HomeMy WebLinkAboutF12-0087 FPE LETTER FOR SHOP DRAWINGS
Reviewed for general conformance with the contract requirements and with other crafts. Approved for submittal to the architects- subject to architects and engineers approval.
G.E. JOHNSON CONSTRUCTION CO,
INC.Signed by
Date 07/25/2012
15400-001
11/06/12
SHOP DRAWING/SUBMITTAL REVIEW
PLANS ARE APPROVED
BY: DEBORAH SHANER, P.E., SHANER LIFE SAFETY
DATE: 11/8/12
COMMENTS: COORDINATE EXACT FDC LOCATION WITH VAIL FIRE
DEPARTMENT. OUTSIDE HORN/STROBE SHALL BE MOUNTED ABOVE FDC.
NOTE: SUBMITTAL WAS REVIEWED FOR DESIGN CONFORMITY AND
GENERAL CONFORMANCE TO CONTRACT DOCUMENTS. THE
CONTRACTOR IS RESPONSIBLE FOR CONFIRMING AND CORRELATING
DIMENSIONS AT JOBSITE FOR TOLERANCE, CLEARANCE, QUANTITIES,
FABRICATION PROCESSES, AND TECHNIQUES OF CONSTRUCTION,
COORDINATION OF HIS WORK WITH OTHER TRADES AND FULL
COMPLIANCE WITH CONTRACT DOCUMENTS.
By David Rhoades at 2:19 pm, Nov 14, 2012