HomeMy WebLinkAboutWeekly Update 2008.10.04 CONSTRUCTION UPDATE October 3, 2008 ELECTRICAL CONDUIT WORK ON LIONSRIDGE LOOP Work to install new electrical conduits on Lionsridge Loop is continuing to facilitate the relocation of overhead power lines to the conduits below grade. Currently, one lane of flagged, two-way traffic is being maintained. Beginning mid-next week, the contractor will close the road to accelerate progress on the remaining work. Emergency vehicle and pedestrian access will be maintained throughout the closure and the road will reopen each night. For more information, contact Chris Delles with the Town of Vail at 477-3418. VAIL SEEKS COMMUNITY MEMBERS TO FILL B&FCA BOARD VACANCIES The Town of Vail is seeking community members to fill three vacancies on its Building and Fire Codes Appeals Board (B&FCA). Applications are due to the town by 5 p.m. Oct. 29. The Vail Town Council will conduct interviews during its work session on Nov. 4, with appointments to follow at its evening meeting. Send letters of interest and experience to: Vail Town Council, Attn. Lorelei Donaldson, Town Clerk, 75 S. Frontage Rd., Vail, CO 81657. For more information and a description of the board visit www.vailgov.com. VAIL VILLAGE Notes from the construction progress meeting held Sept. 30, 2008. (All scheduled activities are subject to change.) Primary Contact Leonard Sandoval, TOV Construction Area Coordinator (970) 390-4677 or (970) 479-2198; Isandoval(a�vail�ov.com Public Project Updates Seibert Circle WET Design crews are working to program the fountain. Contact Todd Oppenheimer at (970) 390-4678 or (970) 479-2161. West Meadow Drive Streetscape Utility work is 75% complete. Prep for south walk and gutter is underway. Beginning Monday, traffic will be reduced to one lane, west bound only between Vail Road and Vail Valley Medical Center 24/7 to facilitate concrete pours. Pedestrian access is being maintained; cyclists are asked to dismount through the area. Contact Chad Salli at (970) 479-2169. Eaqle River Water& Sanitation District Work on Beaver Dam Road Paving is scheduled to occur in approximately two weeks. The entire project is targeting completion by the end of October. Pedestrians are asked to avoid Beaver Dam Road. Contact John Cahill at (970) 477-5447 for more information. Private Project Updates Front Door Site work is continuing on the south side of the project. Interior work on the remaining chalets will continue into winter. Contact Jeff Haselhorst, Hyder Construction at (303) 829-5741. Solaris A hydro-crane is in place at the southeast corner of the site to assist with the removal of the crawler crane and installation of the third tower crane. Village Center Road will be reduced to 1 one-lane, two-way traffic through Sunday. Traffic control is in place. Contact Rob Robinson, The Weitz Company, at (970) 668-4700 or (970) 406-0968. FourSeasons Paver sidewalk from Mayor's Park across the Four Seasons frontage on West Meadow Drive will occur this fall. A lane closure on the South Frontage Road is anticipated to occur within the next two weeks to allow for permanent power to be run to the site. Completion of the tenth floor is underway. The smaller tower crane is anticipated to be removed in early November. Contact Layton Construction, Mark Reed at (970) 401-1777 or Bob Hutchinson at (970) 401-0740. Manor Vail No updates. Contact GE Johnson Construction, John Parr at(719) 330-3337 or Austin Dodder at (970) 300-9035. Mountain View Work on the southeast stairs and streamwalk is underway. Backfill is occurring around the project. Driveway entry and sidewalk repair are scheduled to occur yet this fall. Contact Jeff Pugmire, R.A. Nelson, (970) 748-7645. The Willows The project is aiming for a TCO next week. Contact Paul Burbidge, R.A. Nelson, (970) 949-5152 or (970) 471-6047. Rucksack Exterior masonry and stucco is continuing. Contact Mark Hallenbeck, Highland Builders Corp., (719) 499-9248. Bell Tower Buildinq Structural steel will begin next Wednesday (10/8.) Setting of the ridge beam is scheduled for Oct. 16 and will require a full street closure of Gore Creek Drive for 4 hours in the morning. Contact Kevin Fifield, Beck Building Company, (970) 949-1800 or (970) 904-1283. Announcements • West Forest Road has reopened following replacement of the gondola cable. • Work on the north side of Vail Village Inn Phase III will begin soon and consists of realigning the existing curb and gutter, installing a concrete pan in front of the garage access and installing a heated paver walkway. Work is expected to take up to two weeks to complete. Pedestrian and vehicular access will be maintained; however, driveway access will be narrowed to single lane at times for construction. Call 479-2235. Next Meeting 9 a.m. Tuesday, Oct. 7, Vail Transit conference room, Vail Transportation Center. LIONSHEAD Notes from the construction progress meeting held Oct. 1, 2008. (All scheduled activities are subject to change.) Private Project Updates The Arrabelle at Vail Square Primary Contact Matt Lydens, Vail Resorts Development Company 2 (970) 331-7755; mlydens vailresorts.com Streetscape • Pavers are being installed in front of Montauk and Patagonia. • Additional drain work on the west side of The Arrabelle has begun. Core Site • Punch work is continuing on all buildings and the plaza which involves the use of lifts. • Drains and pavers are being raised or lowered on the plaza to remove the puddles. • Plaza fountain final finishes are almost complete, • Maypole art work is schedule for the middle of October. • Gondola building stone work is almost complete. • Temporary loading dock is being removed and the bike path is being restored to its original configuration. • Concrete steps are poured behind Lionshead Center and asphalt will go down next week. Ritz-Carlton Several road closures are anticipated in October on West LionsHead Circle to facilitate concrete pours and material delivery, weather permitting. More details to follow. Contact Cowboy Jorgensen, PCL Construction Services, Inc., (720) 244-5710. Lion Square Lodqe North —Tower Residences Foundation work is continuing. Steel work is scheduled to begin the third week of October. Framing is ongoing on the existing building. Contact Tony Faulhaber, J.L. Viele Construction, (970) 471-5467 or (970) 476-3082. Landmark Condominiums Pre-cast work for underground parking garage is continuing. Installation of steel is underway. A road closure of West LionsHead Circle is scheduled for 7 a.m. to 5 p.m. Oct. 7. Single-lane closures on West Lionshead Circle are scheduled throughout the month of October. Traffic control will be in place. Contact Howard Olson, The Alter Group, (847) 345-4104. Announcements • Replacement of the retaining wall at Vail Spa Condominiums will require a single-lane closure on West LionsHead Circle near the Ritz-Carlton site from Oct. 6— 17. Extreme Excavating is the contractor. Next Meeting 8:30 a.m. Wednesday, Oct. 8, Arrabelle at Vail Square conference rooms. HELP US SPREAD THE WORD Do you know of others who would be interested in receiving construction updates from the Town of Vail? To sign up for this free service, visit www.vailqov.com/vail-mail. To receive this information via fax, call the Town of Vail Community Information Office at 479-2118. REMOVE YOURSELF FROM THE CONSTRUCTION UPDATE LIST If you no longer wish to receive these updates, please call 479-2118 to remove yourself from the fax list, or unsubscribe using the link at the bottom of this email. 3