ADD/ALTSFRBUILDPERMT Permit #: B,02-0272
Job Address: 5148 GORE CR VAIL
[,ocation.....: 5148 GORE CIRCLE
ParcelNo...: 209918203003
ProjectNo | ?p1p2-O(??
ovitNER coNNEI_,Ly, MICEAEIJ & SAI_'LY O8/2L/2002 phone:
5148 MAIN GORE CIR
VAIIJ CO
816s7
Lricense;
COrflTR,ACTOR HORN BROS. ROOFING
7717 W. 5TH AVE,
Suite E
Lrakewood, Co 802!4
Lricense: 708-B
APPIJICANT HORN BROS. ROOFTNG
7717 W. 6TH AVE,
Sui.te E
Lakewood, Co AO214
License: 708-B
o8/2L/2oo2 Phone: (303) 274-L1L7-
o8/2L/2002 Phone: (SOg) 274-L7.L7.
Description:
REMOVE CEDAR,INSTA]-,L ICE/WATER SHIELD. INSTAIIJ NEW VAI-'I'EY
METAI-,. INSTATI., GERARD ROOFI}IG TECHNOI-,OGIES
Occupancy:
Type Construction:
Valuation: $18,100.00 Add Sq Ft 0
Fireplace Information: Restricted: Y # ofGas Appliances: 0 # ofGas Logs: 0 #of WoodPellet 0
Building---> $23s.00 R$hrarant Plan Review-> $0.00 Total Calculat€d Fe€s-> $390.75
Plan Check-> 5152 . ?5 DRB Feo----> 50.00 Additional F€€s----> 90.00
Investigation-> $0.00 Recrcation F€€ - -> $0. 00 Totol Permit Fee-.> $390. ?5
Will Cdl-__> S3 .00 Clcan-up Depo6it--> go. oo Pryrnents.---> S390. ?5
TOTAL FEES---> S3e0.rs BALANICE DUE--> $0.00
Stafus...: ISSUED
Applied. . : 08121n002
Issued. .. : Q8/21/20Q2
Expires...: 02/17/2003
Approvals:Item: 05100 BUII-,DING DEPARTMENI
O8/2L/2OO2 DF Action: AP
IEem: 05400 PIJANNIIIG DEPARTMENT
Item: 05500 FIRE DEPARTMENT
Item: 05500 PUBLIC WORKS
See page 2 of this Document for any conditions that may apply to this permit.
DECLARATIONS
I hereby acknowledge that I have read this applicafion, filled out in firll the information required, completed an accurate plot plan,
and state that all the information as required is conect. I agree to comply with the information and,ptot plan, to cornply with all
Town ordinances and state laws, and to build tlris stucture according to the towns zoning and subdivision codes, dssign review
approved, Uniform Building Code and other ordinances of the Town applicable thereto,
REQIJESTS FOR INSPECTION SHALL BE MADE TWENTY-F1f,UR HOURS IN ADVANCE BY TEIEPHONE AT 479-2138 OR AT OUR OFFICE FROM 8:00 AM - 5 PM.
Send Clean-up Depoeir To: N/A
OF OWNER OR CONTRACTOR FOR HIMSELF AND OWNER
PAGE 2********'t'****,}{.*'t**i.,tlt*'}{.{t******,t.'**:t****,t.*4t****+*:}****,t**'t**************{.**{.,t*:f'}:*'#'|('t**:|!{t|**
CONDITIONS OF APPROVAL
Permit #: 802-0272 as of 08-21-2002 Status: ISSLIED
{.**'t***{t't*'|t*{.'|.t**1.'|.*{.'}***,N.*:t.,.****t&*!t.***+**********{'*,t.!l,|(,}*!t.'F**'t!|tlt
Permit Type: ADD/ALT SFR BUILD PERMIT Applied: 0gl2t/2002
Applicant: HORN BROS. ROOFING Issued: 08Dl/2002(303)274-llll To Expire: 0A17/2003
Job Address: 5 148 GORE CR VAIL
Location: 5148 GORE CIRCLE
ParcelNo: 209918203003
Description:
REMOVE CEDAR,INSTALL ICVWATER SHIELD. INSTALL NEW VALLEY
METAL. INSTALL GERARD ROOFING TECHNOLOGIES
****{.,F*,l*:**'|,*'|''t4.t|.'.*'t***+*************t$:t***,***,t*:tt:t'8Conditionsi{t*********'l.*+{.+:t.*+**'t.*$1.*'|*+**l.*t,********+
Cond: 12
@LDG.): FIELD INSPECTIONS ARE REQUIRED TO CHECK FOR CODE
COMPLIANCE.
