HomeMy WebLinkAboutVail Lionshead Filing 2 Block 1 Lot 5 Egress AnalysisTown of Vail, Colorado
Dobson Ice Arena
Egress Analysis
FINAL REPORT
ARUP
Town of Vail, Colorado
Dobson Ice Arena
Egress Analysis
May 2001
Ove Arup & Partners Massachusetts, Inc
160 East Main Street, Westborough, MA 01581
Tel +1 508 616 9990 Fax +1 508 616 9991
www.arup.com
Job Number 31761/00
Town of Vail, Colorado Dobson Ice Arena
ARUPDocument Verification
Page 1 of 1
Job title Dobson Ice Arena Job number
31761/00
Document title Egress Analysis File reference
Document ref
Revision
Date
Filename
Dobson - Final Re ort.doc
Draft 1
06/05/01
Description
First draft
Prepared by
Checked by
Approved by
Name
Brian Meacham,
Chris Marrion,
Andrew Hedges
Chris Marrion
Brian Meacham
Signature
Filename
Description
Prepared by
Checked by
Approved by
Name
Signature
Filename
Description
Prepared by
Checked by
Approved by
Name
Signature
Filename
Description
Prepared by
Checked by
Approved by
Name
Signature
Issue Document Verification with Document 2✓
Ova Arup 8 Partners California Lid F8.5
OA Rev 1/00 1 October 2000
Town of Vail, Colorado Dobson Ice Arena
CONTENTS
Page
1. EXECUTIVE SUMMARY 1
2. DISCLAIMER 3
3.
PROJECT DESCRIPTION
4
3.1
Background and Overall Project Scope
4
3.2
Scope of This Effort - Life Safety and Egress Analysis
5
3.3
Form of Analysis
5
4.
FIRE SAFETY GOALS AND OBJECTIVES
7
4.1
Code Objectives - ICC Performance Code
7
4.2
Stakeholder Goals and Objectives
12
4.3
Design Objectives
12
4.4
Performance Criteria
13
5.
DESIGN FIRE SCENARIOS AND TIMES TO HAZARDOUS CONDITIONS
14
5.1
Design Fire Scenarios and Design Fire Curves
14
5.2
Smoke Development and Layer Descent Times
16
6.
EGRESS SCENARIOS AND EGRESS ANALYSIS
17
7.
DESIGN OPTIONS
19
7.1
Fire Initiation and Development
19
7.2
Means Of Escape
21
7.3
Smoke Development And Management
22
7.4
Control of Fire Spread (Compartmentation)
22
7.5
Structural Stability
22
7.6
Fire Detection And Alarm
22
7.7
Fire Suppression
23
7.8
Fire Fighting Facilities
24
7.9
Emergency Lighting, Signage & Power
24
7.10
Fire safety management
24
8.
RESULTS FROM ANALYSES
25
9.
ASSUMPTIONS AND LIMITATIONS
32
9.1
General
32
9.2
Assumptions
32
9.3
Limitations
33
10.
CONCLUSION
34
11.
CODES AND STANDARDS
35
11.1
References
35
11.2
Applicable Codes and Standards
35
Town of Vail, Colorado
1. EXECUTIVE SUMMARY
Dobson Ice Arena
This document summarizes the fire engineering analysis undertaken for the Dobson Ice Arena,
Vail, Colorado, and presents options for attaining an acceptable level of safety that is at least
equivalent to that intended by the Uniform Building Code (UBC) requirements.
The bases for discussing acceptable levels of safety and associated performance criteria for the
Dobson Ice Arena include:
• the ICC Performance Code for Buildings and Facilities, Final Draft (ICC, August, 2000),
• the Uniform Building Code (ICBO, 1997), and
• discussions with and correspondence from Mr. Gary Goodell, Chief Building Official, and
Mr. Michael McGee, Fire Marshal, Town of Vail, Colorado.
The basis for the fire engineering analysis was The SFPE Engineering Guide to Performance -
Based Fire Protection Analysis and Design of Buildings (SFPE, 2000).
The criteria for ascertaining the level of safety acceptable for the Dobson Ice Arena, safe egress
time and time to hazardous conditions, were identified and agreed to in conjunction with the Chief
Building Official and Fire Marshal of the Town of Vail. It is our understanding that this decision
was based on the above documents and on input from Arup Fire. The specific values used for
determining the estimated egress time and the time to hazardous conditions were developed by
Arup Fire. This was done using design fire scenario input and arena use information developed in
concert with the Chief Building Official and Fire Marshal of the Town of Vail, and computer
models selected by Arup Fire.
The design fire scenarios were specified to address a broad range of facility uses, including dinner
dances, merchandise sales events, and concerts. A fire effects model was used to estimate fire and
smoke production from these design fire scenarios and fuel type, quantity and configuration
assumed reasonable for the facility. An egress model was used to estimate likely egress times for
facility occupants given various egress system arrangements, occupant characteristics and design
fire scenarios.
Safe egress time was determined to be available if the model results indicated that occupants
could evacuate the facility prior to hazardous conditions being reached for the design fire and
egress scenarios selected. Hazardous conditions were assumed to be reached when the predicted
smoke layer descended to within 8 feet of floor level. Egress time assumed movement time, as
well as an estimate of pre- movement time.
Once these times were calculated, they were compared against each other to determine whether
the predicted egress time was greater than or less than the onset of hazardous conditions for the
design fires modeled. Where the predicted egress times were greater than the predicted onset of
hazardous conditions, it was determined that changes would be required for the facility to reach
an acceptable level of safety. These changes could range from limiting occupant capacity, to the
addition of more exit capacity, to the addition of a smoke management system to fire safety
management procedures to limit characteristics of the fuel loads.
CAWINDOWS \TEMP\FINAL REPORT.DOC Page I Ove Amp & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado Dobson Ice Arena
Table
1— Summary of Proposed Fire Safety Measures
Fire Protection
Feature
Suggested Supplemental Approaches
Fuel Load
Materials should be selected to limit fire growth rate to "medium" as defined by NFPA 72.
(i.e. max. 300 seconds to reach a 1 MW fire)
• Fuel packages should be separated by a sufficient distance to prevent ignition of two fuel
packages at the same time.
• Fire retardant material should be applied to combustible ceiling components immediately
above pedestrian walkway (mezzanine), or combustible ceiling components in those areas
should be replaced with non - combustible components.
• In addition, one of the following alternatives should be selected in order to either control the
hazard of the materials allowed in the Arena, or to manage the impact of the hazard:
Control Hazard Alternative
• Steady State Fires - Efforts should be made to limit maximum heat release rates to:
Slow /Medium Growth Rate Fires - 2.5 MW per fuel package.
Fast Growth Rate Fires - 1 MW per fuel package
Ultra -Fast Growth Rate Fires - 0.75 MW per fuel package
• Non - Steady State Fires —Where fires are not steady state and meet the above
limitations, then a qualified Fire Protection Engineer should perform an engineering
analysis on the various fuel packages. This would allow the mass of each package to
be evaluated for its contribution to total smoke production in the Arena to determine
limits on how much fuel needs to be consumed to develop a smoke layer that
descends to head level.
• A qualified fire protection engineer should provide written confirmation that an
evaluation of the various hazards specific to individual events has been undertaken,
and that the above criteria are met. (see Appendix D)
Manage Impact of Hazards Alternative
• Where the above limitations are not feasible, other fire protection systems and features
will need to be installed to provide an acceptable level of safety. One alternative noted
is a smoke management system.
Means of Escape
Existing exit door capacity at the main exit and both side exits should be supplemented with
the addition of four 3 -foot doors at the main exit, and two 3 -foot doors at each side exit.
• The fixed seating area should be modified to include 3 -foot wide stairs at both ends of the
fixed seating area (along wall, leading up to 'mezzanine level to exit).
• Additional egress width and openings from the ice rink should be added (as planned in the
renovation).
Smoke
Provided fuel loads and growth rates are limited, either via controls outlined above, by
Management
sprinklers, or by manual suppression, so that tenable conditions are maintained during the
egress period, smoke management is not required.
• If fuel loads and fire growth rates are expected that exceed the above levels, and an
additional margin of safety is desired, addition of a smoke management system is an option.
Compartmentation
In addition to maintaining required ratings on existing assemblies, it is recommended to
enclosing the open side of the refrigeration room with 4 -hour fire - resistive construction,
sealing any existing penetrations and installing 2 sets of 90- minute self - closing doors.
Structural
No modifications or additional features are required in order to provide the desired level of
Elements
life safety. If property protection or business continuity objectives become more important,
additional fire protection measures may be warranted, especially with regard to the roof
structure and material, from interior or exterior exposure fires.
C:\WINDOWS \TEMP \FINAL REPORT.DOC Page 2 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
Dobson Ice Arena
Fire Detection &
a Discussions should be had with the Fire Department regarding procedures for detecting
Alarm
fires as well as transmitting alarm signals and notifying the Fire Department when the beam
type smoke detectors are taken out of service during events due to the potential of false
alarms.
• No modifications or additional features appear to be needed other than those required to
meet code. However, a well designed and intelligible voice paging system is desirable for
facilitating emergency evacuation.
Sprinklers &
0 No modifications or additional features appear to be needed other than those required to
standpipes
meet code. Normal inspection, testing and maintenance is recommended.
Emergency
0 No modifications or additional features appear to be needed other than those required to
Systems
meet code.. Normal inspection, testing and maintenance are recommended.
Fire Safety
0 Fire safety management plan required for (1) each type of major event as well as for special
Management
events that either (2) pose an unusual fire hazard or (3) presents an unusual risk to facility
occupants.
2. DISCLAIMER
This report has been developed in accordance with standards, guidelines, practices and review
procedures generally accepted in the building design and construction, and fire protection
engineering communities. It is based on information provided to Arup Fire that is assumed
accurate and sufficiently complete for the analysis undertaken. Acceptance of this report
indicates acceptance of the information and assumptions that serve as the basis for the analysis.
The concepts outlined in this report assume a complete and operational building, and do not
address protection of the building during construction, renovation or demolition.
The major fire protection features to be incorporated with respect to occupant safety in the event
of a fire are outlined in this report in principle. Property protection, business interruption,
environmental protection and insurance requirements were not specifically considered in the
analysis, as they were not in the proposed scope of work.
Arup Fire makes all reasonable efforts to incorporate practical and advanced fire protection
concepts into its advice. The extent to which this advice is carried out affects the probability of
fire safety. It should be recognized, however, that fire protection and prediction of occupant
behavior is not an exact science. No amount of advice can, therefore, guarantee freedom from
either ignition or fire related damage.
C: \WINDOWS \TEMP\F1NAL REPORT.DOC Page 3 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
3. PROJECT DESCRIPTION
3.1 Background and Overall Project Scope
Dobson lee Arena
The Dobson Ice Arena was reported as being constructed during the time period between 1978
and 1981. The plans that are available are dated March 20, 1978. The facility is owned by the
Town of Vail and operated by the Vail Recreation District.
The building is an earth - sheltered structure with most of its walls and interior areas lying below
grade. The walls are constructed of concrete. The roof structure consists of exposed heavy
timber wooden arches with an exposed wood sub - structure and an untreated wood shake roof
covering. The lower level, with a total floor area of about 31,000 sq. ft., contains an
approximately 17,000- sq. -ft. ice skating rink and a number of accessory office, ticketing,
restroom, locker room and mechanical equipment areas. The upper mezzanine area, with a floor
area of approximately 6,750 sq. ft., includes a bench type seating area and other minor accessory
areas. Total existing floor area for the facility is approximately 37,750 square feet.
Currently, the building is being used as a multi -use facility and, since it is the largest facility of
this type currently available in the town, it is heavily used for a wide variety of events. Uses
range all the way from leisure skating by the public, to children's and adult amateur hockey
practice and games, all with a relatively low occupant load; to rodeos, rock concerts, professional
wrestling and other venues with occupant loads as high as 3 -4,000 persons.
A recent review has highlighted several safety concerns with the Dobson Ice Arena, particularly
with respect to the life safety and egress system (2nd Draft Preliminary Analysis, Dobson Ice
Arena, April 26, 2000, Gary Goodell).
Historical. As originally constructed, the building, with a few exceptions, met UBC
requirements for a facility housing up to 1,000 persons. If it were occupied by no more than
1,000 persons, it would have been permitted to be constructed as Type III 1 -Hour
construction, which would permit the exposed wooden roof structure, and only the three (3)
existing separate exits would be required. The existing non -fire- retardant - treated wood shake
roof would not have been permitted, and there would still be issues with the number of aisles
provided in the seating area and whether or not a second exit would be required from the
refrigeration room.
2. Roof Structure. The roof structure does not meet the requirements for non - combustible
materials and a protected, fire- resistive assembly as is required for Type I F.R. or Type II F.R.
construction.
3. Roof coverinl?. The untreated wood shake roof covering materials do not meet the
requirements for roof coverings for the required Class `B" fire- resistive roof assembly.
4. Refrigeration Room. The refrigeration room may require a second exit door.
5. 4" Exit. Occupancy by more than 1,000 persons requires that a fourth separate exit be
provided, and the current facility has only three separate exits.
6. Interior Means of EUM. The interior means of egress system is inadequate, and does not
meet minimum code requirements for more than 1,000 persons, especially if a large number
of people are present in the ice rink area. The main problems are only one means of egress
CAWINDOWS \TEMP\FINAL REPORT.DOC Page 4 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
3.2
3.3
Dobson Ice Arena
from the ice rink area (the main entrance) and highly inadequate exit widths for the 4 existing
stairs to allow for emergency egress between the lower level and the upper level.
7. Aisles. Not enough stair aisles are provided in the upper level seating area.
Scope of This Effort — Life Safety and Egress Analysis
As part of proposed renovations to the Dobson Ice Arena, and due to the increased occupancy
loads currently being experienced, it was requested that a life safety and egress system analysis be
undertaken and that a life safety and egress system design strategy be developed. Given the
nature of the facility and the background information above, it was requested that the life safety
and egress system analysis use a performance -based approach.
The stated aim of this effort is to identify options for attaining an acceptable level of safety
that is at least equivalent to minimum Uniform Building Code requirements for the Dobson
Ice Arena with respect to emergency egress.
The bases for discussing acceptable levels of safety and associated performance criteria for the
arena included:
• the ICC Performance Code for Buildings and Facilities, Final Draft (ICC Performance Code),
• the Uniform Building Code (UBC), and
• discussions with and correspondence from Mr. Gary Goodell, Chief Building Official, and
Mr. Michael McGee, Fire Marshal, both of the Town of Vail, Colorado.
The basis for the fire engineering analysis was The SFPE Engineering Guide to Performance -
Based Fire Protection Analysis and Design of Buildings (the SFPE Guide).
The rationale for using the ICC Performance Code and the SFPE Guide was to provide structure
to the alternate analysis and design allowed under the alternate methods and materials clause of
the UBC (Article 104.2.8). These documents were selected as representing the building code
community's direction for future building codes and the fire protection engineering community's
consensus on appropriate engineered fire protection methodology.
It is not within the scope of this effort to provide detailed designs for any of the life safety and
egress options identified.
