HomeMy WebLinkAboutB17-0053_A1.0_1493402425.pdfRADON MITIGATION SYSTEM
PROVIDE DESIGN-BUILD ENGINEERING AND CONSTRUCTION OF A PASSIVE RADON MITIGATION SYSTEM FOR THE PROJECT TO WHICH AN INLINE FAN COULD BE
ADDED LATER IF REQUIRED PER THE FOLLOWING CRITERIA AND AS REQUIRED TO MAINTAIN RADON LEVELS AT THE MECHANICAL ROOM, LOWER LEVEL AND
HOUSE BELOW EPA AND OTHER GOVERNMENT STANDARDS. THE RADON MITIGATION SUBCONTRACTOR WILL BE RESPONSIBLE FOR COORDINATING HIS WORK
WITH THE VAPOR BARRIER INSTALLATION AND THE ELECTRICIAN FOR AN ELECTRICAL JUNCTION BOXES AT THE LOCATIONS DETERMINED BY THE RADON
MITIGATION SUBCONTRACTOR FOR THE POTENTIAL FUTURE FANS.
AT A MINIMUM, THE FOLLOWING SYSTEMS/SERVICES WILL BE PROVIDED AS PART OF THE BASE BID BY THE RADON MITIGATION SUB CONTRACTOR.
- SEALING OF THE LOWER LEVEL CONCRETE SLAB TO THE FOUNDATION WALLS
- SEALING OF ALL PLUMBING AND OTHER PENETRATIONS THROUGH THE CONCRETE SLABS AND THROUGH THE BELOW GRADE PORTIONS OF THE FOUNDATION
WALL
- LOCATIONS & INSTALLATION OF PIPES, PORTS, AND OPENINGS IN THE SLAB FOR SLAB DEPRESSURIZATION SYSTEM.
- PROVIDE PASSIVE VENT PIPE SYSTEM WHICH RUNS FROM THE SLAB PENETRATION LOCATIONS(S) TO THE OUTSIDE IN ACCORDANCE WITH THE EPA
STANDARDS. THE VENTS SHALL BE RUN WITHIN THE INTERIOR OR EXTERIOR WALLS TO A LOCATION(S) HIGH ON THE ROOF. COORDINATE VENT LOCATIONS
WITH ARCHITECT AND/OR OWNER
- PROVIDE POWER ADJACENT TO SLAB VENT PENETRATIONS FOR POTENTIAL FUTURE INLINE FAN LOCATION INCLUDING ALL REQUIRED ROUGH IN WIRING AND
JUNCTION BOXES, IN THE EVENT THAT A FAN IS REQUIRED TO BE INSTALLED
- PROVIDE PROVISIONS FOR A SYSTEM FAILURE INDICATOR, INCLUDING ALL REQUIRED ROUGH-IN WIRING, AND JUNCTION BOXES, IN THE EVENT THAT A FAN IS
REQUIRED TO BE INSTALLED.
- PERFORM RADON TESTING AFTER THE HOME/PASSIVE SYSTEM IS COMPLETE TO DETERMINE IF THE HOME PASSES OR IF AN ACTIVE SYSTEM IS REQUIRED IN
ORDER TO MAINTAIN RADON BELOW EPA AND OTHER GOVERNMENTAL STANDARDS.
- IF AN ACTIVE SYSTEM IS REQUIRED, PERFORM FOLLOW UP RADON TESTING AFTER THE SYSTEM IS COMPLETE TO DETERMINE IF RADON HAS BEEN MITIGATED
- PROVIDE AND INLINE FAN IF ACTIVE SYSTEM IS REQUIRED. PROVIDE OTHER EQUIPMENT AND SYSTEM AS REQUIRED TO PROVIDE A FUNCTIONAL RADON
MITIGATION SYSTEM FOR THE UNITS.
CONTRACTOR TO COORDINATE INSTALLATION OF THE 15 MIL VAPOR BARRIER UNDER THE SLAB INCLUDING THE SEALING OF ALL JOINTS, ALL PLUMBING OR
MECHANICAL OR OTHER PENETRATIONS AND THE SEALING AND MECHANICAL FASTENING OF THE VAPOR BARRIER TO THE EXTERIOR CONCRETE FOUNDATION
WALLS.