Cond: 16
(BLDG.): SMOKE DETECTORS ARE REQUIRED IN ALL BEDROOMS AND
EVERY STORY AS PER SEC.3IO.9.1 OF THE 1997I.JBC.
* * * * * * * * + * * * * * * * + * * * * * * * * + 'l * * * * * * r' * * * * * * r' * *** **f t ** | t * t + $ * * * * ** t t * * f * ** + ** ** **** * * * * * * * **** *
TOWN OF VAIL, COLORADO Statement
* * * * i * t * * * +* * ** ***** **** * * t * 'l' * * * * + t * * * +*** t * a +f *f + +f*+* + +* * *+ + f{'** +** * * I * t t * * * * *** **** * * * * **
Statement Number: . R000002913 Amount I 9390.75 Oe/2t/200208r56 AM
Payment Method: Check IniE: DDG
Notation: Rocha 3074
Permit No: BO2-0272 Type 3 ADD/Ar,T SFR BUILD PERMIT
Parcel No: 209918203 003
Sit.e AddreEE: 5148 GORE CR VAIL,
LocaCion: 5148 GORE CIRCLE
Total Feea: $390,75
This Payment: $390.?5 Total AL,L Pmt6: $390,75
Balance: $0.00,3********'****+*+******+***f+*****l'*********,**la***t*t**'i*t*'tt *. *+ i. ***** ** * ** * ** ***'t( * tt '* * * ****
ACCOUNT ITEM LIST:
Account Code DescniDtion Cument Pmts
BP OO1OOOO31111OO BUILD]NG PERMIT FEES 235.00
PF 00100003112300 PLAN CHECK FEES 75?.75
l.lc OO1OOOO31128OO WILL CALL INSPECTION FEE 3.OO
6^q6-"7#
ILDI
fort>
INFORMATION
ll
APPLICATION $''@tr){rn
Permit#:
MWIIOPVAIL
75 S. Frontage Rd.
Vail. Colorado 81657
Phone#'s: 3o3.22<l'o-{E ltla8o.4 3o3.8A.1,, lg.l'""(,odte,t
COMPLETE VALUATIONS FOR BUILDING PERMIT (Labor & Materials
BUILDING:$ELECTRICAL:$Ortre*,$ lg, lorl S
PLUMBING: $MECHANICAL: $TOTAL:$
For Parcel # Contact Assessors Office at 970-328-8640 or visit
Wrlteao3ooj
Job Name: Pt:Kz f'.n tlX
c-L
JobAddress: St y I e"e, 6,<"lt
LegalDescription ll lot 5 Bbck: 3 Firins:
gshfjifB-
ll t"4rySlg
Owners Name: rh' €p1';?lg r<%,t&<elL Phone:*ro,-ll6J,bs3
ArchitecVDesigner:Address:Phone:
Engineer:Address:Phone:
ic lJ') 5^ A'I,tlt uta)-riii;{
rat
Workc|aSs:New()Addition()Remode|()Repair()D"
WorkType: Interior( ) Exterior( ) Both( )boes an EHU exist at this location: Yes ( ) No ( )_
Type of Btdg.: Single-family (7$ Two-family ( ) Multi-family ( ) commercial ( ) Restaurant ( ) other( )
No. of Existing Dwelling Units in this building:No. of Accommodation Units in this building:
NoffvpeofFireplacesExisting:GasAppllances()GasLogs()Wood/Pellet()WoodBurning():
No/Tvpe of Fireplaces ProPosed;
Toes aTireTiErm exlst Yes ( ) No (@Yes() No()
*******ri******ffi1*i!*s*s**rkr*FoR OFFICE USE ONlY******rffittr****i**l*****f.ftft**
7,lr
RE0D AUU 2O ZOOZ
0712612002
\\Va ilBata\cdev\FORMS\PERMITS\BLDGPERM.Doc \ffIozo\5\
o
U
u
tr
u
o
D
tr
Questions? Call the Building Team at 479-2325
Department of Community Development
Project Name:+ S,.t/
Project Address:
/ This Cheklist murt be omoletd beforc a Buildino Permit application is
acepted.