Form of Analysis
Although the ICC Performance Code and the SHE Guide provide similar requirements for
documentation of performance -based designs, the analysis and design process for fire and life
safety is more completely outlined in the SFPE Guide. As a result, this report follows the process
for performance -based fire safety analysis and design of buildings as outlined in the SFPE Guide.
As identified in the SFPE Guide, it is important to understand the form (i.e., deterministic or
probabilistic) and level (i.e., component, system or building) of analysis selected for the project.
For this effort, the form of analysis for the fire engineering assessment is a deterministic analysis
based on "worst credible" fire scenarios for the various areas based on information provided by
the design team regarding use of the space. The basis of the analysis was to evaluate whether
occupants can evacuate safely prior to hazardous conditions being reached. As part of the
analysis, it was necessary to consider two conditions:
Time to the onset of hazardous conditions
(e.g. smoke layer level, visibility, etc. versus time)
CAWINDOWS \TEMPTUNAL REPORT.DOC Page 5 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado Dobson Ice Arena
• Time to evacuate the occupants in the building.
The analysis uses fire and egress computer models, fire protection handbooks and other relevant
methods as appropriate. The analysis takes into consideration the interaction between the
different fire protection systems and components. A graphical representation of the available safe
egress time is provided below.
Pre - movement
ion
Ignition I Alarm or cue
Evacuation
se
Fire development 1 010
Figure 1. Time to Hazard Development vs. Time Required for Safe Egress
The level of analysis selected for this effort is a comparative, system -level analysis that considers:
(1) UBC requirements
(2) The ICC Performance Code levels of tolerable impact, and
(3) Performance criteria selected for compliance with performance objectives.
As part of the analysis, fire effects modeling and egress modeling were used. The fire effects
modeling was used to estimate fire and smoke production from various fire scenarios deemed
reasonable for the facility. The egress modeling was used to estimate likely egress times for
various egress system arrangements and fire scenarios. Table 2 provides a summary listing of the
methods and models used for comparative analysis. Detailed explanations, description of the
analyses and assessment of results are provided in the Appendices to this report.
Table 2 — Analysis Methods
Fire Protection Feature
Methods ..
Hazard Development
The computer model T -ZAM (spreadsheet -based calculation tool
based on equations published in NFPA 92B and CIBSE TM19)
Smoke Management
• NFPA 92B Guide for Smoke Management Systems in Malls, Atria, and
System
Large Areas
• CIBSE TM 19: "Relationships for Smoke Control Calculations"
Technical Memoranda TM19:1995
Egress
Methods (hand calculations) as published in the SFPE Handbook of
Fire Protection Engineering
• Simulex Evacuation Model
Sprinkler Activation
DETACT (NIST)
C: \WINDOWS \TEMPT1NAL REPORT.DOC Page 6 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
4. FIRE SAFETY GOALS AND OBJECTIVES
Dobson Ice Arena
There maybe many fire and life safety goals and objectives for any project— some of which may
be competing. As such, it is necessary to establish the pertinent baseline goals and objectives and
then seek agreement on those to be used in the fire and life safety analysis for a specific project.
For this project, it has been determined to use the goals and objectives identifying in the ICC
Performance Code, as well as those of the Town of Vail Building and Fire Departments.
4.1 Code Objectives — ICC Performance Code
The ICC Performance Code identifies a number of functional and performance objectives that
must be met. For this project, relevant objective can be found in Chapters 3, 17, 18 and 19 (of the
ICC Performance Code).
4.1.1 Use and Design Performance Levels
Starting with Chapter 3, Arup Fire has identified the Dobson Ice Arena as an A -4 Occupancy.
Given the nature of the building use, some percentage of the occupants are assumed to be
consuming alcohol, loud and distracting sounds are expected to be present, and flashing lights are
expected to be present (from ICC Performance Code, Appendix A). These factors will be
incorporated into design and protection system assumptions and bounding conditions.
As an A -4 Occupancy, the Dobson Ice Arena is designated as being in Performance Group III
(Table 303.1). In brief, this means that for the code - mandated level of performance:
• Small and Medium design events may result in a Mild level of damage;
• Large design events may result in a Moderate level of damage; and
• Very Large design events may result in a High level of damage.
The relationship between the Design Hazard Events, Levels of Tolerable Damage and Design
Performance Levels is illustrated in the following graphic (from the ICC Performance Code,
Chapter 3).
C :\WINDOWS \TEMP,FINAL REPORT.DOC Page 7 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail. Colorado
Dobson Ice Arena
Below are excerpts from the ICC Performance code that provide further detail on the levels of
tolerable damage and magnitude of design events.
4.1.2 Levels of Tolerable Damage
The following description of Levels of Tolerable Damage is excerpted from Chapter 3 of the ICC
Performance Code:
304.2 There are four design performance levels defined in terms of tolerable limits of impact to
the building or facility, its contents, and its occupants: Mild, Moderate, High and Severe.
304.2.1 Mild impact. The tolerable impacts of the design loads are assumed as follows:
304.2.1.1 There is no structural damage and the building or facility is safe to occupy.
304.2.1.2 Nonstructural systems needed for normal building or facility use and
emergency operations are fully operational.
304.2.1.3 Injuries to building or facility occupants are minimal in numbers and minor
in nature. There is a very low likelihood of single or multiple life loss.'
304.2.1.4 Damage to building or facility contents is minimal in extent and minor in
cost.2
304.2.1.5 Minimal hazardous materials are released to the environment.
304.2.2 Moderate impact. The tolerable impacts of the design loads are assumed as follows:
304.2.2.1 There is moderate structural damage which is repairable; some delay in re-
occupancy can be expected.
Applies only to hazard — related applied loads.
2 The nature of the applied load (i.e., fire hazard) may result in high levels of expected injuries and damage in localized areas, whereas the balance of
the areas may sustain less injuries and damage.
C: \WINDOWS \TEMP \FINAL REPORT.DOC Page 8 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
INCREASING LEVEL OF PERFORMANCE
PERFORMANCE
GROUPS
Performance Performance
Performance
Performance
Grou I Grou II
Group III
Group IV
VERY
1—
LARGE
HIGH
R
MODEATE
Z
>
T
(Very Rare)
w
T
W
o
T
C
LU
T
LARGE
HIGH
MODERATE
MILD
G
o
T
(Rare)
Z
T
LU
z
C7
T
nU1
W
T
MEDIUM
HIGH
MODERATE
MILD
MILD
H
0
T
(Less
Z
T
Frequent)
C7
a
a
UJ
c
z
SMALL
MODERATE
MILD
MILD
MILD
(Frequent)
Below are excerpts from the ICC Performance code that provide further detail on the levels of
tolerable damage and magnitude of design events.
4.1.2 Levels of Tolerable Damage
The following description of Levels of Tolerable Damage is excerpted from Chapter 3 of the ICC
Performance Code:
304.2 There are four design performance levels defined in terms of tolerable limits of impact to
the building or facility, its contents, and its occupants: Mild, Moderate, High and Severe.
304.2.1 Mild impact. The tolerable impacts of the design loads are assumed as follows:
304.2.1.1 There is no structural damage and the building or facility is safe to occupy.
304.2.1.2 Nonstructural systems needed for normal building or facility use and
emergency operations are fully operational.
304.2.1.3 Injuries to building or facility occupants are minimal in numbers and minor
in nature. There is a very low likelihood of single or multiple life loss.'
304.2.1.4 Damage to building or facility contents is minimal in extent and minor in
cost.2
304.2.1.5 Minimal hazardous materials are released to the environment.
304.2.2 Moderate impact. The tolerable impacts of the design loads are assumed as follows:
304.2.2.1 There is moderate structural damage which is repairable; some delay in re-
occupancy can be expected.
Applies only to hazard — related applied loads.
2 The nature of the applied load (i.e., fire hazard) may result in high levels of expected injuries and damage in localized areas, whereas the balance of
the areas may sustain less injuries and damage.
C: \WINDOWS \TEMP \FINAL REPORT.DOC Page 8 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
Dobson Ice Arena
304.2.2.2 Nonstructural systems needed for normal building or facility use are fully
operational, although some cleanup and repair may be needed. Emergency systems
remain fully operational.
304.2.2.3 Injuries to building or facility occupants may be locally significant, but
generally moderate in numbers and in nature. There is a low likelihood of single life
loss, very low likelihood of multiple life loss."'
304.2.2.4 Damage to building or facility contents may be locally significant, but is
generally moderate in extent and Cost. 1, 2
304.2.2.5 Some hazardous materials are released to the environment, but the risk to
the community is minimal. No emergency relocation is necessary.
304.2.3 High impact. The tolerable impacts of the design loads are assumed as follows:
304.2.3.1 There is significant damage to structural elements but no large falling
debris; repair is possible. Significant delays in re- occupancy can be expected.
304.2.3.2 Nonstructural systems needed for normal building or facility use are
significantly damaged and inoperable; egress routes may be impaired by light debris;
emergency systems may be significantly damaged, but remain operational.
304.2.3.3 Injuries to building or facility occupants may be locally significant with a
high risk to life, but are generally moderate in numbers and nature. There is a
moderate likelihood of single life loss, with a low probability of multiple life loss.', 2
304.2.3.4 Damage to building or facility contents may be locally total and generally
significant.', 2
304.2.3.5 Hazardous materials are released to the environment with localized
relocation needed for buildings and facilities in the immediate vicinity.
4.1.3 Magnitude of Design Fire Events
The following objectives and requirements for Magnitude of Design Fire Events are excepted
from Chapter 17 of the ICC Performance Code:
1701.3.15 Magnitudes of design fire events shall reflect the ignition, growth and spread potential
of fires and fire effluents that can be reasonably expected to impact on buildings as designed or
constructed.
1701.3.15.1 Magnitudes of design fire events are described in terms of the potential spread of
fire and fire effluents given the proposed design, arrangement, construction, furnishing and
use of a building.
1701.3.15.2 Magnitudes of design fire events shall be defined as Small, Medium, Large and
Very Large, where the quantification of the design fire event is a function of building use and
associated Performance Group.
1701.3.15.3 Quantification of the magnitudes of design fire events shall be based on
engineering analyses of potential fire scenarios that can be expected to impact a building
through its intended life. For each design fire scenario considered, the analyses shall include
the ignitability of the first item, the peak heat release rate of the item first ignited, the rate of
heat release and expected fire growth, and the overall fuel load, geometry and ventilation of
the space and adjoining spaces.
CIWINDOWS \TEM"FNAL REPORT.DOC Page 9 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
Dobson Ice Arena
1701.3.15.3.1 When determining (assigning) the magnitude of a design fire event, the
physical properties of fire and its effluents shall only be considered in terms of how
they impact the tolerable levels of damage. The magnitude of the fire event need not
be characterized solely on the basis of the physical size of the fire in terms of its heat
release rate and smoke production rate.
1701.3.15.3.2 Multiple design fire scenarios, ranging from Small to Very Large
design fire events, must be considered to ensure that associated Levels of Tolerable
Damage are not exceeded as appropriate to the Performance Group.
1701.3.15.3.3 The development of design fire scenarios shall consider the use of the
room of fire origin and adjoining spaces in terms of impact of occupants, property
and community welfare.
1701.3.15.3.4 Justification of the magnitudes of design fire events and design fire
scenarios shall be part of the analysis prepared by the design professional, and shall
consider the reasonableness, frequency and severity of the design fire event and
design fire scenarios.
4.1.4 Management of People
The following objectives and requirements for Management of People are excepted from Chapter
17 of the ICC Performance Code:
1801.1 Objective. To promote safe practices and actions of people, and to assure that the actions
and practices of people, that are components of a design, are maintained.
1801.2 Functional statements.
1801.2.1 Through training and education, ensure that people possess the necessary skills and
implement the appropriate actions to prevent fires or other emergencies as appropriate to the
design performance level determined in Chapter 3.
1801.2.2 Through training and education, ensure that people possess the necessary skills and
implement the appropriate actions during a fire or other emergency as appropriate to the
design performance level determined in Chapter 3.
1801.3 Performance requirements
1801.3.1 Provide appropriate information so that occupants and staff can assist in identifying
hazards.
1801.3.2 Develop procedures, and conduct training so that occupants and staff can take
appropriate actions to prevent fires or other emergencies.
1801.3.3 Provide adequate information so that occupants and staff know the appropriate
actions in the event of a fire or other emergency.
1801.3.4 Develop procedures, and conduct training so that occupants and staff can take the
appropriate actions in the event of a fire or other emergency.
1801.3.5 Provide adequate information so that all persons involved in the handling and use of
hazardous materials know the appropriate actions and safeguards for such materials.
1801.3.6 Develop procedures so that all persons involved in the handling and use of
hazardous materials will take the appropriate actions in the event of an emergency.
1801.3.7 Provide the administrative controls to assure that the identified hazards are
controlled, procedures are followed, and training occurs.
CAWINDOWSUEMPTINAL REPORT.DOC Page 10 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
Dobson Ice Arena
1801.3.8 Provide the administrative controls to evaluate and validate all policies, procedures
and training, for occupants and staff. Whenever new occupants, staff, equipment, materials, or
processes are introduced; the administrative controls shall provide for appropriate education
and training.
1801.3.9 Assure that all aspects of a performance —based design that rely on a response or
action from either occupants or staff are clearly identified and documented and that the
necessary training and administrative controls are in place and maintained so that the response
or action is appropriate.
4.1.5 Means of Egress
The following objectives and requirements for Means of Egress are excepted from Chapter 17 of
the ICC Performance Code:
1901.1 Objective. To protect people during egress and rescue operations.
1901.2 Functional statement. Enable occupants to exit the building, facility and premise, or
reach a safe place as appropriate to the design performance level determined in Chapter 3.
1901.3 Performance requirements.
1901.3.1 The construction, arrangement and number of means of egress, exits and safe places
for buildings shall be appropriate to the travel distance, number of occupants, occupant
characteristics, building height, and safety systems and features.
1901.3.2 Means of egress shall be clearly identified, provided with adequate illumination, and
easy and safe to use.
1901.3.3 Means of egress shall provide an unobstructed path of travel from each safe place to
not less than one exit.
1901.3.4 Each safe place shall provide adequate protection from untenable conditions, an
appropriate communication system and adequate space for the intended occupants.
1901.3.5 Means of egress shall enable reasonable use by the occupants in the building with
due regard to human biomechanics and expectation of consistency.
1901.3.6 Suitable means of egress shall be provided in satisfactory arrangement throughout
all buildings, facilities and premises, regardless of when it was constructed, based upon the
number and character of occupants, length of travel, provision of existing alternate paths, time
line of emergency detection and response, risk level, time to exit and safety systems provided.
1901.3.7 Means of egress shall be maintained without obstructions or reductions in capacity
that would hinder the ability of the occupants to safely egress.
1901.3.8 Means of egress shall be readily identifiable. Buildings shall be operated and
maintained in a manner that does not interfere with the identification of exits.
1901.3.9 Means of egress shall be maintained and operated in such a manner to ensure that all
egress facilities are readily openable, and available without special knowledge or effort
consistent with the use or occupancy characteristics.
1901.3.10 Means of egress shall be maintained and operated in such a manner to ensure that
adequate lighting to facilitate safe egress is available.
