TEST, ADJUST AND BALANCE REPORT
PROJECT
223 BEAVER DAM RD
#1271
PREPARED FOR
SKYLINE MECHANICAL
REPORT ISSUE DATE
3/8/2017
PREPARED BY
HVAC TAB llc
P.O. BOX 1926
VAIL, CO 81658
PHONE: 970-376-5198
E-MAIL: mrichardson@hvactab.co
HVAC TAB llc
DATE: 3/8/2017
INSTRUMENT
CALIBRATION REPORT
PROJECT : 223 BEAVER DAM RD
PROJECT ALTITUDE: “HG
INSTRUMENT/ SERIAL # APPLICATION DATE OF USE CALIBRATION
DATE
CALIBRATION
DUE DATE
SHORTRIDGE ADM-870C / #M09211 AIR FLOW READINGS 3/8/2017 06/02/2016 06/02/2017
ANEMOMETER #T57251515001 AIR FLOW READINGS NOT USED 05/06/2016 05/06/2017
SHORTRIDGE FLOW HOOD AIF FLOW READINGS NOT USED * *
TH-720 HYGROMETER/ #TH7200950003 AIR TEMP / HUMIDITY NOT USED 06/03/2016 06/03/2017
PITOT TUBE 18” PRES. READINGS 3/8/2017 N/A N/A
PITOT TUBE 24” PRES. READINGS NOT USED N/A N/A
PITOT TUBE 36” PRES. READINGS NOT USED N/A N/A
PITOT TUBE 48” PRES. READINGS NOT USED NA NA
SHIMPO TACHOMETER / #C105B0010 RPM READINGS NOT USED 06/02/2016 06/02/2017
FLUKE 375 / #21290229 VOLT / AMP NOT USED 06/02/2016 06/02/2017
SHORTRIDGE HDM-250/ #W08162 WATER PRES. READINGS NOT USED 06/02/2016 06/02/2017
ASCROFT / 0-100 PSI / #DO68332-06 WATER PRES. READINGS NOT USED * *
FLUKE 52 II THERMOMETER / 99780167 TEMP. READINGS NOT USED 06/03/2016 06/03/2017
REFRACTOMETER RHA-100 / #RHA-
100
GLYCOL % READINGS NOT USED N/A N/A
* CHECKED TO CALIBRATED METER
REMARKS: AL L R E ADI NG S WITH SHORT R I DG E I NST R UMENT S AR E CORRECTED FOR
TEMPERATURE AND ALTITUDE. PAGE:
HVAC TAB llc
DATE: 3/8/2017
FAN NUMBER FC-1A MUA KEF-1
UNIT DATA UNIT DATA UNIT DATA
MANUFACTURER CARRIER MIELE
MODEL 39SVA07MZL432EBSXF DA 2210
SERIAL 2516R45949 FABR-NR 126960081
SCHEDULE RATING/OUTLET TOTAL 1000CFM OSA -
ACTUAL CFM 1080 CFM 678 CFM
FC-1A MUA IS
INTERLOCKED
WITH KEF-1
FAN TEST REPORT
PROJECT: 223 BEAVER DAM RD SYSTEM: FC-1A MUA / KEF-1
SYSTEM TERMINAL DESIGN INITIAL FINAL NOTES
NO TYPE SIZE AK VEL CFM VEL CFM VEL CFM
FC-1A MUA 1 PITOT 16/10 1000 1080 1080 TOTAL
KEF-1 1 ER 37.5/11 - 686 686 TOTAL
NOTES:
HVAC TAB llc
DATE: 3/8/2017
AIR TERMINAL
TEST REPORT
PAGE:
PROJECT: 223 BEAVER DAM RD SYSTEM: FC-1A MUA / KEF-1