All pages of application is complete
Has DRB approval obtained (if required) Provide a copy of approval form \ A??eetJ
tr
tr
D
D
tr
o
LI
Condominium Association letter of approval attached if project is a Multi-Family complex
Complete site plan submitted
Public Way Permit application included if applicable (refer to Public Works checklist)
Staging plan included (refer to Public Works checklist) No dumoster,oarkinq or material storaqe
allowed on roadwavs and shoulders without wriften approval
Asbestos test and results submitted if demolition is occurring
Architeci stamp and signature (All Commercial and Multi family)
Full floor plans including building sections and elevations(4 sets of plans for Multi-Family and
Commercial)
Window and door schedule
Full structural plans, including design criteria (ie.loads)
Structural Engineer stamp and signature on structural plans (All Commercial and Multi Family)
Soils Report must be submitted prior to footing inspection
Fire resistive assemblies specified and penetrations indicated
Smoke detectors shown on plans
Types and quantity of fireplaces shown
Applicanfs Signature:
Date of submittal:
F:/everyone/forms/bldperm2
Received By:
BUILDING PERMIT ISSUANCE TIME FRAME
If this permit requires a Tpwn of Vail Fire Department Approval, Engineer's (Public Works)
review and approval, a Planlning Department review or Health Department review, and a review
by the Building Department, the estimated time for a total review will take as long as three (3)
weeks.
All commercial (large or sfinall) and all multi-family permits will have to follow the above
mentioned maximum requirpments. Residential and small projects should take a lesser amount
of time. However, if residential or smaller projects impact the various above mentioned
departments with regard to necessary review, these projects may also take three (3) weeks to
review and approve.
Every attempt will be made by this department to expedite this permit as soon as possible.
I, the undersigned, understand the plan check procedure and time frame. I also understand
that if the permit is not picked up by the expiration date, that I must still pay the plan check fee
and that if I fail to do so it ftay affect future permits that I apply for.
Agreed to by:
Print narlne
rrrt""r*
Project Name:
Date:
F : everyone/forms/bldperm3
/ffi."\E4/
NtN0FWnll
HOW DIDWE RATE WITH YOU?
Toum ofVailSurvey
Community Dwelopment Deparfnent Russell Fones! Director,
(970)47e-2139
Check alf that applies-
1. Which Department(s) did you contacg
Building _ Environmental_ Housing_ AdminPlanning DRB _ PEC _
' i:' 2. Wasyourinitialcontactwithourstafiimmediate_slow_or ''r i 'l '
no one available___r_?
3. lf you were required to wait, how long was it before you were
helped?_
4. Was your projixt revieued on a timely basis? Yes / No
lf no, why no?
5, WasfiisyourfirstlimebfileaDRBapp_pECapp_ i. :l
Btdg Permit_ l,t/A | :
6. Please rate fie performance of he staffperson who assisted you:5432lName:
(knowledge, responsiveness, availability)
7. Overall efiectiveness of the Front Service Counter. 5 4 3 2 1
8. What is the best time of day.for you to use fre Front Service
Counter?
9. Any comments you have which would allow us to beter serve you
nexttime?
Thank you for taking the lime to complete this survey. We are
committed b improving our service.
ruri|J0F
WHEN A*PUBLIC WAy PERMIT" rS REQUIRED
PLEASE READ AND CHECK OFF EACH OF THE FOLLOWING QUEMONS REGARDING THE NEED FOR A
"PUBUC WAY PERMIT":
Is this a new residence?
Does demolition work being
public property?
YES
performed require the use of the Right-of-Way, easements or
Is any utility work needed? YES
Is the driveway being repaved?
Is a different access needed to the site other than the existing driveway? YES_
ls any drainage work Seing done that affects the Right-of-Way, easements, or public poIs any drainage work or public property?
YES NO
Is a "Revocable Right-of-Way Permit" required?
NO,
NO
NO
NO
Is the Right-of-Way, ebsements or public property to be used for staging, parking or fencing?YES_ NO____r_
If answer is NO, is a parking, staging or fencing plan required by Public Works?YES NO
If you answered YES to any of these questions, a "Public Way Permit" must be obtained,
"Public Way Permit" applications may be obtained at the Public Work's office or at Community
Development (a sample is attached), If you have any questions please call Leonard Sandoval in Public
Works at 479-2198.
