Press Alt + R to read the document text or Alt + P to download or print.
This document contains no pages.
HomeMy WebLinkAboutEast Vail Conceptual Alternatives Report v3.pdf 1-70 East Vail Landscape and
Water Quality Improvements
Conceptual Alternatives Report
:,
Tr � h - Y'!',1-4.2.0.4'
..0 '+k #4 `r ri t. i{y. Y r r� '1 �"'• i,*,
Ra•']r h :* • : te. ... ` 41. - Berl"+ r�r.-'- ' .- . +/_.4 _- k.
.,, . rY___--!-4.4.-, Y_ � � „it,' `� : . -4 i- ., —�... ,-ti mes
F- y I "—x_z .4r r'[L.� ..}Tx' .4 !j*. f V _ --
'_ .-
r * l ��
4y�� • �21.ry�rr L. - {� -s _ }r4.
,ice' -;^j-. ;tom -
'. ..Y { - Vit' #• �*- -
a_ .
} .,� nFas� �
JK ••,- -... + I-
til _r A"yf • - _ . ,
.•-•,:e10.4,' _ o, • 0 . _ ,_.
l '
•
Prepared for
Town of Vail, Colorado
July 8, 2016
Prepared by: With support from:
MUNDUS BISHOP
WATER & NATURAL RESOURCES
720 S. Colorado Boulevard, Suite 410 S 2601 Blake Street, &lite 300
Denver, Colorado 80246 Denver, Colorado 80205
Phone: 303-757-3655 Phone: 303.477.5244
www.respec.com httri://www.mundusbishop.com/
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
Table of Contents
1 BACKGROUND AND PURPOSE 1
2 SITE CONSIDERATIONS AND CONSTRAINTS 2
2.1 Maintenance 2
2.2 CDOT Requirements 3
2.3 Landscape Aesthetics 3
2.4 Existing Utilities 3
2.5 Water Rights 4
3 WATER QUALITY DESIGN ELEMENTS 4
3.1 Check Dams 4
3.2 Sump Inlets 5
3.3 Sediment Vault 5
3.4 Surface Sediment Basin 5
3.5 Proprietary Treatment Structures 6
3.6 Infiltration Basins 6
3.7 Wetland Polishing 6
3.8 Sweeper Bays 7
4 EXIT 180 LANDSCAPE AND WATER QUALITY 7
4.1 Landscape Approach 7
4.2 Existing Exit 180 Landscape Conditions 8
4.3 Proposed Landscape Concept 11
4.4 Plant and Materials Palette 14
4.5 Exit 180 Water Quality Concepts 15
4.5.1 Retrofit of the Existing Storm Sewer System 15
4.5.2 Wetland Polishing 16
4.5.3 Check Dams 17
4.5.4 Concrete Sweeper Bays and Pans 17
4.6 Water Quality Treatment Train 17
5 SNOW CAST OFF AREA 19
6 TRUCK RAMP SITE 21
7 CONCEPTUAL COSTS 22
8 REFERENCES 23
TABLES& FIGURES
Figure 1 — Vicinity Map
Figure 2 — Example Check Dams
Figure 3 — Example Sediment Vault
Figure 4 — Example Surface Sediment Basin
Figure 5 — Exit 180 Aerial
Figure 6 — Exit 180 Existing Condition
Figure 7 — Exit 180 Existing Vegetation
Prepared by RESPEC, Inc. TOC Page 1 of 2
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
Figure 8 — Exit 180 Existing Conditions at Southeast Corner
Figure 9 — Exit 180 Proposed Concept
Figure 10 — Existing Topographical Character
Figure 11 — Northwest Corner Exit 180 Proposed Concept
Figure 12 — Southeast Corner Exit 180 Proposed Concept
Figure 13 — Plant Palette Samples
Figure 14 — Materials Palette Samples
Figure 15 — Stone-Lined Inlet Concept
Figure 16 — Exit 180 Water Quality Flow Diagram
Figure 17 — Snow Cast Off Area Aerial
Figure 18 — Snow Cast Off Area Low Water Crossing Location
Figure 19 — Truck Ramp Site Aerial
Table 1 — Conceptual Costs
APPENDICES
Appendix A — Appendix A of the Gore Creek Water Quality Improvement Plan
Appendix B — Gore Creek Action Plan Stormwater Control Projects
Appendix C — Existing Site Photos
Prepared by RESPEC, Inc. TOC Page 2 of 2
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
1 BACKGROUND AND PURPOSE
The purpose of this report is to document the development of conceptual alternatives for the 1-70 East
Vail Landscape and Water Quality Improvements project. The recommendation, location citing, and
initial concept for the proposed water quality improvements included in this project were first provided
in Appendix A of the Gore Creek Water Quality Improvement Plan, completed in August of 2013 by
Leonard Rice Engineers, Inc., although Appendix A itself was authored by Alpine Engineering, Inc. in
September of 2012.The applicable portion of Appendix A of the Gore Creek Water Quality Improvement
Plan is included as Appendix A herein. The proposed improvements were further developed in the Gore
Creek Action Plan Stormwater Control Projects, completed in May of 2015 by Alpine Engineering, Inc.
The applicable pages of this document are included as Appendix B herein.
The Town of Vail was awarded funding for the water quality improvements included in this project
through the Transportation Alternatives Program (TAP). The goal of the improvements is to address the
303(d) impairment for aquatic life along Gore Creek that exists from its confluence with Black Gore
Creek near the bridges at milepost (MP) 181.9 of 1-70 all the way to its confluence with the Eagle River.
The 303(d) impairment for aquatic life along Gore Creek is provisional, which means the specific cause of
the impairment is unknown. The three individual project locations are along 1-70, generally between MP
179.8 and 182. Their specific locations are noted by red polygons in Figure 1 below. The three project
sites are named by this report as the Exit 180 site (Exit 180), the snow cast off area under the bridges at
MP 181.9 (snow cast off area), and the base of the runaway trunk ramp (truck ramp site). Existing
conditions at each of the sites are documented in Appendix C.
Figure 1—Vicinity Map
•
• MP"1.8U.
Exit 180 . - =
•
The conceptual design alternatives included in this report have been developed to improve stormwater
quality runoff from the Exit 180 site and from the snow cast off area and truck ramp site near MP 181.9.
The alternatives at the Exit 180 interchange also include landscape improvements. The water quality
alternatives developed in this report include various sediment collection and/or infiltration
Prepared by RESPEC, Inc. Page 1 of 23
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
opportunities at each of the three sites. The concepts chosen by the Town of Vail will ultimately be fully
developed in accordance Town of Vail standards,AASHTO design standards, and CDOT standards.
2 SITE CONSIDERATIONS AND CONSTRAINTS
There are three individual sites included in the 1-70 East Vail Landscape and Water Quality
Improvements project and each presents its own unique list of constraints that need to be incorporated
into the design of the improvements. Additionally, some of the design goals for each site could be
considered mutually exclusive with each other. For example, when a project proceeds with a focus only
on making maintenance as quick, simple, and low-cost as possible, the final design may not provide as
much water quality or aesthetic benefit. On the other hand, when a project proceeds with a focus only
on aesthetic benefit, maintenance may be unreasonably time consuming and costly. Additionally,
because each of the three sites is located within CDOT right-of-way, CDOT must ultimately approve the
design of each site. This section of the report discusses the multiple expectations for each site that must
be balanced to maximize the benefit each site can provide. Each site will be discussed individually and in
more detail later in this report with regard to the considerations and constraints listed in this section.
2.1 Maintenance
There are two major considerations when it comes to maintenance. The first is maintenance of the
water quality facilities themselves. This consideration applies to each of the three sites. It is imperative
that water quality facilities be maintained properly as they will not function if they are not maintained.
Maintenance activities will require the use of a vac truck, at a minimum, and may require periodic
excavation and replacement of infiltration materials and/or vegetation if infiltration is selected as one of
the design concepts to pursue for final design. Maintenance activities for improvements proposed by
this project, including maintenance of landscape areas and irrigation systems, will require additional
maintenance funding. Maintenance will also require that adequate access be provided to each of the
water quality components that need to be maintained. Access roads and ramps must be able to
accommodate the size and weight of the equipment needed to maintain the facility.
The second major maintenance consideration is snow removal and storage operations. Although this
consideration applies only to the Exit 180 site, the Town of Vail will likely be required to acquire
additional snow removal equipment and hire additional snow removal personnel if the proposed
improvements require a significant change to current snow removal and storage operations. Town of
Vail maintenance personnel have been consulted as part of the conceptual alternatives analysis to
understand current snow removal and storage operations and potential constraints. Depending on the
design elements and configuration selected at the Exit 180 site, additional maintenance costs may occur
if additional hauling of snow in the winter is required. Town staff should be consulted to quantify
additional anticipated maintenance costs, as they are not included in the estimate in this report.
