Bill - Please see my comments to yours below. I would like to review these issues with you as soon as possible, per my
prior email and voicemail to you of this afternoon. The below position comes as a surprise based on prior discussions with
the Town, including objectives discussed with the replat dating back several months and to last Fall. Most recently I spent
two days in meetings with the Briar Patch owners to meet a deadline of delivering proposed envelope revisions to the
Town, at the Town's request that envelopes be shown on the amended plat (the building envelopes were abandoned by
the prior plat and no longer exist. It is at the Town's request that they be shown on the amended plat for purposes of
defining preferred areas within which development/modification must occur). The stated deadline for defining the
envelopes was last Thursday. We met that deadline by delivering the proposed envelope lines to the Town and have
requested feedback on the proposed configurations, so to come to some reasonable consensus on those locations. I
understood from yesterday's meeting the supplemental information needed to identify the 40% slope areas around the
proposed envelopes, which we are gathering, and we do not oppose alterations reasonably needed to address
neighboring site setback limitations.
We appreciate your efforts in attempting to finalize the proposed plat with the owners. We recognize the challenging
history this site presents and are hopeful to be able to correct and improve on the myriad of issues with this site. All
the owners desire here is to be able to reasonably undertake future modifications to their residences as circumstances
arise, with the Town's review and approval of plans as may be submitted, based either on lot lines governing or
reasonably defined envelopes controlling, whichever the Town prefers. A considerable amount of time and money has
been spent responding to the Town's request, so we ask the Town's cooperation in resolving the problem with us.
As noted above, see our comments below in response to issues raised.
Regards,
Wendy
Wendy R. St. Charles
*********************
Wendy R. St. Charles, Esq.; Sherman & Howard L.L.C.; 1000 S. Frontage Rd. W., Suite 200; Vail, CO 81657 Direct Dial: 970-790-1612; Fax: 970-476-7118; wstcharles@shermanhoward.com
****************************************************************************
THIS MESSAGE IS INTENDED ONLY FOR THE USE OF THE INDIVIDUAL OR ENTITY TO WHICH IT IS ADDRESSED AND MAY CONTAIN INFORMATION
THAT IS PRIVILEGED, CONFIDENTIAL AND EXEMPT FROM DISCLOSURE UNDER APPLICABLE LAW. If the reader of this message is not the intended
recipient, or the employee or agent responsible for delivering the message to the intended recipient, you are hereby notified that any dissemination, distributions,
forwarding or copying of this communication is strictly prohibited. If you have received this communication in error, please notify the sender immediately by e-mail
or telephone at (970) 476-7646 and delete the original message immediately. Thank you.
From: Bill Gibson [mailto:BGibson@vailgov.com]
Sent: Wednesday, July 13, 2011 3:48 PM
To: St. Charles, Wendy R.
Cc: George Ruther; Nina Timm; John Fee
Subject: Residences at Briar Patch - PEC110034
Hey Wendy,
2
Here is a summary of the issues we discussed related to the most recent version of the Fifth Amendment to the
Residences at Briar Patch plat dated yesterday, July 12th 2011:
The proposed amendments to the existing building envelopes and allowable site coverage alter the scope of the
submitted major subdivision application. As stated on the current Residences at Briar Patch plat “major
amendments such as site re‐design, use changes, etc. will required a Planning and Environmental Commission
review.” The public notice for the submitted major subdivision application was published as “amendments to
the existing Parcels A through F and Units 1 through 3 of the Residences at Briar Patch, and the creation of
Parcels G and H … for the purposes of preserving open space and mitigating high severity rockfall
hazards”. Upon further review of the already published public notice language, Staff believes a new public
notice is required for the now proposed amendments to the building envelopes and allowable site coverage
limits. The public notice for the Planning and Environmental Commission’s August 8th hearing will be published
next week, so please contact me by no later than Noon of Monday July 18th if the Home Owner’s Association
would like to pursue these new requests.
[Bill - Consistent with the public notice, under the current proposed plat it is the existing "Parcels A through F" that
are being amended. It is the Town's request to show building envelopes that resulted in the need to determine
configurations for the envelopes. The building envelopes were abandoned by the 4th amended plat, with only
Parcel lines retained. If the building envelopes, which were abandoned by the prior plat, are not created then the
configuration of the envelopes is not an issue. (See page 3 of the 4th amended plat noting abandonment of the
envelopes.)]
Since the most recent version of the proposed final plat was submitted yesterday afternoon, Staff has not had
adequate time to fully evaluate the request for additional site coverage or to form a final recommendation to
the Commission. Please be aware that in 2004 the Town of Vail adopted amendments to the gross residential
floor area (GRFA) regulations which resulted in additional floor area allowances for many residential properties
in Vail. These 2004 Town Code amendments were intended to streamline the GRFA regulations and to facilitate
the construction of below grade floor area. These regulations were not intended to substantively increase the
bulk and mass of buildings in Vail. Therefore, the Town of Vail did not alter any other zoning standards such as
site coverage, landscaping area, setback, building height, etc. to further facilitate the construction of any
increases in allowable GRFA. In 2005, the Town of Vail approved the Fourth Amendment to the Residences of
Briar Patch which increased the allowable GRFA limits prescribed on the plat to create equity between Briar
Patch and other properties in the Residential Cluster District. As with other properties in this district, the Town
of Vail did not approve any amendments to the plat restricted site coverage, landscaping area, setbacks, building
height, etc. to further facilitate the construction of these increases in allowable GRFA.
