HomeMy WebLinkAboutCascade inspection letter.pdfTo: JR Mondragon
Acting Chief Building Official
Senior Building Inspector
Town of Vail
Subject: Vail Cascade site inspection comments
Date: September 20, 2016
Dear Mr. Mondragon,
Below are comments we received on September 7, 2016 via e-mail from JR Mondragon following a site
visit on September 6th;
11. Tampered resistant outlet are required
12. No 3rd party inspections
3. Solvent plumbing system engineer please address test method to be used for new plumbing,
flow test not permitted, air test? Water test? Can pvc pipe be used for repairs or alterations?
4. Design team shall provide details and methods to address existing conditions and code
compliance ( steel not fire protected, no corridor separation, no fire barriers or fire assemblies,
5. Details for all new and existing membrane and thru penetration/ protecti~n methods.
6. Added mech fans as code requires, fire/radiation dampers.
Since receiving the above mentioned e-mail, we have had Syska (MEP Engineer of Record) and (BCER FLS
Engineer) provide review and comment. Below
1. Tamper resistant outlets
a. Will be installed per code, no action required
2. 3rd party inspections
a. Not permitted by the Town of Vail
b. The contractor will coordinate with the Town of Vail regarding requested inspections
3. Solvent Plumbing System
a. Per Syska plumbing engineer, and response to project RFI # 14, plastic pipe is allowed in
lieu of the black ABS. (see attached RFI # 14}
b. PWl's plumbing contractor George L. Roma has provided a letter and photos concerning
system testing. (see attached)
4. Existing Conditions and code compliance
a. We understand as a result of the 9/5/16 site visit, concerns have been raised about
apparent deficiencies that have been identified as a result of the opening of walls and
ceilings but are not created as a direct result of the work being done on this alteration.
b. The main portion of the facility was constructed in 1982 and the terrace section in 1990.
Several Certificates of Occupancy were issued by the Town of Vail for portions, but not
B L A c .~ •. ; .. ~ •• ~ .. ;ljl;lllA4WllM
all, of the facility which would indicate the buildings were in compliance at the time of
construction and remodel and no deficiencies were noted.
c. The current work being conducted in the buildings is an alteration of existing space .
There is no change in use, occupancy, aggregation of space, or reconfiguration of egress
systems.
d. Improvements being performed during currently permitted renovation are:
i. Fire sprinkler system improvements to existing system.
ii. Fire protection and alarm improvements to existing system.
iii. Dedicated fire lane and improved FDC/hydrant location
iv. Dedicated fire command center
v. Improvements to the parking structure sprinkler system ~ Meeting all current codes where alterations are occurring.
e. As ~suit, the overall condition and level of safety ofthe building will be enhanced.
f. The owners are committed to providing a high level of safety to guests to a reasonable
degree considering the age of the facility and the apparent compliance at some point in
its history.
g. This work provides a significant improvement to what was previously CO'd and existed.
5. Membrane and penetration details
a. See No 4 above
6. Added Mechanical Fans in bathrooms
a. Per Syska (electrical engineer) and response to a project RFI # 24, the electrical engineer
has confirmed the existing circuits can handle the added load of an additional fan if
required. (see attached Syska CFM Code)
b. We will install fire dampers if 1. We are required to have a 2nd fan, 2. If the ceiling is
considered a rated surface. However, Syska, mechanical engineer of record is saying
that a 2nd exhaust fan is not required.
i. Syska's interpretation of the 2~hich is referenced by the 2015 /BC, the
exhaust requirement for priv~oms I toilet located in a hotel is to
/ provide a minimum of 50cfm (intermittent) regardless of separation, fixture type
/ or quantity.
c. Per Syska mechanical engineer the existing 6" duct has the capacity to handle 2 exhaust
fans if a 2nd exhaust fan is required.
c
Corporate Office
3903 W. Martin Avenue
Las Vegas, NV 89118
702.942.8400
pwiconstruction.com
0 N s T R u c
REQUEST FOR INFORMATION
PROJECT NAME: Vail Cascades Resort & Spa
PROJECT NO.: 16-028
TO:
CC:
Kathy Armstrong (KA)
Todd Goulding (TG)
Bud Thompson (BT)
Jack Lavelle (JL)
Steve Weiss (SW)
RE: Proposed Plumbing Piping Material
ACTION REQUESTED BY: ISSUED BY:
T
DATE: 8/31 /2016
R.F.I. # 014
KA /Ryan Taylor Theresa Johnson PWI
TITLE OR SECTION OF WORK:
Plumbing -22-40-00 DRAWING:
SHEET:#
WRITTEN DESCRIPTION OF PROBLEM:
0
The plumber is staffed up and trying to procure pipe material. He is asking if he can use
white PVC vs. the black ABS.