I HAVE READ AND ANSWERED ALL THE ABOVE OUESTIONS.
Contractor Signature
Job or Project Namer
Date Signed:
F:/everyone/forms/bldperm4
Company Name
APPLICATION
FOR TOWN OF VAIL
PUBLIC WAY PERMIT 19
pw*:I[-fIIr
PATCEI#:T f, N I T N T' N T. T T T
Brds. Permit#,8 [ I'I I n I
1.Job Name Str€st Address I ll ll l- | (llunKnown carlLJ I rLl LJ 479-2136 6*1.91
ApCity Phone #
4.
Start Date
Work is for (circte onel
Completion Date
Water Sewer Gas Electric
(Permit Explration Date)
Telephone CATV Landscaping Temp.SiteAccess
Other
c.Trench-width
(min,4'I
Bond Amount $
ALL MATERIAL. EOUIPMENT. AND TRAFFIC
JOB IS STARTED.
7.Rubber out-riggers ere required on
Asphalt surfaces underneath the
A signature below indicates a
signatures are obtained, permittee
necessary Town of Vail signatures.
BE ON THE JOBSITE BEFORE THE
working on asphalt.
at all times.
utility locations and approvals. Once all utility company
application through the Public Works office to obtain the
up to one week to process.
Depth
Total SF $
Total LF $
Permit Fee Total Permit Fee
Public Seruice Company (1-800-
Public Service Natural Gas Group (1-600-922-1987)
U.S. West (1 -800-922-1 987)
TCI Cablevision of the Rockies (1-800-922-1987)
Eagle River Water & Sanitatlon District (970-476-7480, ext.
Holy Cross Electric Company (1'800-922-1987)
Town of Vail Electricians (970-47S-2158)
Town of Vail Inigation (970-479-2158)
Town of Vail Public Works Construction Inspector (970-479-2198)
9.
10.
11.
12.
THERE WILL BE NO TOTAL STREET CLOSURESI A construction traffic control plan must be approved by the
Public Works Department prior to issuance of the permit,
All excavation must be done by hand within 18" of utilities - (Senate Bill 172).
Permittee must contact Public Works Deoarlmeni at 479-2198 24 hours prior to commencing of work. Failure to notify
lhe Town will result in forfeiture of bond money. Schecluled inspections which are not ready may result in the Town
charging the contractor a reinspection fee.
I ceftity that I have read all chapters of Title 8 - Public Ways and Property, of the Vail Municipal Code and all ulility
company agreements, signed liy me, and will abide by the same, and that all utilities have been notified as required.
Contractor's of Agreemont namg clsarly
ATTACH PLAN OF WORK, INCLUDING CONSTRUCTION TRAFFIC CONTROL PLAN
Show streets with names, buildings, and location of cuts. USE DASH LINES FOR CUT.
Date ol Signature
White - Public Works
Yellow - Contractor
How it relates to Building Permits:
Fill out the attached che[k list wth the Buitding permit Aoptication.
If yes was answered to any of the questions then a "Public Way" permit is required. You
can pick up an applicatifn at either Community Development, located at 75 South Frontage
Road or Public Works, lQcated at 1309 Elkhorn Drive.
Notice sign-offs for uti companies. ALL utilities must field verifo (locate) respective
utilities prior to signing
schedule a locate.
pplication. Some utility companies require up to 48 hours notice to
A construction traffic staging plan must be prepared on a separate sheet of paper.
An approved site plan
devices (signs, cones,
also be used. This plan will show locations of all traffic control
.) and the work zone, (area of construction, staging, etc.). This
plan will expire on lst and will need to be resubmitted for consideration for
approval through the er. Be aware that your resubmission for winter may be denied
of construction.depending on the
Sketch of work being must be submitted indicating dimensions (length, width
and depth ofwork). Th may be drawn on the traffic control plan or a site plan for the job.