[Bill - As we confirmed yesterday, the site coverage ratios for this site are substantially below zoning requirements
for cluster developments. Nothing contemplated under the current map approaches the site coverage allowance
permitted in other cluster zoning sites and thus site coverage ratios should not be an issue. Existing site coverage
requirements on the 4th amended plat are simply a reiteration of the Parcel area, with no further relevance, as far
as we can tell.]
The proposed building envelope amendments must comply with the Residential Cluster District setback
requirements prescribed in Section 12‐6E‐6, Setbacks, Vail Town Code. The proposed amendments to the Parcel
A building envelope must be corrected to comply with the 20 foot front setback requirement along Buffer Creek
Road. The proposed amendments to the Parcel E building envelope must be corrected to comply with the 15
foot side setback requirement adjacent to Eiger Chalets.
[Bill - The plat is being revised to address these comments as requested by the Town.]
Pursuant to Section 12‐21‐10, Development Restricted, Vail Town Code “no structure shall be built on a slope of
forty percent (40%) or greater…” Pursuant to Section 12‐21‐12 “slope” is “the gradient of undisturbed land
surface prior to site improvement of a lot, site, or parcel.” The Town’s archive plans for the Residences at Briar
3
Patch identify natural slopes of 40% or greater in close proximity to the existing building envelopes. Some
portions of the proposed amended building envelopes appear to encroach onto these steep grades contrary to
the requirements of Section 12‐21‐10. The proposed amended building envelopes must be corrected to avoid
these natural steep slopes or a variance application must be submitted for review. Topographic survey data
clarifying the location of the natural 40% or greater slopes and the proposed building permit envelopes must be
submitted for review. This survey data must be submitted to my attention at the Community Development
Department by no later than Noon on Monday, July 18th.
[Bill - Per our discussion yesterday, the surveyor is undertaking site work around the proposed envelopes
to evaluate "existing" 40% slope, which is most relevant. The Code obviously contemplates an evaluation of the
40% slope at the time plans are considered. Since we are defining envelope boundaries with existing
development (other than Parcel C), existing site conditions are most relevant, which we know have been
altered per plans previously approved.]
As we discussed, the proposed amendment to the Parcel D building envelope and it’s proximity to the adjacent
ridgeline will be a point of deliberation for the Planning and Environmental Commission. As stated on the
current Residences at Briar Patch plat “the sites are defined by specific building envelopes which are oriented to
place homes into the hillside, not on it.” As we discussed, the proximity of the existing building envelopes to the
ridgelines was an issue of debate during the original review of the building envelope configurations in 1993.
[Bill - We understand the sensitivity to the ridgeline and have attempted to "tuck" the envelope in toward the front
of the residence to address this concern. Slope evaluations will support that the proposed envelope pulls "away"
from the ridge, rather than "toward" the ridge. John Fee is sending you the topo for this site, as discussed.
Photos may also facilitate the perspective, as well, which we are pleased to provide.]
The existing and proposed building envelopes must be staked on site prior to the Planning and Environmental
Commission’s hearing. In order for Staff to understand the scope of the proposed amendments and to form a
recommendation to the Commission, the envelopes must be staked for a Staff site visit to Briar Patch. The
existing and proposed building envelopes must be staked by no later than Noon on Monday, July 18th.
[Bill - The intention is to stake the site, as requested. The surveyor proposed waiting until closer to the PEC
hearing date to be assured stakes remained in place, but we will ask them to get the staking underway right
away.]
If the co‐applicants (Briar Patch Homeowner’s Association and the Town of Vail) wish to proceed with the submitted
major subdivision application to establish Parcel G and to create Parcels A‐F around the existing building envelopes, this
application will be reviewed by the Planning and Environmental Commission on July 25th. If the co‐applicants wish to
pursue amendments to the building envelope and allowable site coverage, the major subdivision application can not be
reviewed earlier than August 8th.
[Bill - If the lot (Parcel) lines can control for future development, there is likely no need to create building envelopes. We
understand the confusion on this issue, based on the inconsistencies in the prior plat, but we are doing our best to work
with the Town to correct the problem, but we must have consistent direction if we are to meet timeline objectives. Please
tell me your first availability to discuss this issue, so that we can obtain clarity as to whether (i) the Town requests we
create envelopes in the areas where Parcels now exist, or (ii) whether the Town prefers we forego envelopes and allow
lot lines to govern. We appreciate the efforts to run this issue to ground definitively, as quickly as possible.]
Please feel free to contact me via email or at 479‐2173 if you have any questions or comments.
[Bill - I left you a voicemail to discuss as soon as you are available.]
Sincerely,
Bill
4
Bill Gibson, AICP
Town Planner
Community Development
970.479.2173
970.479-2452 fax
vailgov.com
twitter.com/vailgov