RE: OUTLINE SPEC FOR MORE DETAILS
PROPOSED SQUARE FOOTAGE ANALYSIS:
2440 CHAMONIX LANE, VAIL, CO
Zone District: Two-Family Primary/Secondary residential (PS)
Lot is .3558 acres, equal to 15,499 SF
Allowable GRFA
.46 SF per 1 SF of site area < 10,000 SF of site area 10,000 x 0.46 equals 4,600 SF
.38 SF per 1 SF of site area > 10,000 SF of site area 5,000 x 0.38 equals 1,900 SF
.13 SF per 1 SF of site area > 10,000 SF of site area 499 x 0.13 equals 65 SF
_______________________________________________________________________________
Total Allowed Gross Residential Floor Area (GRFA) for entire lot 6,565 SF
Proposed Square Footage Summary
Habitable SF GRFA SF
Lower Level 1,627 SF 1,312 SF *1
Main Level 1,721 SF 2,475 SF
Upper Level 1,675 SF 1,675 SF
Double Height Space 484 SF*2
Garage Deduction (300 sf/space) (1,200) SF*3
_____________________________________________________________
Total 5,023 SF 4,746 SF
*1 53% of the Lower Level wall is above existing or finished grade whichever was more restrictive,
therefore 53% of the Lower Level SF is counted as GRFA (LOWER LEVEL HABITABLE + GARAGE 2,475 SF * .53 = 1,312 SF)
*2 Double Height Space with ceiling height over 16' is counted twice. 465 SF is counted over the Main level and shown in the
GRFA calculation.
*3 385 SF of Garage Area that is over the allowable 1200 SF is shown in the GRFA calculation.
Site Coverage
Allowable Site Coverage is 20% of the lot 3,100 SF
Proposed Site Coverage 2,483 SF
Proposed Site Coverage for Roofs beyond 4' 122 SF
Total Proposed Site Coverage 2,605 SF
Total Remaining Site Coverage 495 SF
- Setbacks
20' from front
15' from sides
15' from rear
Patio can extend to 1/2 the distance of the setback
Decks can encroach set back 5'
Roof or architectural projections can encroach 4'
- Height
Flat or mansard roofs not to exceed 30'
Sloping roof not to exceed 33'
- Garage
Allow 1,200 sq. ft. before area counts towards GRFA. 1,585 SF is provided.
- Parking Required per Chapter 10
Primary dwelling unit is more than 4,000 SF but less than 5,500 SF GRFA 4 spaces are required. 4 covered 9' x 18' (in garage)
spaces provided.
See Sheet A2.1 for landscape coverage information.
Scale
Date
Drawn by
Checked by
US Mail Only: P. O. Box 2378
Physical / Fedex: 210 Edwards
Village Blvd, Bldg A Suite A103
Edwards, Colorado 81632-2378
(970) 926 4301, Fax: 926 4364
hans@berglundarchitects.com
www . berglundarchitects.com
4
1
A5.1
A
3.2
PROJECT DIRECTORY
1
2
3
4
A9.1
A6.1
1
A6.1
1
100
LIVING
1
A4.1
SIM.
SYMBOL LEGEND
ABBREVIATIONS
MATERIAL LEGEND
DRAWING LIST:
VICINITY MAP
100
A
BUILDING
SECTION NO.
SECTION CUT
SHEET NO.
DETAIL NO.
DETAIL CUT
SHEET NO.
ROOM NUMBER
EXTERIOR ELEVATION
DOOR MARK
DETAIL CUT
REFERENCE GRID LINE
SPOT ELEVATION
DRAWING REVISION
INTERIOR ELEVATION
WINDOW MARK
Galvanized
Laminated Wood Beam
General Contractor
Hardware
Gypsum Wallboard
Grade
Gypsum
RW
RO
SEW
SECT
SAN
SHLV
Cpt Carpet
Ceramic
CER
SIM
SHT
W/
Reinforce (d)
REINF
FD Floor Drain
With (comb. form)
Required
Round Head Sheet Metal Screw
GA
FDN
FTG
Room
RM
RHSM
REQD
Gauge
Foundation
Footing
WD
W/O
Wood
Without
and Air Conditioning
Heating, Ventilating,
Lavatory
Manufacturer
Laminate
Inside Diameter
Miscellaneous
Mechanical
Not In Contract
Medicine Cabinet
Masonry Opening
Horizontal
On Center
Not to Scale
Oriented Strand Board
Opposite
Outside Diameter
Property
Plywood
Perforated (d)
Prefinished Sheet Metal
Penny (nails, etc.)
