HomeMy WebLinkAboutB13-0401 COMCHECK.pdf Generated by COMcheck-Web Software
Envelope Compliance Certificate
2012 IECC
Section 1: Project Information
Project Type:Alteration
Project Title : Solaris 5HW
Construction Site: Owner/Agent: Designer/Contractor:
141 East Meadow Drive Sharon Cohn Scott Nevin
Vail,Colorado 81657 Solaris Davis Partnership Architects
0225 Main Street,Unit C101
Edwards,Colorado 81632
970-926-8960
Section 2: General Information
Building Location(for weather data): Vail,Colorado
Climate Zone: 6b
Building Space Conditioning Type(s): Residential
Activity Type(s) Floor Area
Hotel:Guest rooms 3377
Section 3: Requirements Checklist
Envelope PASSES
Climate-Specific Requirements:
R-Value Proposed Max.Allowed
Post-Alteration Assembly Cavity Cont. U-Factor SHGC U-Factor SHGC
Window:Wood Frame,2 Pane w/Low-E,Tinted, Fixed, Fixed --- --- --- --- --- ---
Exemption:Glazing replacement in existing sash or frame.
Door:Wood, Non-Swinging --- --- 0.350 --- 0.350 ---
Air Leakage, Component Certification, and Vapor Retarder Requirements:
1. Continuous air barrier is provided throughout the building thermal envelope.
2. Air barrier joints and seams are sealed.The joints and seals are securely installed in or on the joint for its entire length.
3. Penetrations of the air barrier and paths of air leakage are caulked,gasketed or otherwise sealed in a manner compatible with
the construction materials and location.Joints and seals are sealed in the same manner or taped or covered with a moisture
vapor-permeable wrapping material.The joints and seals are securely installed in or on the joint for its entire length.
4. The air barrier is continuous for all assemblies that are the thermal envelope and across the joints and assemblies.
5. Recessed lighting fixtures installed in the building envelope are Type IC rated as meeting ASTM E283,tested to—2.0 cfm,and are
sealed with gasket or caulk.
6. Completed building air leakage tested to<=0.40 cfm/ft2.
7. Air leakage of fenestration.Windows/non-glazed sliding and swinging doors/skylights with no weepage openings—0.20
cfm/ft2.Skylights with weepage—0.30 cfm/ft2.Curtain walls/storefront glazing<=0.06 cfm/ft2.Doors:glazed swinging
entrance/revolving/rolling<=1.00 cfm/ft2. Doors:garage<=0.40 cfm/ft2.
Exceptions:
J Field-fabricated assemblies.
Project Title: Solaris 5HW Report date: 10/09/13
Data filename: Page 1 of 3
8. Doors and access openings from conditioned space to shafts,chutes stairways and elevator lobbies are gasketed,weatherstripped or
sealed.
Exceptions:
J Door openings required to comply with International Building Code as per Section C402.4.4.
9. Stairway and shaft vents are provided with Class I motorized dampers with a leakage rate—4 cfm/ft2. Dampers are installed with
controls so that they are capable of automatically opening upon activation of any fire alarm or the interruption of power to the damper.
10.Outdoor air supply and exhaust openings are provided with Class IA motorized dampers having a leakage rate4 cfm/ft2.
Exceptions:
Gravity(nonmotorized)dampers having a leakage rate20 cfm/ft2 are permitted for exhaust and relief dampers for buildings less
than three stories in height above grade,or where the design outdoor air intake or exhaust capacity300 cfm.
Dampers smaller than 24 inches in either dimension are permitted to have a leakage40 cfm/ft2.
11.Cargo doors and loading dock doors are weather sealed.
12.Building entrance doors have a vestibule equipped with self-closing devices.
Exceptions:
Building entrances with revolving doors.
Doors not intended to be used as a building entrance by the public,or intended solely for employee use.
Doors that open directly from a space less than 3000 sq.ft.in area.
Doors used primarily to facilitate vehicular movement or materials handling and adjacent personnel doors.
Doors opening directly from a sleeping/dwelling unit.
Alteration projects that replace an existing door,provided,however,that existing vestibules(i.e., pre-alteration)are not removed.
13.Component R-values&U-factors labeled as certified.
14.No roof insulation is installed on a suspended ceiling with removable ceiling panels.
15.'Other'components have supporting documentation for proposed U-Factors.
16.Insulation installed according to manufacturer's instructions, in substantial contact with the surface being insulated,and in a manner
that achieves the rated R-value without compressing the insulation. Except when instructed otherwise,edge joints between overlapping
layers of continuous insulation are staggered.
17.Radiant panels and associated components,designed for heat transfer from the panel surfaces to the occupants or indoor space are
insulated with a minimum of R-3.5
Section 4: Compliance Statement
Compliance Statement: The proposed envelope alteration project represented in this document is consistent with the building plans,
specifications and other calculations submitted with this permit application.The proposed envelope alteration project has been designed to
meet the 2012 IECC requirements in COMcheck-Web and to comply with the mandatory requirements in the Requirements Checklist.
Chandler Deimund - Project Manager C" M 10/9/2013
Name-Title Signature Date
Project Title: Solaris 5HW Report date: 10/09/13
Data filename: Page 2 of 3
Generated by COMcheck-Web Software
Interior Lighting Compliance
Certificate
2012 IECC
Section 1: Project Information
Project Type:Alteration
Project Title : Solaris 5HW
Construction Site: Owner/Agent: Designer/Contractor:
141 East Meadow Drive Sharon Cohn Scott Nevin
Vail,Colorado 81657 Solaris Davis Partnership Architects
0225 Main Street,Unit C101
Edwards,Colorado 81632
970-926-8960
Section 2: Interior Lighting and Power Calculation
A B C D
Area Category Floor Area Allowed Allowed Watts
(ft2) Watts/ft2 (B x C)
Hotel:Guest rooms: Exempt
Total Allowed Watts= N/A
Area Category Exemption Qualifications
Total Wattage Total Pre-Alt. #Fixtures
Activity Area Pre-Alt. Post-Alt. Fixtures Repl./Added
Hotel:Guest rooms(3377 sq.ft.): Exemption:Less than 50%fixture 9513 9513 111 13
replacement.
Section 3: Interior Lighting Fixture Schedule
A B C D E
Fixture ID: Description/Lamp/Wattage Per Lamp/Ballast Lamps/ #of Fixture (C X D)
Fixture Fixtures Watt.
Hotel:Guest rooms(3377 sq.ft.): Exempt
Total Proposed Watts= N/A
Section 4: Requirements Checklist
Interior Lighting PASSES
Section 5: Compliance Statement
Compliance Statement: The proposed lighting alteration project represented in this document is consistent with the building plans,
specifications and other calculations submitted with this permit application.The proposed lighting alteration project has been designed to meet
the 2012 IECC,Chapter 8, requirements in COMcheck-Web and to comply with the mandatory requirements in the Requirements Checklist.
Chandler Deimund - Project Manager C" 0 10/9/2013
Name-Title Signature Date
Project Title: Solaris 5HW Report date: 10/09/13
Data filename: Page 3 of 3