1. plumber and PWI think White PVC is a better product.
2. Suppliers in area do not have quantity of black ABS.
3. JR inspector at TOV is ok with white PVC.
The Town of Vail inspector has said he is fine with this but needs approval in writing
from plumbing engineer.
Response Requested by: 8/31 /2016
SOLUTION:
Syska approves the use of PVC piping for the application as you have indicated above.
Please contact me should you have any further questions or require additional
information.
Ryan Taylor Syska Hennessy Group, Inc .
N
• NATIONWIDE 1 ·800.920·9966 PWI CONSTRUCTION, Inc.
GEORGEL.ROMA,LLC
Commercial Plumbing
September 20th., 2016
RE: Proposed Sanitary Inspection Procedure
Vail Cascade Hotel
To Whom It May Concern,
As it relates to the sanitary system at the Vail Cascade our alterations of the
system to comply with the blueprints have been at an extremely minimal. That is to
say 90%+ of the re-directed vertical branch arms are less than 5' in determined
length, with the majority being less than 3'.
Typical industry inspection on this type of work is strictly "visual". We are
using PVC/solvent type product (approved by the engineer), fastened to the cast iron
with a 'no hub band'. The end product is a sturdy, sound and leak-free code approved
system.
There has been discussion on filling the entire vertical stack (including the
original cast iron) as a means of inspection. A visual inspection of the stacks show
that they appear to be in working order.
Our concern is that filling the stacks with 4 stories of water/head-pressure
could prove to be disastrous. These stacks have been in place for quite some time and
according to the Owner and in proper working with no issues.
An alternate option is a "flow test" on the branch arms we have installed. This
test would entail running water thru the open system while the inspector assesses for
leaks.
This will be very time consuming for the inspector, and somewhat out ofline
due to the length of pipe being tested. The work we've installed in place is under
warranty for one year and as with most plumbing systems, if tight at first the system
rarely deviates and stays that way.
For reference, have included pies of the typical alterations;
~ Lavi arms relocation off existing stack
~ Toilet extension form original location (Off of existing stack)
~ Shower line to new drain, altered from old tub line, from existing stack.
Please look these over and consider our request for inspection.
Regards,
George Roma
Operations Mgr.
9559 Lk. Douglas Pl ~ Orlando, FL 32817
Phone: 407-681-4357 ~ George@romaplumbing.com
Bud Thompson
From:
Sent:
To:
Cc:
Subject:
Attachments:
Tyler,
Darnell, Suzanne <SMDarnell@leoadaly.com>
Friday, September 09, 2016 1:20 PM
Tyler Aldrich; Grayson, Kathleen; Lee, Kwan; Miller, Pat
Todd Goulding; Bud Thompson; David Johanson (djohanson@lauruscorporation.com);
Jack Lavelle; Steve Weiss; Russ Thrasher; Theresa Johnson
RE: PWI -RFI #24
2996_001.pdf
The RFI indicates that the Town of Vail Building Department directed PWI to provide exhaust for both the toilet and
shower in a private bathroom.
To date, Syska has not received any such plan review comments from the local AHJ stating this requirement.
Per Syska's interpretation of the 2015 IMC, which is referenced by the 2015 IBC, the exhaust requirement for private
bathrooms/ toilet located in a hotel is to provide a minimum of 50cfm (intermittent) regardless of separation, fixture
type or quantity.
Whereas for public spaces, the exhaust requirement is based specifically on room type (separate toilet and shower
rooms) with exhaust rates based on quantity of shower heads for shower rooms.
Before Syska can formally respond, can you furnish a formal plan review document from the local AHJ stating this
requirement?
They would like the opportunity to contact the official as well to discuss, before we provide direction on how to
proceed.