The current understanding between the Town of Vail and CDOT is that CDOT maintenance crews are
likely willing to consider maintenance responsibilities for the water quality facilities at each of the three
sites, but the full scope of the maintenance activities has not yet been determined. While CDOT is likely
to agree to perform sediment removal at sump inlets or sediment vaults, CDOT may not agree to accept
responsibility for the removal and replacement of infiltration media or maintenance of landscaping
materials or vegetation that could surround the water quality facilities at the Exit 180 site. Once the
Prepared by RESPEC, Inc. Page 2 of 23
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
design has been fully accepted by CDOT at the FOR meeting, it is anticipated that an intergovernmental
agreement (IGA) or a memorandum of understanding (MOU) will be developed to assign maintenance
responsibilities for the proposed improvements.
2.2 CDOT Requirements
CDOT requirements for the snow cast off area under the bridges at MP 181.9 and the base of the
runaway trunk ramp are essentially limited to the maintenance considerations described above,
although improvements in the median and outside of the eastbound lane of 1-70 at the truck ramp site
may require guardrail because of clear zone criteria. However, improvements at the Exit 180 site must
also meet a myriad of CDOT roadway design criteria. The RESPEC team has had several meetings with
CDOT representatives regarding potential alternatives at the Exit 180 site. CDOT's concerns include site
distance, z slope criteria,the potential for ponded water or other obstructions within the clear zone, and
the time required to maintain the facilities. Representatives from CDOT's various program areas
including utilities, hydraulics, traffic, maintenance, environmental, and materials, among others, will
have input into the final design at the FIR and FOR stages of the project.
2.3 Landscape Aesthetics
The three sites included in the 1-70 East Vail Landscape and Water Quality Improvements project can be
separated into two general categories, those that include an aesthetic landscaping component and
those that will simply be revegetated. The Exit 180 site is the only one of the three sites that will receive
landscaping. The snow cast off area under the bridges at MP 181.9 and the base of the runaway trunk
ramp are simply to be revegetated once construction of the water quality facilities is complete.
Providing water quality treatment and landscaping elements at the same site can sometimes result in
conflicts between the proponents of the two functions when the desire for what would be perfect for
one function is placed ahead of what would be most practical for both functions. While a site can be
designed with aesthetics as a high priority, the design has to account for changes to site conditions over
time and the need for maintenance. When landscaping is located in the immediate vicinity of a water
quality facility, especially one that is expected to collect a very large amount of sediment, consideration
has to be given to the viability of the landscape aesthetic not only immediately following the
establishment of vegetation, but as sediment and other pollutants accumulate at the site over time.
Frequent maintenance may be able to alleviate the situation, but the frequency required may be more
than what is economically feasible or practical. If the incoming sediment load is disregarded during the
design of the landscaping, the site will not end up with the desired aesthetic. Vegetative elements of the
landscape design should not be located where heavy sediment is expected to accumulate. Conversely,
the areas where sediment is expected to accumulate should ideally be comprised of materials from
which the sediment is easily removed if maintenance staffing and/or budgets are not able to
accommodate labor-and time-intensive sediment removal activities.
2.4 Existing Utilities
The Exit 180 site has an extensive amount of utilities including water, sanitary, electric, fiber optic,
telephone, and storm sewer. There may be others not yet identified. The existing storm sewer lines will
be an integral part of the water quality improvements, as they will continue to convey runoff from inlet
to inlet, ultimately discharging to Gore Creek. The snow cast off area does not appear to have any
Prepared by RESPEC, Inc. Page 3 of 23
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
utilities and the truck ramp site likely only includes CDOT's large fiber optic line that runs the length of I-
70.The intent of the design of each site will be to avoid all existing utilities to the extent possible.
2.5 Water Rights
Colorado water law does not allow for water quality facilities to permanently pond water. Water quality
facilities must be designed to continuously release or infiltrate at least 97% of runoff from a 5-year
storm within 72 hours after the end of the rainfall event.They must be designed to continuously release
or infiltrate runoff from events greater than a 5-year storm as quickly as practicable. In no event may
they hold water longer than 120 hours.
3 WATER QUALITY DESIGN ELEMENTS
This section will discuss several general options that can be utilized at one or more of the three project
sites. It will also discuss general pros and cons to each in terms of water quality treatment, aesthetics,
and maintenance requirements.
3.1 Check Dams
Check dams are small berms placed across drainage swales to slow the velocity of runoff in those
swales. This allows sediment to fall out and provides an opportunity for suspended or dissolved
pollutants to infiltrate into the soil or be absorbed by local vegetation. Check dams are designed to
overflow during larger storm events. Sediment should be removed once it reaches half the height of the
berm. Check dams can be also developed as landscape form elements that incorporate plantings to
provide an aesthetic benefit in addition to a water quality benefit. Figure 2 shows a few examples of a
check dams that contribute to the landscape aesthetic.
Figure 2—Example Check Dams
At
. :4:lia '' ^• id'.
�' '� _ ,�Y;: ,1.:' ^.1?. .moi, , �.,yr V ,,
'. j ':'
,` ' .. �E•• '•}rte .�::K�� W-. {: r /�.:..:
- s. z'..1.P
.,
` .4•'
The manner in which a check dam is cleaned and maintained is dependent upon the materials used to
line the upstream invert of the swale. A vac truck can typically be used in all cases. If needed, a small
drainage pipe can be placed through the berm to allow the area upstream of the check dam to drain
more quickly. Check dams will become overrun by sediment without proper maintenance.
Prepared by RESPEC, Inc. Page 4 of 23
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
3.2 Sump Inlets
Sump inlets are simply storm inlets that have an inlet bottom a foot or more beneath the lowest storm
sewer invert out of the inlet. The volume beneath the lowest invert out of the inlet is designed to
capture and store sediment. The deeper the bottom of the sump below the lowest storm sewer invert
out, the more sediment can be captured and stored in the sump. Sump inlets can be cleaned with a vac
truck. The only disadvantage to sump inlets is that water may pond in the sediment storage area, and
ponded water is frequently considered a public nuisance. It is possible this can be somewhat mitigated
by including small holes in the sides and bottom of the structure and backfilling around the structure
with course gravel to allow the stored water to drain. The frequency at which each sump inlet requires
maintenance can be determined through monthly inspection over the course of the first year each sump
inlet is in service.
3.3 Sediment Vault
Sediment vaults are similar to sump inlets in that they have a storage volume beneath the invert out of
the structure. Sediment vaults are typically larger than sump inlets and can include baffles, walls, weirs,
screens, and orifices that trap sediment and floating debris. Large sediment vaults can be expensive to
construct and may require multiple access hatches or grates so that they may be easily cleaned with a
vac truck. They will also pond water beneath the outlet, although this ponding may be reduced by
including small holes in the sides and bottom of the vault and backfilling it with coarse gravel to allow it
to drain. The frequency at which each sediment vault requires maintenance can be determined through
monthly inspection over the course of the first year each vault is in service. Figure 3 shows an example
of a sediment vault.
Figure 3—Example Sediment Vault
' 4
ifo
•
3.4 Surface Sediment Basin
A surface sediment basin serves as a collection point for sediment and is accessible by a vehicle.
Maintenance crews can drive into a surface sediment basin and collect sediment with a front loader. It
typically has three walls against which a loader or skid steer can push and scoop sediment. Figure 4
shows an example of a large surface sediment basin during construction and full of sediment. The
frequency at which each surface sediment basin requires maintenance can be determined through
monthly inspection over the course of the first year it is in service
Prepared by RESPEC, Inc. Page 5 of 23
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
Figure 4—Example Surface Sediment Basin
,,.
l J - •tet^� _.� K5 _.w^^ - - - _-�3_
•
t
3.5 Proprietary Treatment Structures
Proprietary treatment structures are underground treatment facilities that are manufactured by various
companies including Contech, Oldcastle, and AquaShield, among others. These structures often use
hydrodynamic separation to remove coarse sediment. They may also contain cartridges that can remove
dissolved pollutants. They are an excellent option where space is very limited, flow rates are very small,
and inspection can be provided regularly. They are also relatively expensive to purchase and may
become quickly overwhelmed by large amounts of sediment. They may also require some form of filter
cartridge that may need replacing on a regular basis, adding to maintenance costs.
3.6 Infiltration Basins
Infiltration basins are depressions designed to store runoff on the surface and infiltrate it gradually into
the ground. They may be vegetated or not and are dry except in periods of heavy rainfall. They can be
very effective at removing pollutants by filtering runoff through the soils and they are easy to construct.