Submit completed to the Public Work's office for review. If required, locates will
be scheduled for the T of Vail electricians and irrigaUon crew. The locates take place in
ire up to 48 hours to peform.the morning, but may
The Public Workt Inspector will review the application and approve or deny
the permit. You will
needed. Most permits
contacted as to the status and any requirements that may be
released within 48 hours of being received, but please allow up
to one (1) week to
As soon as the permit
"Building Permit" to be
"Building Permit".
approved, the Building Department will be notified, allowing the
Please do not confuse the "Public Way Permit" with a
D NOTE: The above is for work in a public way ONLY. Public Way
Permits are valid until November 15th. A new Public Way Permit is required
each year if work is
mean an automatic
complete. Re-application each November 15th does not
I have read and understa the above.
Date Signed
IJJ/MIAF
DRAINAGE AND CULVERT TNSPECTTONS ARE REqUTREp By PUBLTC WORKS!
Please read and check off each of the items below:
a The Town of Vail Building Department has developed the following procedures to
ensure that new construction sites have adequately established proper drainage
from building sites along and adjacent to Town of Vail roads or streets.
n The Town of Vail Public Works Department will be required to inspect and approve
drainage adjacent to Town of Vail roads or streets and the installation of temporary
or permanent culverts at access points from the road or street onto the construction
site, Such approval must be obtained prior to any requests for inspection by the
Town of Vail Building Depaftment for footings, temporary electrical or any other
inspection. Please call Leonard Sandoval at 479-2198 to request an inspection from
the Public Works Depaftment. Allow a minimum of 24 hour notice.
o Also, the Town of Vail Public Works Department will be approving all final drainage
and culvert installation with resulting road patching as necessary. Such approval
must be obtained prior to any Final Ceftificate of Occupancy issuance.
Agreed to by:
Print Name
Project Name:
Date Signed:
F:/everyone/forms/bldperm6
Signature
read and check off each of the items below.
of complete text are available upon request)
CODE 5-2.10: DEPOSITS ON PUBLIC WAYS PROHIBITED
Unlawful deposits: SuO;ec{ to subsection C thereof, it is unlawful for any person to litter, track or
deposit, or cause to be littdred, tracked or deposited, sand, gravel, rocks, mud, dift, snow, ice, or any
other debris or material upon any street sidewal( alley or public place, or any portion thereof.
Notice; Abatement: The Director of Public Works may notiff and require any person who violates or
causes another to violate thp provision of subsection A hereof, or who has in the Director's employment
a person who violates or causes anodrer to violate the same, top remove such sand, gravel, rocks, mud,
dirt, snow, ice or any other debris or material within twenty four (24) hours after receipt of said notice
by the Director of Public Wprks. In the event the person so notified does not comply with the notice
within the period of time hQrein specified, the Director of Public Work, or other authorized agent, may
cause any such sand, gravdl, rocks, mud, dirt, snow, ice, debris or any other material to be removed
from any street or alley at the expense ofthe notified.
Summons and Penalty: As an alternative to the notice for removal provided in subsection B above,
any person who violates or causes another to violate the same, may be issued a summons to appear
before the Municipal Court of the Town for said violations, and upon being found guilty of a violation
hereunder be punished as prrovided in Section 1-4-1 of this code.
Notice and Penalty: It it unlawful for any person to fail or refuse to comply with the notice of the
Director of Public Works as;Provided in subsection B hereof, and any such person shall, in addition to
payment of the expense of incurred by the Director of Public Works, as provided in subsection B
hereof, upon being found ilty of a violation hereunder, be punishable as provided in Section 1-4-1 of
this Code. (1997 Code:nce 6 (1979),
coDEs 7-3A-1 AND 7-3A-3:OBSTRUCTING TRAFFIC & IMPOUNDMENT AUTHORIZED
a No person shall park any upon a street or at any other place within this Municipality in such a
as to interfere with the free movement of vehicular traffic or propermanner or under such
street or highway maintenance. (Ord. 2(1968) g 1)
D Whenever any police officeq finds a vehicle attended or unattended, standing upon any portion of a
street or upon any place wifhin this Municipality in such a manner as to constitute a violation of any
section of this Article, or left unattended for a period of twenty four (24) hours or more and presumed to
be abandoned under the cpnditions prescribed by Colorado Revised Statutes section 42-4-1102, as
amended, the officer shall rfquire the vehicle to be removed or cause it to be removed and placed in
storage in the nearest garagf or other place of safety designated or maintained by this Municipality, and
the charges for towing and storage of such vehicle shall be charged to the owner of the vehicle in
addition to a ten dollar ($10) impoundment charge. (Ord. 2(1968) g 3: Ord. 28(1981) S 1)
I have read and will comply with thd above code provisions:
Print Name
Position or Relationship to Project:
Date Signed:
F:/everyone/form s/bld perm T
Signature
Vail 2002
Vail Village/Lionshead Construction Hours Handout
The Vail Village and Lionshead are invaluable assets to the community. Thousands of
people come to Vail each year to sightsee, recreate, shop and to enjoy the Vail Valley.
