HomeMy WebLinkAboutB15-0274_A6.2_1460575800.pdfLEVEL 1 - GUEST SUITE &
EXERCISE
19' - 6"
5
LEVEL 1A - EXERCISE &
BEDROOM
13' - 4 1/2"
4
FAMILY ROOM
RE: STRUCT.
RE: STRUCT.
RE: STRUCT.
GLASS FLOOR
RE: STRUCT.
3/4" FINISH FLOOR
RE: FLOOR PLANS & SPEC
REGLET
2X FURRING HELD 1/2"
OFF OF CONCRETE
FOUNDATION WALL
SEE 1/A6.1 FOR TYP. SLAB-
ON-GRADE ASSEMBLY
SEE 1/A6.2 FOR
FOUNDATION NOTES
LEVEL 2 - GARAGE &
BEDROOMS
33' - 0"
1
STORAGE
WEST GARAGE
LEVEL 1 - GUEST SUITE &
EXERCISE
13' - 4 1/2"
EXTERIOR
RE: STRUCT.
GS14
ASSEMBLY
TYP. STONE VENEER WALL ASSEMBLY
SEE 1 / A6.1
APPROX. LINE OF EXISTING GRADE
SEE 1/A6.1 FOR TYP. TWO
SIDED POUR AND TEMP.
SHORING WALL DETAIL NOTES.
APPROX. LINE OF BEDROCK
TEMPORARY SHORING
RE: STRUCT.
RE: STRUCT.
TYP. STONE VENEER
WALL ASSEMBLY
SEE 1/A6.1
LEVEL 1 - GUEST SUITE &
EXERCISE
19' - 6"
RE: STRUCT.
RE: STRUCT.
RE: STRUCT.
TYP. PATIO ASSEMBLY
SEE 1/A6.2
1
RE: STRUCT.
STONE CAP
LEVEL 1 - GUEST SUITE &
EXERCISE
19' - 6"
4
5
LEVEL 1A - EXERCISE &
BEDROOM
13' - 4 1/2"
STEAM ROOM
EXTERIOR
RE: STRUCT.
TYP. 3" ASSEMBLY CONSISTING
OF APPROX. 3/4" THICK STONE
OVER APPROX. 2 1/4" MORTAR
BED OVER REINFORCED CONC.
SLAB PER STRUCT.
1' - 8 5/8"
RE: STRUCT.
RE: STRUCT.
W.P. MEMBRANE CONT. OUT
HORIZONTALLY 3'-0" -
CONTINUE MEMBRANE UNDER
DOOR SILLS AND UP WALLS
SEE 1/A6.1 FOR TYP. SLAB-
ON-GRADE ASSEMBLY
CONC. SLAB RE STRUCT.
2" RIGID INSULATION @ PATIOS
4" GRAVEL BED UNDER
CONCRETE SLAB PER SOILS
ENGINEER
RECOMMENDATIONS/STRUCT.
MIRA DRAIN DRAINAGE
MEDIUM OVER WATERPROOF
MEMBRANE RE:SPEC
W.P. MEMBRANE CONT. FROM
B.O. FOOTING TO T.O. CONC.
MIRA DRAIN DRAINAGE MEDIUM
OVER R-15 3" RIGID FOAM
INSULATION PANEL OVER
WATERPROOF MEMBRANE RE:
SPEC. ALTERNATE INSULATION/
DRAINAGE MEDIUM MAY BE
PROPOSED PER SPEC.
4" DIA. RIGID PERFORATED PIPE
SURROUNDED BY FILTER FABRIC
AND A MIN . OF 4 INCHES OF
DRAIN GRAVEL SLOPED 1% MIN.
TO DAYLIGHT PER SOILS REPORT.
RE: SOILS REPORT FOR
ADDITIONAL FOUNDATION AND
PERIMETER DRAIN
REQUIREMENTS & SPEC
CONCRETE FOUNDATION FOOTER
RE: STRUCTURAL DRAWINGS
CONCRETE FOUNDATION WALL
RE: STRUCTURAL DRAWINGS
LEVEL 1 - GUEST SUITE &
EXERCISE
19' - 6"
LEVEL 1A - EXERCISE &
BEDROOM
13' - 4 1/2"
RE: STRUCT.