However, they are also prone to fail without frequent maintenance or if runoff is not pretreated prior to
reaching the infiltration basin.
If an infiltration basin is vegetated and the basin fills up with large sediment, the vegetation will most
likely be destroyed during sediment removal operations. If an infiltration basin is lined with decorative
cobble, the cobble will likely have to be removed and replaced during sediment removal operations. In
either case, maintenance requirements of infiltration basins are typically extensive if peak performance
is desired. If they are not maintained with proper frequency,they often become unsightly.
3.7 Wetland Polishing
Wetland polishing consists of discharging runoff that has already had the majority of sediment removed
into an area populated with wetland plantings. The water is allowed to spread out over the wetland
polishing area and the wetland plants treat the water quality by trapping the remaining sediment and
retaining excess nutrients and other pollutants such as heavy metals. If the great majority of sediment is
not removed prior to runoff entering the wetland polishing area,the wetland can quickly become buried
in sediment, depending on the sediment load in the runoff. Wetland polishing areas need to be designed
to receive minimal sediment so that maintenance activities that could destroy the wetland plants can be
limited.
Prepared by RESPEC, Inc. Page 6 of 23
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
3.8 Sweeper Bays
Sweeper bays and concrete pans are roadside facilities that allow sediment to accumulate where it can
be easily cleaned with a street sweeper. Sweeper bays and concrete pans are an alternative to soft
shoulders that often allow sediment to mix with native soils, making it difficult to remove the sediment
without removing the native soils.
4 EXIT 180 LANDSCAPE AND WATER QUALITY
This section will discuss landscaping and water quality concepts at Exit 180. It will discuss optional
features as well as how these concepts can be developed to facilitate maintenance and meet CDOT
roadway criteria. An overall aerial of the Exit 180 site is shown in Figure 5 below.
Figure 5—Exit 180 Aerial
k
.. � y ` s.� r ;4� a : e r ur!,- ,-,.-4'.;,•4'.. v y �."" _
_
q
:'� f
. �ryu
' "! r , ��. a�% � t� �� '�I * -! IX� rte + ,� �
-- .: ��
w ���
+rte J -• r I „ .n.{ a �I --
4.1 Landscape Approach
The Vail Valley is an exceptional natural landscape. Its alpine forests, rock formations, riparian corridors,
wetlands, and creeks and waterfalls provide unsurpassed natural beauty. In contrast, the landscape
surrounding the Exit 180 site is a patchwork of native and non-native plants, mono-cultural grassland,
and areas highly disturbed by sediment accumulation, snow storage activities, and traffic patterns. The
approach to the proposed landscape design concepts draws on the aesthetic qualities of the
surrounding valley, and on select features within the project site, to develop a palette of context-
appropriate forms and materials. The Exit 180 site is a gateway to East Vail, and the location is highly
visible to all motorists, pedestrians, and bicyclists traveling through the area. The proposed concepts
address the need for aesthetic improvements appropriate to the site's context and use.
As discussed previously in Section 2.3, the proposed landscape improvements must provide multiple
functions. They should create an inviting and aesthetically pleasing experience while complementing
and integrating with the water quality improvements and current and future maintenance demands.
Our approach integrates landform, plant material, stone, and hardscape elements to balance aesthetics,
water quality, and maintenance activities.
Prepared by RESPEC, Inc. Page 7 of 23
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
While the concepts aim to balance functions, aspects of the aesthetic landscape treatment may affect
current maintenance practices and require additional maintenance staff and equipment. Additional
snow hauling, maintenance of sediment vaults and other water quality infrastructure, and landscape
and irrigation maintenance will result in increased costs. The Town of Vail should estimate and consider
these additional costs when evaluating alternatives.
4.2 Existing Exit 180 Landscape Conditions
As shown on the Exit 180 Existing Conditions map in Figure 6 on the following page, the Exit 180 site
landscape is currently dominated by a single grass species, Smooth Brome (Bromus insermis). Although
Smooth Brome is a non-native grass, the current stand has value as a sediment stabilizer and
groundcover. Within the Smooth Brome are patches of wetland plant species shown in Figure 7 below,
fescue species, and a variety of tree and shrub species.
Figure 7—Exit 180 Existing Vegetation
11‘10.01,r
s � 111411110111110111
111111.11.
E 11 spa
Current snow storage, winter road treatments, and traffic patterns have adversely affected several areas
within the project site. These areas are in high-visibility locations as shown in Figure 8, and sediment
loads and snow storage methods result in very poor or non-existent plant growth.
Figure 8—Exit 180 Existing Conditions at Southeast Corner
"CI -‘111064111
4.
Prepared by RESPEC, Inc. Page 8 of 23
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
Figure 6-Exit 180 Existing Condition
--- -- .___------',--;-----------_-::-042-5:---- --_ __ _ - _ _---------th— — -------------------------- _ �g�'
0 0. o o m };.' r4,--kkF �`�,.-_-__--- - $G- ----— _ may- _, -- i
qr
®_ • S . .-._ ' 1 -may !E'VA t-c .4.,--,..--..._,..,
•
40---------
.
C:2)/
0 s
Li
-
------------- 0�e-----------
17raf.eRoad ------ --------
- 2414i Fall neQDr.
!Y
----:_-_----._=_-7-_-_,--- r-N---r--- - - _________----- , - 4k. do Af.,., 4,...oe• . e 0,,, 41' el tk ke 0-0'i,...-.0' --__ *so
-rte ® 1 L e' �1....m.. �- --
ti, r
� —. �Y �_ ter`-- �— J_ 0 � �~ ~~` __ - �_ �..__4
ti
-------- --_____, ---- ..------- Iiii--17--y .-
*t. �J1 -, as
i
4.41111t--..--- ---- --- - -- __, -- -,abl...1.1.-°"....
'.+.t ail a OO �' lll� ,<n`O 0 4M O1000 aloft° Q
�, tId o P�I\ � jl� - � O Parking7-_-
a' . �
...� ir
_ ' �— - �' li, _ --•„ .-�� _ '._ _
(14
_- - s ,_ .. Big Horn Rd. ---
r -
..)T-.- . .
.k.,4.`+► _
Gore Creek _ "
Legend ttt-1- -----
f a
N
b 0 Existing Tree — 16 ., BikeTrail11�IC 'Snow Storage ■ Existing Inlet 1CD 7m177
a Existing Wetland Plants f 11......_ Existing
Existing Topographic °1 Views • Existing Signage 0 25 50 100
Existing Grass(Primarily Existin Boulders
Smooth Brome) Sediment Accumulation g
Existing Condition .JULY 2016
1-70 E Vail Landscape and Water Quality Improvements MUNDUS BISHOP
CO I$IIITIN6 k SSRVICES
Prepared by RESPEC, Inc. Page 9 of 23
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
Figure 9—Exit 180 Proposed Concept
Figure 9: Proposed Concept
-- ._
Lfit
Qo
'1-0
00 it
o ` - :�n y
00
ti ° ��� mall Latae Dr9--_;._ 1:
•
1-7o FrontageRoado� 5ee f � •� •
0 c o O o p Q Enlarib gement •
• @ e a Figure 11 b -------- -- —„ ` --,�i __,..
ilkih
. --- -T__
-*•,, 7•,,--i,z) ...,_"____.1r-..,4"4,`". 1-.1.41111r5-#C ii\17--ilio--v-O.......
:..44...,, -.- 40::._ -__as,• (i)__. daulliL=p .-.. ------ __ - •-
c;:) D 0 ------- 7_-_:.-----___ ------------- - -
'K....„....
� _ �9`eVaHeR�lo ■ U" 5ee • • ���.�• •S �+ � . . . _ !+
4
3 %. ----~ nal7raii Enlargement [ t7 p } O % g /�
r ( �� •• o pa A Figure 12 p0o� Q Parking set `3) C7 f_:)
0
v,.
CM (4Clit
' - + • �r F0 Big Horn Rd. • • �f�
111110 0
�. (sl :ter_ f' -- ~_�
0
III
--\
AA. Gore Creek .
