HomeMy WebLinkAboutPEC130014 Letter of Intent.pdf . �
5trate?i( Land Maim, Inc.
Civil Engineering•Land Planning.Entitlements
Friday, April 5, 2013
Attn: Mr. Warren Campbell
Town of Vail:
Department of Community Development
75 South Frontage Road
Vail, CO 81657
RE: Letter of Intent(McDonald's Raze and Rebuild at 2171 N. Frontage Road West)
Dear Mr. Campbell,
As we have discussed, our client McDonald's USA, LLC, is planning the redevelopment of their
existing restaurant located at 2171 N. Frontage Road West. The proposed development will
include an approximately 3,330 S.F. building with generous bicycle parking, tandem drive-thru
capability, enhanced landscaping, new lighting, and seating for approximately 70 patrons. As
part of the proposed development, the existing site will be razed and new pavement, lighting,
utilities, and landscaping will be provided. The site is located at 2171 N. Frontage Road West.
The site is bounded on the north and east by an existing shopping center, on the west by a hotel
and drive aisle, and on the south North Frontage Road.
SITE
�M1 i ° , ,s • mot"
West Vail
s
As you can see from the enclosed Site Plan, careful consideration was given to the layout of the
planned McDonald's site with one-way traffic rotation around the periphery of the lot. By doing
this, the layout affords access to the site without stacking traffic into the shopping center drive
aisle. During the concept phase of the project, McDonald's team looked several different
building orientations, and traffic circulation options. The layout shown on the attached plans
affords the best access to the site, while routing the drive thru traffic away from the shopping
8235 Cottongrass Court•Castle Pines•CO•80108
Email: rpalmer @strategicls.net
Phone:720.384.7661
Website:http://www.strategicls.net
�' I.
Mr. Warren Campbell Strateqi[Land Mutions, Inc
Letter of Intent Civil Engineering-Land Planning•Entitlements
Friday-April 05, 2013
Page 2
center drive aisles. During the concept phase McDonald's team looked at rotating the site layout
180-degrees, but found that the drive thm traffic would stack into the adjacent drive aisle,
congesting traffic within the shopping center.
The site currently operates 24 hours a day, with the lobby open from 5:00 am until 10:00 pm.
The new restaurant will operate the same hours. A typical day and evening shift will require 20-
employees. Approximately 50 employees will be utilized to operate all shifts at the restaurant.
Delivers are expected three times a week during non-peak hours. Trash service is also expected
three to four times a week occurring during non-peak times.
The new site will use landscape to screen adjacent uses and roads. The adjacent uses are
commercial/retail, and this site is an operational McDonald's, so no conflicts are expected. All
access to the site is taken from internal shopping center drives, with no direct access to N.
Frontage Road.
As part of this development the building roof drains will be captured by an underground storm
drain system, which will help eliminate ice in the parking lot. Additionally, snow storage has
been provided adjacent to the drive aisles and parking locations.
As described in this letter McDonald's is planning to raze their existing restaurant and build a
new modern facility. The existing facility will be taken to dirt with new lighting, landscaping
pavements, and a new building. McDonald's team has worked to develop the site layout, and to
develop architectural elevations which meet the zoning and vision for the area. If you have
questions regarding what is proposed,please feel free to call me. Thank you!
Sincerely,
ST TEGIC LAND SOLUTIONS, INC.
Robert J. Palmer, PE (CO, NM,Az)
President for SLS, Inc.A Colorado Corporation
Attachments: As noted above.
cc: Mr.Mark House,McDonald's via:mark.house @us.mcd.com
8235 Cottongrass Court•Castle Pines•CO•80108
Email: rpalmer @strategicls.net
Phone:720.384.7661