Refrigerator
Radius or Riser
Not Applicable
AAD
ADD
AGG
ADJ
AOR
BM
ARCH
ALT
BD
BS
BET
BRG
AFF
CL
BLDG
CAB
CLOS
CMU
CJ
CONC
COL
DP
DIA
DET
CONT
BO
DR
DN
DW
EL
EA
DRWG
DS
EQ
EJ
EXIST
EXT
FE CABT
FOC
FOS
FP
FL
FIN
DIM
GC
GALV
Glass
GLB
GR
GL
Head
HD
HDW
GWB
Highway
Height
HWY
HT
HVAC
GYP
Addendum
Attic Access Door
Aggregate
Adjacent
Area of Refuge
Alternate
Beam
Architectural
Board
Between
Both Sides
Bearing
Above Finished Floor
Interior
Joint
JT
INT
ID
MO
MFG
LAV
LAM
Maximum
Material
MAX
MC
MTL
Minimum
NIC
MISC
MIN
MECH
Cabinet
Building
Centerline
Closet
Concrete
Column
Construction Joint
Detail
Diameter
Dampproofing
Continuous
Concrete Masonry Unit
HOR
Bottom Of
Opening
OPG
OC
NTS
d
OD
OSB
OPP
Plate
PL
PFSM
PLWD
PERF
Project
Product
PROD
PROP
PROJ
Drain
Dishwasher
Down
Elevation
Each
Drawing
Downspout
Equal
Existing
Exterior
Expansion Joint
Face Of Concrete
Face Of Stud
Fire Extinguisher Cabinet
Refer
REF
REFR
Floor
Fireproof R
Finish
NA
Dimension
Tongue and Groove
Toilet Paper Holder
Sound- Transmission Class
Vinyl Asbestos Tile
United States Gage
Unless Noted Otherwise
Uniform Building Code
SL
SQ
SPEC
STC
SM
SUB
STRUCT
STL
TV
TEL
SUSP
SUPPL
IE
THK
TEMP
TO
T&B
T&G
TPH
STD
Roof Window
Sewer
Sanitary
Section
Rough Opening
Sliding
Shelves
Similar
Square
Specification
Sheet Metal
Sheet
Steel
Substitute
Structure (al)
Television
Telephone
Suspend (ed)
Supplement (al)
That Is
Thick
Tempered
Top Of
Top and Bottom
Standard
UG
TYP
TS
USG
UBC
UNFIN
U.N.O.
VENT
VIF
VERT
VAR
VAT
WC
V
WT
WIN
WP
Typical
Underground
Tube Steel
Unfinished
Variable
Vertical
Ventilate
Verify In Field
Voltage
Water Closet
Weight
Window
Waterproof
T Tread
FINISHED WOOD
ROUGH FRAMING OR
ROUGH SAWN TRIM
WOOD BLOCKING
CONCRETE
STONE
TILE
GLAZING
FRAME WALL
CONCRETE MASONRY
PARTICLE BD. OR
GLU-LAM WOOD
WOOD FIBER BD.
RIGID INSULATION
CARPET
ACOUSTICAL CEILING
STEEL
PLYWOOD
SHEET METAL
BATT INSULATION
GYP. WALL BOARD/
STUCCO/ PLASTER
ALUMINUM OR
SECTION PLAN
SECTION PLAN
ROCK/
SOIL/ COMPACTED FILL
SAND
NON-COMPACTED FILL
Issue Date:
ELEV. 100'-0"
T.O. PWD.
