July 2, 2008
CONSTRUCTION ACTIVITY RESTRICTED FOR HOLIDAY WEEKEND
Construction activity in Vail's rights-of-ways will be restricted for the upcoming Fourth of July
weekend. On July 3, construction deliveries can continue so long as trucks are not staged or
stacked on Vail's roads. From July 4 - July 6, all deliveries are restricted. For more information,
contact Leonard Sandoval at (970) 390-4677.
SUMMER PARKING MANAGEMENT PLAN UNDERWAY
Thanks to everyone who met with the Town of Vail over the past week to help address ongoing
parking concerns. The town is asking for continued assistance in implementing alternative
parking and transportation options to help free up additional close-in parking spaces for
shoppers and diners, especially in the Village structure. Those options include filling Vail's
available outlying parking spaces at the former Wendy's lot in West Vail which contains 75
spaces, plus 100 spaces at the town-owned Timber Ridge property on the North Frontage
Road, as well as additional spaces that have been located on or near construction sites. Use of
van pools, car pools and public transit is also highly encouraged. For its part, the town is
working with employers to help coordinate bus service adjustments to accommodate the
changes. Also, management and monitoring of the parking structures by the town's newly
expanded summer parking staff is underway. In particular, attempts are being made to limit the
number of vehicles entering the Vail Village parking structure from 6 to 7:50 a.m. with access
limitations continuing throughout the morning. For more information, visit www.vailqov.com.
CONSTRUCTION PROGRESS MEETING SCHEDULES
Weekly Vail Village and LionsHead construction progress meetings have concluded for the
season. The next Vail Village meeting will take place Aug. 12, LionsHead meetings will resume
in the fall. Distribution of this update will mirror the construction progress meeting schedules;
look for the next update in mid-August. For project-specific information, see contacts below.
VAIL VILLAGE
Notes from the construction progress meeting held July 1, 2008
(All scheduled activities are subject to change.)
Primary Contact
Leonard Sandoval, TOV Construction Area Coordinator
(970) 390-4677 or (970) 479-2198; Isandoval(a�vailqov.com
Public Project Updates
Seibert Circle
Crews are addressing issues found during testing. WET Design will return next week to resume
programming the fountain. Contact Todd Oppenheimer at (970) 390-4678 or (970) 479-2161.
Vail Transportation Center Reroof
A reroof of the bus terminal at the Vail Transportation Center is nearing completion. Contact
John Gallegos at (970) 479-2170.
Eaqle River Water& Sanitation District Work
Water and sewer line work on Beaver Dam Road is underway and is anticipated to continue
through October. Access to all residences will be maintained; however, it will change from east
1
to west as work progresses. Pedestrians are asked to avoid Beaver Dam Road. Contact John
Cahill at (970) 477-5447 for more information.
Private Project Updates
Front Door
The final tower crane is scheduled for removal on July 7. Minor landscaping is all that is left
around the plaza and Vista Bahn ski yard. Work continues on the chalets. The Lodge at Vail spa
has a TCO and the Mountain Club is expected to be complete within a couple of weeks. Contact
Jeff Haselhorst, Hyder Construction at (303) 829-5741.
Solaris
Pre-cast deliveries are continuing. Steel deliveries are anticipated to begin next week. The
project has been granted permission to use the south gate (off of East Meadow Drive) from 7 to
10 a.m. Mon. - Fri. beginning July 7. No work will take place July 4-6. Contact The Weitz
Company, Rob Robinson at (970) 668-4700 or (970) 406-0968.
FourSeasons
Work continues on the sixth floor. Concrete pours are occurring regularly. No work will take
place from July 4-6. Contact Layton Construction, Mark Reed at (970) 401-1777 or Bob
Hutchinson at (970) 401-0740.
Manor Vail
All asphalt is complete. The project is aiming to have public access to Ford Park through the site
open by July 4. Contact GE Johnson Construction, John Parr at (719) 330-3337 or Austin
Dodder at (970) 300-9035.
Mountain View
No updates. Contact Jeff Pugmire, R.A. Nelson, (970) 748-7645.
The Willows
Streetscape is essentially complete. Scaffolding is moving around to the final exterior section.
Crane removal is scheduled for Aug. 12-14. Contact Paul Burbidge, R.A. Nelson, (970) 949-
5152 or (970) 471-6047.
Rucksack
Foundation work is 90% complete. Framing is continuing. The construction fence is tucked back
onto the site. Contact Mark Hallenbeck, Highland Builders Corp., (719) 499-9248.
Bell Tower Buildinq
Unloading of debris from the third floor will continue through Friday. Contact Kevin Fifield, Beck
Building Company, (970) 949-1800 or (970) 904-1283.
Announcements
• Katsos Ranch recreation path is open; restoration of picnic areas is continuing. Users
should anticipate equipment on the path and possible delays. Contact Gregg Barrie with
the TOV at (970) 479-2337 for more details.
• The next Vail Village construction progress meeting is scheduled for Aug. 12.
Next Meeting
9 a.m. Tuesday, Aug. 12, Vail Transit conference room, Vail Transportation Center.
2
LIONSHEAD
Notes from the construction progress meeting held July 2, 2008.
(All scheduled activities are subject to change.)
Private Project Updates
The Arrabelle at Vail Square
Primary Contact
Matt Lydens, Vail Resorts Development Company
(970) 331-7755; ml dens vailresorts.com
Streetscape
• All streetscape work has wrapped up for the season, with punch list items and drainage
work to occur in the fall.
Core Site
• Work will wrap up on Wednesday for the holiday weekend, punch list work will resume
on Monday.
• Top soil is being installed in the ski yard, with sod expected early next week.
• Waterfall wall and plaza fountain are anticipated later this summer.
Ritz-Carlton
Excavation is continuing and concrete pours are occurring regularly. Pre-cast deliveries will
resume on Monday; a traffic plan to limit delays due to vehicle backing is being implemented.
Contact Cowboy Jorgensen, PCL Construction Services, Inc., (720) 244-5710.
Lion Square Lodqe North —Tower Residences
Shoring is nearing completion. Excavation and foundation work is continuing. Contact Tony
Faulhaber, J.L. Viele Construction, (970) 471-5467 or (970) 476-3082.
Announcements
• LionsHead construction progress meetings will resume in the fall. Watch this update for
a meeting announcement.
Next Meeting
TBD
HELP US SPREAD THE WORD
Do you know of others who would be interested in receiving construction updates from the Town
of Vail? To sign up for this free service, visit www.vailqov.com/vail-mail. To receive this
information via fax, call the Town of Vail Community Information Office at 479-2118.
REMOVE YOURSELF FROM THE CONSTRUCTION UPDATE LIST
If you no longer wish to receive these updates, please call 479-2118 to remove yourself from
the fax list, or unsubscribe using the link at the bottom of this email.
3