Legend ,. . .. - _
0 0 Existing Tree — Bike Trail �I Proposed Wall ��� Check Dams 0 Potential future Parking A
Wetland Plants �' Views _] Focal Landscape Feature 4Q Wetland Polishing Area
�0 25 50 0
S • Existing Boulderssormigive
Enhanced Native Planting1 Preserve ExistingTrees
Existing Grass(Primarily • Existing Inlet ® Re-Aligned Trail
Smooth Brorne) w • Existing Signage •p Proposed Tree 0 Enhanced Topography
Proposed Concept JULY2016
1-70 E Vail Landscape and Water Quality Improvements RESPEC MUNDUS BISHOP
Prepared by RESPEC, Inc. Page 10 of 23
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
4.3 Proposed Landscape Concept
At the overall project site scale the proposed concept, shown in Figure 9 on the previous page, draws on
the existing undulating topography along the slopes flanking 1-70, shown in Figure 10, to create a more
pronounced pattern of rolling landforms. The concept includes regrading and installing boulders along
portions of the existing slopes to increase and accentuate the wavy form, creating visual interest. The
enhanced topography and stone also provides pockets for planting drifts of plants to add texture, color,
and seasonal variability. In addition to the installation of large drifts of native wildflowers, grasses, trees,
and shrubs, seeding and weed control measures are proposed within the existing Smooth Brome stand
to increase biodiversity and enhance aesthetics.
Figure 10—Existing Topographical Character
164
.11100
prom
4
Ilketikp-
Within the framework of the enhanced landform, and in other select locations throughout the site, the
concept includes focal points defined by more intensive planting, terracing, landform, and stone. These
focal points are strategically located to provide a gateway into East Vail. Two highly visible focal points
are identified in Figure 9 on the previous page, and illustrated in enlargements in Figures 11 and 12.
Figure 11 shows a landscape feature concept for the northwest corner of Exit 180, at a focal point visible
from the westbound 1-70 off-ramp and the frontage road. This concept preserves desirable existing
trees, and supplements them with boulder planter walls, grasses, perennials, shrubs, and additional
trees.The boulder walls are set back from the concrete apron to allow room for maintenance access and
to accommodate sight distances. The wall faces restate the form and pattern of the geologic formations
in the valley's adjacent mountainsides, thematically tying them to their context. This concept includes
river cobble or angular stone around the inlet to provide a hard yet permeable surface for maintenance.
At the southeast corner of Exit 180, a focal point viewed from the eastbound 1-70 off-ramp and Big Horn
Road, another landscape feature concept includes a raised berm, boulders, and planting area as shown
in Figure 12. By extending the existing berm along Big Horn Road, this concept creates a raised planting
Prepared by RESPEC, Inc. Page 11 of 23
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
Figure 11—Northwest Corner Exit 180 Proposed Concept
_________
FRONTAGE ROAD
. —, --.
—.�–
EXISTING TREES TO REMAIN
-
P
1.�
ori\ c
NATIVE PLANTING
�' a , , 6� •
"l : !.P
- 'Wil1�' r – BOULDER RETAINING WALL
oil
- it . -
a , do, . , ORNAMENTAL PLANTING
K
�1 ' , , • �Sx ?:1111/*
til SOD
EXISTING INLET
DECORATIVE ROCK ARMORING
------.. ........N
Prepared by RESPEC, Inc. Page 12 of 23
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
Figure 12—Southeast Corner Exit 180 Proposed Concept
/..
' + ~ ~ SOD
CONCRETE PAN
f
_ 011,OMJ
- -
TONE RETAINING W ALL
/JRNAMENTALPLATING NM
,f NATIVE PLANTING
----141.iii
. v '*'—' • lh — - AL-
ROPOSED INLET j,40., 44 f
,�.. ���ti_]_
,� i P. ::* - . ., - s• . r
-- wilisor . :
BO DER ARMORING `"''`
\ s--N\,,,, I 't 1":115 ? -) 44:c 71 4_
N..
N.--`.,._,.....,.......:://
09N
Rpt
a
"Ns''sN4'..NN'::\.,..
Prepared by RESPEC, Inc. Page 13 of 23
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
area at the focal view and screens a potential snow storage area, and stormwater and water quality
infrastructure. This feature includes boulder armoring around the proposed stormwater inlet to allow
for removal of accumulated sediment while maintaining a natural aesthetic. The same boulders are
placed along the slope above the inlet, and extend to create the informal retaining wall. As in the
northwest corner and other locations subject to heavy maintenance activity and adjacent traffic, the
landscape feature at this location is set back from the proposed concrete apron.
As depicted in Figure 9, a potential realignment of the Eagle Valley Regional trail may allow for the
creation of a constructed wetland polishing area as described in Section 3.7. This improvement would
provide an added level of water quality treatment beyond the sediment removal achieved by proposed
upstream water quality measures.
The proposed concept provides opportunities for sediment removal, infiltration, aesthetic
improvements, and functional maintenance. Future refinements of the design will define the balance
between these elements in more detail. Ecological and environmental inventories, budget
considerations, and the community's desired aesthetic character will inform the next steps in the design
process.
4.4 Plant and Materials Palette
Given the context of the Vail Valley and adjacency to the Gore Creek riparian corridor, a mostly-native
plant palette consisting of aspen, spruce, fir, and native shrubs, grasses, wetland species, and
wildflowers is recommended. Native plants emphasize a sense of place, thrive in the local climate, and
can provide a variety of colors and textures throughout the year. Within the focal areas of the Exit 180
site, there are also opportunities to introduce other ornamental or annual species for additional color
and interest if desired by the community.
Figure 13—Plant Palette Samples
�.
+a". a '4
-" , :, e _'.0',{1 ,,;:i.-1 g; ',�i F^` t s b-4
li
11'
r-'--,;,r PR` f v i i i yap „ r '�� .y� .
, • 441 #'.L i 19. „ 11-„.1f47,
1T 4"
x
1 t�r,F 11 qF.- f r Td" 4 41 t\-, " {t, 4 -' i ¢ b r
i d '. SGA" 47J,rA +� e• .. '"s 1 �ic -�` r •�I
i 1 r f1 . I I , I. ` a3 ..8— ,c._1( r�� y , i "
}F
In addition to the above plant palette, the concept includes natural stone as a design element. Boulders,
stone slabs, angular stone, and cobble may be incorporated into the design features. Large boulders can
add interest and create planting pockets along steep slopes. Dry-stacked stone retaining walls surround
select focal points and protect planting. Decorative rock may be placed between the concrete aprons
and the planter walls to provide a durable surface that complements the landscape features. As
Prepared by RESPEC, Inc. Page 14 of 23
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
mentioned previously, boulder, cobble, or angular stone armoring around inlets may be installed to
provide a surface that accommodates sediment removal maintenance and integrates into the landscape
aesthetic. Examples of these are shown in Figure 14 below.
Figure 14—Materials Palette Samples
.. t-mss. "�-ami-` ' •_. y �1 -v.
4.`
A rt
ft-
•
i ` 1.N�
� �5�.'M L '4 3
4.5 Exit 180 Water Quality Concepts
The water quality concepts that have been considered best suited for use at the Exit 180 site include
sump inlets, check dams, sediment vaults, infiltration basins, and a wetland polishing area. The options
for water quality improvements at various locations throughout the Exit 180 site, including advantages
and disadvantages, are discussed below.
4.5.1 Retrofit of the Existing Storm Sewer System
The current storm sewer network at the Exit 180 site consists of seven catch basin inlets and two main
outfalls to Gore Creek. The most basic configuration of water quality improvements includes replacing
each of the seven existing stormwater catch basin inlets with sump inlets. Sediment will accumulate at
these sump inlets. It can then be removed prior to discharging to Gore Creek. Doing this alone will
provide a significant water quality benefit in addition to preventing the existing storm sewer pipes from
becoming clogged with sediment and losing hydraulic function. The sump inlets will need to be
inspected at least quarterly during their first year of service to determine how often they should be
cleaned. A vac truck can be used to clean each new sump inlet, and they are all readily accessible.
To increase removal of sediment and other pollutants from the Exit 180 site, the downstream catch
basin on each existing storm sewer outfall could be replaced with more substantial sediment vaults.
These will provide a greater degree of performance than simple sump inlets and will serve as a more
significant barrier to sediment from the Exit 180 site reaching Gore Creek. A sediment vault is
significantly more expensive than a simple sump inlet but the level of performance is also much higher.
Much consideration has been given to the idea that an infiltration basin, or some other form of
biofiltration, could be constructed at each existing catch basin location. New catch basins would have
their inlet points raised above grade so that polluted runoff would be forced to pond and then infiltrate
into the ground resulting in water quality treatment. Various materials that could be used to line the
bottom of these infiltration basins were considered. Options included combinations of sand, gravel,
cobble, and riprap as well as a mixed media that could support a vegetated basin.