CAWINDOWSUEMPT NAL REPORT.DOC Page I I Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
4.2
4.3
Stakeholder Goals and Objectives
Dobson Ice Arena
An important step in the performance -based process is to determine the fire safety goals and
objectives of interest to the stakeholders, and to prioritize them for the specific project being
addressed. The primary stakeholders that have been identified for this project include:
• Vail Recreation District —Jim Heber, Dobson Arena Manager
• Vail Recreation District — Dennis Jerger, Dobson Arena Facility Superintendent
• Town of Vail — Gary Goodell, Chief Building Official
• Town of Vail — Michael McGee, Fire Marshal
Based on discussions with the stakeholders, and review of background materials for this project, it
is the understanding of Arup Fire that the primary fire safety goal of this project is the following:
• Provide an acceptable level of life safety for the building occupants and emergency
responders (minimize fire- related injuries and prevent undue loss of life).
Secondary goals that have been identified include:
• Minimize impact of the fire protection systems on the existing building features and envelope,
• Provide a cost effective fire safety solution,
• Provide property protection (contents and structure), and
• Minimize business interruption.
It should be noted however that the property protection and business interruption goals and
objectives have not been analysed in a quantitative manner, but will be provided to some degree
when the life safety goals are addressed.
Design Objectives
A design objective is a stakeholder objective that is translated into values that can be quantified in
fire protection engineering terms and from which performance criteria can be developed.
Quantification can be in deterministic or probabilistic terms. The process of developing
quantifiable design objectives focuses on targets, where the targets may be the structure,
compartment, process, occupant, etc, that are being protected to meet a specific stakeholder
objective.
For this project, it was proposed that the primary design objectives be established in terms of time
to reach hazardous conditions and available safe egress time. By defining the design objectives
in these terms, specific performance criteria can be developed against which design options can be
evaluated on their ability to meet the code and stakeholder objectives for life safety. In addition,
by using the time to reach hazardous conditions, the secondary objectives of property protection
and business continuity can be assessed as well.
With respect to the primary objective of life safety, the hazardous conditions will be viewed in
terms of tenable conditions. Although several approaches are theoretically possible for assessing
tenability, the variability and uncertainty associated with the use of the Dobson Arena, with the
population that may be present, and with the available analysis tools, it has been agreed to focus
on two fundamental parameters:
CAWINDOWS \TEMP\FINAL REPORT.DOC Page 12 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
4.4
• smoke layer height
• temperature
Dobson Ice Arena
By focusing on these two parameters, the issues of visibility (travelling in smoke), species impact
(smoke intake to the body), and radiant heat flux to the skin (from the hot upper layer) are
accounted for.
Performance Criteria
4.4.1 Life Safety Criteria
Given the above design objectives, the following performance criteria have been established:
• For the period of time that the hot layer remains higher than 8 feet (2.5m) above the level of
egress, a tenability temperature threshold of 165 °F (74 °C) will be used.
As noted above, no performance criteria are set for toxicity. This is in line with the view that
limiting conditions for toxic products (asphyxiants and irritants) are unlikely to be exceeded if the
smoke layer does not descend into the path of travel. Toxicity calculations are also reliant on the
nature of the burning fuel. Results from calculations such as these therefore need to be treated
with caution, as uncertainty about the chemical composition of the fuel, and of individual
response to irritants leads to a potentially wide range of analysis results.
The temperature criterion is suggested based on discussion provided in the text, Introduction to
Performance -Based Fire Safety, by Custer and Meacham (NFPA, 1997). The layer height of 8
feet above floor level is more conservative than the 5.5 feet or 6 feet sometimes used in
engineered designs, thus providing for a factor of safety to account for uncertainty in the
calculations and actual fire conditions.
The above performance criteria form the basis of this analysis.
4.4.2 Property Protection and Business Continuity Criteria
Property protection is typically achieved through material control, fire separation, smoke control,
and fire suppression systems. Business continuity is typically achieved through the same criteria,
although sometimes at different levels.
As property protection and business continuity are secondary objectives, no specific criteria have
been established. Rather, the approach taken is to assume that if the life safety criteria have been
met, the associated property protection and business continuity objectives will be met as well.
C: \WINDOWS \TEMPT1NAL REPORT.DOC Page 13 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
5.
5.1
Dobson Ice Arena
DESIGN FIRE SCENARIOS AND TIMES TO HAZARDOUS CONDITIONS
Design Hazard Events, Design Fire Scenarios and Design Fire Curves
As defined in the SFPE Guide, design fire scenarios describe possible fire events from ignition
or established burning through extinguishment or burn -out. Design fire scenarios are a
representative subset of all possible fire scenarios, typically selected to represent "worst credible"
events and scenarios that will challenge the fire protection systems. For design purposes, design
fire scenarios are equivalent to design hazard events as defined in the ICC Performance Code.
In brief, the design fire scenarios /design hazard events describe the fire /people/buil ding
interaction. If proposed fire safety features limit fire damage to an acceptable level for the design
scenarios /events considered, then the design options are considered acceptable.
Referring to performance matrix and ICC Performance Code objectives discussed in Section 4,
the primary objectives for the Dobson Arena are to limit design hazard events to Medium, thus
limiting the tolerable level of damage to Mild.
Once a set of design fire scenarios /design hazard events are established, design fire curves are
developed to represent the development and growth of the fire that is anticipated by the design
fire scenario. Together, design fire scenarios and design fires are used to evaluate possible design
options to determine if the performance criteria are met.
Through correspondence from and discussions with the project stakeholders, it was determined
that the design fire scenarios /design hazard events of concern relate to various configurations of
the Dobson Arena for a range of events involving large numbers of people. The primary
scenarios of concern were narrowed down to the following: hockey game, concert events, the
annual Ski Swap, dinner dances, and conferences and conventions.
The approach taken to address design hazard events, design fire scenarios, and design fire curves
is as follows.
1. It is assumed from the Performance Matrix (ICC Performance Code, Chapter 3), that the
target level of tolerable damage is Mild, which should not occur for Small or Medium fire
hazard events. Although it is recognized that larger events could occur, they would likely
occur as a result of larger than anticipated fuel loads, fire protection system failure, over
capacity of occupant load, or similar feature outside of the bounding conditions for the design.
2. Given (1), the aim is to demonstrate a high probability of success for the fire protection
system to limit the tolerable level of damage to Mild for the range of fire loads, occupant
loads and fire protection systems considered.
3. Once bounding conditions are identified for the above, indicate bounding conditions that must
be maintained to achieve the desired performance, indicate the potential impact of larger fires,
and suggest options for mitigating the larger fires that could result.
Table 4 below illustrates various event scenarios, including postulated occupant loads and
potential fire scenarios, as determined via discussion with the project stakeholders. The scenarios
were evaluated for the design fire events listed. These design hazard events were translated into
design fire curves of Slow, Medium and Fast, as described in Table 5. Later in the report, it is
illustrated how a more severe fire, and Ultra -Fast fire, impacts the Dobson Arena, and what
additional fire protection features may be considered if warranted.
C \WIND0WS \TEMPT1NAL REPORT.DOC Page 14 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
Table 4 - Design Fire Scenarios
Dobson Ice Arena
Scenario
Event
Population
Number
Fixed
Rink Area Total
Design Hazard Event
Seating
Up to 400, including
Fast growing fire in ancillary
Hockey
players, officials,
space (i.e. concession area)
1
Game
800
people standing 1200
around in other areas
Medium fire event
Concert -
Fast growing fire on stage.
2
Open Rink
900
2100
3000
Large fire event.
Floor
Concert or
Fast growing fire on stage.
3
Convention -
Seating on
800
1800
2600
Large fire event.
Rink Floor
Fast growing fire on rink floor.
4
Ski Swap
400
800
1200
Large fire event.
Dinner
Medium growth rate fire on table
ignited by candle.
5
Dance, 6'
0
800
800
round tables
Small fire event.
Dinner
Medium growth rate fire on table
Dance,
ignited by candle.
6
buffet, long
0
1200
1200
tables
Small fire event.
The above scenarios were selected primarily based on the following factors:
• Differences in occupant loading,
• Difference in fire hazard(s),
• Differences in seating arrangements, and
0 Differences in egress arrangements.
Q\WINDOWS \TEMP\PINAL REPORT.DOC Page 15 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
5.2
Dobson Ice Arena
The fuels, fuel characteristics, and fuel arrangements used as the basis for developing the design
fire curves are detailed in Appendix A. It was assumed that the ventilation conditions were
constant for the main arena area in all cases. A summary of the design fire curves is provided in
Table 5.
Table 5 -Design Fires
Scenario
Fire Location
Fire Growth
Max AnticipatedHRR
Plume Type
Ancillary space (i.e.
Rate
Fire size determined by
1
concession area)
Fast
sprinkler response.
Sprinklers assumed to
Axi- symmetric
Medium fire event
limit further fire growth.
Fire size determined by
2
On stage.
Fast
sprinkler response.
Axi- symmetric
Sprinklers assumed to
limit further fire growth.
Fire size determined by
3
On stage
Fast
sprinkler response.
Sprinklers assumed to
Axi- symmetric
limit further fire growth.
Fire size determined by
4
On rink floor
Fast
sprinkler response.
Sprinklers assumed to
Axi - symmetric
limit further fire growth.
Fire size determined by
5
On table on rink floor
Medium
sprinkler response.
Sprinklers assumed to
Axi- symmetric
limit further fire growth.
Fire size determined by
6
On table on rink floor
Medium
sprinkler response.
Sprinklers assumed to
Axi- symmetric
limit further fire growth.
Smoke Development and Layer Descent Times
Given the design fire curves identified above, an analysis of smoke production, smoke filling, and
smoke layer descent times was undertaken. This analysis is an essential component of the time to
hazardous conditions assessment.
The smoke production correlations contained within CIBSE Guide TM 19, and NFPA 92B - Guide
for Smoke Management Systems in Malls, Atria and Large Areas ", National Fire Protection
Association were used to analyze the development of the descent of the upper smoke layer, as
well as the temperature. The results of this analysis are contained in Appendix C.
C: \WIND0WS \TEMP\F1NAL REPORT.DOC Page 16 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
6. EGRESS SCENARIOS AND EGRESS ANALYSIS
Dobson Ice Arena
Similar to the development of design fire scenarios and smoke filling times to determine the time
to hazardous conditions, the development of egress scenarios and time to evacuation are essential
components of the analysis.
Much like the design fire scenario development, the egress scenario development focused on a
few representative scenarios that covered a range of uses for the Dobson Arena. The primary
scenarios of concern were determined to be the following.
Table 6a — Egress Scenarios
Scenario
Number
Event
Fixed
Population
Rink Area
Total
Seating
Up to 400, including
1
Hockey Game
800
players, officials, people
1200
standing around in other
areas
2
Concert, Open Rink
900
2100
3000
Floor
Concert or
3
convention - Seating
800
1800
2600
on Rink Floor
4
Ski Swap
400
800
1200
5
Dinner Dance, 6'
0
800
800
round tables
6
Dinner Dance,
0
1200
1200
buffet, long tables
As noted before, the above scenarios were selected primarily based on the following factors:
• Differences in occupant loading,
• Difference in fire hazard(s),
• Differences in seating arrangements, and
• Differences in egress arrangements.
As noted in the SFPE Guide and other references, calculation of egress time should include pre -
movement time (time to see or hear alarm, decide that there is an emergency, and decide to move)
and movement time. This means that the analysis must consider fire detection (by devices or by
people) and alarm signalling (by devices or by people), as well as expected travel time.
C: \WINDOWS \TEMPT[NAI REPORT.DOC Page 17 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
Dobson Ice Arena
Based on discussions with the stakeholders, including the facilities people, it is assumed that staff
response will be immediate upon alarm, meaning that pre- movement time after the fire alarm has
sounded will be minimal. Example recognition times are given in DD240 — Fire Safety
Engineering In Buildings. For notification systems using non -voice type systems times of greater
than 4 minutes are given for occupancies where people are awake and predominantly familiar
with the building, alarm and evacuation procedures. For occupancies where occupants are awake,
but may be unfamiliar with the building, alarm system and evacuation procedures a recognition
time of greater than 6 minutes is stated. As the Arena is open with exits visible from most areas,
where a fire starting in the public area should be visible to most people, and it is anticipated that
the response time will be quite minimal, a 4 minute pre- movement time is used.
Given the design fire and egress scenarios outlined above, as well as the assumption that egress
begins soon after alarm, egress times have been estimated. The following table summarizes the
exit times for the various fire scenarios, as assessed using `hand calculations' from the SFPE
Handbook of Fire Protection Engineering, and using the computer based egress model Simulex.
Additional details are contained in Appendix B.
Table 6b — Calculated Egress Time Summary
Note that the hand calculations assume the occupant density at the doors is 10 square feet per
person, queue time is greater than travel time to an exit, and that occupants in the seats use the
mezzanine exits only, while the occupants on the lower level use the main exits only.
In addition to the primary egress calculations, egress estimations were also developed for
situations in which an exit is assumed to be blocked. Simulex models showed that for a blockage
of the front door during scenario 2, egress time was calculated to be 9 minutes.
C: \WINDOWS \TEMP\FINAL REPORT.DOC Page 18 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Hand Calculations'
Egress
Scenario
Detection
Time (min)
Pre - movement
Time (min)
Egress Time
(min)
Total Time
(min)
Egress Time
(min)
Total Time
(min)
Note that the hand calculations assume the occupant density at the doors is 10 square feet per
person, queue time is greater than travel time to an exit, and that occupants in the seats use the
mezzanine exits only, while the occupants on the lower level use the main exits only.
In addition to the primary egress calculations, egress estimations were also developed for
situations in which an exit is assumed to be blocked. Simulex models showed that for a blockage
of the front door during scenario 2, egress time was calculated to be 9 minutes.
C: \WINDOWS \TEMP\FINAL REPORT.DOC Page 18 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
7. DESIGN OPTIONS
Dobson Ice Arena
The following sections outline the design options that have been identified to address the design
fire scenarios. The various design options identify the fire protection measures required to meet
with the performance requirements and performance criteria. In some cases, the design options are
management related, such as "make the building non - smoking," whereas other design options
related to fire protection features or systems. In some cases the design features will be in place,
and in other places they will be new.
The following sections are formatted in such a way to identify the control mechanism (title), the
objective for implementing the control mechanism (objective), and the related design option or
feature (design feature).
7.1 Fire Initiation and Development
7.1.1 Fire Initiation
Objective
Reduce the frequency of ignitions.
Design Features
• Require that the Dobson Arena be `non- smoking' throughout.
• Undertake routine maintenance of electrical systems, wiring and components.
• Practice good housekeeping measures, including routine cleaning and no interior storage of
trash.
• Minimize the storage of highly combustible material. In specific, store flammable liquids in
appropriately rated dispensing containers (not to exceed fire code limits) and in appropriately
rated storage cabinets (e.g., where the Zamboni is stored).
7.1.2 Control Fire Development
Obiec tive
Reduce the rate of fire development and resulting smoke and heat production.
