HomeMy WebLinkAboutPEC150002 0003 Power Point 032315Extraordinary People.
Extraordinary Care.
Extraordinary Facilities.
Presentation of
West Wing CUP Application
Vail Planning and Environmental Commission
March 23, 2015
1
Today’s Agenda:
Introduction
Tom Braun
2. Massing/Arch/Meadow Drive
Russ Sedmak
Project Overview/Conditions
Tom Braun
Wrap-up
LAGATTA
2
Massing/Architecture/Meadow Drive
Russ Sedmak, Heery
LAGATTA
3
MEADOW DRIVE STREETSCAPE PLAN MARCH 9 REVISION
X
NEW PLANTER/SEATING WALL & LANDSCAPING
EXISTING CENTRAL WING
EXISITNG WEST WING
NEW SOUTH EXPANSION
3.5 ft.(+/-)
7 ft.(+/-)
X
EXISTING CENTRAL WING
EXISITNG WEST WING
EXISITNG SIDEWALK & LANDSCAPING
OUTDOOR DINING COURT W/SCREEN WALL
NEW SOUTH EXPANSION
8 ft.(+/-)
12 ft.(+/-)
X
4
VVMC – WEST WING
FINAL LANDSCAPE PLAN
5
VVMC – WEST WING
FINAL LANDSCAPE PLAN
3 SPRUCE TREES
11 ASPEN TREES
6 ASPEN TREES
3 SPRUCE TREES
EXSTG. TREE TO BE PROTECTED
VVMC – WEST WING
6
SOUTHWEST CORNER EXISITNG
7
SOUTHWEST CORNER PERSPECTIVE
MARCH 9 REVISION
8
SOUTHWEST CORNER PERSPECTIVE
MARCH 23 REVISION
9
EXISTING CENTRAL WING
10
WEST ENTRY EXISTING CONDITION
11
WEST ENTRY PERSPECTIVE
FEBRUARY 23 PRESENTATION
12
NORTHWEST VIEW PERSPECTIVE
MARCH 23 REVISION
13
SOUTH EXISTING CONDITION
14
SOUTH EXPANSION PERSPECTIVE MARCH 9 REVISION
15
SOUTH ELEVATION MARCH 9 REVISION
16
SOUTH ELEVATION MARCH 23 REVISION
17
18
Project Overview/Conditions of Approval
Employee Housing
Parking Lot/Interim Plan
Parking Management
Leased spaces for 15 space reduction
Leased spaces for 41 space demand
Construction Management Plan
Rooftop mechanical
Public
Works comments
Middle Creek
LAGATTA
19
Project Overview/Conditions of Approval
Employee Housing
LAGATTA
20
Project Overview/Conditions of Approval
2. Parking Lot/Interim Plan
LAGATTA
21
Project Overview/Conditions of Approval
2. Parking Lot/Interim Plan
TOV access easement
Buffer between lot and Middle Creek
Town Council sign-off
LAGATTA
22
Project Overview/Conditions of Approval
3. Parking Management
LAGATTA
23
Today - 106 patient/guest spaces
(extensive turnover of parking spaces)
Construction of WW - 91 employee spaces
(limited turnover of parking spaces)
Parking Management will result in significant reduction of VVMC generated traffic on West Meadow Drive
91 spaces
1,325 trips on typical peak day
+/-262 trips on typical peak day
Project Overview/Conditions of Approval
3. Parking Management
LAGATTA
24
Project Overview/Conditions of Approval
3. Parking Management
LAGATTA
25
Project Overview/Conditions of Approval
3. Parking Management
Prior to implementing changes to parking management
Detailed design of interim access improvements,
Town Council approval of improvements to Town Hall site,
Access permit approval
from CDOT for interim South Frontage Road access improvements to both VVMC and Town Hall site,
Construction schedule demonstrating completion of improvements prior to November 1, 2015,
Plans for manual traffic control measures (if deemed necessary by the Town) until such time interim access improvements are in place, and
Plans for how parking changes will be implemented,
to include but not limited to improved wayfinding on Campus and in immediate vicinity (road signs), outreach/education programs, role of valet/concierge, any physical improvements to
East Structure.
LAGATTA
26
Project Overview/Conditions of Approval
Leased spaces for 15 (21) space reduction
Leased spaces for 41 space demand
LAGATTA
27
Project Overview/Conditions of Approval
6. Construction Management Plan
LAGATTA
28
Project Overview/Conditions of Approval
7. Rooftop mechanical
LAGATTA
29
Project Overview/Conditions of Approval
8. Public Works comments
• Demonstrate valet parking conformance with Town Code and potential conflicts with valet spaces and truck turning movements. Any change to the number of valet parking spaces will directly
affect the minimum number of required off-site parking spaces to be leased pursuant to Condition 4,
• Provide a final drainage study,
• Modify drainage plan to route clean groundwater
(from de-watering system) separately from storm water,
• Work with town staff to define the preferred location for the water quality vault.