RE: STRUCT.
1/2" 1 1/2"
3/4" FINISH FLOOR
RE: FLOOR PLANS & SPEC
REGLET
2X FURRING HELD 1/2"
OFF OF CONCRETE
FOUNDATION WALL
FAMILY ROOM
RE: STRUCT.
SEE 1/A6.1 FOR TYP. SLAB-
ON-GRADE ASSEMBLY
SEE 1/A6.2 FOR
FOUNDATION NOTES
LEVEL 2A - BEDROOMS
26' - 7 1/2"
RE: STRUCT.
8
RE: STRUCT.
MECHANICAL RM.
BEDROOM #4
LEVEL 3A - MAIN LEVEL
39' - 9"
W STL. BEAM RE: STRUCT.
LEVEL 1A - EXERCISE &
BEDROOM
13' - 4 1/2"
6"
FSB14
ASSEMBLY
FSB14
ASSEMBLY
DSB10
ASSEMBLY
TYP. STONE VENEER WALL ASSEMBLY
SEE 1 / A6.1
APPROX. LINE OF BEDROCK
TEMPORARY SHORING
RE: STRUCT.
RE: STRUCT.
SEE 1/A6.1 FOR TYP. TWO
SIDED POUR AND TEMP.
SHORING WALL DETAIL NOTES.
POUR STOP ANGLE
WINDOW RE: WINDOW SCHEDULE
C
LEVEL 1 - GUEST SUITE &
EXERCISE
19' - 6"
RE: STRUCT.
RE: STRUCT.
RE: STRUCT.
FAMILY ROOM
FAMILY RM.
PATIO
RE: STRUCT.
3 1/2" 5"
5"
11/16"
1/2" SHIM SPACE
SEE 4/A6.2 FOR TYP.
PATIO ASSEMBLY
XOOX LIFT AND SLIDE DOOR
3/4" FINISH FLOOR
RE: FLOOR PLANS AND SPEC.
SEE 1/A6.1 FOR TYP. SLAB-
ON-GRADE ASSEMBLY 2 1/4"
SEE 1/A6.2 FOR
FOUNDATION NOTES
FORM BRACING
CONCRETE FORM
P.T. PLATE TO PROTECT
PREPRUFE FROM
CONCRETE FORM
FOLD PREPRUFE BACK
@ TOP OF SHORING WALL
SEE 3/A6.1 FOR TYP. ONE
SIDED POUR ASSEMBLY
Scale
Drawn by
Checked by
US Mail Only: P. O. Box 2378
Physical / Fedex: 210 Edwards
Village Blvd, Bldg A Suite A103
Edwards, Colorado 81632-2378
(970) 926 4301, Fax: 926 4364
hans@berglundarchitects.com
www . berglundarchitects.com
Issue Date
REVISION
1 1/2" = 1'-0"
8/3/2015 13:10:06
A6.2
FOUNDATION
DETAILS
AG
HB
165 FOREST RD VAIL, CO
07/27/2015
VAIL VILLAGE FILING 1, BLOCK 7, LOT 29
PRELIMINARY
BUILDING PERMIT SET
1 1/2" = 1'-0"
2
FOUNDATION DETAIL @ ELEVATOR GRID
5
1 1/2" = 1'-0"
4
FOUNDATION DETAIL 2 @ WEST
GARAGE GRID 1 - GS14 ASSEMBLY
1 1/2" = 1'-0"
5
FOUNDATION DETAIL @ PATIO GRID 1 -
GS14 ASSEMBLY
1 1/2" = 1'-0"
1
FOUNDATION DETAIL @ STEAM RM.
GRID 4
1 1/2" = 1'-0"
3 FOUNDATION DETAIL @ STAIR GRID 5
1 1/2" = 1'-0"
8
FOUNDATION DETAIL 2 @ MECHANICAL
RM. GRID 8 - FSB14 & DSB10 ASSEMBLY
1 1/2" = 1'-0"
7
FOUNDATION DETAIL @ FAMILY ROOM
GRID C
1 1/2" = 1'-0"
6
FOUNDATION DETAIL @ T.O. ONE SIDED
POUR DURING CONSTRUCTION
No. Revision Date
Revision
Description
04/13/16