The community and merchants rely upon the summer/winter tourism to generate
revenue. Our summer/winter guests expect a pleasant experience while in Vail.
To insure that all of the proposed construction has as little negative impact on the
community and on our guest as possible, the Town of Vail finds it imperative to create
and implement the Vail Village/Lionshead Construction Master Plan. Maps of the Village
and Lionshead are included to show areas of construction being affected by this plan.
It would be irresponsible for the Town of Vail, the Construction Contractors and the
Merchants, to not actively participate to minimize the impact of construction on the Village
and Lionshead areas.
Givens
The following givens are intended to provide the basic foundation by which construction
will be completed in the Village:
. The public's health, safety and welfare shall be honored at all times.
o Adequate pedestrian, loading/delivery, vehicle, and emergency vehicle access and
circulation shall be maintained.
r Roadways and pedestrian walkways shall be kept clean and free of dirt and debris.
. All construction deliveries, equipment, tools, materials, etc. to the Village must go
through Check Point Charlie. All Lionshead construction activity must go to the Vail
Police Department for a parking permit. Do not use delivery zones for construction
parking, refer to approved staging plan or make other arrangements for parking.
. The hours of Outside Construction Activity shall be as follows:
- April 15 - June 21 & September 9 - November 15,7 a.m. until 7 p.m., seven days
a week. Between June 22 -September 6 work must end bv 4:00 p.m. on Fridavs'
November 15 - April 15, 2003 work allowed within daylight hours only'
- Deliveries shall be restricted to the hours ot7 a.m. to 11:30 a.m. on Gore Creek
Drive and 7 a.m. to 8:30 a.m. on Bridge Street.
- Special delivery permits must be requested in advance, from Public Works in
conjunction with Code Enforcement at Checkpoint Charlie.
- No construction activity shall occur on Saturday or Sunday between June
22 & September 6
No outside activity shall occur on the following dates:
Friday,15, Saturday, February16, Sunday, February 17, and Monday,
February
Saturday,
8. {Presidents Weekend}
25, Sunday, May 26 and Monday, May 27 (Memorial Davl
Friday,28, Saturday, June 29 and Sunday, June 30. (Vail Arts Festival)
Wed
Sunday,
July 3, Thursday, July 4. Friday, July 5, Saturday, July 6 and
Z.(hCependence Day)
Saturday,31, Sunday, September l, and Monday, September2
13, Saturday,September 14, Sunday, September 15 in
September 21 and Sunday, September 22.and then on Saturday,
) - {October Fest)
November 28, ffihanksqivinq Davl Friday, November 29, Saturday,
30 and Sunday, December 1.
December 25, Thursday, December 26, Friday, December 27
Saturday,28, Sunday, December 29. {Christmas Dav Holidavl
Monday,30, Tuesday, December 31, Wednesday January I,
No Work allowed the entire week of the Christmas/New Year
Holiday.
. The Town of Vail Ordinance has been waived by the Town Manager from 7a.m.
o
The following
Village/Lionshead Con
o Full and complete
construction activity
s are established to insure the success of the Vail
Master Plan:
ration and understanding from all parties involved in the
regards to this plan.
r Strict adherence
plan.
compliance with the requirements outlined in the construction
r Respect and
lf you have any q
for the affected interests and parties.
, Please contact the Town of Vail Public Works Department
(Gonstruction I ) or Vail Police Department (Code Enforcement Officer)
Friday,
(Vail
Thursday,
N
- 7p.m. For construotion activities from April 15 through June 21 , and from September
9 through Novembef 15. The Noise Ordinance shall be in effec{ and strictly regulated
from Ju-ne 22 througtp September 8 and November 15 to April 15, 2001
All construction sitep will be required to obtain an Approved Construction-Staqinq
Plan from the Towit of Vail Public Works Department in conjunction with Code
Enforcement. (The {pproved staging/parking plan is required to be on site at all
times).