LAGATTA
30
Project Overview/Conditions of Approval
8. Public Works comments
LAGATTA
31
Project Overview/Conditions of Approval
8. Public Works comments
LAGATTA
32
Temporary
Fence/barrier
Snow Storage
Management
Immediate Improvements completed by 11/1/15
Landscape
Restoration
Project Overview/Conditions of Approval
9. Middle Creek
Water Quality
Vault (potentially)
LAGATTA
33
Wrap Up
Employee Housing
Parking Lot/Interim Plan
Parking Management
Leased spaces for 15 (21) space reduction
Leased spaces for 41 space demand
Construction Management Plan
Rooftop mechanical
Public
Works comments
Middle Creek
LAGATTA
34
End of Presentation
LAGATTA
35
ROOF PLAN
VERTICAL LOUVERED SCREEN
VERTICAL LOUVERED SCREEN
SLOPED ROOF SCREEN
36
Parking and Circulation
LAGATTA
37
Parking and Circulation
LAGATTA
38
Parking and Circulation
West Wing Parking Demand
Parking formula proposed by VVMC MP:
1 space per patient bed
1 space per exam room
1 space per day shift employee
Existing TOV Formula:
Hospital - 1 space
per patient bed
Hospital - 1 space/150sf net floor area
Medical offices – 1 space/200sf net floor area
Offices – 1 space/250sf net floor area
LAGATTA
39
Parking and Circulation
West Wing Parking Demand
Parking formula proposed by VVMC MP:
1 space per patient bed
1 space per exam room
1 space per day shift employee
Existing TOV Formula:
Hospital - 1 space
per patient bed
Hospital - 1 space/150sf net floor area
Medical offices – 1 space/200sf net floor area
Offices – 1 space/250sf net floor area
LAGATTA
40
Parking and Circulation
Basement Level
No new parking demand
LAGATTA
41
Parking and Circulation
Level 1
4 spaces - 2 new employees, 2 new patient treatment tables/HHSM
SPRI parking demand discussed with Level 4.
LAGATTA
42
Parking and Circulation
Level 2
5 spaces – 3 new employees, 2 exam rooms/Cath Lab
LAGATTA
43
Parking and Circulation
Level 3
No new parking demand
LAGATTA
44
Parking and Circulation
Level 4
23 spaces - 10 new employees, 13 net new exam rooms/Steadman Clinic
6 spaces – 6 new employees/SPRI
LAGATTA
45
Parking and Circulation
West Wing Parking Demand
Level B: none
Level 1: 4 spaces
Level 2: 5 spaces
Level 3: none
Level 4: 29 spaces
Re-location/reduction in CMM: -8 spaces
Total WW net new parking demand:
30 Spaces
LAGATTA
46
Parking and Circulation
Parking Resources
LAGATTA
47
Parking and Circulation
Parking Resource
Drawing to be updated
Explain grading and ADA
Total number of spaces is evolving, valet, etc
LAGATTA
48
Parking and Circulation
Parking Resources
LAGATTA
49
Parking and Circulation
Parking Resources
LAGATTA
50
Parking and Circulation
Parking Resources
LAGATTA
51
Parking and Circulation
Parking Solution
29 spaces eliminated in re-design of West Lot
30 space demand from WW expansion
59 – total spaces with West Wing
Solution:
59 off-site leased spaces (until completion of East Wing)
LAGATTA
52
Parking and Circulation
Parking Management
77 VVMC Employee Spaces
209 Spaces:
103 Employees
106 Patients/Guests
59 off-site leased
Spaces
(29 replacement spaces, 30 new spaces)
LAGATTA
53
Parking and Circulation
Parking Management/Implications on Meadow Drive
Today - 106 patient/guest spaces
With Construction of WW- 77 employee spaces
+/-65% reduction of VVMC generated traffic on West Meadow Drive
“no increase to traffic on West Meadow Drive with opening of West Wing”
LAGATTA
54
Parking and Circulation
West Wing/Implications on Meadow Drive
LAGATTA
55
Parking and Circulation
West Wing/Implications on Meadow Drive
LAGATTA
56
End of Presentation