Design Features
• Interior finishes:
- Wood lattice ceiling above pedestrian walkway:
- Although the ceiling structure is protected by automatic sprinklers, there is a concern
that a fire could develop in the lattice in such a place that sprinkler effectiveness is
suspect. As a result, it is suggested that some form of fire retardant be used on the
lattice above the pedestrian walkway. Options include:
- (1) coat with fire retardant material
- (2) replace with fire resistant material
• Construction elements:
- Timber beams:
CAWfNDOWS \TEMP\FINAL REPORT.DOC Page 19 Ove Amp & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
Dobson Ice Arena
- The massive timber beams would not be expected to ignite easily or burn rapidly
unless there were a significant fire. In addition, the ceiling structure is protected by
automatic sprinklers. For these reasons, no additional protection is suggested.
• Automatic sprinklers:
- Provided throughout.
• Combustible loads (i.e., fuel packages):
- Limits on maximum heat release rates and fire growth rates are desirable. Although this
cannot be achieved in all cases, limitations can be imposed on fuel loading for convention
center and display type arrangements.
- Limits can also be imposed through combustibility and heat release rate limitations on
typical furnishings and contents, such as tables, chairs, tablecloths, and the like.
Following requirements set forth in the UBC is acceptable for control of such fuel loads.
- Associated fire growth rate and fuel load limitations are suggested as follows:
• Materials should be selected to limit fire growth rate to "medium" as defined by
NFPA 72. (i.e. max. 300 seconds to reach a 1MW fire)
• Fuel packages should be separated by a sufficient distance to prevent ignition of
two fuel packages at the same time.
• Fire retardant material should be applied to combustible ceiling components
immediately above pedestrian walkway (mezzanine), or combustible ceiling
components in those areas should be replaced with non - combustible components.
• In addition, one of the following alternatives should be selected in order to either
control the hazard of the materials allowed in the Arena, or to manage the impact
of the hazard:
Control Hazard Alternative
• Steady State Fires - Efforts should be made to limit maximum heat release
rates to:
Slow/Medium Growth Rate Fires - 2.5 MW per fuel package.
Fast Growth Rate Fires - 1 MW per fuel package
Ultra -Fast Growth Rate Fires - 0.75 MW per fuel package
Non - Steady State Fires — Where fires are not steady state and meet the above
limitations, then a qualified Fire Protection Engineer should perform an
engineering analysis on the various fuel packages. This would allow the mass
of each package to be evaluated for its contribution to total smoke production
in the Arena to determine limits on how much fuel needs to be consumed to
develop a smoke layer that descends to head level.
Manage Impact of Hazards Alternative
• Where the above limitations are not feasible, other fire protection systems
and features will need to be installed to provide an acceptable level of safety.
One alternative noted is a smoke management system.
- As an accurate assessment of the combustible loading present at the various events is
critical to determining whether the Arena's goals and objectives will be met, it is
recommended that a process be developed with the local Authorities and put in place to
CAWINDOWS \TEMPTINAL REPORT.DOC Page 20 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado Dobson Ice Arena
conduct an evaluation of combustible materials for each event. It is recommended that
this process involve a review by a qualified Fire Protection Engineer of the combustible
materials and provide a written evaluation to all stakeholders for each event as to:
- The maximum heat release rate of the individual fuel packages.
- Estimated fire growth rate
- Amount of smoke produced and its impact on the time to egress and untenable conditions
- Amount of radiant energy produced and resultant separation distances to adjacent fuel
packages to help reduce potential for radiant ignition of adjacent fuel packages.
Events such as hockey games, dinner dances, etc. whose combustible loading and
configuations would not change from event to event, could be evaluated for a few different
layouts, and would not be expected to be analysed each time the event occurs.
An example letter regarding the analysis is contained in Appendix E.
• Compartmentation and Ventilation — General
- Back of house /non - public areas (i.e. mechanical /electrical rooms, storage, etc.) should be
fire separated from the public areas.
7.2 Means Of Escape
Objective
Allow occupants adequate time to reach a place of safety in the event of a fire.
Design Features
• Smoke detectors are provided throughout the building to detect a fire at an early stage.
Activation of the smoke detection system will automatically activate the fire alarm system.
• All occupants in the building have access to at least two exit routes under normal conditions,
allowing for at least one path to a clear exit should an exit be block by the fire.
• The combustibility of interior finishes and contents in the path of exit travel is minimized.
• Facility staff are on hand for all events to assist in safe, quick, and orderly evacuation in the
event of fire or other emergency.
It is also recommended that the following are provided:
• Existing exit door capacity at the main exit and both side exits should be supplemented with
the addition of four 3 -foot doors at the main exit, and two 3 -foot doors at each side exit.
• The fixed seating area should be modified to include 3 -foot wide stairs at both ends of the
fixed seating area (along wall, leading up to `mezzanine level to exit).
Additional egress width and openings from the ice rink should be added (as planned in the
renovation).
C: \WINDOWS \TEMP\FINAL REPORT.DOC Page 21 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
7.3
7.4
7.5
7.6
Dobson Ice Arena
Smoke Development And Management
Objective
Reduce the hazard resulting from smoke by limiting its production and controlling its movement.
Design Features
• Passive smoke management is proposed to be used to maintain tenable conditions during
evacuation in the building, in conjunction with controlling the hazard/fuel load. The detailed
analysis of this is contained in the Appendices.
• If it is not possible, or feasible to manage the hazard introduced by the combustible material
brought into the arena, then one alternative would be to provide a smoke management system
sized to extract the smoke produced from the largest anticipated fire. Sample calculations are
provided in Appendix D. However, extract quantities would need to be confirmed, and would
be based on the largest fuel load anticipated to be provided for the various events.
Control of Fire Spread (Compartmentation)
Objective
Reduce the likelihood of fire spreading from the room of fire origin to other areas or
compartments of the building.
Design Features
Compartmentation by fire rated construction is generally provided between main arena area
and `back of house' areas. In addition to maintaining required ratings on existing assemblies,
it is recommended to enclosing the open side of the refrigeration room with 4 -hour fire -
resistive construction, sealing any existing penetrations and installing 2 sets of 90- minute self -
closing doors. (This option to ensure separation of hazards is in lieu of adding a second exit,
which has limited practicality for a normally unoccupied room.)
• The arena is fully sprinklered.
Structural Stability
Ob; ec tive
Minimize the likelihood of premature collapse of part or all of a structure due to fire.
Design Features
• The arena is fully sprinklered.
• In specific areas (above pedestrian walkway /path of exit travel), the wood ceiling structure
will be fire retarded or replaced. This will help to minimize the likelihood of the ceiling
structure contributing to a fire, and thus assist in maintaining structural stability.
Fire Detection And Alarm
Objectives
Provide early detection of a fire in order to notify occupants and emergency personnel, or to
activate an active fire protection system, such as a smoke management or suppression system.
C: \WINDOWS \TEMP\FINAL REPORT.DOC Page 22 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
V&A
Design Features
Dobson Ice Arena
An automatic fire detection system is provided for early detection and notification to building
personnel (employees, occupants, etc.), security personnel, and the Fire Department, of a fire
condition. This system will also supervise all of the fire protection systems and activate
appropriate ancillary systems.
Automatic detection devices provided throughout include, or should include:
• Smoke detectors throughout all areas, including beam -type smoke detection in the main arena
area
• Manual pull stations
• Water flow switches on sprinkler systems
• Tamper switches on all sprinkler valves
The automatic detection system will sound audible and visible notification appliances. It also
automatically notifies the Vail Fire Department of an alarm.
In addition to the automatic detection system, it is anticipated that detection within the arena is
likely to be through visual detection. Occupants should be awake and alert. Occupants should
become aware of a fire through the direct visual connection they have with the fire source and the
smoke that will be developed.
The arena is provided with automatic alarm notification appliances to notify the occupants of a
fire. In addition, facility staff will be trained to notify the public of emergency conditions and to
assist in the safe and quick evacuation of occupants.
It has been indicated that during some events, the beam type smoke detectors are taken out of
service to prevent false alarms. Fire safety management procedures should be developed in
conjunction with the local authorities and put in place to address applicable items including
providing 1) alternative means for detecting a fire as quickly as possible (i.e. fire
wardens /watchers, etc.) and 2) means to notify the Fire Department with all pertinent details
regarding taking the detector out of service (reason, duration, acknowledgement, etc.) and 3) the
means to notify the Fire Department of a fire in order to limit delays during this period.
Fire Suppression
Objectives
Control or extinguish fire.
Design Features
• Fire extinguishers will be provided throughout the building.
• Sprinklers are provided throughout the building. The sprinklers help to ensure that a fire
cannot develop and grow to a point where flashover could occur. Sprinklers limit the fire
growth and prevent fire spread. Typically, a fire would be controlled by one to four sprinklers.
• In spaces with low ceiling heights and high fire loads, sprinklers are also be provided. In
these areas, they will provide early suppression of fires, limiting heat and smoke spread and
resulting damage.
CAWINDOWS \TEMPTINAL REPORT.DOC Page 23 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado Dobson Ice Arena
7.8 Fire Fighting Facilities
Objective
Assist fire fighters in their rescue and fire control operations.
Design Features
• The fire department will be automatically notified of a fire via the fire detection system.
• Adequate access is provided to the arena for fire fighting equipment.
7.9 Emergency Lighting, Signage & Power
Emergency lighting and exit signage are to be provided throughout the building, to the
requirements of the local codes.
7.10 Fire safety management
The Dobson Ice Arena appears to be well managed and should have a well - defined fire safety
management policy.
This policy should be developed with the various stakeholders and should include details of.
• limits on total occupants for the range of expected events
• evacuation and fire department response plans for the above events
• additional event staff for large events to facilitate fast and safe evacuation
• good housekeeping /fire prevention procedures
• regular maintenance of all fire protection equipment
• training of staff in evacuation procedures and first aid fire fighting
• management of occupants with special needs
• regular fire evacuation drills
• hot work permit system
• limiting fuel loads and materials as outlined herein
• limiting occupant loads as specified herein.
C: \WINDOWS \TEMPT]NAL REPORT.DOC Page 24 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
8. RESULTS FROM ANALYSES
8.1 General
Dobson Ice Arena
The following summarizes the results for each fire scenario. Information regarding inputs and the
design scenario conditions are detailed within the Appendices.
8.2 Egress Calculations
Table 8a summarizes the times calculated for egress using both hand calculations, and Simulex.
Table 8a — Calculated Egress Time Summary
Notes:
1. Hand calcuations assume density of 10 sq ft per person at exit
2. Detection time assumed to occur when fire reaches I MW (2.5 min for fast growth rate, and 5 minutes for medium growth
rate) either by automatic or manual means.
3. Total time = detection time + pre- movement time + egress time
Times calculated using these methods are fairly consistent for each scenario. As would be
expected, egress times increase with increasing populations.
8.3 Smoke Calculations
Table 8b provides predictions of the smoke filling times produced by fires of different growth
rates. The estimated fire sizes at the time that the smoke descends to 8ft above floor level at the
mezzanine level are given along with estimated smoke temperatures. The calculations were
performed using computer spreadsheets called T -Zam, which is a computer program developed by
Arup Fire (based on equations contained within CIBSE TM 19: Relationships for smoke control
calculations, 1995). The results are presented in their entirety at the end of this report.
CAMNDOWS \TEMPTINAL REPORT.DOC Page 25 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Hand Calculations'
Egress
Scenario
Detection
Time (min)
Pre - movement
Time (min)
Egress Time
(min)
Total Time
(min)
Egress Time
(min)
Total Time
(min)
Notes:
1. Hand calcuations assume density of 10 sq ft per person at exit
2. Detection time assumed to occur when fire reaches I MW (2.5 min for fast growth rate, and 5 minutes for medium growth
rate) either by automatic or manual means.
3. Total time = detection time + pre- movement time + egress time
Times calculated using these methods are fairly consistent for each scenario. As would be
expected, egress times increase with increasing populations.
8.3 Smoke Calculations
Table 8b provides predictions of the smoke filling times produced by fires of different growth
rates. The estimated fire sizes at the time that the smoke descends to 8ft above floor level at the
mezzanine level are given along with estimated smoke temperatures. The calculations were
performed using computer spreadsheets called T -Zam, which is a computer program developed by
Arup Fire (based on equations contained within CIBSE TM 19: Relationships for smoke control
calculations, 1995). The results are presented in their entirety at the end of this report.
CAMNDOWS \TEMPTINAL REPORT.DOC Page 25 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
Table 8b — Smoke filling times for various fire growth rates
Dobson Ice Arena
Fire Growth Rate Predicted time for
smoke layer to
descend to 8 ft
above mezzanine
Predicted average
temperature of smoke
layer at Ti
Approximate
convective heat
release rate (fire
size) at T1
Approximate total
heat release rate
(fire size) at T1
floor level (T1)
11'
.11
11
time
Material
:1'
111
111
•
'
1' .1'•
11
11
•
(no.)
1 ' 1'
111 I
11
As can be seen from the above table, the predicted time for the smoke layer to descend to 8ft
above the mezzanine floor level ranges between approximately 4.5 minutes and 12 minutes
depending on the fire growth rate. For the fast fire growth rate the time is 6.5 minutes.
It has been postulated that the most probable fire growth rate for a ski -swap type event would be
that of a fast growing fire, although the actual nature of the fire load could result in faster or
slower fire growth rates (hence the range of fire growth rates considered for the analysis). The
design fires considered, therefore, may not represent the actual fire conditions, but rather a range.
The following table provides an indication of dimensions that the above fire sizes represent.
While it is unlikely that some of the items shown in the table will be present in the arena, they are
included for comparison.
Table 8C — Equivalent Fire Load
Approximate total heat
release rate at critical
Equivalent Fire Load
Shop
Christmas
Stacking
Suitcases
Display
Timber
time
Material
trees
chairs
Material
(kW)
(ft 2)
(no.)
(no.)
(no.)
(ft 2)
(lb)
see rate 1
see rate 2
see rote 3
see rote 5
see rate 6
see rote 7
13,700
295
21
343
46
1522
1674
7,000
150
11
175
23
778
856
3,500
75
5
88
12
389
428
1,500
32
2
38
5
167
183
Note 1: data source CIBSE TM19
Note 2: data source NFPA 92B, CIBSE TM 19
Note 3: data source NFPA 92B
Note 4: data source NFPA 92B
Note 5: data from lull scale testing carried out by Arup Fire
Note 6: data source NFPA 92B, CIBSE TM 19
Note 7: assuming 20 minute effective bum time, data source CIBSE TM19
C: \WINDOWS \TEMP\FINAL REPORT.DOC Page 26 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
8.4
8.5
Dobson Ice Arena
The first column of the above table considers typical shop material. Although the fire load for the
ski -swap event for example is not clearly defined, it is likely that the floor area of the rink will, in
several ways, resemble a shop sales area. For the fast fire growth rate, the fire area after 6.5
minutes is predicted to be 150 ft2 (approximately 12 ft x 12 ft) for typical shop fire loads. This
represents a considerable fire size.
Effect of Sprinklers on Fire Growth
It is our understanding that the entire arena space is protected by an automatic sprinkler system. In
many situations sprinklers have been shown to be effective in controlling fire growth, however
there are circumstances where the activation times of sprinklers are delayed in particular where
floor to ceiling heights are large, and thus their effectiveness is reduced,.
