Brent Wilson
From:Chris Hutto <chris.hutto@groundeng.com>
Sent:Thursday, November 12, 2015 12:29 PM
To:Brent Wilson; Shane Sorensen
Cc:Evan Rubin; Steven Stokely; Bill Looney
Subject:RE: TOVstamped Marriott Chiller structural pdf
Attachments:15-6563 - Vail Marriott Chiller - Matl Test Reports 151112.pdf; 15-6563 - Final
Summary 151112.pdf; 15-6563.TOV SI 12_Final Report.Vail Marriott Chiller.prt.pdf
Brent,
Thanks for getting us those stamped drawings to clear the OD list. Please find attached the Vail Marriott Chiller ‐ Matl
Testing Reports, Final Summary and TOV Report of Special Inspections, the last you would need to submit to the TOV
yourself.
Let me know if there are any concerns or questions.
Thanks,
Chris Hutto, CET
Area Manager
GROUND Engineering Consultants, Inc.
PO Box 464, 101A Airpark Drive, Unit 9 • Gypsum, CO 81637
Phone 970‐524‐0720 • Fax 970‐524‐0721• Cell 970‐366‐7013
chris.hutto@groundeng.com www.groundeng.com
From: Brent Wilson [mailto:brentw@randhmechanical.com]
Sent: Thursday, November 12, 2015 7:16 AM
To: Shane Sorensen; Chris Hutto
Subject: TOVstamped Marriott Chiller structural pdf
Chris & Shane,
Enclosed is finally our town of Vail stamped drawing, for your records. Shoot over the weld and grout inspection reports
and then we can wrap this one up.
Appreciate your help on this,
Brent
Brent Wilson - PE, LEED AP
Principal Engineer
R & H Mechanical
“People & Products You Can Count On”
825 A Chambers Ave
Eagle, CO 81631
Mobile: 970.390.7673
Office: 970.328.2699
Fax: 970.328.0234
November 12th, 2015
Subject: Summary of Materials Testing Services and
Special Inspection Services, Vail Marriott New Chiller
Room and Pumps Vail, Colorado
Ground Engineering Job Number: 15-6563
Mr. Evan Rubin TOV Permit Number: B15-0294
Vail Marriot C/O Evan Rubin, LLC
715 W. Lionshead Circle
Vail, CO 81657
Attn: Mr. Rubin,
This letter summarizes the special inspection and materials testing services GROUND Engineering
Consultants, Inc. (GROUND) performed during construction of the Vail Marriott Chiller Room and Pumps
Project in Vail, Colorado. The special inspection and materials testing services were performed at times
scheduled by the Contractor and/or Subcontractors between August 26th, 2015 and September 9th, 2015.
During construction, structural steel welded and/or bolted connections were periodically observed during
construction by a certified welding inspector (CWI). Also, observations and testing were performed on the
expansion anchors, drilled and epoxied bolts and grout placement into existing CMU walls. The
observations and testing were completed at times scheduled by the Contractor or Subcontractor.
Based on the field observations to date, RFI’s received and/or project documentation received from the
design team, it is our opinion that the materials observed for the welded connections, anchor bolt
installation and CMU grout placements were in general accordance with project plans, specifications,
and/or applicable RFI’s.
The observations and materials testing as indicated above were performed periodically to provide data to
the Owner, Contractor and Subcontractors to assist them in evaluating the general compliance of the
materials and/or work with the contract documents at the times of our observation and testing. We did
not supervise, direct nor have any control over any of the Contractor’s or Subcontractor’s work. We were
not responsible for the Contractor’s or Subcontractor’s scheduling of our services, means, methods,
procedures, techniques, or sequences of construction, nor responsible for ensuring that any Contractor or
Subcontractor performed or completed the work in accordance with the contract documents or
construction industry standards.
If you have any questions concerning this letter, please contact our office.
Sincerely,
GROUND Engineering Consultants, Inc.
Chris Hutto, C.E.T. Reviewed by Carl Henderson, P.E.
Client:
www.groundeng.com
Englewood, Commerce City, Loveland, Granby, Gypsum, Grand Junction, Casper
Vail Marriott - New Chiller Room and Pumps
Mr. Evan Rubin
Vail Marriott C/O H. Evan Rubin, LLC
715 W. Lionshead Circle
Vail, CO 81657
Comments or Photos:
Yes No
Discrepancies Reported this Date?
