( %)
DD = Dry Density (pcf)
+4 = Percent retained on the No. 4 sieve
-200 = Percent passing No. 200 sieve
112 252A
t i E P W O RTH -PA W LAK G EOTEC H N ICAL
H
w
w
U_
2
F-
a
u1
0
LOGS OF EXPLORATORY PITS I FIGURE 2
PIT 1
PIT 2
ELEV. =8660'
ELEV. = 8365'
0
0
WC =12.9
W
DD =104
LL
WC =28.9
- 200 =29
5
DD-96
5
2
a
oo.;
WC =23.6
W
::: ':
DD =94
- 200 =10
,o.
J
10 10
LEGEND:
®FILL; about 1 foot of organic sandy silty clay over
sandy silty clay, medium stiff, moist, brown to
dark brown.
CLAY (CL); silty, very sandy, stiff, very moist,
brown, low to medium plasticity.
0§0 GRAVEL and COBBLES (GM -GP); probale
boulders, sandy, slightly silty, dense, moist to
wet with depth in Pit 1, brown.
TOPSOIL; organic sandy silty clay, moist, dark
brown.
SAND (SC); clayey, silty, medium dense, moist
to very moist, brown, slightly porous, low to
medium plasticity.
2" Diameter hand driven liner sample.
Disturbed bulk sample.
_ J
Free water depth measured in the pit at the time of excavation.
NOTES:
1. Exploratory pits were excavated on July 27, 2012 with a John Deere 35D mini- excavator.
2. Locations of exploratory pits were measured approximately by pacing from features shown on the site plan
provided.
3. Elevations of exploratory pits were obtained by interpolation between contours shown on the site plan provided. The
logs of exploratory pits are drawn to depth.
4. The exploratory pit locations and elevations should be considered accurate only to the degree implied by the method
used.
5. The lines between materials shown on the exploratory pit logs represent the approximate boundaries between
material types and transitions may be gradual.
6. Water level readings shown on the logs were made at the time and under the conditions indicated. No free water
wsa encountered in Pit 2. Fluctuations in water level may occur with time.
7. Laboratory Testing Results:
WC = Water Content ( %)
DD = Dry Density (pcf)
+4 = Percent retained on the No. 4 sieve
-200 = Percent passing No. 200 sieve
112 252A
t i E P W O RTH -PA W LAK G EOTEC H N ICAL
H
w
w
U_
2
F-
a
u1
0
LOGS OF EXPLORATORY PITS I FIGURE 2
0
.o
OR
0 1
c
cC{
Q
X
w 2
c
0
U)
3
0
Q
E
0
U
5
0
1
2
3
C_
0
Q)
a 4
E
0
U
6
Moisture Content = 28.9
Dry Density = 96
Sample of: Very Sandy Silty Clay
From: Pit 1 at 4 Feet
Expansion
upon
wetting
percent
pcf
0.1 1.0 10 100
APPLIED PRESSURE - ksf
7 L-
0.1
Moisture Content = 23.6
Dry Density = 94
Sample of: Clayey Silty Sand
From: Pit 2 at 6 Feet
Compression
upon
wetting
percent
pcf
1.0 10 100
APPLIED PRESSURE - ksf
112 252A C -< ,"cecn SWELL- CONSOLIDATION TEST RESULTS FIGURE 3
HEPWORTH- PAWLAK GEOTECHNICAL
HEPWORTH - PAWLAK GEOTECHNICAL, INC.
TABLE 1
SUMMARY OF LABORATORY TEST RESULTS
Job No. 112 252A
SAMPLE
LOCATION
NATURAL
MOISTURE
CONTENT
(%1
NATURAL
DRY
DENSITY
(pd)
GRADATION
PERCENT
PASSING
NO. 200
SIEVE
ATTERBERG LIMITS
AASHTO
CLASSIFICATION
SOIL OR
BEDROCK TYPE
PIT
DEPTH
(ft)
GRAVEL
M
SAND
(%)
LIQUID
LIMIT
1 %1
PLASTIC
INDEX
l %1
1
4
28.9
96
Very Sandy Silty Clay
7-71/2
49
41
10
Slightly Silty Sandy Gravel
2
2'/2
12.9
104
29
Clayey Silty Sand
6
23.6
94
Clayey Silty Sand