The floor to ceiling height in the center of Dobson Arena is in excess of 45 ft. If a fire were to
occur in the center of the arena (which would be possible in a ski -swap event), the fire size at
sprinkler activation would be larger than if a fire were to occur towards the edges of the arena
where the floor to ceiling heights are lower.
Sprinklers are less effective at controlling large fires as the proportion of the sprinkler discharge
that reaches the seat of the fire is reduced.
Calculations have been performed using the NIST computer program DETACT to calculate the
response time and heat release rate at sprinkler response. These are summarized in the table
below.
In comparing this with Table 813, it can be seen that sprinklers may not go off prior to the time
that the smoke layer descends to 8 feet above the Mezzanine Level for any of the fire scenarios.
Table 8D — Sprinkler Response Analysis
Fire Growth Fire
Rate
I
Size at Sprinkler Activation
(1\1«)
Time at Sprinkler Activation (min)
-I
Fire in an Ancillary Space
It is our understanding that all storage areas are provided with fire rated doors. If closed, these
doors should minimize the quantity of smoke entering the arena space.
C: \WINDOWS \TEMP\FINAL REPORT.DOC Page 27 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
8.6 Summary
Dobson Ice Arena
Given the above summary of the analyses contained herein, the following conclusions may be
made:
- The times calculated for evacuation for the different scenarios are greater than the times for
the smoke layer to descend to 8 feet above the Mezzanine Level where none of the hazard
reduction or mitigation alternatives were considered. (see Table 8E)
- Sprinklers may not activate prior to the time that the smoke layer descends to 8 feet above the
Mezzanine Level for any of the fire scenarios due to the heat release rate required to raise the
temperature in the vicinity of the sprinklers.
Table 8E — Comparison of Egress Time and Time to Untenable Conditions
Scenario
Number
Event
Egress
Hand Ca1c. (min)
Time
Simulex (min)
Time to
Untenable
Conditions
Safe Egress Time -7
Available?
1
Hockey Game
8.2
10.5
6.5
No
Concert -
2
Open Rink
12.3
12.5
6.5
No
Floor
Concert or
3
Convention -
11.5
11.5
6.5
No
Seating on
Rink Floor
4
Ski Swap
8.7
9
6.5
No
Dinner Dance,
5
6' round
11.2
11
9
No
tables
Dinner Dance,
6
buffet, long
12
12
9
No
tables
C: \WINDOWS \TEMP\FINAL REPORT.DOC Page 28 Ove Arup R Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
Dobson Ice Arena
Given the above results, it can be seen that alternatives are needed to either control the hazard (i.e.
limit maximum heat release rates, etc.), or to provide fire protection features that manage the
impact of the hazard on the arena (i.e. smoke management). Table 8F presents a comparison of
the various scenarios with their resultant levels of impacts for various alternatives.
Table 8F — Arena Event vs Level of Impact for various hazard reduction /mitigation options
Scenario
Number
Event
Unmitigated
(i.e. as is)
Sprinklers
Fuel Control
Smoke
Management
1
Hockey Game
Mild
Mild
Mild
System
Mild
Concert -
2
Open Rink
Mild
Mild
Mild
Mild
Floor
Concert or
3
Convention -
Seating on
Moderate -High
Moderate -High
Mild
Mild
Rink Floor
4
Ski Swap
High
High
Mild
Mild
Dinner Dance,
5
6' round
Mild
Mild
Mild
Mild
tables
Dinner Dance,
6
buffet, long
Mild
Mild
Mild
Mild
tables
Based on this information and the goals and objectives previously established of limiting the level
of impact to mild, the following recommendations are made:
CAWINDOWS \TEMP\PINAL REPORT.DOC Page 29 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
Table 1— Summary of Proposed Fire Safety Measures
Dobson Ice Arena
Fuel Load
Materials should be selected to limit fire growth rate to "medium" as defined by NFPA 72.
(i.e. max. 300 seconds to reach a 1 MW fire)
• Fuel packages should be separated by a sufficient distance to prevent ignition of two fuel
packages at the same time.
• Fire retardant material should be applied to combustible ceiling components immediately
above pedestrian walkway (mezzanine), or combustible ceiling components in those areas
should be replaced with non - combustible components.
• In addition, one of the following alternatives should be selected in order to either control the
hazard of the materials allowed in the Arena, or to manage the impact of the hazard:
Control Hazard Alternative
• Steady State Fires - Efforts should be made to limit maximum heat release rates to:
Slow /Medium Growth Rate Fires - 2.5 MW per fuel package.
Fast Growth Rate Fires - 1 MW per fuel package
Ultra -Fast Growth Rate Fires - 0.75 MW per fuel package
• Non - Steady State Fires — Where fires are not steady state and meet the above
limitations, then a qualified Fire Protection Engineer should perform an engineering
analysis on the various fuel packages. This would allow the mass of each package to
be evaluated for its contribution to total smoke production in the Arena to determine
limits on how much fuel needs to be consumed to develop a smoke layer that
descends to head level.
Manage Impact of Hazards Alternative
• Where the above limitations are not feasible, other fire protection systems and features
will need to be installed to provide an acceptable level of safety. One alternative noted
is a smoke management system.
• A qualified fire protection engineer should provide written confirmation that an evaluation of
the various hazards specific to individual events has been undertaken, and that the above
criteria are met. (see Appendix D)
Means of Escape
0 Existing exit door capacity at the main exit and both side exits should be supplemented with
the addition of four 3 -foot doors at the main exit, and two 3 -foot doors at each side exit.
• The fixed seating area should be modified to include 3 -foot wide stairs at both ends of the
fixed seating area (along wall, leading up to 'mezzanine level to exit).
• Additional egress width and openings from the ice rink should be added (as planned in the
renovation).
Smoke
Provided fuel loads and growth rates are limited, either via controls outlined above, by
Management
sprinklers, or by manual suppression, so that tenable conditions are maintained during the
egress period, smoke management is not required.
• If fuel loads and fire growth rates are expected that exceed the above levels, and an
additional margin of safety is desired, addition of a smoke management system is an option.
Compartmentation
In addition to maintaining required ratings on existing assemblies, it is recommended to
enclosing the open side of the refrigeration room with 4 -hour fire - resistive construction,
sealing any existing penetrations and installing 2 sets of 90- minute self - closing doors.
C: \WINDOWS \TEMP \FINAL REPORT.DOC Page 30 Ove Arup & Partners Massachusetts, . Inc
Draft Final Report - 28 May 2001
Town of' Vail, Colorado
Dobson Ice Arena
Structural
No modifications or additional features are required in order to provide the desired level of
Elements
life safety. If property protection or business continuity objectives become more important,
additional fire protection measures may be warranted, especially with regard to the roof
structure and material, from interior or exterior exposure fires.
Fire Detection &
Discussions should be had with the Fire Department regarding procedures for detecting
Alarm
fires as well as transmitting alarm signals and notifying the Fire Department when the beam
type smoke detectors are taken out of service during events due to the potential of false
alarms.
• No modifications or additional features appear to be needed other than those required to
meet code. However, a well designed and intelligible voice paging system is desirable for
facilitating emergency evacuation.
Sprinklers &
0 No modifications or additional features appear to be needed other than those required to
standpipes
meet code. Normal inspection, testing and maintenance is recommended.
Emergency
No modifications or additional features appear to be needed other than those required to
Systems
meet code.. Normal inspection, testing and maintenance is recommended.
Fire Safety
Fire safety management plan required for (1) each type of major event as well as for special
Management
events that either (2) pose an unusual fire hazard or (3) presents an unusual risk to facility
occupants.
If it is desired to provide the maximum flexibility and consider using fuel packages of higher heat
release rates, or fast /ultra -fast growth rates within the Arena, a mechanical smoke management
system could also be considered.
Appendix D provides an analysis of the effect of a mechanical system sized to extract 100,000
CFM, on delaying the descent of the upper layer. However, extract quantities would need to be
confirmed, and would need to be based on the largest fuel load anticipated to be provided for the
various events.
C: \WINDOWS \TEMP\FINAL REPORT.DOC Page 31 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
0
9.1
ASSUMPTIONS AND LIMITATIONS
General
Dobson Ice Arena
This section of the report.defines the assumptions used in the assessment and the limitations on
the application of the results. In this context, assumptions are defined to be inputs to the analysis,
which may include simplifications of reality based on engineering judgement or accepted
approaches that are necessary to enable the issues in question to be rationally addressed. These
inputs are described in order that users of the report are made aware of them and their
applicability can be reviewed. Limitations are defined as boundaries to the applicability of the
results, including aspects that have specifically been excluded from consideration. Furthermore,
the assumptions used in the analysis may imply limitations on the use of the results.
Typical assumptions include tenability criteria and models used. Limitations may include a
decision that no particular property protection issues are to be addressed and that the design
solution is subject to a strong fire safety management plan and training of occupants.
Assumptions
The general assumptions used in this analysis are provided below. Any alterations to the design
that result in any of the assumptions becoming invalid will result in the need for a new fire
engineering analysis.
• All fire protection systems and management strategies will be installed and fully maintained
in accordance with this report and relevant Standards.
• The building will contain various occupancies including an ice arena, offices and storage
areas.
• The works of Pauls and Bryan (SFPE Handbook of Fire Protection Engineering) are
acceptable methods for predicting occupant movement times. Simulex software is validated
for use.
• The criteria for tenability described in this report should help to ensure an adequate level of
life safety is being provided for the occupants to evacuate prior to the onset of untenable
conditions.
• Occupants are familiar with the building and capable of moving and responding to an alarm.
• Occupants will be coherent and their judgement will not be impaired so that they will move
away from the fire to an exit and leave the building within the time calculated herein,
including recognition and response times, and they will not remain in the fire compartment.
• Simulex is an acceptable method for predicting occupant movement times.
• The fire growth rates and smoke spread analysis predicted by the CIBSE TM 19 smoke
spread model and the NFPA 92B Guide For Smoke Management Systems In Large Areas
provide sufficiently accurate results for the purposes of design. (See Appendices)
• The fuel loads are representative of those analyzed herein with particular regard to growth
rate, maximum heat release rate and duration.
• The fuel loads in the arena will not exceed those used in this analysis.
• Security measures will be provided to limit the occurrence of arson.
CAWINDOWSUEMPTINAL REPORT.DOC Page 32 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
9.3 Limitations
Dobson Ice Arena
The following limitations apply to the fire safety analysis. Any change in the limitations or in the
assumption stated within this report or part of the analysis may alter the final design solution and
hence needs to be referred to a qualified fire engineer for review prior to altering the design.
9.3.1 Building Characteristics
• The building is used as an arena. If the building use is to change in the future, the building
will have to be re- assessed. (i.e. fuel loads, occupant loads, egress, etc.)
• Fire protection systems within the building will include those discussed herein.
• All fire protection systems will be installed and maintained as per their relevant standards and
as discussed herein.
9.3.2 Occupant Characteristics
• The analysis is limited to the population figures, characteristics, egress provisions and
installation of the fire safety systems discussed in this report.
• None of the exits can be blocked for any reason at any time (i.e. furnishings, displays, storage,
etc)
• The occupant loads in each area need to be strictly adhered to
• Occupant judgement is assumed to be rational and should not be impaired. For example, use
of the space for consumption of alcohol will need to be avoided as occupants' judgement in
responding to an emergency situation cannot be impaired by the use of alcohol, drugs, etc.
9.3.3 Fire Characteristics
• The building will be non - smoking throughout.
• Fire growth rates of materials will need to be limited to slow or medium growth rates.
• Fuel loads (i.e. furnishings, contents, etc.) will need to be separated so that multiple fuel
packages will not be able to be ignited by radiant energy.
• The analysis does not assess the level of property protection and business interruption within
the subject building. Acceptance of this assessment, including the scope of works and
limitations contained therein, is considered to be an acceptance of the risk for contents and
property protection within the building. Responsibility for this risk is considered to be
subrogated to the owner and their insurer unless otherwise directed via further correspondence
in which case this report becomes invalid.
C: \WINDOWS \TEMP\FINAL REPORT.DOC Page 33 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
10. CONCLUSION
Dobson Ice Arena
This document represents the fire engineering analysis for the Dobson Ice Arena. The approach
uses a performance -based fire engineering methodology to provide fire safety measures tailored to
the specific needs and challenges of the design. Recommendations are provided with regards to
fire protection systems and managing fuel loads to help ensure occupants can evacuate prior to the
onset of untenable conditions and meet the goals and objectives established by the stakeholders.
C: \WINDOWS \TEMP\FINAL REPORTDOC Page 34 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
11.
11.1
11.2
CODES AND STANDARDS
Dobson Ice Arena
References
SFPE Engineering Guide on performance Based Fire Protection Analysis and Design of
Buildings, SFPE, 2000.
ICC Building Performance Code Draft, Preliminary Committee report, August 1998
SFPE Handbook of Fire Protection Engineering, P. DiNenno(ed), NFPA Boston MA, 1988.
Chartered Institution of Building Services Engineers (CIBSE), "Relationships for Smoke Control
Calculations" Technical Memoranda TM19:1995
"NFPA 92B - Guide for Smoke Management Systems in Malls, Atria and Large Areas ", National
Fire Protection Association.
Applicable Codes and Standards
NFPA 101— Life Safety Code, 2000
CIWINDOWS \TEMP\FINAL REPORT.DOC Page 35 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
ArupFire
Appendix A
Design Fires
Dobson Ice Arena
C: \WINDOWS \TEMP\FINAL REPORT.DOC Page 36 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
DESIGN FIRES
The primary design fire scenarios reviewed were:
• Concerts
• Ski Swap
• Dinner /Conference setup
Dobson Ice Arena
Smoke filling times were modeled for various fire growth rates ranging between ultra -fast and
slow. The fires were assumed to be in the center of the arena and the smoke plumes were
assumed to be axisymmetric. The table below gives typical fire growth rates for some common
materials (results are from actual fire tests):
Design Fire
Fire Type
Fire Growth Rate
1
Cotton (also PE, PE /Cot, Acrylic /Nylon /PE),
>Ultra- Fast
garments in 12ft high rack (see note
3
2
1 /2 -in plywood wardrobe with fabrics (see note
> Ultra- Fast
2)
3
Metal wardrobe with fabrics (see note 2)
Fast
4
Wood pallets, stack 5 ft high (see note 3)
Fast
5
Love seat, wood frame, foam cushions (see
Medium
note 2)
6
Mail bags, filled, stacked 5ft high (see note 3)
Medium
7
Waste paper basket (see note 1)
Slow
Note 1: data source CIBSE TM19
Note 1: data source NFPA 72
Note 3: data source NFPA 92B
It is likely that items of clothing at a ski -swap event will either be on rails or on tables. The rate of
fire growth in the initial stages of a fire is usually greater for vertically aligned combustibles.
Thus, ignited clothing on hangars is likely to produce faster fire growth rates than clothing on
tables.
The above table contains a limited amount of data for clothing fires, ranging from Fast to >Ultra -
Fast fire growth rates. The case of the clothing in 12ft high racks is more typical of warehouse
storage — it is considered unlikely that storage of this kind will be present at a ski -swap event
(although the exact nature of the ski -swap fire loads has not been made available for this
analysis). Perhaps the fire type in the above table that would best represent the ski swap event is
that of a metal wardrobe (as in the fire tests the only combustibles present were the cloths in the
wardrobe and the paint on the metal).