LAGATTA
57
Parking and Circulation
Parking Resources
WB40
WB62
LAGATTA
58
BASEMENT PLAN-SOUTH EXPANSION
8’
PROPERTY LINE BELOW
PROPERTY LINE
FEB. 23 BLDG. LINE
59
1st FLOOR PLAN-SOUTH EXPANSION
19’-3”
15’
8’
PROPERTY LINE BELOW
PROPERTY LINE BELOW
FEB. 23 BLDG. LINE
60
19’-3”
2ND FLOOR PLAN-SOUTH EXPANSION
PROPERTY LINE BELOW
FEB. 23 BLDG. LINE
61
3rd FLOOR PLAN-SOUTH EXPANSION
19’-3”
15’
8’
PROPERTY LINE BELOW
PROPERTY LINE BELOW
FEB. 23 BLDG. LINE
62
4th FLOOR PLAN-SOUTH EXPANSION
19’-3”
15’
8’
PROPERTY LINE BELOW
FEB. 23 BLDG. LINE
63
MEADOW DRIVE STREETSCAPE PLAN FEBRUARY 23 PRESENTATION
X
NEW PLANTER/SEATING WALL & LANDSCAPING
EXISTING CENTRAL WING
EXISITNG WEST WING
EXISITNG SIDEWALK & LANDSCAPING
OUTDOOR DINING COURT W/SCREEN WALL
NEW SOUTH EXPANSION
3.5 ft.(+/-)
7 ft.(+/-)
X
64
MEADOW DRIVE STREETSCAPE PLAN MARCH 9 REVISION
X
NEW PLANTER/SEATING WALL & LANDSCAPING
EXISTING CENTRAL WING
EXISITNG WEST WING
NEW SOUTH EXPANSION
3.5 ft.(+/-)
7 ft.(+/-)
X
EXISTING CENTRAL WING
EXISITNG WEST WING
EXISITNG SIDEWALK & LANDSCAPING
OUTDOOR DINING COURT W/SCREEN WALL
NEW SOUTH EXPANSION
8 ft.(+/-)
12 ft.(+/-)
X
65
SOUTH EXISTING CONDITION
66
SOUTH EXPANSION PERSPECTIVE FEBRUARY 23 PRESENTATION
67
SOUTH EXPANSION PERSPECTIVE MARCH 9 REVISION
68
SOUTHWEST CORNER EXISITNG
69
SOUTHWEST CORNER PERSPECTIVE
FEBRUARY 23 PRESENTATION
70
SOUTHWEST CORNER PERSPECTIVE
MARCH 9 REVISION
71
SOUTH ELEVATION FEBRUARY 23 PRESENTATION
72
SOUTH ELEVATION MARCH 9 REVISION
73
74
Employee Housing
Chapter 23
Employee Generation Rates
LAGATTA
75
Employee Housing
Emergency (140%)
Imaging (78%)
Patient Care Unit (53%)
VVMC Surgery (32%)
VVSC Surgery (30%)
Patient Care Unit (53%)
Cardiopulmonary (75%)
Howard Head PT/OT (40%)
Steadman/SPRI (83%)
Vail
Summit Ortho (167%)
Materials Management (87%)
SPD (39%)
De-compression
Existing facility
National Trends
Local Trends
LAGATTA
76
Employee Housing
National Trends
Out-patient surgeries
Shorter hospital stays
Local Trends
Since 2008, declines in:
Admissions
Births
Patient days
ED visits
Surgeries
Edwards Surgery Center
Urgent Care facilities
LAGATTA
77
Employee Housing
Basement Level
No impact to employee generation
LAGATTA
78
Employee Housing
Level 1
2 new employees from the expansion of HHSM.
The new SPRI space will generate new employees, discussed below.
LAGATTA
79
Employee Housing
Level 2
3 new employees from Cath Lab
LAGATTA
80
Employee Housing
Level 3
No impact to employee generation
LAGATTA
81
Employee Housing
Level 4
10 new employees from Steadman Clinic
6 new employees from SPRI
LAGATTA
82
Employee Housing
21 new employees
Mitigation – 20% of 21 employees = 4.4 employees
Cash in lieu
Exception to 50% of req. mitigation to be on-site
LAGATTA
83
Employee Housing
“exception may be granted based on one of the following findings”:
a. Implementation of the on-site unit mitigation method would be contrary to the intent and purpose of the applicable
zone district.
b. Implementation of the on-site unit mitigation method would be contrary to the goals of the applicable elements of the Vail comprehensive plan and the town's development
objectives.
c. Exceptional or extraordinary circumstances or conditions apply to the site that prevents the implementation of the on-site unit mitigation method.
d. The method of mitigation
proposed better achieves the intent and purpose of this chapter and general and specific purposes of this title than the on-site mitigation unit method.
LAGATTA
84
Employee Housing
LAGATTA
85
Employee Housing
LAGATTA
86