Prepared by RESPEC, Inc. Page 15 of 23
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
Due to the extremely high sediment load arriving at each existing inlet location, it was determined that
none of the options for infiltration at the existing inlet locations would ultimately be viable on a long-
term basis given the extensive maintenance that would be required. Vegetated inverts would be
destroyed every time sediment removal occurred and would then have to be replaced. Sand, gravel,
cobble, and riprap would be extremely difficult to clean and would likely need to be removed and
replaced frequently. Additionally, CDOT is unlikely to approve a design that will likely result in ponded
water adjacent to their roadways. Ultimately, infiltration basins would be a poor choice at each of the
existing catch basin inlet locations.
However, it is possible to provide an aesthetic element at each new sump inlet location that would
provide a hard surface against which to remove accumulated sediment, but also allow for a minimal
amount of infiltration. Figure 15 below shows the concept of a sump inlet and/or sediment vault being
surrounded by tightly set boulders. These would be easily cleaned with a vac truck while allowing runoff
to drain quickly to the sump inlet/vault, along the majority of sediment.
Figure 15—Stone-Lined Inlet Concept
I Irl I�
F Lay INLET/SEDIMENTVAULT
J_:.�1�i BOULDER ARMORING
1111141
1111Pa
VEGETATION
1S - '
PLAN
NTS
• VEGETATION
11 /11I r�
�F -. trial %
BOULDER ARMORING
SECTION
NTS
4.5.2 Wetland Polishing
Although infiltration is not ideally suited to a location that receives a large sediment load, once the
sediment has been removed from the runoff, infiltration is an ideal way to remove dissolved pollutants
and excess nutrients. If sump inlets and sediment vaults will replace all existing catch basin inlets, storm
runoff leaving the system will generally be free of sediment provided the sump inlets and sediment
Prepared by RESPEC, Inc. Page 16 of 23
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
vaults are properly maintained. It is proposed that a wetland polishing area be created in conjunction
with the proposed realignment of the Eagle Valley Regional trail. This area would be located outside the
Gore Creek floodplain and would provide wildlife habitat in addition to treating water quality.
Maintenance requirements would be very limited provided the upstream sump inlets and vaults are
routinely cleaned. Water would be allowed to pond in the wetland polishing area and infiltration and
treatment by wetland plants would result. This concept is an extremely low cost option that has the
potential to provide significant benefit to Gore Creek.
4.5.3 Check Dams
Check dams could be used along the existing swales throughout the Exit 180 site to slow runoff and trap
traction sand and other pollutants coming off the highway. Although check dams are not considered a
vital water quality facility at the Exit 180 site, they would provide benefit and potentially reduce the
amount of required maintenance each new sump inlet would have to receive. If used, check dams will
need to be located outside the clear zone for CDOT to approve them in their right-of-way.
4.5.4 Concrete Sweeper Bays and Pans
Several locations at the Exit 180 site could benefit from a solid shoulder. The current cinder and crushed
asphalt shoulder material is not aesthetically pleasing and has the potential to migrate to Gore Creek
during a large runoff event. It appears that vehicles often leave the paved asphalt at the Exit 180 site,
potentially encouraging mobility of the cinders and crushed asphalt. Concrete pans with varying widths
to match existing shoulder width are proposed at Exit 180. These will stabilize the shoulder and provide
a location along which a street sweeper can collect accumulated sediment. They will be sloped outward
to ensure that snowmelt does not freeze on the roadway.
Additionally, the westbound off ramp provides an excellent opportunity to locate a sweeper bay due to
the extremely wide shoulder in this area and heavy erosion that currently occurs just upstream of the
exiting inlet in that location. The edges of the sweeper bay will be kept several feet off the paved travel
way and the bay itself will be sloped away from the road.
4.6 Water Quality Treatment Train
The water quality concepts discussed in section 4.5 will be designed to function in series, as a treatment
train. The treatment provided by each facility will enhance, or be enhanced by, the facilities upstream or
downstream from it. Check dams, concrete pans, and concrete sweeper bays will provide pretreatment
by removing the coarsest sediment. Sump inlets will serve this same purpose by capturing the majority
of sediment that gest past the check dams, concrete pans, and sweeper bays. Two sediment vaults at
the downstream end of the existing storm sewer system will provide primary treatment, as they will be
able to remove the smaller, typically suspended sediment and floatables that may not be captured by
the sump inlets. Finally, secondary treatment will be provided by the wetland polishing area, which will
be successful in removing dissolved pollutants and nutrients, provided the majority of sediment is
removed at the upstream treatment facilities. Otherwise, the wetland polishing area will become
bogged with sand. Figure 16 shows each of these proposed elements on an overall site diagram of the
Exit 180 site. The option shown is the preferred option that will offer the most benefit, but simply using
sump inlets at each of the eight existing inlet locations will offer some benefit as well.
Prepared by RESPEC, Inc. Page 17 of 23
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
Figure 16-Exit 180 Water Quality Flow Diagram
•
O O rae. - - $44D- ---
c_ccv? ...:___cs=0_,„--\_ ,,,...,.,...-- ---- -_-_---,-.:,:,.-...z----...:_-_—_,....-„,.-_____-.---__ , -
t
__.)._... ...._._,j Fall Line Dr. -
V 74FrorRaaeR4ado-- 7:::_ "'D Q� O - - ----
— _ 700. o 0 a o��
'
I ' F1f` �yrv(ii ; * .f �lAh�1 •
- —I 1 5-:_, - --�
— — r — — — I CEJ -
- __
- - 4 - - -`\ I -I I- - - - - - -
� N I I I
-„Iv_ . 04.2111.-IV 11Pek W.'. AiltlIllum..,
r
Ter'- :1•64.454balfill4 I
w,
r
- -� I -
04
* €
-- _ EaExisting Storm Sewer.!e Vale . to be andoned \ * 'iII �_- -- -------- _
A — -
_ d : n:< d_
ill n
d _.RelorralTil oO / ��t07o C3 0 D ` C
'�`° ► � oaro � I
aOC�0O d ,
J__________0 41%NW ID
-'-.1111-. ..-..-.10,..- i
Big Horn Rd. "`__ -
1 .,, .7_,___. _
-Jimmiliimilmilm.,1 ii_ ii., I
; w
--* ------------------Cr\........
f �'`� 1 Gore Creek W . -+�'�' -
0 0 Existing Tree im P rBikeTrail Sr.e'- Proposed Wall (It( Check Darns 1Q Preserve Ex isting Trees
O• Existing Boulders Focal Landscape Feature Enhanced Topographydip Plants 77
0 25 50 100• Existin Inlet Enhanced Native Planting Proposed SumpInletExisting Grass(Primarily 0 Potential Future ParkingrExisting Signage
Smooth Brame) — — — — Existing Storm Sewer SOO Proposed Tree ® Proposed Sediment Vault ® Wetland Polishing Area
Proposed Concrete Pan -- -- -- Proposed Storm Sewer
Re-Aligned Trail
Exit 180 Water Quality Flow Diagram JULY 2016
I-70 E Vail Landscape and Water Quality Improvements R SPEC MUNDUS BISHOP
CO SUE?VJ C a ar•V LIS
Prepared by RESPEC, Inc. Page 18 of 23
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
5 SNOW CAST OFF AREA
The snow cast off area is the second of the three individual project sites. It is located under the bridges
at MP 181.9. This area is referred to as the snow cast off area because when snow plows pass over the
bridges at MP 181.9, a significant amount of snow, traction sand, and other pollutants gets thrown off
the edge of the bridges. This snow and debris then settles on a large area between Big Horn Road and
Upper Gore Creek that gradually slopes toward Upper Gore Creek. Recent pictures of this site are
included in Appendix C. This site was chosen for water quality treatment because it was assumed that
this heavy sediment and pollutant load would eventually migrate into Upper Gore Creek and contribute
to the impairment of Gore Creek.A detailed aerial of the snow cast off area is shown in Figure 17 below.
Figure 17—Snow Cast Off Area Aerial
1;1-'
µY • ,. '
e �'y 1 l' } 1f a
1! Yes
— - -., -:',- '...,V 1 .
: 1
=
, ,,,.: ._, ., .,,,_ .,:.. \„,...„ , :--:j _.. ''' 71:':"6'.14:'-'1:;::*:"r.'''''.:
. L 61, `P
" t 1 \ ,
The Gore Creek Water Quality Improvement Plan cites three categories of stressors as potential causes
of aquatic health impairment along Gore Creek. These include riparian buffer degradation, the impacts
of impervious cover and urban runoff, and pollutants associated with land use activities. Pollutants
associated with land use activities that could apply at the snow cast off area include sediment in the
form of traction sand used by CDOT, deicers used by CDOT, trace metals, and petroleum products. The
originally proposed plan to treat water quality at the snow cast off area included terracing the entire site
to limit sediment movement and promote infiltration and providing a perimeter ditch to convey the
reduced runoff volume to a large sediment basin.
