HomeMy WebLinkAboutWeekly Update 2008.05.23 CONSTRUCTION UPDATE May 23, 2008 PARKING STRUCTURE REMINDER Due to an anticipated increase in visitors to Vail over the upcoming holiday weekend and beyond, contractors are asked to park on the north side (Frontage Road side) of both the Vail Village and LionsHead parking structures. Town of Vail parking staff will be directing construction vehicles to those locations. Also, increased enforcement of over-the-line and oversized vehicle violations is underway to ensure adequate parking. For more information, call Mike Rose, Town of Vail Parking and Transit Manager, at 479-2349. CDOT NIGHTIME WORK ON I-70 Beginning May 27, the Colorado Department of Transportation will begin nighttime work on I-70 between Dowd Junction and the East Vail exit. Work will be performed between the hours of 6:30 p.m. and 6:30 a.m. Sunday through Thursday and will include resurfacing, replacement of guardrail sections and continuation of the glare screen near powd Junction. Speed limits will be reduced to 40 mph in the construction zone; normal speeds will resume during daytime hours. For more information, look for weekly ads on Fridays in the Vail Daily; call the I-70 Hotline at 476-2024; and watch for the project Web site, coming soon. TEVA MOUNTAIN GAMES The Teva Mountain Games will return to Vail June 5— 8 with events scheduled throughout Vail Village and Golden Peak. Construction deliveries and other activities in Vail's rights-of-way will be limited during the event. A schedule of events and locations is attached to this update. For more information, visit www.tevamountainqames.com. For questions or concerns on allowable work hours, contact Leonard Sandoval at (970) 390-4677. VAIL VILLAGE Notes from the construction progress meeting held May 20, 2008 (All scheduled activities are subject to change.) Primary Contact Leonard Sandoval, TOV Construction Area Coordinator (970) 390-4677 or (970) 479-2198; Isandoval(a�vailqov.com Public Project Updates Seibert Circle The majority of the mechanical equipment is installed and most of the stone work is anticipated to be complete next week. The project is targeting completion in approximately two weeks. At that time, the design team will calibrate and program the fountain, which is anticipated to take an additional week. Contact Todd Oppenheimer at (970) 390-4678 or (970) 479-2161. Eaqle River Water& Sanitation District Work The District is completing a utility crossing of Vail Road. Following the crossing, water and sewer line work on Beaver Dam Road will begin and is anticipated to be underway from late May through October. Access to all residences will be maintained; however, it will change from east to west as work progresses. Also, work is underway on the abandonment of an old water line in Vail Valley Drive. Motorists should expect delays. Contact John Cahill at (970) 477-5447 for more information. 1 Private Project Updates Front Door Work continues on the chalets, with the tower crane scheduled for removal May 28-29. Bike path, Vista Bahn ski yard and landscaping work is occurring as weather permits. Contact Jeff Haselhorst, Hyder Construction at (303) 829-5741. Solaris Pre-cast work is underway, with deliveries occurring off of the South Frontage Road. Crawler crane delivery is tentatively set for the first week in June; the operation would take place from 2 a.m. to 7 a.m. Contact The Weitz Company, Rob Robinson at (970) 668-4700 or (970) 406- 0968. FourSeasons No updates. Contact Layton Construction, Mark Reed at (970) 401-1777 or Bob Hutchinson at (970) 401-0740. Manor Vail Ford Park access from Vail Valley Drive near Northwoods is anticipated to be complete this week. Paver work on the Ford Park path through Manor Vail near Golden Peak will also begin this week. Contact GE Johnson Construction, John Parr at (719) 330-3337 or Austin Dodder at (970) 300-9035. Mountain View The crane currently used for setting pre-cast is scheduled to demobilize in the early morning hours the week of June 2. Then, a hydro-crane will be brought in to finish pre-cast, which is anticipated to be complete by mid-June. On June 16, work to complete the boulder wall above the streamwalk will resume. Flaggers will be in place to ensure pedestrian safety. Contact Jeff Pugmire, R.A. Nelson, (970) 748-7645. The Willows Road prep is underway for final street configuration of Willow Road. Interior work is continuing. Work on the retaining wall and stairs up to Vail Road is occurring as weather permits. Contact Paul Burbidge, R.A. Nelson, (970) 949-5152 or (970) 471-6047. Nine Vail Road Landscaping is continuing. Contact Howard Bridgland, Nedbo Construction, (970) 977-0329. Rucksack Demolition of the front section of the Rucksack Building is underway. Fencing currently in the right-of-way will be pulled back toward the site no later than June 27. Contact Mark Hallenbeck, Highland Builders Corp., (719) 499-9248. Announcements • Katsos Ranch recreation path drainage work is continuing. Paving is scheduled for May 31, weather permitting. Users should anticipate delays or closures, the project is targeting an early June completion. Contact Gregg Barrie with the TOV at (970) 479- 2337 for more details. • Work on the Ford Park raw water project to convert irrigation systems from domestic water to untreated water is continuing. Contact John Cahill with the ERW&SD at (970) 477-5447 or Todd Oppenheimer with the TOV at (970) 479-2161 for more information. 2 • Contractors are asked to remove silt sacks from storm sewers and hay bales from ditches to accommodate higher water flows occurring due to spring run-off conditions. Next Meeting 9 a.m. Tuesday, May 27, Vail Transit conference room, Vail Transportation Center. LIONSHEAD Notes from the construction progress meeting held May 21, 2008. (All scheduled activities are subject to change.) Private Project Updates The Arrabelle at Vail Square Primary Contact Matt Lydens, Vail Resorts Development Company (970) 331-7755; mlydens@vailresorts.com Streetscape—west side of mall • Concrete steps and walls will be formed this week. • Lifts are working on the west side of the Arrabelle on exterior punch list items. • Pavers continue to be installed south of Haagen Dazs. Core Site • Work continues from man lifts on the plaza finishing downspouts and punch list items. • Grading continues in the skier yard. • Final coat of the stucco ceiling is being completed above the escalators. • Stone seating around the ice rink is installed and fire place is complete. Ritz-Carlton Excavation and shoring continues. Pre-cast is underway and will continue through mid-June. Cowboy Jorgensen, PCL Construction Services, Inc., (720) 244-5710. Lion Square Lodqe North —Tower Residences Shoring is continuing. Excavation of underground parking will begin next week. Asbestos abatement will continue for approximately two more weeks. Contact J.L. Viele Construction, Tony Faulhaber at (970) 471-5467 or (970) 476-3082. Next Meeting 8:30 a.m. Wednesday, May 28, Arrabelle at Vail Square conference rooms. HELP US SPREAD THE WORD Do you know of others who would be interested in receiving construction updates from the Town of Vail? To sign up for this free service, visit www.vailqov.com/vail-mail. To receive this information via fax, call the Town of Vail Community Information Office at 479-2118. REMOVE YOURSELF FROM THE CONSTRUCTION UPDATE LIST If you no longer wish to receive these updates, please call 479-2118 to remove yourself from the fax list, or unsubscribe using the link at the bottom of this email. 3