HomeMy WebLinkAboutWeekly Update 2008.09.05 CONSTRUCTION UPDATE
September 5, 2008
OKTOBERFEST WORK HOURS
Construction activity and deliveries in public rights-of-way will be restricted during the upcoming
Oktoberfest weekends: Sept. 5-7 in LionsHead and Sept. 12-14 in Vail Village. Work is allowed
to continue within private project sites, so long as it does not exceed Vail's noise ordinance. For
more information, contact Leonard Sandoval at (970) 390-4677. For information on Oktoberfest
activities, visit www.vailoktoberfest.com.
WEST VAIL ROUNDABOUT PAVING
Crews hired by the Town of Vail will begin re-paving the West Vail roundabouts next week. The
work will necessitate a closure of the West Vail Interstate 70 on- and off-ramps from 7 a.m. to 7
p.m. Sept. 14 and again on Sept. 16. Motorists are asked to plan ahead and use the Main Vail
roundabout to access businesses and residences in West Vail. For more information, contact
Town of Vail Project Engineer Chad Salli at 479-2169.
CONSTRUCTION PROGRESS MEETING SCHEDULES
Weekly Vail Village construction progress meetings have resumed at 9 a.m. Tuesdays in the
Vail Transit Conference Room, located in the Vail Transportation Center. LionsHead
construction progress meetings take place at 8:30 a.m. Wednesdays in the Arrabelle at Vail
Square conference rooms. For specific project information, see contacts below.
VAIL VILLAGE
Notes from the construction progress meeting held Sept. 2, 2008.
(All scheduled activities are subject to change.)
Primary Contact
Leonard Sandoval, TOV Construction Area Coordinator
(970) 390-4677 or (970) 479-2198; Isandoval(a�vailgov.com
Public Project Updates
Seibert Circle
Crews are continuing to address leaks found during testing. Contact Todd Oppenheimer at
(970) 390-4678 or (970) 479-2161.
West Meadow Drive Streetscape
Removal of old asphalt is underway and utility relocation will begin next week. Traffic is reduced
to one lane, west bound only between Vail Road and Vail Valley Medical Center. Pedestrian
and bicycle access is being maintained. Contact Chad Salli at (970) 479-2169.
Eaqle River Water& Sanitation District Work on Beaver Dam Road
Paving is complete from Vail Road to Beaver Dam Circle, with clean-up and shoulder underway.
Utility work continues in Beaver Dam Circle, to be followed by prep for paving. The entire project
is targeting completion by the end of October. Pedestrians are asked to avoid Beaver Dam
Road. Contact John Cahill at (970) 477-5447 for more information.
Private Project Updates
Front Door
No updates. Contact Jeff Haselhorst, Hyder Construction at (303) 829-5741.
1
Solaris
A single lane closure on Village Center Chute is scheduled for Sept. 6 to facilitate the relocation
of a construction trailer. Erection of the second tower crane is underway. Contact Rob
Robinson, The Weitz Company, at (970) 668-4700 or (970) 406-0968.
FourSeasons
Work is now underway on the ninth floor; there is one more floor plus the roof yet to go. Contact
Layton Construction, Mark Reed at (970) 401-1777 or Bob Hutchinson at (970) 401-0740.
Manor Vail
TCO inspections are underway. Contact GE Johnson Construction, John Parr at (719) 330-3337
or Austin Dodder at (970) 300-9035.
Mountain View
Work is underway on the boulder wall adjacent to the stream walk. Contact Jeff Pugmire, R.A.
Nelson, (970) 748-7645.
The Willows
Asphalt repairs and curb and gutter work is underway on Vail Road. On Sept. 6, Vail Road will
be reduced to one lane to allow for excavation of the curb and gutter. Concrete is scheduled for
Monday, Sept. 8th. During the concrete pour, Vail Road will again be reduced to one lane.
Traffic control will be in place. The project is targeting a September TCO. Contact Paul
Burbidge, R.A. Nelson, (970) 949-5152 or (970) 471-6047.
Rucksack
No updates. Contact Mark Hallenbeck, Highland Builders Corp., (719) 499-9248.
Bell Tower Buildinq
Installation of the tower crane will take place from 7 a.m. to noon Sept. 8, to facilitate the top
floor remodel. The crane installation will necessitate a full road closure of Gore Creek Drive.
Traffic control will be in place to assist with delivery trucks backing out of Gore Creek Drive.
Contact Kevin Fifield, Beck Building Company, (970) 949-1800 or (970) 904-1283.
Next Meeting
9 a.m. Tuesday, Sept. 9, Vail Transit conference room, Vail Transportation Center.
LIONSHEAD
Notes from the construction progress meeting held Sept. 3, 2008.
(All scheduled activities are subject to change.)
Private Project Updates
The Arrabelle at Vail Square
Primary Contact
Matt Lydens, Vail Resorts Development Company
(970) 331-7755; mlydens@vailresorts.com
Streetscape
• Planter and paver removal in front of First Bank to facilitate asphalt repair begins
Monday.
2
• The bike path on the south side of the side will be closed beginning Monday. The path
will be closed between the Treetops driveway and the Antlers. Detour will be via the
LionsHead Mall.
Core Site
• Punch list items are underway.
Ritz-Carlton
Excavation around the ramp area is ongoing. Pre-cast work resumes on Monday. The second
tower crane is scheduled to arrive Sept. 29. Contact Cowboy Jorgensen, PCL Construction
Services, Inc., (720) 244-5710.
Lion Square Lodqe North —Tower Residences
No updates. Contact Tony Faulhaber, J.L. Viele Construction, (970) 471-5467 or (970) 476-
3082.
Landmark Condominiums
A large concrete pour scheduled for 7 a.m. to 2 p.m. Sept. 9 will necessitate a closure of West
LionsHead Circle between Concert Hall Plaza and the North Day Lot. Traffic control will be in
place. Contact Howard Olson, The Alter Group, (847) 345-4104.
Next Meeting
8:30 a.m. Wednesday, Sept. 10, Arrabelle at Vail Square conference rooms.
HELP US SPREAD THE WORD
Do you know of others who would be interested in receiving construction updates from the Town
of Vail? To sign up for this free service, visit www.vailqov.com/vail-mail. To receive this
information via fax, call the Town of Vail Community Information Office at 479-2118.
REMOVE YOURSELF FROM THE CONSTRUCTION UPDATE LIST
If you no longer wish to receive these updates, please call 479-2118 to remove yourself from
the fax list, or unsubscribe using the link at the bottom of this email.
3