SITE ELEV. = 116'-0"
Power Actuated Fastened
PAF
Issue Date
CODE INFORMATION
GENERAL NOTES
ARCHITECT
BERGLUND ARCHITECTS, LLC
P.O. Box 2378
210 Edwards Village Blvd
Suite A103
Edwards, CO 81632
Phone: (970) 926-4301
Fax: (970) 926-4364
hans@berglundarchitects.com
STRUCTURAL
ENGINEER
LANDSCAPE
ARCHITECT
CLIENTS CONTRACTOR SURVEYOR
Eagle Valley Surveying
Contact: Mike Post
41199 Hwy 6 & 24, Eagle Vail
Avon, CO 81632
Phone: (970) 949-1406
Fax: (970) 479-0055
mikepost@evsurvey.com
MECHANICAL
ENGINEER
SOILS ENGINEER
HP Kumar
Contact: Steve Pawlak
5020 County Road 154
Glenwood Springs, CO 81601
Phone: (970) 945-7988
Fax: (970) 945-8454
hpkglenwood@kumarusa.com
KRM Consultants Inc.
Contact: Tim Hennum
P.O. Box 4572
Vail, CO 81658
Office: (970) 949-9391
Fax: (970 949-0839
krm@krmconsultants.com
Vail Custom Builders
Contact: Ted Leach
0429 Edwards Access Road
Northstar Center A207
P.O. Box 2809
Edwards, CO 81632
Phone: (970) 376-0802
Office: (970) 926-8771 x5
ted@vailcustom.com
John-Michael & Erin Liles
Contact: John-Michael Liles
736 High Street
Denver, CO 80209
Phone: (317) 709-4567
johnliles26@gmail.com
Ceres+ Landscape
Architecture
Contact: Scott Sones
P.O. Box 2134
Eagle, CO 81631
Phone: (970) 328-6080
Fax: (970) 328-6084
scott@Ceres-plus.com
DESIGN BUILD
CODE: 2015 IRC, 2015 IECC OCCUPANCY TYPE: SINGLE FAMILY HOME
ENERGY CONSERVATION: THE BUILDING COMPLIES WITH THE ENERGY CONSERVATION REQUIREMENT FROM CHAPTER 4 OF THE
2015 INTERNATIONAL ENERGY CODE PER ZONE 6B ADOPTED BY THE TOWN OF VAIL, AND AS DEMONSTRATED BY PRESCRIPTIVE
BUILDING THERMAL ENVELOPE, AS FOLLOWS:
The following is a summary for the climate zone 6B of Table 402.1.1 requirements of the IECC and as adopted by The Town of Vail, and an outline of
the proposed R values of the assemblies of the building which are defined in the Construction Document Drawings and Specifications:
Maximum Glazing U-Factor - Requirement of .32 for new single family dwelling units, this can be a weighted average.
The windows and doors with dual glazed Low E/i89 glazing (Low E on two surfaces) exceed this requirement.
Ceiling & Roof Insulation - Requirement of R-49 which is reduced to R-38 per 402.2.1 since the construction techniques provide a full R-38 insulation
value over the wall top plate.
Typical Roof Condition - The design provides a full R-38 insulation value over the wall top plate as follows: Provide R62.4 at roof cavities with
5/8" plywood over 14” TJIs: with 4” minimum of 2# closed cell spray foam insulation with an R value of 6.6 per inch equaling R26.4 and 12” of
blown in cellulose insulation with R3.6 per inch equaling R36.
Basement Walls Insulation - Requires R-15 of continuous insulation or R-19 cavity insulation. "15/19" shall be permitted to be met with R-13 cavity
insulation on the interior of the basement wall plus R-5 continuous insulation on the interior or exterior of the home":
Provide R-23.2 per the sum of the provided R values of the R-10 continuous exterior rigid foam insulation drainage board over the
concrete wall with 2x wood furring set 1" off concrete with 2" of 2# closed cell spray foam insulation with R-13.2 (R-6.6 per inch) and 5/8"
drywall exceeds the requirement.
Exterior Walls Insulation - Requires R-20: Exterior walls with 5.5” cavity:
Provide R22.8 with 1” minimum of spray foam insulation @ inside of sheathing with an R value of 6.6 per inch equaling R6.6 and 4.5” of
blown in cellulose insulation with R3.6 per inch equaling R16.2 or approved equal.