A detailed inspection of the snow cast off area was completed during site visits by the project team and
Vail public works employees on May 17 and June 15 of 2016. Pictures from these visits can be found in
Appendix C. Contrary to what had been expected, the great majority of the snow cast off area had a
strong stand of riparian vegetative buffer in place. Additionally, a thick layer of cast off sediment
appeared to have formed over several years and appeared to be quite stable in place. In light of these
Prepared by RESPEC, Inc. Page 19 of 23
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
findings, there was strong agreement that a "no action" alternative may be a reasonable approach to
the snow cast off area, as terracing the site would require destruction of the existing strong stand of
vegetative buffer and may result in more sediment entering Upper Gore Creek than if no improvements
were completed.
A third alternative was developed as a middle ground concept that would leave in place the existing
vegetative buffer but also test the theory that the sediment layer was stable and stood little chance of
migrating to Upper Gore Creek. This third alternative does not include any large-scale grading of the site
that would destroy existing vegetation. Instead, a small surface sediment basin could be constructed
while providing a low water crossing at the intersection of an existing access road and an existing
drainage swale running through the snow cast off area. The drainage swale at the low water crossing
currently has a drainage basin that naturally encompasses a large portion of the existing snow cast off
area. The low water crossing would incorporate a restricted outlet beneath the crossing to slow low
flows and allow sediment to be captured while also allowing the basin to drain. Higher flows would
simply pass over the low water crossing. Figure 18 shows a more detailed aerial and proposed location
of the low water crossing and surface sediment basin.
Figure 18—Snowr.I.:_.1s, ,._ Cast Off Area Low Water Crossing Location`
1 ...v. . __
_ _ x.
, f
y .
.:1_ -44 `r 6 - .-"-; ' . eiiii \' 4.; ."Iiii.-
40-
" •. tae: - z .'.
1 t
A Y
Y'
•
S .-�/ •
v
I
.,
r.o M1:til
i
The existing access roadway would be improved as needed to meet CDOT requirements for
maintenance access and the low water crossing would be constructed to meet those requirements as
well. Any area disturbed by construction of the low water crossing and surface sediment basin will be
revegetated with a native seed mix once construction of the water quality facilities is complete.
Frequent inspection of the surface sediment basin will provide information as to whether there is active
sediment transport across the snow cast off area.
Prepared by RESPEC, Inc. Page 20 of 23
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
6 TRUCK RAMP SITE
The truck ramp site is the third of the three individual project sites. It is located immediately east of the
bridges at MP 181.9. This area is referred to as the truck ramp site because it is located directly below
the top of the westbound runaway truck ramp located east of the bridges at MP 181.9. Recent pictures
of this site are included in Appendix C. This site was chosen for water quality treatment because it is
located at the end of a long stretch of 1-70 that drains directly into Upper Gore Creek. The three existing
inlets and one existing surface sediment basin are the last opportunity to capture all the traction sand
and deicing chemicals CDOT places along 1-70 before it ends up in Gore Creek. These chemicals and
sediment have a strong potential to affect the water quality of Gore Creek. A more detailed aerial of the
truck ramp site is shown in Figure 19 below.The existing facilities have been noted as well.
Figure 19—Truck Ramp Site Aerial
•
+� . tea• .. .y i„� -.� ..
.'11' .7-:•.A.---
.`. ` • 1 ti --; F_ -.
`7' •,r 1 Tt Vii':• .
•
'a= ,;; - , Ex Inlet
_ .•µ '41 it ^� •• ••A.; r - y
f• _ L'4� s I
The originally proposed plan to treat water quality at the truck ramp site included infiltration basins at
each of the three existing inlets. Due to the extraordinarily high sediment load reaching each of the
three inlets, it is anticipated that any engineered infiltration media would quickly become overwhelmed
by traction sand and the smaller sediment particles found in plowed snow. Infiltration basins at this site
would quickly become permanent retention basins or require a level of maintenance that is
unreasonable. Given the heavy sediment load and minimal space available there are few options
available for water quality treatment at the truck ramp site. Sump inlets and surface sediment basin are
the two main options at this site. The choice between the two will depend on the maintenance
equipment available or preferred for use. If sediment sumps are used, a vac truck is required. If surface
sediment basins are used, a vac truck may also be used, but a skid steer or other small front end loaded
may also be used.
Prepared by RESPEC, Inc. Page 21 of 23
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
Ancillary treatment at the site includes the potential to grade the outside of the eastbound lanes to
drain back to the inlet located in the eastbound shoulder. This would reduce the amount of runoff
running down the south bank of Upper Gore Creek, thereby reducing the amount of bank erosion and
sediment migrating into Upper Gore Creek. All disturbed areas at the truck ramp site will be revegetated
with a native seed mix once construction of the water quality facilities is complete.
Improvements in the 1-70 median and shoulder of the eastbound lanes of 1-70 may require additional
guardrail to be installed because of clear zone criteria. Access for maintenance activities will be designed
in consultation with CDOT maintenance staff.
7 CONCEPTUAL COSTS
The total project budget for water quality improvements at the three individual sites is$1,140,000.00, of
which $700,000 is federal funds and $440,000 is from the Town. The total project budget for landscape
improvements at the Exit 180 site is $1,090,000.00, all of which comes from the Town. These figures
include design survey, professional engineering and professional landscape architecture services,
environmental investigations and clearances, geotechnical investigations, and project coordination.
The purpose of a conceptual cost estimate early in the project is two-fold.The first purpose is to provide
a comparative analysis between the various concepts and alternatives presented. It is helpful to know
which options will generally be more expensive and which will be generally less expensive to construct.
The cost to maintain the various types of water quality facilities and landscape elements over time is
also significant, but has not been evaluated specifically for this report. The cost to make changes to
snow removal and storage operations has also not been specifically evaluated other than noting that
changes to these activities will be associated with an increase in cost to the Town of Vail, perhaps even
requiring additional capital investment in snow removal equipment and staff. Town personnel are the
best resource for determining the cost the Town will incur to maintain water quality facilities and
landscaped areas.
There are certain costs associated with every project that are traditionally bid as lump sum costs. These
may include mobilization, construction surveying, traffic control, temporary erosion and sediment
control, and water control and dewatering, among others. They are often estimated as a percentage of
the more quantifiable bid items. For the purposes of this report, these bid items have been assigned a
value of approximately 25% of the total cost. This value will be refined in future design phases as the
nature of the improvements is also refined. A contingency of approximately 15% has also been added to
the estimate.
Current conceptual estimates for water quality improvements at all three sites and landscaping at the
Exit 180 site are included in Table 1 below. Recommended improvements were intended to match the
funding available for all three sites, but there are options for minimizing costs. With respect to water
quality improvements, Option 3 included in Table 1 will provide the most benefit for the funding
available for the project with consideration being given to maintenance, CDOT roadside design criteria,
and aesthetics at the Exit 180 site.
Prepared by RESPEC, Inc. Page 22 of 23
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
With regard to landscape improvements, the proposed landscape concept that is presented and the
associated conceptual cost estimate reflect a comprehensive approach to improving the aesthetics and
ecology of the Exit 180 site. As the concept is refined during preliminary design, the Town of Vail may
choose to shift or reduce the allocation of costs from one or more landscape elements to others, or to
reduce overall landscape costs if necessary. As the designs of both the water quality and landscape
improvements progress and are refined, changes in anticipated cost will need to be considered.
Table 1—Conceptual Costs
Location/Improvement Items Included Conceptual
Estimate
Exit 180
Landscaping Full proposed concept $961,000
Water Quality Option 1 8 sump inlets $234,000
Water Quality Option 2 6 sump inlets, 2 sediment vaults, concrete pans $643,000
Water Quality Option 3 6 sump inlets, 2 sediment vaults, concrete pans, $819,000
wetland polishing area
Snow Cast Off Area
Option 1 No improvements $0
Option 2 Small sediment basin and low water crossing $51,000
Truck Ramp Site
Option 1 3 sump inlets and site grading $81,000
Option 2 3 surface sediment basins and site grading $70,000
For the purposes of cost estimating, the grading and infrastructure required for the wetland polishing
area is included with the costs of the water quality improvements, while seed and other plantings are
included with the landscaping costs. Similarly, while concrete pans along the asphalt roadway will
provide aesthetic enhancement, they are primarily intended to facilitate sediment collection and are
therefore included in the cost of the water quality improvements. Finally, while check dams will serve a
minor water quality function, they are primarily aesthetic landforms and their cost is included with the
landscape costs.
8 REFERENCES
Leonard Rice Engineers, Inc., 2013. Gore Creek Water Quality Improvement Plan, prepared by Leonard
Rice Engineers, Inc., Denver, CO.