CAWINDOWS \TEMP\FINAL REPORT.DOC Page 37 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
Dobson Ice Arena
C: \WINDOWS \TEMP \FINAL REPORT.DOC Page 38 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
Town of Vail, Colorado
Dobson Ice Arena
C: \WINDOWS \TEMP\FINAL REPORT.DOC Page 39 Ove Arup & Partners Massachusetts, Inc
Draft Final Report - 28 May 2001
ArupFire
Appendix C
Smoke Analysis
Town of Vail, Colorado
CONTENTS
C -1. GENERAL
C -2. ULTRA -FAST GROWTH RATE FIRE
C -3. FAST GROWTH RATE FIRE
C-4. MEDIUM GROWTH RATE FIRE
C -5. SLOW GROWTH RATE FIRE
Dobson Ice ,Arena
C: \WINDOWS \TEMP \0002APPENDIX C - SMOKE ANALYSIS. DOC Ove Arup & Partners Consulting Engineers PC
Draft 1 May 5, 2001
Town of Vail, Colorado
C -1. GENERAL
Dobson Ice Arena
Appendix C contains the results of the calculations for analysing smoke layer development, and
the temperature of the smoke layer.
Four different fire growth rates are contained herein: Ultra -fast, fast, medium and slow. The heat
release rates for each of these analyses are contained in each section along with a graph showing
upper layer development versus the increasing temperature of the upper layer. The equations used
in CIBSE Guide TM 19 were used to model the smoke production and resultant smoke layer
development.
CAWINDOWS \TEMP \0002APPENDIX C - SMOKE ANALYSIS.DOC Page DI Ove Arup & Partners Consulting Engineers PC
Draft 1 May 5, 2001
Town of Vail. Colorado
C -2. ULTRA -FAST GROWTH RATE FIRE
tf x
Fie Y Geale Danmerts Help
Fire Model Results Case Script -- -
Fke a,d
D.IODg
Smoke
Aocess
Oplms
I
Po.1
-a
RID
I u.a<a By mq.p N.pwf oe Tr -.smv, oL+ol.r
Ie. lOm
Ukn. Ga.nq Fn
FIRE DESCRIPTION
iFire CarMaMz
Cwv<cs:re lraakn • 70 S
j N<n Naase.ae -300 kW /m/
c Leap Oerony - I /
Cakdsm value of Iw1 . • IB NO W / Yp
I ! Fire type -.T- sq.mm
� i Frt MS e.pu •0.1880 ssaYW
I COMPMTYENT DESCRIPTION
WaN.OD m
l I1.Iai • D m
Depth • O0 D I
•ODm
Bue pre ikon kr <I • 0 D m
Poor >ea•OD ma
Mw aea •Do m�
Cpmpanmxn Maw area • OD T,
I 1 Om
/ 6111pkB I Bakeny neq. • 0 0 m
- I Bakwy iWln�0 ➢m
- � CnanMVp zc aYak • OD m
I
Time (a)
Heat Release (MN)
Heat Release ON
Notes
Total
Comect"
I Total
IConvect"
30.0
169.2
118.1
1700.5
1190.3
Veres o l
6000
676.8
173.8
13569.9
9198.9
2 <.21 .52.1 Veris o0 -
90.0
1522.8
106600
45760.2
32032.1
120.0
2707.2
18%.0
108423.1
7%%A
150.0
1230.0
296100
211711.5
1181991
180.0
6091.2
1263.6
365776.6
256063.6
ZIRD
8290.8
SBO361
580770.6
106539.1
210.0
10828.8
758121
8668/5.5
606791.9
170.0
13705.2
9593.6
1231153.3
863907.3
300.0
16920.0
11814.0
16928/6.1
1181992 3
Ne Ve. Croxe Doaaneris Heel
- - - - -- -Smnke KAnrlpl RPCUItc
Ete ena
SI✓bEV '
Roaw
Optlae '
fYM
SncM
toy( -)
Nags
22.7
Ne'c
IL'C
10'c
V'C
0'L
12.0
Veas oO
7.5
Yeas al
52
Veris Oil
3.8
VeaS o8
3.0
Veres o l
2.{
2 (- 2117 13ml Vales o0 -
2.1
2(- 237.83m Vents dl
1.9
2 <.21 .52.1 Veris o0 -
O
Time (s)
SDO
toy( -)
Nags
22.7
Veas al
12.0
Veas oO
7.5
Yeas al
52
Veris Oil
3.8
VeaS o8
3.0
Veres o l
2.{
2 (- 2117 13ml Vales o0 -
2.1
2(- 237.83m Vents dl
1.9
2 <.21 .52.1 Veris o0 -
BUILDING DESCRIPTON
Il.o. (in Baw to mol)- Ip.S .
Fb« xea IM: o'1 «rain
SMOKE MODEL DEECRtPT10N
i ntype -. TN19, EpI. 32
se OmaO. Epn. ]]. auvmnsxa pYm.. small
� aqe aawtx Fp.ca
(i ro n« m>p. eo aYayT.neM PYme : opx.ps
i pb
Oren xd moan Man<.Mn mme impegxne
apoY<urpppr - I.- x sM a ,,1« N- J
:mawlve kssas Imn brx na k Ju/<q.
isdbY to a rttkpyirf sqI
rfs rws el xwke wnks<s - o➢n kq,kq
TNTIl 011 PROVISIONS J
;ase Script
aea Br ana.N Negpx w Tknmr. o«par
mro
a Fw 0, M, FN
'E DESCRIPTION
M
•I,kaF, sae- 100kW1ma
WG OIL,. I., I Ipa
prilic r & hNI • 18 W /kg
e tp : T - Sq..W
Ma pup.- D.INOfSa-
.P ENT DESCRIPTION
M•O.Om
y11•BDm
itn•DDm
do. wan • OD m
Aoe nrgle • OD m
dw Base apere IMwr kv<I • 0.
ti•OD
0.0
dw a<a -m/
rpann.rM Maoe spa • OD m
em
sn epb • 0➢ m
p Y<ptn.D ➢m
ILDING DESCRIPTION
on ore wF<Ip moll. I.s m
DNE MODEL DESCRIPTION
me t,oe TN19. EpI. s2
Dm�D. Em. ss /w.vm. -wM pYa.,e, fm,1i
brq aawtx seuoe
pa pnxq. to aa�srmm.mr pYao< a openap
ups a-q moanr DYx•f .nx wme <IpYq«wr
oke txnp<ralae tM<n as tM arxaw 1«[M
IL�r<afsaf Imm byx m xpwa<a.
ra,rnre kssas Imm byx pa fmYla.q.
Lify to a niknire fpn
sz xelE o1 smote paNCles • OD13 kphq
IITILITION PROVISIONS J
Dobson Ice Arena
CAWINDOWSWEMP\0002APPENDIX C -SMOKE ANALYSIS.DOC Page D2 Ove Arup & Partners Consulting Engineers PC
Draft I May 5, 2001
Town of Vail, Colorado
C -3. FAST GROWTH RATE FIRE
Fik Virg GeMe Docuner4s Help
Fire Model Results Case Script
iDODTOn Prena
FFe MrW �
:. B121dry
Sllld(G I
it
i
1'
Ploeesa t
f
Run
FYe
II
Rut
Dobson Ice Arena
$IIIgIla I i LNwaMl4p scrtm xreln • OD m
I BUILDING DESCRIPTION
Time (a)
Crtx<d by � Hedges on Th-day.
Onceer
Notes
Total
19.2000
i Total
I
120.0
6696
+
I
I
fast Grown9 Fn
150.0
1046.2
7324
FIRE DESCRIPTION
36655.4
-
100.0
Fin [onstatz
Coveive tnnun =1
11154.6
904713
63329.9
Nex rekase rne: 600 kwlmk
210.0
2050.6
1435.5
Fn load Denny • 0 NU I m
100553.6
Vets off
240.0
Calonric value o11uN = 18 NU Ikg
1874.9
214405.9
150081.2
Frre type T Sgtland
27001
3389.8
2372.91
FR Mx outpu = 0 0465 s t a k W
213679.2
62.30
�'.
COMPARTMENTDESCRIPTION
2929.5
418709.3
2930%.5
wdh 0.0m
330.0
5063.9
3544.7
Herpre • Do m
390093.7
Vats off
3600
Depn =ODm
42185
723469.3
506458.5
oM Miatn • D D m
390.0
70727
4950.9
oo -00m
643858.7
88.29
j
• aDOn 14Nr kv0 •0 0m
Dase b...
5741.8
11487742
804141.9
Fbor -- 0.0 ma
450.0
9416.3
6591 4
14129083
9890218
Z < -2.116 74m1 VeNs off
480.0
Lortpa4- surrace ana • 0.0 m
31.33
10448
000
= 000
Bakany
B dWm • 00 m
rDOny dean = 0-0 m
21
Z <• Z11710m1 VeNs olf
$IIIgIla I i LNwaMl4p scrtm xreln • OD m
I BUILDING DESCRIPTION
Time (a)
He Release ("
Heat Release (W)
Notes
Total
CDnrectlre
i Total
iCorindve
120.0
6696
468 7
268175
18772.2
8.51
150.0
1046.2
7324
523648
36655.4
4136
100.0
1506.6
11154.6
904713
63329.9
23729
210.0
2050.6
1435.5
1436480
100553.6
Vets off
240.0
2678.4
1874.9
214405.9
150081.2
731
27001
3389.8
2372.91
305256.0
213679.2
62.30
300.0
4185.0
2929.5
418709.3
2930%.5
421851
330.0
5063.9
3544.7
557276.7
390093.7
Vats off
3600
6026 4
42185
723469.3
506458.5
6.30
390.0
70727
4950.9
919798.2
643858.7
88.29
4200
8202 6
5741.8
11487742
804141.9
6591 4
450.0
9416.3
6591 4
14129083
9890218
Z < -2.116 74m1 VeNs off
File View [4-tie Doclmmlts Help
- - r Smoke Model Results
Fire Mm
a�V
511011!
Pro -
0"b"
R-
Fire
E
PhINN (1n Dase to root) • 14.6 m
F-1 area li< DYOr rail aw
i
SMOKE MODEL DESCRIPTION
Plane type'. TMi B. Eqn. 5 2 all
AF. 002<0. W ]]. Aisvmmxnc pkane. sm
d brye diamwer source
Do nn efrxpe to ausynrrMrlc plume x opmvg
jM arM -fir, Plume .IMn 11ame mpnpmKr
aas
Smoke I'mP<rxUt Iakm as tM average for[M
ayn
IRa6xlre losses imn Byer n« kwwd<a.
I [onn„a,re msses rrom by <r nA incwded.
IDa]y to a nikcTlr. sib.
ss yMld or smaN< p.-, = 0.026 kgkg
ENTILATION PROVISIONS
type. No WNilalion
Case Script
Crtxed DY apart. Fkdpes m t-day. On--
10. 2DOO
Fasl Grt Fn -
FIRE DESCRIPTION
Fre Cons ,
[onrenir<rrtnun -101
Hex rekase me =500 kW Ima
F. Load DmsaV • D -I, m a
Cxmfre value of IW = IB NU 1 kg
Fir. type' T. Squared
Fie Mx onpu • 00455 .I a kw
COMPARTMENT DESCRIPTIDN
h=ODm
Wpa•OOm
D.qh =ODm
e -•00m
oa Mrya =DDT
•Dase aDOre rkor krN • D D m
i fbor� arta0 0 m s
•OOms
Compagmera aveace arte • 0 0 m �
b=DOO
j axcony nagb • 00 m
aakonyawN =DDm
LKamelVp screen .ktn • OD m '
I
BUILDING DESCRIPTION
Nagll (in DaF<ta mol) = 14.6 m
ibor area Ne'. 0lor ral.art
I
SMOKE MODEL DESCRIPTION
Plumelyp< TM9. Eqn. 52
Aso DO]4O. Eqn ]3 Ae,symmnac *11 small
brye eamxx swore.
Do pat chxge to anayrmrelra plane x opevq
ID � xw m.a1y Plum. rrm rbm...n�gm »r
Smoke nmperiurt 1ak.n as In¢ average for the
Yer
ICI Raaiaare losses rmm bym na bckrded.
I
emaaa�re bss.s itpn bym na �ckw<d.
-Rkk to a rtlknive sign.
s ykla or smoxe p.-I • 0 025 k0kg
ENTILATIDN PROVISIONS.
type: 1b VimblMb-
C- \WINDOWS \TEMP \0002APPENDIX C - SMOKE ANALYSIS.DOC Page D3 Ove Arup & Partners Consulting Engineers PC
Draft I Mai 5, 2001
Co-d-
MeA rVleeSe
Smoke mass
lbw (kg !s)
SmaMe
Temp. (C)
Va4 mess
ibw (kg fs)
Clear Layer
HW" (m)
NsdaMy (m)
Hales
k
14355
2842
3581
000
8.51
81
Vets off
18749
2646
4136
000
808
65
Vans off
23729
2828
4760
000
768
5 3
Vets off
2929.5
27.94
5457
0.DO
731
44
Vents off
3544.7
27.47
62.30
0.00
6.96
3.7
Vents off
36001
421851
26.82
70841
0 D
6.63
32
Vats off
390.0
4950.9
25.98
80.23
0.00
6.30
2.7
Vets off
4200
5741.8
43.15
88.29
0.00
5.06
2.5
Z <- Z116.38m1 Vents otf
450.0
6591 4
40.34
95.82
0.00
5.35
2.3
Z < -2.116 74m1 VeNs off
480.0
7499 5
31.33
10448
000
486
21
Z <• Z11710m1 VeNs olf
510.0
8466.3
3421
11430
0.00
441
1.9
Z <• ZI 17.65m VeNs oll
540.0
9491.6
3101
12535
0.00
3.98
1.7
Z <- ZI 17 BOIRI Vets tI �.
........,,111■..''•'._..
1111 �
■
...................
,
PhINN (1n Dase to root) • 14.6 m
F-1 area li< DYOr rail aw
i
SMOKE MODEL DESCRIPTION
Plane type'. TMi B. Eqn. 5 2 all
AF. 002<0. W ]]. Aisvmmxnc pkane. sm
d brye diamwer source
Do nn efrxpe to ausynrrMrlc plume x opmvg
jM arM -fir, Plume .IMn 11ame mpnpmKr
aas
Smoke I'mP<rxUt Iakm as tM average for[M
ayn
IRa6xlre losses imn Byer n« kwwd<a.
I [onn„a,re msses rrom by <r nA incwded.