No. of Pages Attached:
Field Representative:
Drill and Epoxy Cover Report
Date:Date Job NameJob Number:Job Number
As scheduled, a representative visited the project site to perform special inspections for drill and epoxy at
locations requested.
General Contractor:General Contractor Rep. Notified:Rep Notified
August 26, 2015 15-6563
R&H Mechanical Ciro
1
Shane Sorensen
Client:
www.groundeng.com
Englewood, Commerce City, Loveland, Granby, Gypsum, Grand Junction, Casper
Vail Marriott - New Chiller Room and Pumps
Mr. Evan Rubin
Vail Marriott C/O H. Evan Rubin, LLC
715 W. Lionshead Circle
Vail, CO 81657
Location: 1.)
2.)
3.)
4.)
Orientation (vertical/horizontal): 1.) 3.)
2.) 4.)
Hole Diameter (inches): 1.) Length (inches): 1.)
2.) 2.)
3.) 3.)
4.) 4.)
Hole Spacing (inches): 1.) 3.)
2.) 4.)
Drilling Equipment:
Method to Clean Hole:
Epoxy Type:
Epoxy Expiration:
Placement Method:
Type (rebar/bolt/anchor): 1.) Size: 1.) Length (inches) 1.)
2.) 2.) 2.)
3.) 3.) 3.)
4.) 4.) 4.)
Placement Method:
Additional Reinforcing Steel:
Field Representative:
Comments:
Reinforcement
Epoxy
Documents Used:
Drill and Epoxy
Drilling
Subcontractor: Rep. Notified:
pGeneral Contractor: Rep. Notified:
p
Job Number:Report Date:August 26, 2015 15-6563
R&H Mechanical Ciro
Adams Construction Chris
Plans
Into existing west concrete wall for two beam face plates
Horizontal
3/4 5
10x11.5
Hammer Drill
Wire brush, compressed air
N/A
N/A
N/A
Expansion anchor 3/4 7
Hammer, socket wrench
N/A
Shane Sorensen
Client:
www.groundeng.com
Englewood, Commerce City, Loveland, Granby, Gypsum, Grand Junction, Casper
Vail Marriott - New Chiller Room and Pumps
Mr. Evan Rubin
Vail Marriott C/O H. Evan Rubin, LLC
715 W. Lionshead Circle
Vail, CO 81657
Comments or Photos:
Yes No
Discrepancies Reported this Date?
No. of Pages Attached:
Field Representative:
Drill and Epoxy Cover Report
Date:Date Job NameJob Number:Job Number
As scheduled, a representative visited the project site to perform special inspections for drill and epoxy at
locations requested.
General Contractor:General Contractor Rep. Notified:Rep Notified
September 2, 2015 15-6563
R&H Mechanical Ciro
2
Shane Sorensen
Client:
www.groundeng.com
Englewood, Commerce City, Loveland, Granby, Gypsum, Grand Junction, Casper
Vail Marriott - New Chiller Room and Pumps
Mr. Evan Rubin
Vail Marriott C/O H. Evan Rubin, LLC
715 W. Lionshead Circle
Vail, CO 81657
Additional Comments or Photos:
Comments
Date:Date Job NameJob Number:Job Number
General Contractor:General Contractor Rep. Notified:Rep Notified
September 2, 2015 15-6563
R&H Mechanical Ciro
Client:
www.groundeng.com
Englewood, Commerce City, Loveland, Granby, Gypsum, Grand Junction, Casper
Vail Marriott - New Chiller Room and Pumps
Mr. Evan Rubin
Vail Marriott C/O H. Evan Rubin, LLC
715 W. Lionshead Circle
Vail, CO 81657
Location: 1.)
2.)
3.)
4.)
Orientation (vertical/horizontal): 1.) 3.)
2.) 4.)
Hole Diameter (inches): 1.) Length (inches): 1.)
2.) 2.)
3.) 3.)
4.) 4.)
Hole Spacing (inches): 1.) 3.)
2.) 4.)
Drilling Equipment:
Method to Clean Hole:
Epoxy Type:
Epoxy Expiration:
Placement Method:
Type (rebar/bolt/anchor): 1.) Size: 1.) Length (inches) 1.)
2.) 2.) 2.)