Alpine Engineering, Inc.,2015. Gore Creek Action Plan Storm water Control Projects, prepared by Alpine
Engineering, Inc., Edwards, CO
Prepared by RESPEC, Inc. Page 23 of 23
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
Prepared by RESEPC, Inc.
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
Appendix A
Appendix A of the Gore Creek Water Quality Improvement Plan
Prepared by RESEPC, Inc.
` r 1{ sF# ..01, 411111.4' a .14. .
I
.`‘• ",./. .4. ' •.. . . '• 4 )4pr .c , . ..1110.:p :', A
... ii'2-4'.,4... 4:'.4,111;.1.."r .4.74':..'..ili(nr4,4 . ..
11,
i 1 !+ 1 ;1 1 k r 1,t,-y * .11 A.
rr rk{'i
•
, pp . ... , •• ,-; J... -a . . . . 4- i . ..
1414 +P.44:0 i . .... • e',IF":110111„ 1 -
*''N .N.'
..o.,•.••• _ . .: . . 1,4; • . ,,,..• : .• 4. "Al.:AO. ' all?.A -„r
ni4 '
. . if. . d
1, .1 Nei 4 if.
Y .4 k r • 1 r . '. ..+ 4 .
7 a I I `' *+i'1 • F1 • 7- MIFF' Y N r.I•J. •' ,+I~� + • . ' F,rt ~'
iii
3 t•• ', L}r+"t.57 .`'J ' • 5 5_ 77.1 f.• I' 4, IV L.` • I ���' '•i. , i 1 • J t
•
Cr ��F•$t 1 ih 1. f *......
j •4El .I y
PIA
5 i
. .'.4 r,:r',A;;.ipet . 4. 4 4. .1.-. ' -, . ..elf.!-''''r Ai'.- . ' ..
• :1',' ' ON ' t .
Jr+��j, a�IP' F F 1•'
1 r15..11 I. ll'. Ili:ivilk 1 -1111 'ft •r/..,0
M 7 f (ar 1 - A. . •
; ^ r � +mayX ' F e
+ t t 5 a 1 r ^#ti �7 w ,
Ir lytic k t • •. { , •.4 #. . ti4( _` • } •
' 'i ' _rr_ ,fr 1 T •*�'__ '!mss • . , • .4
_ al:'ll.'
i
..
Illti' . 3-"111111111. .'a • :air
- ...: _ •
7.47.11: I ' .'IL7. 416
fbei, 1
�IIr r
P IX A: 'IST OF BMP AND LID PROJECTS FOR
. f i
f"
.- _ ,� ,.y STORMWATER AND DRAIN ,
I -
• ; IMPROVEMENTS
+ • ." ' "4+ r• . `.+ r1
Or s 44141111111411*
•
.
- -_ • • J 1 • - ‘..[::r
.,X141 I -414116- '•A
•
ill
•
f l .
{ • • .t „r€ y ; a
• „• 4•- + :-411r f '-' 1111"P'.
. -,fr y - " . } r t
•
Appendix A
List of BMP and LID Projects for Stormwater and Drainage
Improvements
The projects listed and discussed in Appendix A are conceptual in nature. Each project will
require additional work prior to construction for design, permitting, and bidding, possibly
including some or all of the following: geotechnical studies, percolation testing, drainage
studies, and field topographical map displaying existing utility locations, current land ownership
and easements. Individual projects will need to be evaluated for required permits such as: Town
of Vail public way and grading permits, CDOT special use permit, CDPHE stormwater permit, or
US Army Corps of Engineer's 404 wetlands permits.The projects have been listed and numbered
from East Vail, upstream to West Vail, downstream.
1. EAST VAIL REACH PRIORITY
BMP Recommendation Point I-70 Bighorn Road Overpass and Truck
Ramp I-70
Location 39°37'34.97"N
106°16'40.55"W
and
39°37'31.09"N
106°16'41.27"W
Gore Creek Station 619+00
Potential Pollutant and Source I-70 metals and Hydrocarbons, Chlorides,
Sediments, Snowmelt Concentrated
Recommended BMP Retention Basins, Terraced Grading
Estimated Design Fee $42,500-$52,500 Truck Ramp
$40,000-$50,000 Over Pass
Estimated Construction Costs $180,000-$220,000Truck Ramp
$210,000-$550,000 Over Pass
Category CDOT
Notes Snow collection and overthrow store
contaminants for large spring loading
4 Detention basin at existing culvert inlet
70' above stream bed-good for infiltration
at truck ramp basin level
1. East Vail Big Horn Road Overpass and 1-70 Runaway Truck Ramp Retention Basins
The major degraders of Gore Creek seem to manifest themselves even before the confluence of Gore
Creek and Black Gore Creek. Evidence for this being the first aquatic life testing station that is upstream of
East Vail housing after the confluence already shows impairment while stations in the wilderness of
Deluge and Black Gore Creeks indicate healthy streams. One potential non-point source could be the 1-70
Alpine Engineering Inc. 9/25/12 A-1
drainage area around the runaway truck ramp. A preemptive BMP installed in this region above
impaired water may have much more of an effect than any of the more reactive BMPs
suggested within the Gore Creek Reach. Sediment control of this 1-70 corridor has been greatly
improved in recent years yet actual retention of runoff can be even more environmentally
conscience than solely separating traction sand and water. Retention of runoff under the
runaway ramp forces stormwater to percolate through the ground to return as a base flow.
Infiltration leaves the majority of contaminants at ground level improving water quality of Gore
Creek below. The shoulders and medians of 1-70 below the truck ramp channel water towards
the bridge over Bighorn Road below. Inlets direct water to the south side of bridge before it
daylights over steep terrain into the confluence below. Small berms can be graded behind w-
beam guardrails on shoulders and medians to create catch basins for the settlement of road
sediments and contaminants. Although these basins will collect runoff and store the water
above ground, it is important to note these basins do not have to affect roadside safety for
passing travelers. The need not be more that 12" deep because the water will filter through
bioretention soil mix, engineered to infiltrate the ground. Standing water will only remain after
large storm events and their holding time is dependent on evaporation rates and infiltration
rates of the retention pond base media. For this reason as well, plant selection is important and
vegetation must be able to with stand flood and drought conditions. The heavier the vegetation
is, the higher the uptake of nutrient and filtration of contaminants. Large runoff events will be
allowed to pass through an overflow weir and into the existing sub-highway pipe system to Gore
creek below. Layout of this regional BMP site can be seen in image 1 below.
Alpine Engineering Inc. 9/25/12 A-2
,.. ��` #: Vi _a �;.
kFi'+-tp i } 0-4';', :his
f. Ex' - - .ei Drain
.d A. ,
a
+ ' '
T.
a.
J. (2) n
V ..
i
-4',--
k
A
, • ilk-. A-.-•--,o it- k• I
I_ f 1 • Itif';:. 7-- ., 2 . , t'.' „.,,,,4r. .. . . ., - , _,. ,..-,,,_
- l'. . .- 41' - II. . . •'—.....-• ,......:.?;,. -.:19.r. . AO 4 At
w. �.,r. - l ` a .k yl P`
diii
Y :0._ft
Ur f` "'`" ".-- :r -
- - ,: .14.° , C1 o(21e earth
Imagery Da[e.9f23.r!e9�F1 .,a 39'37'27.76"N 10616'41.98"W elev 8669 fl 4 •_ • Eye a,II 9631 fl
Image 1. Proposed Retention Basin Below 1-70 Truck Ramp
Just down stream of the Deluge Creek and Gore Creek confluence, a series of ponds have
formed. Another 50 meters below those is a large grassy area that receives a large amount of
snow plow overthrow from 1-70 and Bighorn road (See Image 2). Over the course of the long
winter, snow in this region can collect a large amount of contaminants from traction sand and
road salts to other vehicle hydrocarbons. Atmospheric debris also settles on top of snowpack
and is then released in higher concentrations during the spring melt. The debris can be a
significant addition of total suspended solids. An unsettled gravel road under the west bound
bridge produces more runoff and sediment. Located just above the first 303(d) impaired reach,
snowmelt and runoff in this region may be the first major nonpoint source contaminant loading
region. Proper containment and treatment of this area is advised. The vegetation pressure in
this area is high due to the constant relocation and collection of the snow. There are only a
handful of trees and shrubs in the area, a meager buffer between snowmelt contaminants and
Gore Creek. Utilization of terraces and capture trenches in the area would create lag time for
the surface runoff especially during the spring. Capture of the water in detention basins after
diversion channels would provide the important settling of nutrients and sediments as well as
infiltration.