IDa]y to a nikcTlr. sib.
ss yMld or smaN< p.-, = 0.026 kgkg
ENTILATION PROVISIONS
type. No WNilalion
Case Script
Crtxed DY apart. Fkdpes m t-day. On--
10. 2DOO
Fasl Grt Fn -
FIRE DESCRIPTION
Fre Cons ,
[onrenir<rrtnun -101
Hex rekase me =500 kW Ima
F. Load DmsaV • D -I, m a
Cxmfre value of IW = IB NU 1 kg
Fir. type' T. Squared
Fie Mx onpu • 00455 .I a kw
COMPARTMENT DESCRIPTIDN
h=ODm
Wpa•OOm
D.qh =ODm
e -•00m
oa Mrya =DDT
•Dase aDOre rkor krN • D D m
i fbor� arta0 0 m s
•OOms
Compagmera aveace arte • 0 0 m �
b=DOO
j axcony nagb • 00 m
aakonyawN =DDm
LKamelVp screen .ktn • OD m '
I
BUILDING DESCRIPTION
Nagll (in DaF<ta mol) = 14.6 m
ibor area Ne'. 0lor ral.art
I
SMOKE MODEL DESCRIPTION
Plumelyp< TM9. Eqn. 52
Aso DO]4O. Eqn ]3 Ae,symmnac *11 small
brye eamxx swore.
Do pat chxge to anayrmrelra plane x opevq
ID � xw m.a1y Plum. rrm rbm...n�gm »r
Smoke nmperiurt 1ak.n as In¢ average for the
Yer
ICI Raaiaare losses rmm bym na bckrded.
I
emaaa�re bss.s itpn bym na �ckw<d.
-Rkk to a rtlknive sign.
s ykla or smoxe p.-I • 0 025 k0kg
ENTILATIDN PROVISIONS.
type: 1b VimblMb-
C- \WINDOWS \TEMP \0002APPENDIX C - SMOKE ANALYSIS.DOC Page D3 Ove Arup & Partners Consulting Engineers PC
Draft I Mai 5, 2001
Co-d-
MeA rVleeSe
Smoke mass
lbw (kg !s)
SmaMe
Temp. (C)
Va4 mess
ibw (kg fs)
Clear Layer
HW" (m)
NsdaMy (m)
Hales
k
14355
2842
3581
000
8.51
81
Vets off
18749
2646
4136
000
808
65
Vans off
23729
2828
4760
000
768
5 3
Vets off
2929.5
27.94
5457
0.DO
731
44
Vents off
3544.7
27.47
62.30
0.00
6.96
3.7
Vents off
36001
421851
26.82
70841
0 D
6.63
32
Vats off
390.0
4950.9
25.98
80.23
0.00
6.30
2.7
Vets off
4200
5741.8
43.15
88.29
0.00
5.06
2.5
Z <- Z116.38m1 Vents otf
450.0
6591 4
40.34
95.82
0.00
5.35
2.3
Z < -2.116 74m1 VeNs off
480.0
7499 5
31.33
10448
000
486
21
Z <• Z11710m1 VeNs olf
510.0
8466.3
3421
11430
0.00
441
1.9
Z <• ZI 17.65m VeNs oll
540.0
9491.6
3101
12535
0.00
3.98
1.7
Z <- ZI 17 BOIRI Vets tI �.
PhINN (1n Dase to root) • 14.6 m
F-1 area li< DYOr rail aw
i
SMOKE MODEL DESCRIPTION
Plane type'. TMi B. Eqn. 5 2 all
AF. 002<0. W ]]. Aisvmmxnc pkane. sm
d brye diamwer source
Do nn efrxpe to ausynrrMrlc plume x opmvg
jM arM -fir, Plume .IMn 11ame mpnpmKr
aas
Smoke I'mP<rxUt Iakm as tM average for[M
ayn
IRa6xlre losses imn Byer n« kwwd<a.
I [onn„a,re msses rrom by <r nA incwded.
IDa]y to a nikcTlr. sib.
ss yMld or smaN< p.-, = 0.026 kgkg
ENTILATION PROVISIONS
type. No WNilalion
Case Script
Crtxed DY apart. Fkdpes m t-day. On--
10. 2DOO
Fasl Grt Fn -
FIRE DESCRIPTION
Fre Cons ,
[onrenir<rrtnun -101
Hex rekase me =500 kW Ima
F. Load DmsaV • D -I, m a
Cxmfre value of IW = IB NU 1 kg
Fir. type' T. Squared
Fie Mx onpu • 00455 .I a kw
COMPARTMENT DESCRIPTIDN
h=ODm
Wpa•OOm
D.qh =ODm
e -•00m
oa Mrya =DDT
•Dase aDOre rkor krN • D D m
i fbor� arta0 0 m s
•OOms
Compagmera aveace arte • 0 0 m �
b=DOO
j axcony nagb • 00 m
aakonyawN =DDm
LKamelVp screen .ktn • OD m '
I
BUILDING DESCRIPTION
Nagll (in DaF<ta mol) = 14.6 m
ibor area Ne'. 0lor ral.art
I
SMOKE MODEL DESCRIPTION
Plumelyp< TM9. Eqn. 52
Aso DO]4O. Eqn ]3 Ae,symmnac *11 small
brye eamxx swore.
Do pat chxge to anayrmrelra plane x opevq
ID � xw m.a1y Plum. rrm rbm...n�gm »r
Smoke nmperiurt 1ak.n as In¢ average for the
Yer
ICI Raaiaare losses rmm bym na bckrded.
I
emaaa�re bss.s itpn bym na �ckw<d.
-Rkk to a rtlknive sign.
s ykla or smoxe p.-I • 0 025 k0kg
ENTILATIDN PROVISIONS.
type: 1b VimblMb-
C- \WINDOWS \TEMP \0002APPENDIX C - SMOKE ANALYSIS.DOC Page D3 Ove Arup & Partners Consulting Engineers PC
Draft I Mai 5, 2001
Town of Vail, Colorado
C -4. MEDIUM GROWTH RATE FIRE
Dobson Ice Arena
III Q X
File View D-te D.Uivi p H*
Fire Model Results _.. ____ -_ _ -__ _- Case Script --
F and:
Buldrg
Smoke
Process
OFII Or15
Run
Fae
I
Run
Smoke Bakony depM • 0 0 m
Cnsnelknp screen Math - B D m
ool�son Arena I
ere M by mart. Hedges on TvasdaY. OctaOer
IB, 2000
Gva«ip Fire '..
FIRE DESCRIPTION
Fir< COry -
Ganvectiw fxtkn • 70 Y
Heal ukase rte • WD kW I m j
Fke tpad DensrtY = 0 AU / m
1 C «odfk rakre of fuel • IB W Ikp
I � Rretype.T SW.r
Flee heat -ppA • 0.0120 A 1 k kW
I
COMPARTMENT DESCRIPTION
wlem•DOm
R «pM =DDm I
Dept,
WWdw MMh =00m !,
YbindoM helpta = DO m
j yNndoM base abo.e 11oor krel • O D m
Fbor ma = 0.0 m 0 i
W- GO m�
Companmwd 0 D m
d. = 0.00
Bakony MqM • 0 0 m
Time (s)
Heat Release (kW)
Heat Release (kJ)
Notes
Total
Convective
E Total
s Convective
5400
34992
24494
630031.0
441021 7
5700
38988
27292
740%7.0
518676.9
600.0
43200
30240
864216.0
604951.2
630.0
4762.8
3334.0
100042602
700298.3
660.0
5227.2
3659.0
1150245.4
805171.8
69001
57112
3999.2
13143211
920025.2
7200 .
6220.8
4354.6
14933031
1045312.1
750.0
6750.0
4725.0
1687837.5
1161486.3
?80.0
7300.8
5110.6
18985731
1329001.1
8100
7873.2
5511 2
2126157.7
1488310.4
8400
8467.2
59270
2371239.4
1659867.6
870.0
%82.8
63580
2634466.2
18441263
Fib View C-R Docu -A, Help
Smoke Model Results -
Fire WW
BI%dlFg
Smoke
Races
177Jt10'LS
Fee
Rut
Srmke
. .... ..... . . . .... . ....... ... .. . ...............
C. \WINDOWS \TEMP \0002APPENDIX C - SMOKE ANALYSIS.DOC
BUILDING DESCRIPTION
Hl (five Wse to roof)- 145
Fbor -fik OtorvMI-
SMOKE MODEL DESCRIPTION
PNu type: T1119. Eq, 52
pso 00340. Eqs. 33 . adsymrMmp pW small
ana krye au,Nter awloe.
i
D. - chanl4 tc aaisymmMlnc plume at opennA
hegN
Detect and modfy plane Moen Ill
urs
SmWe temper tare taken at the arenpe for [he
kyer
RadMNve fosses from kyer iwt inc40td.
CmducYlve bsses from layer na bckdM
I`lek to a rtf4ct re W'
A4,s Yield of smoke pxicks • OD25 kpMp
VENTILATION PROVISIONS J
- -J
Case Script
Dotson hang
C,MuW by md-, HedOes on Tvnday, October
19, 2000
'. nedhan faoM«A Fke .
F
F IRE DESCRIPTION
c�i ea ns
C iradan • 70 Y
H ukase rate 50131-1
F IMad Dense, • 0 MI I m ,
C..f,c value of I N • 18 W I kA
Fire type T SWared
Fee Mat - -•00120 a t A kW
COMPARTMENT DESCRIPTION
vlmm� =DDm
H «Ak =DDm
Degn•OOm
vMnaoM Mean • D.D m
'. MMndoM Ease afore IIMtt keel • OD m
'. Fbor ana • 0 0 m �
MA- ana =00m
C-P nmem -- arta • 0 0 ma
d.•0m
Bakony "I,t = 0.0
akony m
B dean • 0 0 m
ChiMellnp scorn Mkth • 0,0 m
{ BUILDING DESCRIPTION
H«pk (flrt base to roof) • 14.5 m
Fk r ana fik D for rail.an
iSMOKE MODEL DESCRIPTION j
j % . DD74D. pe. TN19,
.>K oD2 Eqn d 2
I I Eqn. 33_ adsrmmnnc pk,me, :.�alli
Iii a Samex soume.
II
Do nor cnanpe to ansymmetne Dome a opmnA
I � M<R and modify pMn Mwn Ikme impnpeme�
1
Smoke nmpentue taken as the arenpe IDr Sue
yer. I
j Riiii bsses I- byer na mc4ded.
I
I Condualre bsses fnm kyer nor kwbded. I
'4PEky to a nfkpti.e'W
s Yk1d of smoke pmides 0 025 kAMD %.
NTILATI ON PROVISIONS
Page D4 Ove Arup & Partners Consulting Engineers PC
Draft I May 5, 2001
man
lot
VeTts OR
:1 IIIIIIIIIIIIII�IIIIIIIIIIIIIII
'�IIIIIIIIIIIIIII�
111®''
1111111111111111111111®'
"'
II�IIIIIIIIIIIIIIIIIIIIIIII�
' off
- oil
GO
-
vil
.'e 111111111111
1111111111111111115♦'
'IIIIIIIIIIIIIIIIIII�
111®
off
. .... ..... . . . .... . ....... ... .. . ...............
C. \WINDOWS \TEMP \0002APPENDIX C - SMOKE ANALYSIS.DOC
BUILDING DESCRIPTION
Hl (five Wse to roof)- 145
Fbor -fik OtorvMI-
SMOKE MODEL DESCRIPTION
PNu type: T1119. Eq, 52
pso 00340. Eqs. 33 . adsymrMmp pW small
ana krye au,Nter awloe.
i
D. - chanl4 tc aaisymmMlnc plume at opennA
hegN
Detect and modfy plane Moen Ill
urs
SmWe temper tare taken at the arenpe for [he
kyer
RadMNve fosses from kyer iwt inc40td.
CmducYlve bsses from layer na bckdM
I`lek to a rtf4ct re W'
A4,s Yield of smoke pxicks • OD25 kpMp
VENTILATION PROVISIONS J
- -J
Case Script
Dotson hang
C,MuW by md-, HedOes on Tvnday, October
19, 2000
'. nedhan faoM«A Fke .
F
F IRE DESCRIPTION
c�i ea ns
C iradan • 70 Y
H ukase rate 50131-1
F IMad Dense, • 0 MI I m ,
C..f,c value of I N • 18 W I kA
Fire type T SWared
Fee Mat - -•00120 a t A kW
COMPARTMENT DESCRIPTION
vlmm� =DDm
H «Ak =DDm
Degn•OOm
vMnaoM Mean • D.D m
'. MMndoM Ease afore IIMtt keel • OD m
'. Fbor ana • 0 0 m �
MA- ana =00m
C-P nmem -- arta • 0 0 ma
d.•0m
Bakony "I,t = 0.0
akony m
B dean • 0 0 m
ChiMellnp scorn Mkth • 0,0 m
{ BUILDING DESCRIPTION
H«pk (flrt base to roof) • 14.5 m
Fk r ana fik D for rail.an
iSMOKE MODEL DESCRIPTION j
j % . DD74D. pe. TN19,
.>K oD2 Eqn d 2
I I Eqn. 33_ adsrmmnnc pk,me, :.�alli
Iii a Samex soume.
II
Do nor cnanpe to ansymmetne Dome a opmnA
I � M<R and modify pMn Mwn Ikme impnpeme�
1
Smoke nmpentue taken as the arenpe IDr Sue
yer. I
j Riiii bsses I- byer na mc4ded.
I
I Condualre bsses fnm kyer nor kwbded. I
'4PEky to a nfkpti.e'W
s Yk1d of smoke pmides 0 025 kAMD %.
NTILATI ON PROVISIONS
Page D4 Ove Arup & Partners Consulting Engineers PC
Draft I May 5, 2001
Town of Vail. Colorado
Dobson Ice Arena
SLOW GROWTH
Heat Release (k"
y'T -zAM Vn 1.9 June 2000
eQ�i
File V,, DeateDxumerit.� Help
Convective
Fire Model
Case Script
540.0
845.6
591.9
152257.5
106500.2
1fi18
570.0
942.2
659.5
179067.0
125346.9
600.0
1044.0
730.8
19. 2DOC
146196.5
6.91
630.0
1151.0
805.7
2417691
169238.8
1580
660.0
1263.2
884.3
2779780
194583.2
690.0
1380.7
966.5
3176273
222339.4
6.56
720.0
1503.4
1052.4
360691.6
252617.1
15.14
750,0
1631.3
1141.9
407894.1
285525.8
780.0
1764.4
1235.1
458821.8
321175.3
6.22
010.0
19027
1331.9
513821.4
359675.0
11.95
840.0
20482
1432.4
5730415
401134.7
- -
870.0
2195.0
1536.5
6366627
115663.9
5.90
6.1
Vents off
810.0
1331.9
11.12
15.05
000
5.75
5.7
Veils Off
BI0.0
14321
1/.13
17.34
0.00
5.60
5.3
Vents dl
870.0
15385
13.82
19.75
600
5.45
4.9
VeNS all
,,, kW
111111111111111111111111''1'111
1111111111111111;"''
/'1111111
COMPARTMENT DESCRIPTION
00
11111111111111��..�i11111111111
:
RM
Fire
111111�!::ii1111111111111111111
00 120 110 240 X0 300 420 410 50 M "D 7W M 84
Vhb� 0 D
Heat Release W againstrime (a)
File view C
FFe •sd
: Blifiy
i�
S1EIDts
PI'OCeSa
OPIM=
I, Fa•
R�
Smok-
e
it
I
1
Time
Heat Release (k"
Heat Release (k))
Notes
Total
Convective
S Total
SConvectrie
540.0
845.6
591.9
152257.5
106500.2
1fi18
570.0
942.2
659.5
179067.0
125346.9
600.0
1044.0
730.8
2088522
146196.5
6.91
630.0
1151.0
805.7
2417691
169238.8
1580
660.0
1263.2
884.3
2779780
194583.2
690.0
1380.7
966.5
3176273
222339.4
6.56
720.0
1503.4
1052.4
360691.6
252617.1
15.14
750,0
1631.3
1141.9
407894.1
285525.8
780.0
1764.4
1235.1
458821.8
321175.3
6.22
010.0
19027
1331.9
513821.4
359675.0
11.95
840.0
20482
1432.4
5730415
401134.7
- -
870.0
2195.0
1536.5
6366627
115663.9
5.90
III
Bate DocumeNa Help
Smoke Model Results
i BUILDING DESCRIPTION
I HYY•M (In Da,< M mot) • 14.5 m
Ploor area rk D1a.,W.-
SMOK E YODEL DESCRIPTION
j Rt<lype: TNt9. Egn.Sz
vsw DD74a. Eqi. D]. Aaerrrsletri, pkme. ,mall
4r0< dianwer soum.