Floor Insulation - Requires R-30: The building has been designed with a conditioned and finished basement space.
Provide 14" of blown in cellulose insulation with R-3.6 per inch equaling R-50.4
Basement Slab - Requires R-15 for 4' horizontally under slab (since the slab is heated).
Provide R25 @ slab edge with continuous R-15 3" rigid foam insulation under the slab and R-10 continuous exterior insulation & drainage
board @ exterior of foundation.
Provide full cavity blown in cellulose sound insulation at all interior walls and at all floor assemblies.
SINCE BUILDING COMPLIES W/ 2015 IECC PRESCRIPTIVE BUILDING ENVELOPE, RES-CHECK OR SIM. ENERGY MODELING IS NOT REQ'D
ADDITIONAL REQUIREMENTS PER TOWN OF VAIL CODE AMENDMENTS:
ROOF COVERING: Meets Section 1505.6 of the Town of Vail Code- Standing seam roofing will be installed to meet the required Class A roof or
Class A roof assembly.
FIRE SPRINKLER SYSTEM: Building is to be equipped throughout with an automatic sprinkler system installed in accordance with NFPA 13 and the
Town of Vail. A monitored fire alarm system will also be provided.
PLUMBING: See plumbing documents from Plumbing Contractor
MECHANICAL: See mechanical drawings and documents from Mechanical Contractor
ELECTRICAL: See load calculations from electrical contractor for service and electric panel sizing
PROJECT INFORMATION
1/4" = 1'-0"
3/23/2017
12:54:36 PM
A1.0
COVER
SHEET
3-23-2017
CPM
HB
LILES RESIDENCE
3-23-2017
PERMIT SET
3-23-2017
PERMIT SET
LILES RESIDENCE
2440 CHAMONIX LANE
VAIL, CO 81657
A1.0 COVER SHEET
SURVEY
LANDSCAPE DRAWINGS
L1 LANDSCAPE PLAN
ARCHITECTURAL DRAWINGS
A2.0 SITE PLAN
A2.1 LANDSCAPE COVERAGE
A2.2 AREA CALCS
A2.3 STAGING PLAN
A3.1 LOWER LEVEL FLOOR PLAN
A3.2 MAIN LEVEL FLOOR PLAN
A3.3 UPPER LEVEL FLOOR PLAN
A3.4 ROOF PLAN
A4.1 ELEVATIONS
A4.2 ELEVATIONS
A4.3 ELEVATIONS
A4.4 ELEVATIONS
A4.5 3D VIEWS
A4.6 3D VIEWS
A4.7 INTERIOR 3D VIEWS
A5.1 SECTIONS
A5.2 SECTIONS
A5.3 SECTIONS
A5.4 SECTIONS
A5.5 SECTIONS
A5.6 SECTIONS
A6.1 FOUNDATION DETAILS
A6.2 FOUNDATION DETAILS
A6.3 FOUNDATION DETAILS
A6.4 FOUNDATION DETAILS
A6.5 FOUNDATION DETAILS
A6.6 FOUNDATION DETAILS
A6.7 WALL DETAILS
A6.8 DECK AND HANDRAIL DETAILS
A6.9 ROOF DETAILS
A6.10 ROOF DETAILS
A7.1 FIREPLACE SHEET
A7.2 FIREPLACE SHEET
A7.3 STAIR SHEET
A7.4 STAIR SHEET
A7.5 STAIR SHEET
A7.6 STAIR SHEET
A7.7 STAIR SHEET
A7.8 STAIR SHEET
A7.9 STAIR SHEET
A7.10 STAIR SHEET
A. The contract documents, aka construction documents, consist of the
architectural and structural drawings/notes, the exterior color/material
schedule, architectural finish schedule, and the project outline specifications
as well as the agreement between the contractor and owner. Any work
shown, specified and/or noted in one of the documents shall be supplied as
though fully covered in all. Any discrepancy between the different parts
should be reported to the architect immediately.
B. Contractor will assume responsibility of items requiring coordination and
resolution during the construction process.
C. All work shall comply with all state and local codes and ordinances, and shall
be performed to the highest standards of craftsmanship by journeyman of
the appropriate trades.
