HomeMy WebLinkAboutsummary of work.xlsxROOM
Entryway
Downstairs
Bathroom
Powder Room
Dining room
Living room
Fireplace
Master Bedroom
Master Bathroom
Entire unit
Door schedule
BARKIN
PROJECT LIST
PROJECTS
Wrap two drywall ceiling beams - front & end of hall
Open up stair wall - final framing and opening To Be Determined
Create faux post at bottom of stairs
New top plate and trim on stairwell
New hand rail and metal brackets on stairwell
Replace carpet on stairs with wood flooring - Need bullnose stair edging matching floor selection
Replace Baseboard Heater in Hallway - 1
Paint stair way/entry as necessary
Remove/dispose/ tub, toilet, wallpaper, vanity, mirror and all fixtures
New toilet, drains, shower valves, vanity plumbing
Remove fan and replace with fan/light and duct
Remove/Replace floor tile - cut hall tile along bath door seam to allow for new tile or threshold
Shower pan - build new
Shower Caddy - Recessed shower shelf
Shower Bench - 12" long x 16" high
Tile - Shower floor
Tile - Shower walls
Tile Bathroom Floor and baseboard
Texture & paint walls
New vanity w/ counter/mirror, new faucet, lighting
Euroglass shower door
New bathroom door - Change handling - opening out into laundry closet (right hand swing)
New bath accessories - towel bar, toilet paper holder, etc.
Note - cut out 5x7 of wall paper before removing for posterity
Note - leave existing baseboard heater in place
Paint entire bathroom
Remove/dispose of vanity, toilet, mirror, lighting, wall paper, etc.
Fan/light remains
Texture & paint walls
Install wood flooring
New vanity/faucet/mirror/lighting
New toilet, vanity plumbing
New bath accessories - towel bar, toilet paper holder, etc.
Note - cut out 5x7 of wall paper before removing for posterity
Note - leave existing baseboard heater in place
Paint entire bathroom
Remove carpet, pad, base & case
Wood flooring
Install new baseboard & casing
Remove both baseboard heaters - replace with one large one
Clad beam - 2"x6"x8' - master stairwell/dining wall
Replace baseboard heater - 1
Remove carpet, trim, fireplace cabinet/hearth
Wood flooring
Remove/Replace baseboard heater on back wall (remove fireplace heater permanetly)
Wrap 2 6x8x14 beams
Wrap 2 14footx2 inch beams
Decorative metal staps on beams
Ceiling lighting - three track lights - beam closest to fireplace has one track only
- Need suggestions on track lighting - 4-5 lights - low profile
Remove fireplace fan switch & replace with track lighting switch
Wall mount TV location - left of sliding glass door
Replace baseboard heater - 1
Paint walls as necessary due to electrical demolition
Design Fireplace: Stone, mantle, posts, shelving, stone, material selections
New Fireplace insert
- New hearth
- Fireplace stone
- Mantle
- Shelving - both side - symetrical
- Shelving - potentially below mantel
Remove carpet, baseboard, casing, doors, handrail top plate
Remove Chandalier and replace with two track lights on both sides of high beam
Remove ceiling fan and replace with new one
New carpet & pad
Replace doors, base & case
Wrap 6x6 post
Wrap ceiling beams
Decorative metal staps on beams
Top plate and casing
Expand Closet into remaining area in sauna
Basic California closet
Replace baseboard heaters - 2
Paint entire master bedroom walk-in closet
Remove vanity, tile floor & tile walls, wall paper
Remove front sauna wall and insert pocket door
Remove back sauna wall and move to enclose toilet closet to enlarge master closet
Move toilet to other side of sauna wall
New toilet, vanity sinks, drains, etc
Texture & paint walls
Tile floors
Rustic wood double vanity with counter top, Light slab top
Mirror
Vanity Light Bar
Possible Fan in toilet closet AND VENTING?, leave master bath baseboard in place
Install sliding barn door
Note - leave existing baseboard heater in place
Note - cut out 5x7 of wall paper before removing for posterity
Paint entire bathroom
Replace pad/carpet
Replace interior doors/handles, casing, baseboards
Replace closet doors
Replace all baseboard heaters - except down stairs bedrooms, one entry and fireplace heate;
Paint areas of disturbance outside of bathrooms, master closet and entry.
Clad beams & posts
Decorative metal straps for beams - TBD
Clad beams & posts painting
Window, door casing and base boards
Front closet – 36 inch opening – 2-18" inch doors
Garage Door – 32 inch right 4_5/8"
Downstairs bathroom 24 " left -
Bedroom 1-30" left
Bedroom one – 60" closet - 2 slabs - bi-pass
Bedroom 2 - 30 inch right
Bedroom 2–48 inch closet - 2 slabs - bi-pass
Utility closet – 71 3/4"opening - 2 slabs - bi-pass
1st floor closet under stairs – 28 inch right
2nd floor top of stairs closet – 28 left
Powder room – 24 left
Master stairs entry 30 inch right
Master walk-in closet 28 right
Master bedroom closet 28th left
Master bathroom barn door
Master bathroom toilet slab and pocket door – 24"