Do rM <hape to ausYr^^ralric plume Y opernD
Oa14ct aM modify IMnle Ikrn<kripr:p<trMr
Smok<2mlperatue tW<n ss lM av,r lath
i rer
Rath.. k,s<, fmm Nye nM -d.
CatMa[ire Mzes born kYer rat k i KkKl.
"y toanrk,ti s,I,
s rkk of :„ak< per ties = D Dn kDhf
NTILATION PROVISIONS J !.
I,
I:
I
Time (a)
Convedlrc
F1etY rek:•u
Smoke mesa
�,, (kB h)
Smoke
Telrq. ('L7
Vera mess
Illlw (kg /5)
pes Layer
MaYRf (m)
Visibility (m)
Flolm
570.0
659.5
1fi18
30.22
O.f10
7.69
11.0
Vert•df
60040
730.8
1805
31.75
0.00
6.91
10.0
Vents df
630.0
805.7
1580
33.38
0.00
6.74
9.2
VeNS off
690.0
884.3
1567
35.09
0.00
6.56
. 8./
VeNs off
690.0
969.5
15.14
3869
0.00
6.39
7.7
Vents off
720.0
10524
15.20
38.78
0.00
6.22
7.1
Vents off
750.0
1141.9
11.95
/0.77
Q00
6.06
6.6
Vents df
- 780.0
1235.1
1 /.W
/2.86
0.00
5.90
6.1
Vents off
810.0
1331.9
11.12
15.05
000
5.75
5.7
Veils Off
BI0.0
14321
1/.13
17.34
0.00
5.60
5.3
Vents dl
870.0
15385
13.82
19.75
600
5.45
4.9
VeNS all
_ B x
I Case Script - - --
Dm :en wa,a
crta[<d by a�a.. N<d•es on Tkasd<1'. aa<e<r
19.2000
j Ya. Gowp Pke
FIRE DESCRIPTION
I FIr4 CoMaNs
jCenvtwiv< fnaion • ro i
1" rtlu,e 1e•11D4W /ma
iln lead Dens<y • 0 MI / m
i CalaYfk wake of fuN - IS 141 /kf
� Fn tpA. T - Sprar<A
! fke MY oupul • OD010 a [ � kYl'
COMPARTMENT DESCRIPTION
YNdm•DDm
Hei•M • OD m
Oepte • 0D m
! wlneoa .am • oA m
'. YNndw MYM • OA m
i YVmdo. ease aeove Iba keel • OD m
floor arts -pDm/
ndw arts • D.D m I
I C4mpanm<M suriao< arts = 0.0 m %
.DDo
i wkeny MpM • OA m
lrcany dpN • DO m
ChmeYZq urten .:dm = 0 0 m
j BUILDING DESCRIPTION
llaipt (fart ease to mol) = 14.5 m
P1oor arts f4' O to nil n
I
iSMOKE MODEL DESCRIPTION
nNltMtyp<: TA19. EOTt. 32
� e DD740, E4i� 31 Altlsvmmenc pMM. smart
Iw•. eamNa soum..
� De tw[ cMrge [o aakvmmeno plume a opain0
ID.tea and mo3ry pk,nthen nam< •reero<m <r
i
fmoke trarp<mN<tak4n as tM average ratM
Yer.
I RaelNrt<k,,., Iran bv.r:at aakre.a.
I
Iron: nr<r na InekMM.
.. Y to a relkcllre slpl.
s, yk+d o1 make paeoks • 0
D15 M•M•
J
C: \WINDOWS \TEMP \0002APPENDIX C -SMOKE ANALYSIS.DOC Page DS Ove Arup &Part
ners Consulting Engineers PC
Draft 1 May 5, 2001
D15 M•M•
J
C: \WINDOWS \TEMP \0002APPENDIX C -SMOKE ANALYSIS.DOC Page DS Ove Arup &Part
ners Consulting Engineers PC
Draft 1 May 5, 2001
Aruphre
Appendix D
Trial Designs
Town of Vail, Colorado
CONTENTS
D -1. TRIAL DESIGN 1 - CONTROL MAXIMUM HEAT RELEASE RATE
D -2. TRIAL DESIGN 2 - SMOKE MANAGEMENT
Dobson Ice Arena
F:\ GGOODELL \1CCPERF\DOBSON \0002APPENDIX D - TRIAL DESIGNS.DOC Ove Arup & Partners Consulting Engineers PC
Draft 1 May 5, 2001
Town of Vail. Colorado
Dobson Ice Arena
D -1. TRIAL DESIGN 1 - CONTROL MAXIMUM HEAT RELEASE RATE
In order to increase flexibility in use of the space, it may be possible to limit the heat release rate
of the fuel, for fuels having a high fire growth rate.
The following two figures illustrate that by limiting heat release rates to l MW and 0.75 MW for
fast and ultra -fast growth rate fires respectively, that this should delay the descent of the upper
layer to 8 feet above the mezzanine level to times that may be associated with that calculated for
egress, including detection and pre- movement times.
F:\ GGOODELL \ICCPERF\DOBSON\0002APPENDIX D - TRIAL DESIGNS. DOC Page D I Ove Arup & Partners Consulting Engineers PC
Draft 1 May 5, 2001
Town of Vail, Colorado
�<Xr.aw V« 2.1 U .ry 2W
Re DescrWtron BWdmg Detaes Smoke NorMl I Verd#ztion OPtiorrs i Process Options I a
Fire Type 7;?
O x
Fire and Fuel Con!
000 4w
Convective fraction:
Heat release rate:
Fuel load.
Calorific value for fuel 0004w
Combustion efficiency
Steady State Fire
Compartment fire I
o4w
User defined: o w em W no M
Heat Release (IA1Q against Time (s)
Steady state after
Steady state post fl Time HeatRelease(kW) HeatRelease2
"ate: Filt> --
File name:
Figure D -1- Fast Fire With Maximum Heat Release Rate limited to 1 MW
Dobson lee Arena
_ 61i xl
Figure D -2 - Smoke Level - Fast Fire With Maximum Heat Release Rate limited to 1 MW.
F:\ GGOODELL \ICCPERF\DOBSON \0002APPENDIX D - TRIAL DESIGNS.DOC Page D2 Ove Arup & Partners Consulting Engineers PC
Draft 1 May 5, 2001
Town of Vail, Colorado
Fke Desorption ; gril" Doaas Smoke Model 1 Ventilation Option Process Ol#lons
Fire Type iT- Squ, -
Fire and Fuel Con
Convective fraction:
Heat release rate
Fuel load
Calon fi c value for fuel:
Combustion efficiency
Steady State Fire
* Compartment fire:
r Userdefined
Steady state after:
r Steady state post f
File name
Dobson Ice Arena
_1011 XI
Figure D -3 - Ultra Fast Fire With Maximum Heat Release Rate limited to 750 KW
,+.*' Tsaw Vera+ M"MV 20" sly! xJ
F.. Description I BUINI g Detass I Smoke Me" I VenWm— 0O ns I Process Opfksu I
Fire Type IT - 8qua x
Fire and Fuel Con
Convective fracti on.
Heat release rate:
Fuel load
Calorific value for fuel
Combustion efficiency
Steady State Fire"
Compartment fire
Userdefined:
f Steady state after.
r Steady state post t
,;1 , F;;c Firc _
File name
Figure D-4 — Smoke Layer for Fast Fire With Maximum Heat Release Rate limited to at 750 KW.
F:\ GGOODELL \ICCPERF\DOBSON\0002APPENDIX D - TRIAL DESIGNS.DOC Page Dj Ove Arup & Partners Consulting Engineers PC
Draft 1 May 5, 2001
Town of Vail, Colorado
D -2. TRIAL DESIGN 2 - SMOKE MANAGEMENT
El
Dobson Ice Arena 1
Another means that could be used to increase the flexibility of the arena if it is desired to have
fuel loads of fast/ultra -fast growth rates would be to provide a smoke management system. The
following graph indicates the effect of 100,000 CFM of extract for a fast growth rate fire and its
resultant delay in the descent of the upper layer.
Figure D -5 Effect of Smoke Management System on Upper Layer Descent
III 1<
fie View CmMBD. -Rams H*
- - -... _Smoke Model Results __ Case Script - -- - -
i
Fft Wm
- �..
Bsdq
J
Fee
I '
I MDI
CnaN BY w PP IMGw. m wP4B WPINN, -
moo
IBIS' C.II..NF.. fan OP- Fn
FIRE DESCRIPTION
Nn CBrM.rb
Cm..aM haNMm • TB S
Nul slew Ike .
NO YW /m4
in lmt D.INBY • O
CaMi AN N hN - • 1. IB W W /YO
Fr 1)p.. T 5pgrat
Fln Mr. 0,IFQH5'tjkW
/
S.w N %UNMY _. NNS - U 0
000W
COIPMTIENT
DESCRIPTION
n.oDm
Dead, .ODm
. }N •ODm
MBB'O.Om
Bawd.•. Ibd N.tl •ODm
ikalana•DDma
•ODm
I � C.mP�BIwN w1sB /wa • BD m
.911MIe � -- -- - NlBmy NNya • OD m
Bak ,dSm, •" P
CnnwtlNN sawn M!n -CAR,
Tyne (s)
c011VeLT"e
HeM'ebsse
(WY)
��IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIII�
6mDke
T-W CC)
Vero -
lbw (kg k)
CbW LerW
Heist (m)
VISb41Y Im)
Niles
930.0
7000.0
46.25
120.65
3754
696
2.4
!...�illll
960.0
7000.0
45.38
.
IIII������IIIIIIIIIIIIIIIIIIIII��B
6.75
24
Vents m Mleclive
9900
7000.0
44.57
125.99
37.45
665
23
,��i��lllllllllll
1020.0
7000.0
4383
12848
37.22
6.56
IIIIIIIII
Verism leffeCt a
10500
III���IIII��IIII
4314
130.90
36.99
647
!4e�111111111111111111111
Vents m e0ective
10800
7000.0
42.50
133.28
36.78
6.39
,
Vents m eBectiYe
Illlllllllllllllllr
7030 0
41.91
135.6D
36.57
632
..��IIIIIIIIIIIIIIIIIIIIIIIIIII
Vents On effectwe
1U0.0
7300.0
41.35
137.87
36.37
6.N
2.2
Verism eNective
1170.0
70000
IIIIIIIIIIIIIII��IIIIIIII����
140.10
36.17
618
22
Verttm IeBective
1200.0
7000.0
4036
...!����1111111111111
35.98
6.11
2.1
Vents m lellxllve
12300
70000
3990
IIIIIIIIIIIle11111111111111111111111111111111111�
35.80
6.05
2.1
Verism (e-t-
1260.0
7000.0
39.48
146.48
35.62
6.00
2.1
1111111!,
illllllllllllllllllllllllllllllllllllllll
. ����111111111111111111111111111111111111111111111
CnaN BY w PP IMGw. m wP4B WPINN, -
moo
IBIS' C.II..NF.. fan OP- Fn
FIRE DESCRIPTION
Nn CBrM.rb
Cm..aM haNMm • TB S
Nul slew Ike .
NO YW /m4
in lmt D.INBY • O
CaMi AN N hN - • 1. IB W W /YO
Fr 1)p.. T 5pgrat
Fln Mr. 0,IFQH5'tjkW
/
S.w N %UNMY _. NNS - U 0
000W
COIPMTIENT
DESCRIPTION
n.oDm
Dead, .ODm
. }N •ODm
MBB'O.Om
Bawd.•. Ibd N.tl •ODm
ikalana•DDma
•ODm
I � C.mP�BIwN w1sB /wa • BD m
.911MIe � -- -- - NlBmy NNya • OD m
Bak ,dSm, •" P
CnnwtlNN sawn M!n -CAR,
Tyne (s)
c011VeLT"e
HeM'ebsse
(WY)
Smoke C e
Ilow (kg h)
6mDke
T-W CC)
Vero -
lbw (kg k)
CbW LerW
Heist (m)
VISb41Y Im)
Niles
930.0
7000.0
46.25
120.65
3754
696
2.4
Vert, m 1aHmW.1
960.0
7000.0
45.38
123.15
37.69
6.75
24
Vents m Mleclive
9900
7000.0
44.57
125.99
37.45
665
23
VenNm ellecI-
1020.0
7000.0
4383
12848
37.22
6.56
2.3
Verism leffeCt a
10500
7000.0
4314
130.90
36.99
647
203
Vents m e0ective
10800
7000.0
42.50
133.28
36.78
6.39
22
Vents m eBectiYe
1110.01
7030 0
41.91
135.6D
36.57
632
2.2
Vents On effectwe
1U0.0
7300.0
41.35
137.87
36.37
6.N
2.2
Verism eNective
1170.0
70000
40.84
140.10
36.17
618
22
Verttm IeBective
1200.0
7000.0
4036
142.27
35.98
6.11
2.1
Vents m lellxllve
12300
70000
3990
WAG
35.80
6.05
2.1
Verism (e-t-
1260.0
7000.0
39.48
146.48
35.62
6.00
2.1
Was effective
BUILDING DESCRIPTION
N.iBN On Ss» I. Iv ,) • 14.6 m
FYwra •m00.a ma
SMOKE YODEL DESCRIPTION
Pnmwt,e._ NFPAWB. Em. 14
NxI -ivew 1MIB Fgn.61 / DOMB. Eqs. 3J
IWrrmwllk WnE MY I.. aBw. 11NBYN nei
N - FPMxM- atarrlwek 0- a _N
A.qN.
De.w MNI Away PY . a1I. Yrengm.r
Rata N. base hwn brw Iw LwN4aE.
c«rlm.. rn.. N.m Ny.r nw n..•tat.
rn anaaNe Elm.
a yNMI el Fm W. BneMF • DAN Yp�p
With Ventilation (100,000 cfm) NTILATDNrRDVSIDNf _j
F:\ GGOODELL \ICCPERF\DOBSON\0002APPENDIX D- TRIAL DESIGNS. DOC Page D4 Ove Arup & Partners Consulting Engineers PC
Draft 1 May 5, 2001
r