D. These documents are intended to include all labor, materials, equipment and
services required to complete all work described herein. It is the
responsibility of the contractor to bring to the attention of the architect any
conditions which will not permit construction per the intentions of these
documents. It is the responsibility of the architect to provide details and/or
directions regarding design intent where it is altered by existing conditions or
where neglected in the documents.
E. All change orders must be approved in writing by the owner prior to
contractor performing any work associated with a change order unless
owner has authorized contractor to proceed.
F. Any materials proposed for substitution of those specified or called out by
trade name in these documents shall be presented to the architect for review
and approval. The contractor shall submit samples, product data,
manufacturers installation recommendations and a side by side analysis /
spread sheet comparing ASTM testing/performance or other applicable
standards, warranty, limitations, maintenance considerations, cost, lead
time/schedule impact, any incompatibility/impact to other products or
systems in project, and impact on LEED certification if applicable for the
project for the proposed substitution and the specified product. Once all
required information is received by architect, a minimum of three weeks’
time is required for review and approval and or denial of substitution.
G. Submit samples as required by drawings and specifications. All samples
shall be reviewed by the architect before the work is performed. Work must
conform to the reviewed samples. Any work which does not conform shall
be removed and replaced with work which conforms at the contractor's
expense. Subcontractors shall submit requests and samples for review
through the general contractor when work is let through him or her. Required
verifications and submittals to be made in adequate time as to not delay
progress. Once competed samples including all required product
information if applicable is received by architect, a minimum of three weeks’
time is required for review and approval and or denial of samples.
H. Shop drawings must be thoroughly reviewed and stamped approved by
contractor prior to submitting to architect to make sure they meet
construction document requirements and are accurate in terms of correct
quantities, dimensions, handing and design intent. Shop drawings shall be
submitted to the architect for his or her review where called for anywhere in
these documents. Review shall be made by the architect and architect’s
consultants for general compliance with construction drawings and design
intent only. Architect’s review is required before work is begun, and work
shall conform to the reviewed shop drawings, subject to replacement as
required per above. Architect will try to identify any discrepancies in shop
drawings, but contractor is ultimately responsible for shop drawing accuracy
as the shop drawings are a product of their subcontractor.
I. The building inspector shall be notified by the contractor when there is need
of inspection as required by the 2015 international building code/international
residential code, 2015 IECC, or any applicable or local code or ordinance.
J. The contractor shall be responsible for the safety and care of adjacent
properties during construction, for compliance with federal and state
O.S.H.A. regulations, and for the protection of all work until it is delivered
completed to the owner. Contractor to repair any damage to adjacent
properties or completed work at his or her own expense.
K. All dimensions noted take precedence over scaled dimensions. Dimensions
noted with "N.T.S." denotes not to scale.
L. Contractor shall verify and coordinate all openings through floors, ceilings,
and walls with all architectural, structural, mechanical, plumbing, and
electrical drawings. Verify with structural engineer if holes/notches can be
cut in structural members prior to doing so.
M. Contractor to coordinate new construction w/ existing conditions and notify
architect and structural engineer about discrepancies of drawings of existing
house/conditions and assumptions. Every reasonable effort should be made
by contractor to protect and/or minimize damage to existing conditions.
A8.0 WINDOW & DOOR SCHEDULE
A8.1 WINDOW DETAILS
A8.2 WINDOW & DOOR DETAILS
A8.3 WINDOW & DOOR DETAILS
A10.0 ELECTRICAL SCHEDULE AND NOTES
A10.1 LOWER LEVEL RCP
A10.2 MAIN LEVEL RCP
A10.3 UPPER LEVEL RCP
STRUCTURAL DRAWINGS
S1 SPECIFICATIONS
S2 FOUNDATION PLAN
S3 MAIN FLOOR FRAMING PLAN
S4 UPPER FLOOR / LOW ROOF FRAMING PLAN
S5 ROOF FRAMING PLAN
S6 DETAILS
S7 DETAILS
S8 DETAILS
S9 DETAILS
REVISION SCHEDULE
# DESCRIPTION DATE
04/28/17