HomeMy WebLinkAboutWeekly Update 2008.08.15 CONSTRUCTION UPDATE
August 15, 2008
GORE VALLEY TRAIL DETOUR IN PLACE
A portion of the Gore Valley Trail recreation path is closed through Nov. 20 to facilitate the skier
bridge renovation project in Cascade Village. The closure is in place from Westhaven Drive to
the Glen Lyon Bridge. Users are being detoured to the South Frontage Road. A concrete barrier
is in place to separate vehicular traffic from pedestrians and signs are in place along the detour
route. For more information, contact Town of Vail Project Engineer Chad Salli at 479-2169.
CONSTRUCTION ON BLACK GORE CREEK SAND STORAGE AREA—WEST VAIL PASS
The Colorado Department of Transportation (CDOT) will start the Black Gore Creek Sediment
Removal project today (8/15). Traction sand from I-70 has accumulated within a pond in Black
Gore Creek, which runs along the south side of the interstate. This project, a joint effort between
CDOT and U.S. Forest Service, will remove the sand and restore the area as closely as
possible to its original state. This work, scheduled for completion on Oct. 31, was contracted to
American West Construction, LLC. The work involves excavating sand within Black Gore Creek
and constructing a sand-storage area near East Vail close to the new chain-down station.
TRAFFIC IMPACTS - The Vail Pass recreation path will be restricted to one lane during
working hours from the CDOT access gate to the sand removal area (a distance of
approximately 1 mile.) This path is restricted to bicycles and pedestrians. Two-way bicycle and
pedestrian traffic will share the open lane during sand-removal operations between the hours of
6:30 a.m. and 5:30 p.m., Monday through Friday. Also, there may be brief delays for motorized
traffic on the frontage road at the sand-storage area. For more information, contact Nancy
Shanks at (970) 385-1428 or (970) 749-3579.
CONSTRUCTION PROGRESS MEETING SCHEDULES
Weekly Vail Village construction progress meetings will resume on Sept. 2 in the Vail Transit
Conference Room, located in the Vail Transportation Center. LionsHead construction progress
meeting schedules are yet to be determined, contact Matt Lydens at 331-7755 for details. For
project-specific information, see contacts below.
VAIL VILLAGE
Notes from the construction progress meeting held Aug. 12, 2008
(All scheduled activities are subject to change.)
Primary Contact
Leonard Sandoval, TOV Construction Area Coordinator
(970) 390-4677 or (970) 479-2198; Isandoval(a�vailqov.com
Public Project Updates
Seibert Circle
Crews are continuing to address leaks found during testing. Contact Todd Oppenheimer at
(970) 390-4678 or (970) 479-2161.
Eaqle River Water& Sanitation District Work
Water and sewer line work on Beaver Dam Road is ahead of schedule; the District has brought
in extra crews in an effort to complete the entire project this year, rather than over two summers
as originally scheduled. Paving from Vail Road to Beaver Dam Circle is anticipated to occur by
the end of August. The entire project is targeting completion by the end of October. Pedestrians
1
are asked to avoid Beaver Dam Road. Contact John Cahill at (970) 477-5447 for more
information.
Private Project Updates
Front Door
The ski club and six of the chalets have received Temporary Certificates of Occupancy (TCO.)
Contact Jeff Haselhorst, Hyder Construction at (303) 829-5741.
Solaris
Setting of pre-cast concrete and steel is continuing. The tower for the second tower crane will
be delivered Saturday, with the top of the crane scheduled for installation in September. Contact
The Weitz Company, Rob Robinson at (970) 668-4700 or (970) 406-0968.
FourSeasons
Work is now underway on the eighth floor; there are two more floors plus the roof yet to go. A
crawler crane is in place through September to help set steel for the roof. Tower cranes will be
on site until spring. Contact Layton Construction, Mark Reed at (970) 401-1777 or Bob
Hutchinson at (970) 401-0740.
Manor Vail
TCO inspections are underway. Contact GE Johnson Construction, John Parr at (719) 330-3337
or Austin Dodder at (970) 300-9035.
Mountain View
Exterior skin and site work are underway. Interior finishes have begun. Contact Jeff Pugmire,
R.A. Nelson, (970) 748-7645.
The Willows
Exterior stucco and landscaping work, as well as interior finishes are underway. The project is
targeting a September TCO. Contact Paul Burbidge, R.A. Nelson, (970) 949-5152 or (970) 471-
6047.
Rucksack
Exterior masonry and stucco has begun. The project is targeting completion before Christmas.
Contact Mark Hallenbeck, Highland Builders Corp., (719) 499-9248.
Bell Tower Buildinq
Removal of the roof is scheduled to begin after Sept. 2. A crane will be staged on the south side
of the building to facilitate the work. Contact Kevin Fifield, Beck Building Company, (970) 949-
1800 or (970) 904-1283.
Announcements
• West Meadow Drive streetscape is anticipated to begin Sept. 2. Phase 1, which will
stretch from Vail Road to approximately the Alphorn Condominiums, will occur this fall.
Phase 2 will begin in spring 2009, encompassing the area from the Alphorn to Dobson
Ice Arena.
• The next Vail Village construction progress meeting is scheduled for Sept. 2.
Next Meeting
9 a.m. Tuesday, Sept. 2, Vail Transit conference room, Vail Transportation Center.
2
HELP US SPREAD THE WORD
Do you know of others who would be interested in receiving construction updates from the Town
of Vail? To sign up for this free service, visit www.vailqov.com/vail-mail. To receive this
information via fax, call the Town of Vail Community Information Office at 479-2118.
REMOVE YOURSELF FROM THE CONSTRUCTION UPDATE LIST
If you no longer wish to receive these updates, please call 479-2118 to remove yourself from
the fax list, or unsubscribe using the link at the bottom of this email.