The Town of Vail re$erves the right io amend the Vail Villagellionshead Construction
Plan regulations at afiyiime should abuses or problems arise.
The Three-Strike frule will be enforced. Step 1. (Written warning), Step 2.
(Written warning), $tep 3. (Construction site will be Red Tag until all issues are
resolved).
i Expectations
970-479-2198 970476-7603
Ir
Vail2002 Staging / Parking Plan Information
The Stasine / Parkine Plan Philosonhv- Is a very important step in the building
process. Striking a balance between safe public access and giving construction projects
room to build is becoming increasingly challenging, for us to meet all the needs of those
who will be impacted by construction projects. The fact is, there is less room to build in
the Town of Vail.
Developing a creative Staging Plan is a must. Staging in the Town of Vail Public Right of
Way is a Privilege, not a given right. We take into account when we review and approve
staging / parking plans, impacts on neighborhoods, tourism, business and the traveling
public along with your right to build.
The Genersl Contractor is resnonsiblc for all subcontractors and all construction
activitv relatine to the buildins oroiect. The staging plan will be enforced according to
the Approved Set of Building and St^ging Plans. You are required to keep a copy of the
Approved Staging Plan on site.
Two staging /parking plans are required, a sunmer and winter. Summer staging plans
expire on November 1, and winter staging plans expire on April 15. (NSIgJb.erejS ng-AI
street parkins in the winter season and all materials. equipment. etc must be 10' off the
edge of asphalt).
Enforcement of all staging / parking plan is as follows.
A) Staging / Parking Plans to scale required.
B) Once the plan is approved, they will be held to complete compliance.
C) We will use a 3 step and you're out, process.
Step One- Verbal and written wamings as to the staging plan violation, then have
contractor sign and date field memo warning.
Step Two- Police Department issue tickets and tows or public works writes second
written waming to all violators who have been notified under step one and who are still
in violation of the approved Staging i Parking Plan. The Town of Vail Chief Building
Official will call the contractor and notiff them, the next time any violation happens, the
building department will red tag the construction site for 48 hours.
Step Three- If still in violation after step two, a 48 hour Red Tae will be issued to the
project site.
If you have any Questions, Please contact the Town of Vail Construction Iaspector at
970-479-2t98
TOIflN|'FVAIL
F:bdev\IFORMS\PERMITS\Staging-Parking.doc
tl
Requirements for an Acceptable Staging Plan
It is preferred that and Approved Site Plan is used to draw a staging plan, but a hand
drawn plan may be used as long as it is dawn to scale and is neat and legible.
l.) The Staging Plan must show the following:
(a) Show all parking that is required for the job site. (Including construction
equipment).
(b) Show the location of all material that will be staged on site.
(c) Show the location ofall dumpsters and port-o-john that are to be on site.
(d) If a fence is required, then show the location of the fence and describe the
material used for the fence.
(e) Iftrees and / or vegetation is required to be protected, then show how this will be
done.
(0 If this staging plan is for a Demo Permit, then show staging for dump trucks and
all related equipment. If the Town of Vail Right of Way area is needed for
staging, then a flraffic Control Plan is required in conjunction with the staging
plan.
(g) Please provide and show an Erosion Control Plan.
(h) No equipment, vehicles, materials are allowed on Town of Vail Right of Way in
the Winter Staging Plan.
2.) If work needs to occur in the right of way, then add a Traffic Control Plan to the
staging plan showing the following:
(a) The work zone (area that is to be performed)
(b) Traffrc Control pevices (waming, signs, cones, flaggers, etc.)
(c) Distances that all devices will be set up from the work zone. Also show all
dimensions of work being performed in the right of way. All traffic control plans
must conform to the MUTCD manual.(Manual of Uniform Traffrc Control
Devices)
2.) This plan will be reviewed by Public Works and if Necessary the Police, Fire, and
Community Development Department. Once the staging plan is approved, it will be
registered with the departments listed above and enforced.
3.) The Village and Lionshead area have outside constuction restrictions, Please become
familiar with the Vail 2002. Vail Villase and Lionshead Construction Hours handout.
F :\cdev\FORMS\PERMITS\SIaging-Parking.doc