3.) 3.) 3.)
4.) 4.) 4.)
Placement Method:
Additional Reinforcing Steel:
Field Representative:
Comments:
Reinforcement
Epoxy
Documents Used:
Drill and Epoxy
Drilling
Subcontractor: Rep. Notified:
pGeneral Contractor: Rep. Notified:
p
Job Number:Report Date:September 2, 2015 15-6563
R&H Mechanical Ciro
Adams Construction Chris
Plans
Into existing east CMU wall for two beam face plates
Horizontal
7/8 6
(N plate) 15.5Wx15Vx8.5V
(S plate) 9Wx8.5Vx15V
Hammer Drill
Wire brush, compressed air
Powers Fasteners Quik-Shot AC100+Gold (Cross-referenced as equivalent to specified Hilti HIT-HY 200)
November 2016
Caulk gun
Bolt 3/4 8
Hand set
N/A
Shane Sorensen
Bolts for south side of plates were epoxied first, and allowed to cure, then plates were used as guides for drilling holes for north
bolts.
Client:
www.groundeng.com
Englewood, Commerce City, Loveland, Granby, Gypsum, Grand Junction, Casper
Vail Marriott - New Chiller Room and Pumps
Mr. Evan Rubin
Vail Marriott C/O H. Evan Rubin, LLC
715 W. Lionshead Circle
Vail, CO 81657
Job No:
Date:
Field Representative:
General Comments
As scheduled, a representative arrived on-site to perform the below discussed services and we have
the following comments.
Shane Sorensen
15-6563
August 26, 2015
While on site, we observed Adams Construction placing grout into the cells of the existing east CMU wall for future placement of
epoxy anchor bolts to hold beam face plates. The cells grouted correspond to the north three bolts for each of the two face
plates. Six 8" CMU courses were grouted. Quikrete Non-Shrink General Purpose Grout was mixed at approximately 1 gallon of
distilled water per 50 lb. bag of grout mix. Four 3"x3"x6" grout samples were cast for compressive strength testing.
Chris with Adams Construction was notified of our observations.
Date:
Specimen Set Number:
9
71
Specimen Set Number 1 A 1 B 1 C 1 D
Width Measurement #1
Width Measurement #2
Width Measurement #3
Width Measurement #4
Height Measurement #1
Height Measurement #2
Height Measurement #3
Height Measurement #4
Cross Sectional Area
Height to Width Ratio
Load
Strength (psi)
Specified Strength
Test Date
Age
Average Strength (28 day)
63,220 80,390 82,460 81,870
5430 7080 7150 7260
7 282828
8/26/2015 2039
3"x3"x6" block
Specifications
- 3000 3000 3000
9/2/2015 9/23/2015 9/23/2015 9/23/2015
GROUT PROPERTIES
Project:
Job Number:
11.1711.53 11.24 11.42
Laboratory ID #:
5.86
5.87
3.32
3.41
5.92
3.37
5.90
3.46
1.81 1.76 1.76
6.17
6.18
6.12
6.11
3.29
3.39
3.36
3.39
3.33
3.38
3.38
Compressive Strength of Grout Specimens
Cast Date:
Vail Marriott C/O H. Evan Rubin, LLC
40-90
Compressive Strength Test Data (ASTM C 1019)
Standard Initial Cure
ASTM C511 - Moist Room
Initial Cure:
Final Cure:
Temperature:
Client:
Attn:
Placement Location:
Unit Type:
Quickrete Non-Shrink General Purpose Grout
8-11 Slump (inches):
Supplier / Mix ID:
CMU cells in line with north 3 bolts to be installed for west two beam face plates
1
August 26, 2015
Mr. Evan Rubin
715 W. Lionshead Circle
Vail, CO 81657
15-6563
Vail Marriott - New Chiller Room and Pumps
3.39
6.04
3.32
3.27
3.39
7160
6.05
6.01
6.00
5.98
5.96
5.97
3.43
5.95
1.80
Corporate
41 Inverness Dr East
Englewood, CO 80112
Tel:(303)289 1989
Fax:(303)289 1686 Offices: Denver, Loveland, Western Slope, Granby, Casper WY
North Denver
7393 Dahlia Street
Commerce City, CO 80022
Tel:(303)289 1989
Fax:(303)289 6742
Client:
www.groundeng.com
Englewood, Commerce City, Loveland, Granby, Gypsum, Grand Junction, Casper
Vail Marriott - New Chiller Room and Pumps
Mr. Evan Rubin
Vail Marriott C/O H. Evan Rubin, LLC
715 W. Lionshead Circle
Vail, CO 81657
Date: Location: Job Number:
Yes No
Outstanding Discrepancies Reported this Date?
