HomeMy WebLinkAboutB14-0010 REV4 Special Inspection Summary ������ Client: Mr.Jim Selby
Aspen Wireless
1920 W. Burnley Lane
ENGINEERING CONSULTANTS MapleCity, M149664
Vail Transportation Light Pole Upgrade
Structural Steel Cover Report
Date: �une�2,2014 Location: site JOb NUI71b21': 14-6534
As scheduled, a representative arrived to perform special inspection services. The following is a summary of
services provided on this date.
As directed by Chad with Aspen Wireless:
1)GROUND inspected welded connections of plate to existing beam and plate to new beam. A summary below is of the following:
A)It was observed that only one connection was placed on each end of the beam web, rather than the two on each side of the web,
discrepancy item#1.
B)It was observed that plates were used in lieu of 4x4 angle or bent plate. GROUND is requesting clarification from the EOR. Picture#1
attached to the second page of this report,discrepancy item#2.
2)GROUND inspected torched cut beams and found the beams had no Reentrant(radius)corners as perAWS D1.1-10 section 5.16,
gouges greater than allowed per AWS D1.1-10 section 5.15.4.4 and slag not removed.Picture#2 attached to the second page of this report,
discrepancy item#3.
3)in regards to note#2 on page SP-4 and of notes on pages,GROUND was not provided continuous observation while depositing of the
welds,discrepancy item#4.
4)GROUND has received and reviewed Welding Procedure Specification(WPS),Welder Qualification Test Record(WQTR)for Thompson
welding in accordance with AWS D1.1 and a continuity log.
5)It is noted on this date,the welds in place on todays inspection were found in general compliance with AWS D1.1-10 table 6.1;however,
remain non-compliant per discrepancy item#1-4.
Chad was informed of the observations, E-mailed a copy of this report and current discrepancy list.
Yes No
Outstanding Discrepancies Reported this Date? � �
No. of Pages Attached: �
Field Representativ�,,,,�s�r���eng.com
Englewood, Commerce City, Loveland, Granby, Gypsum, Grand Junction, Casper
������ Client: Mr.Jim Selby
Aspen Wireless
1920 W. Burnley Lane
ENGINEERING CONSULTANTS MapleCity, M149664
Vail Transportation Light Pole Upgrade
Comments
Date: �une�2,2014 Location: site JOb NUI71bel': 14-6534
Additional Comments or Photos:
�
``Y_
�
,`
?k
s,�
.P�
t � t�
r d R�
�� .
- .� f�. � ! '_ ,� � �� ' _- _
.l: � . "', +:
� �� '
�
� � c
• No radius�nd gouges
� '�� �
,
� R
I �+ I�I
� � i�lt
, . I � ��y �i
— , . �:R'
y .
W ^�
.,.., . i i� �. �a i
Englewood, Commerce City, Loveland, Granby, Gypsum, Grand Junction, Casper
������ Client: Mr.Jim Selby
Aspen Wireless
1920 W. Burnley Lane
ENGINEERING CONSULTANTS MapleCity, M149664
Vail Transportation Light Pole Upgrade
Structural Steel Cover Report
DBte: June 16,2014 Location: Site JOb NUI71b21': 14-6534
As scheduled, a representative arrived to perform special inspection services. The following is a summary of
services provided on this date.
As directed by Chad with Aspen Wireless:
1)GROUND re-inspected torched cut beams and found the beams to be in general compliance with AWS D1.1-10 clause 5,discrepancy
item#3 is closed on this date.
2)GROUND has received and reviewed Approved stamped Town Of Vail updated detail SP-2 in regards to discrepancy item#1 and#4.
These items closed on this date.
Chad was informed of the observations, E-mailed a copy of this report and current discrepancy list.
Yes No
Outstanding Discrepancies Reported this Date? � �
No. of Pages Attached: o
Field Representativ�,,,,�s�r���eng.com
Englewood, Commerce City, Loveland, Granby, Gypsum, Grand Junction, Casper
������ Client: Mr.Jim Selby
Aspen Wireless
1920 W. Burnley Lane
ENGINEERING CONSULTANTS MapleCity, M149664
Vail Transportation Light Pole Upgrade
Structural Steel Cover Report
DBte: June 29,2014 Location: Site JOb NUI71b21': 14-6534
As scheduled, a representative arrived to perform special inspection services. The following is a summary of
services provided on this date.
1)GROUND has received and reviewed revised SP-2 dated 6/20/14 with stamped approved plans from the Town of Vail.This closes out
discrepancy item#2 on this date.
Chad was E-mailed a copy of this report and updated discrepancy list.
Yes No
Outstanding Discrepancies Reported this Date? � �
No. of Pages Attached: o
Field Representativ�,,,,�s�r���eng.com
Englewood, Commerce City, Loveland, Granby, Gypsum, Grand Junction, Casper
������ Client: Mr.Jim Selby
Aspen Wireless
1920 W. Burnley Lane
ENGINEERING CONSULTANTS MapleCity, M149664
Vail Transportation Light Pole Upgrade
Field/Fab. Shop? Field Job Name: Vail ski Museum
Fabrication Shop: Job Number: �a-s53a
General Contractor: Aspen wireiess
Outstanding Structural Steel Discrepancy Log
Date Item CWI Date Per Plan/
Reported Number initials Description of Discrepancy Resolved Per RFI
only one connection was placed on each end of the beam web, rather than the Per revised
6/12/14 1 JB two on each side of the web, 6/16/14 SP-2
It was observed that plates were used in lieu of 4x4 angle or bent plate. Per approved
6/12/14 2 JB GROUND is requesting clarification from the EOR. 6/29/14 and revised
SP-2 6/20/14
torched cut beams were found with the beams with no Reentrant(radius) PerAWS
6/12/14 3 JB corners as per AWS D1.1-10 section 5.16,gouges greater than allowed per 6/16/14 D1.1
AWS D1.1-10 section 5.15.4.4 and slag not removed
in regards to note#2 on page SP-4 and of notes on pages,GROUND was not Per Revised
6/12/14 4 JB provided continuous observation while the depositing of welds 6/16/14 SP-2
It is the responsibility of the contractor to schedule our office to perform retesting once the necessary corrective
action has been made or provide our office with documentation that resolves the discrepancy.