Thanks you,
Suzanne M. Darnell, AIA, LEED AP
Associate, Project Manager 1w----1
The Offices at Mockingbird Station, 5307 E. Mockingbird Lane, Suite 400, Dallas, TX 75206-5117
T 214.526.1144 F 214.526.1411
leoadaly.com SMDarnell@leoadaly.com
PLANNING ARCHITECTURE ENGINEERING INTERIORS
From: Tyler Aldrich [mailto:tyler.aldrich@pwiconstruction.com]
Sent: Thursday, September 08, 2016 1:50 PM
To: Darnell, Suzanne; Grayson, Kathleen; Lee, Kwan; Miller, Pat
Cc: tgoulding@blacklinegroupllc.com; Bud Thompson; David Johanson (djohanson@lauruscorporation.com); Jack
Lavelle; Steve Weiss; Russ Thrasher; Theresa Johnson
Subject: PWI -RFI #24
LAD Team,
1
Please find attached for your review and response, PWI Construction's RFI #024 relative to the Room Type for room
#384.
Thank You
Tyler Aldrich Superintendant
PWI Construction, Inc. I Natiowide
pwiconstruction.com I 702.888.2768
CONFIDENTIALITY AND PRIVILEGE NOTICE: This email communication, including any and all attachments, (collectively, this "Communication"), is intended
solely for the person(s) to whom it is addressed. This Communication may contain information that is privileged, confidential and/or proprietary. Any unauthorized
use, disclosure or copying of this Communication is strictly prohibited. If you have received this Communication in error, please contact the sender immediately
and destroy any and all copies of this Communication.
2
OCCUPANCY CLASSIFICATION .. ( Hotels, motels, resorts and dormitories -_:)
Bathrooms/toilet-private•
Bedroom/living room
Conference/meeting
Dormitory sleeping areas
Gambling casinos
Lobbies/prefunction
Multipurpose assembly
Offices
Conference rooms
Main entry lobbies
Office spaces
Reception areas
Telephone/data entry
Private dwellings, single and multiple
Garages, common for multiple unitsb
Kitchensb ..
Living areas"
Toilet rooms and bathrooms•
1., Public spaces
Corridors
Courtrooms
Elevator car
Legislative chambers
Libraries
Museums (children's)
Museums/galleries
Places of religious worship
~ Shower room (per shower head)'
Smoking loungesb
• f4 Toilet rooms -public'
Retall stores, sales floon and
showroom floon
Dressing rooms
Mall common areas
Sales
Shipping and receiving
Smoking loungesb
Storage rooms
Warehouses (see storage)
cop~t1niwnatlcnlic.d."'c0ii~RNATIONAL MECHANICAL CODE9
Provided bl' IHS undot bnA -ICC No reproduction or ~ pennlnod wtthoul llcena from IHS
TABLE 403.3.1.1-contlnued
MINIMUM VENTILATION RATES
PEOPLE OUTDOOR
OCCUPANT DENSrTV AIRFLOW RATE IN
"1000 FT'" BREATHING ZONE,
R~CFUJPERSON
-
5
5
5
7.5
7.5
s
50 s
10 s
s 5
30 s
60 5
--
--
Based upon number
ofbedrooms. First 0.35 ACH but not less bedroom, 2; each than 1 S cfm/person additional bedroom,
l
--
--
70 5
--
so 5
IO 5
40 7.5
40 7.5
120 5
--
70 60
--
--
40 7.5
15 7.5
--
70 60
--
--
(continued)
AREA OUTDOOR
AIRFLOW RATE IN
BREATHING ZONE,
R0 CFMIFT'"
-
0.06
0.06
0.06
0.18
0.06
0.06
0.06
0.06
0.06
0.06
0.06
-
-
-
-
0.06
0.06
-
0.06
0.12
0.12
0.06
0.06
-
-.
-
-
0.06
0.12
0.12
-
0.12
-
lJoon&H•Sylka Honn .. oy G~llt5547004, u--GJncan. lolnnril
Nol for Reulo, 09/0&'2015 08:37;10 MDT
VENTILATION
EXHAUST
AIRFLOW RATE
CfMIFT'•
25/50'
-
-
-
-
-
-
-
-
-
-
-
0.75
25/100,
-
20/SOr
-
-
1.0
-
-
-
-
-
50120{
-
5ono•
0.25
-
-
-
-
-
-
37