Loading...
HomeMy WebLinkAboutWeekly Update 2008.06.13 CONSTRUCTION UPDATE June 13, 2008 MANAGED PARKING RETURNS TO FORD PARK Beginning June 17, a parking attendant will be at Ford Park at 7 a.m. on approximately 40 "peak days" and will request that vehicles looking for all-day parking not related to Ford Park activities use the Vail Village or LionsHead parking structure. This to allow close-in parking for events such as the Hot Summer Nights concert series, Bravo! Vail Valley Music Festival, Vail International Dance Festival and the Vail Lacrosse Tournament. Vehicles will be charged $5 for event parking. For a list of the designated paid parking days, visit www.vailc�ov.com. COLORADO STAGE BIKE RACE The Colorado Stage bike race is scheduled to be in Vail Aug. 23 —24 and will necessitate road closures throughout Vail. A large amount of coordination and cooperation will be required for the event. For logistical questions, contact Vail Police Sgt. Chris Botkins at 390-4159. For more details about the event, visit www.coloradostaqebike.com. More information will be included in this construction update as the event nears. VAIL VILLAGE Notes from the construction progress meeting held June 10, 2008 (All scheduled activities are subject to change.) Primary Contact Leonard Sandoval, TOV Construction Area Coordinator (970) 390-4677 or (970) 479-2198; Isandoval(a�vailqov.com Public Project Updates Seibert Circle WET Design is scheduled to arrive today (6/13) to calibrate and program the fountain, which is anticipated to take two weeks. Contact Todd Oppenheimer at (970) 390-4678 or (970) 479- 2161. Vail Transportation Center Reroof A reroof of the bus terminal at the Vail Transportation Center is underway. Impacts to the parking structure are expected to be minimal and the contractor is required to maintain access to all buildings at all times. Contact John Gallegos at (970) 479-2170. Vail Road and Vail Valley Drive Overlays Curb and gutter work is occurring on Vail Road and Vail Valley Drive in preparation for overlays of both roads scheduled for June 17-18, weather permitting. Call Chad Salli at (970) 479-2169. Eaqle River Water& Sanitation District Work Water and sewer line work on Beaver Dam Road is underway and is anticipated to continue through October. Access to all residences will be maintained; however, it will change from east to west as work progresses. Pedestrians are asked to avoid Beaver Dam Road. Also, work is underway on the abandonment of an old water line in Vail Valley Drive. Motorists should expect delays. Contact John Cahill at (970) 477-5447 for more information. 1 Private Project Updates Front Door The plaza area is nearing completion, with final landscaping underway. Work continues on the chalets with the first group scheduled for completion by mid-July. The tower crane will be removed after the Fourth of July weekend. Contact Jeff Haselhorst, Hyder Construction at (303) 829-5741. Solaris The first tower crane will be assembled on-site this weekend. The last portion of excavation is underway. Pre-cast deliveries are continuing daily. Contact The Weitz Company, Rob Robinson at (970) 668-4700 or (970) 406-0968. FourSeasons Prep for the Vail Road sidewalk near the Main Vail roundabout is underway. Contact Layton Construction, Mark Reed at (970) 401-1777 or Bob Hutchinson at (970) 401-0740. Manor Vail Site work is continuing, with the project aiming to have public access to Ford Park through the site open by July 1. Contact GE Johnson Construction, John Parr at (719) 330-3337 or Austin Dodder at (970) 300-9035. Mountain View Work to complete the boulder wall above the streamwalk is anticipated to resume next week. Flaggers will be in place to ensure pedestrian safety. Contact Jeff Pugmire, R.A. Nelson, (970) 748-7645. The Willows Paving of Willow Road is scheduled to occur early next week. Contact Paul Burbidge, R.A. Nelson, (970) 949-5152 or (970) 471-6047. Rucksack Demolition is essentially complete. Next week, a crane will be on-site. Contact Mark Hallenbeck, Highland Builders Corp., (719) 499-9248. Announcements • Katsos Ranch recreation path is open; shoulder work, landscaping and restoration of picnic areas is continuing. Users should anticipate equipment on the path and possible delays. Contact Gregg Barrie with the TOV at (970) 479-2337 for more details. • Work on the Ford Park raw water project to convert irrigation systems from domestic water to untreated water is complete, with landscaping work underway. Contact John Cahill with the ERW&SD at (970) 477-5447 or Todd Oppenheimer with the TOV at (970) 479-2161 for more information. Next Meeting 9 a.m. Tuesday, June 17, Vail Transit conference room, Vail Transportation Center. 2 LIONSHEAD Notes from the construction progress meeting held June 11, 2008. (All scheduled activities are subject to change.) Private Project Updates The Arrabelle at Vail Square Primary Contact Matt Lydens, Vail Resorts Development Company (970) 331-7755; mlydens@vailresorts.com Streetscape • Snowmelt, sand and pavers are currently being installed in front of the Landmark. • Steps are complete in front of the General Store. • Lifts are working on all sides of the building exterior (stonework, stucco, etc.) • Pavers are complete south of Haagen Dazs and on the plaza. Core Site • Work in plaza continues from lifts on downspouts, stucco and stonework. • Bike path grading continues in the skier yard. • Waterfall wall and plaza fountain are anticipated in the next month. • Work around escalators and spa entrance is wrapping up with clean up and the installation of the chandeliers remaining. Ritz-Carlton No updates. Contact Cowboy Jorgensen, PCL Construction Services, Inc., (720) 244-5710. Lion Square Lodqe North —Tower Residences Excavation and shoring is continuing. Contact Tony Faulhaber, J.L. Viele Construction, (970) 471-5467 or (970) 476-3082. Next Meeting 8:30 a.m. Wednesday, June 18, Arrabelle at Vail Square conference rooms. HELP US SPREAD THE WORD Do you know of others who would be interested in receiving construction updates from the Town of Vail? To sign up for this free service, visit www.vailqov.com/vail-mail. To receive this information via fax, call the Town of Vail Community Information Office at 479-2118. REMOVE YOURSELF FROM THE CONSTRUCTION UPDATE LIST If you no longer wish to receive these updates, please call 479-2118 to remove yourself from the fax list, or unsubscribe using the link at the bottom of this email. 3