No. of Pages Attached:
Field Representative:
Structural Steel Cover Report
As scheduled, a representative arrived to perform special inspection services. The following is a summary of
services provided on this date.
September 8, 2015 Site 15-6563
As directed by Chris Adams, GROUND inspected the following:
1st visit
1) Inspected fillet welded connections of shear plate to anchored embed and shear plates to beams for the new chiller pad. It was found
the shear plate was not welded on two sides at all connections and the center cross beams were welded in lieu of bolted as detailed in 3/S1.
These connections are not completed per project plans. Chris had called the Project team and GROUND was requested to arrive later in the
afternoon. The following inspections are reported in below in 2nd visit.
2) GROUND received and reviewed Welding Procedure Specification (WPS) and Welder Qualification Test Record (WQTR) in accordance
with AWS D1.1.
2nd visit
3) GROUND arrived on site and contacted Chris.
4) GROUND received and reviewed E-mail dated September 8, 2015 in regards to the welded shear plate in lieu of bolted and this
connection is found acceptable per Engineer of Record; however, it has not been approved by the Town of Vail. This will be added as
discrepancy item #1. (TOWN OF VAIL APPROVED PLANS RECEIVED 11-12-15; OD ITEM # 1 CLEARED 11-12-15) CH
5) GROUND reinspected welded connections and have found all connections are in compliance with E-mail received, project plans and in
general compliance with AWS D1.1-10 clause 6 table 6.1.
Chris was present during the inspections and copied on todays field report.
Brent Wilson with Rand H Mechanical was E-mailed a copy of todays report and current discrepancy list.
0
Josh Bash/ Chris Hutto
Client:
www.groundeng.com
Englewood, Commerce City, Loveland, Granby, Gypsum, Grand Junction, Casper
Vail Marriott - New Chiller Room and Pumps
Mr. Evan Rubin
Vail Marriott C/O H. Evan Rubin, LLC
715 W. Lionshead Circle
Vail, CO 81657
DateField/Fab. Shop?
Fabrication Shop:
Job Name:Job Name
Job Number:Job Number
General Contractor:Rep Notified
Outstanding Structural Steel Discrepancy Log
Date
Reported
Item
Number
CWI
initials Description of Discrepancy
Date
Resolved
Per Plan /
Per RFI
It is the responsibility of the contractor to schedule our office to perform retesting once the necessary corrective
action has been made or provide our office with documentation that resolves the discrepancy.
Field Vail Marriot-New Chiller Room and Pumps
15-6563
9/8/15 1 JB
E-mail dated September 8, 2015 in regards to the welded shear plate in lieu of
bolted. this connection is found acceptable per Engineer of Record; however, it
has not been approved by the Town of Vail 11/12/15
Per Plans
Rec 11/12/15
FINAL REPORT OF SPECIAL INSPECTIONS
Project:Permit Number:
Project Location:
Owner ____________________________________________________________________________
Address City:Zip:
Design Professional In Charge:
Address:
City:State:Zip:Phone:
Fax:E-mail:
To the best of my information, knowledge, and belief, the special inspections and/or testing required for
this project, have been completed in accordance with the contract documents.
Interim reports submitted prior to this Final Report of Special Inspections form a basis for, and are to be
considered an integral part of this final report. Any discrepancies that were noted in all interim reports
have been corrected.
Prepared by:
Type or Print Name
Signature
Date
Preparer’s Seal and Signature Required
-12-
--------------------
Special Inspections Agency
GROUND Engineering Consultants, Inc.
PO Box 464
Gypsum CO 81637 (970)524-0720
(970) 524-0721
Carl Henderson, P.E.
chris.hutto@groundeng.com
carl.henderson@groundeng.com
Vail Marriott New Chiller Room
Vail Martiott
Vail Marriott
715 W Lionshead Cir Vail 81657
B15-0294
11-12-2015
*See 15-6593 Final Summary 151112 and reports*