Alpine Engineering Inc. 9/25/12 A-3
.It it\
r
\ lI •F � 11,141%
ti0f'
Snow Collection A - `•
To be terraced wit , •.
'} , ; diversion trench an® '
�' 'Z. basin • Pr .:,_qt,„
- r~-fi•r +r;
�• • if . :
. ,
. . . , . __ ...._ . „..
,, ,,, „ .. , ,,,,i, _ ..„
,. ....,.. . ......,-, .. ._ ,,,,,_, ,, , „.. . ...„.. .
. , ...,,_ _ , ,.. : . . i . 1440:30.
r (a .+�r � •' ..0 a i. k•1 y r , r - t
.Fri :.l. •, ,._ L h r1 . .' !_ . 1/ 4• ;� F �
c. t
y
M .d'-'41#4:1 4^,s c ,. ,w • t . 5.
« .'l +SOA
P ,,-' "4,,Goog 7,arth
Im ay el Date:412 312 0 11. 19'37'35'7.1'R}.1-06 16-2,2,,r4 W elev-8651 ft _ • Eye alt 9790 f1
Image 2.Snow Overthrow Location and Proposed Trench and Basin Treatment
2.EAST VAIL REACH
BMP Recommendation Point I-70 Median _
Location North of Vail Racquet Club Townhouse
Drive
39°37'50.39"N
106°17'9.68"W
Gore Creek Station 586+00
Potential Pollutant and Source Sediment from Traction Sand, Chloride de-
icer, Hydrocarbons from Vehicles
Recommended BMP Detention Pond
Category CDOT
Alpine Engineering Inc. 9/25/12 A-4
3. EAST VAIL REACH
BMP Recommendation Point Big Horn Road and I-70 Median
Location 24" CMP effluent just north of Big Horn
Rd. East of Streamside Circle E.
39°37'59.53"N
106°17'26.67"W
Gore Creek Station 570+00 River Right,
Potential Pollutant and Source I-70 metals and Hydrocarbons, Chlorides
Recommended BMP Detention Pond, Infiltration System
Category TOV or CDOT property??
4. EAST VAIL REACH
_BMP Recommendation Point Big Horn Road
Location North side across from Streamside Cr. Bus
Stop at Big Horn Creek
39°38'11.76"N
106°17'48.86"W
Gore Creek Station 547+00
Potential Pollutant and Source Big Horn Rd. metals and Hydrocarbons,
Chlorides, Runoff of all housing
developments on North side of Big Horn
from Streamside Cr. To the East
Recommended BMP Bio Retention
Category TOV Right of Way/Easement
5. EAST VAIL REACH
BMP Recommendation Point Columbine Lake
39°38'17.34"N
106°18'3.43"W
Location Gore Creek Station 528+00
Big Horn Rd. Hydrocarbons, Sediments
Potential Pollutant and Source Residential Phosphates,Nitrates
Bio retention System as a treatment train
Recommended BMP with Columbine Lake
Category TOV Property
Alpine Engineering Inc. 9/25/12 A-5
6. EAST VAIL REACH
BMP Recommendation Point Big Horn Rd and Pitkin Creek Intersection
39°38'31.43"N
106°18'18.42"W
Location Gore Creek Station 510+00
Big Horn Rd. Hydrocarbons, Sediments
Potential Pollutant and Source Residential Phosphates,Nitrates
Recommended BMP Bio Retention System
Category TOV Right of Way/Easement
Notes 12ft above Gore Creek Bed
Alpine Engineering Inc. 9/25/12 A-6
7. EAST VAIL REACH PRIORITY
BMP Recommendation Point Big Horn Rd, I-70 Exit 180
39°38'37.68"N
106°18'30.04"W
Location Gore Creek Station 498+00
Big Horn Rd. and I-70 Hydrocarbons,
Potential Pollutant and Source Sediments
Recommended BMP Retention Ponds
Estimated Design Fee $42,500-$52,500
Estimated Construction Costs $230,000-$280,000
Category TOV Right of Way/Easement, CDOT
6 or more ponds can be constructed in area
to handle excess cinders and contaminant
Notes loading
7. 1-70 East Vail Exit 180 Retention Ponds
The 1-70 East Vail Exit 180 area is comprised of a large area of impermeable surface.The contaminants on
the exit ramps and frontage roads include petroleum hydrocarbons and heavy metals associated with
vehicle operation, all of which are transported by the water of a runoff event. Engine oils, antifreeze,
brake dust, fuel, and rubber are left behind on roadways, especially in areas of rapid acceleration and
deceleration. Road salts, traction sand and trash are also deposited on these roadways introducing even
more stream stressors. Precipitation that falls on to these surfaces collects and concentrates
contaminants which are then channeled through the stormwater inlets and piping directly into Gore
Creek. Contaminant detention and treatment is critical to improving water quality. A preliminary
evaluation of the area shows that precipitation falling within the blue region, highlighted in Image 3, will
collect in the areas highlighted in red. These depressions are filled in by intermittent grasses which help
with a nutrient and contaminant filtration, however the area can be better utilized for stormwater quality.
Alpine Engineering Inc. 9/25/12 A-7
r I" \ti .k..
r # _
+y. y r, 'lam, '•i(
•bisection,. '
it% ,.‘, ,_ .. ..?•:. .- , .1.r
- k'. "r -
�
�;SS
•
Imagery Data'9/23/2011 39'38'38.84"N 106..18'25.88":W el2"v 8393gft? li'L - E'11 c.]I; 10362 f[
Image 3. East Vail Stormwater Catch Basin and Proposed Retention Basins
The University Of New Hampshire has proven retention systems such which can effectively treat
suspended solids (97% removal efficiency), while meeting petroleum hydrocarbon quality standards for
the state.They can also remove 99%of zinc.While removal of road salt chlorides from water is minimal in
all natural systems besides total evaporation of water.Vegetated Infiltration systems do reduce the spike
in chloride levels by slowing the stormwater input through detention.
The existing stormwater inlets capture water from the blue highlighted area and channel it parallel to the
underpass road to Gore Creek. The depression areas surrounding these stormwater inlets have excellent
potential as bioretention basins. These basins would provide an area for sediment capture, pollutant
treatment, and infiltration of stormwater into the groundwater. The area already provides substantial
snow storage which could be modified to retain the portions of runoff. Proximity to level roadways allows
convenient access for construction and maintenance equipment. Images 4-9 illustrate existing conditions
for proposed location.
Alpine Engineering Inc. 9/25/12 A-8
•
NI c
.411100,
.wit. M1
Image 4.Current Inlet south of EBI-70 Off Ramp(Imagery Date 8-29-12)
"111111111111Pir
_ter
3'.
N rl F.fr• f 7•} Irk-
•
111
Image 5.Current Inlet south of WB 1-70 On Ramp(Imagery Date 8-29-12)
Alpine Engineering Inc. 9/25/12 A-9
unt WAY
•
I• m rix
f
' X4s "i�aa fif � `4 ti } ys
•
.7 mil •
Image 6. Current Inlet North of WB 1-70 Off Ramp(Imagery Date 8-29-12)
,. d7+• _ f 'A4� - ..,.ems - _!—•
Ar-
-
•
•
Image 7. Current Inlet and Grading of EB 1-70 Off Ramp(Imagery Date 8-29-12)
Alpine Engineering Inc. 9/25/12 A-10
Appendix A References
Aspen Urban Runoff Management Plan:
http://www.aspenpitkin.com/Departments/Engineering/Stormwater/Development-
Construction/
Denver Urban Drainage and Flood Control District Drainage Criteria Manual
http://www.udfcd.org/downloads/down critmanual.htm
Information from University of New Hampshire Stormwater Center including the 2007 and 2009
Biannual Reports: http://www.unh.edu/unhsc/
Seattle's Stormwater Manuel Vol. 3 Stormwater Flow Control and Water Quality Treatment
Technical Requirements
http://www.seattle.gov/dpd/codes/dr/DR2009-17.pdf
Alpine Engineering Inc. 9/25/12 A-24
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
Appendix B
Gore Creek Action Plan Stormwater Control Projects
Prepared by RESEPC, Inc.
IIIIIIIIIIIIII:IIIIIIIIIII: ig''eli.. � , PRIORITY: �daI • r '%t \ .t: y. � .' oN LEVEL 4,fror Q IIIIIIIIt
� i J
8
.., - , „ _
, , .
wrika,
. .
. : .
, . . .
,. Nizp4. , , .
. : . .j.;.A. „.. .., 41tit
. .
• r • w
c ` " moo t: ,
,. i.•,. W474ti'l, 7. �+*� fir' . i •} 'p •• ;1 -' y • is,-..
vi A
* ; _,....d, 1 . „
.i.,..._ ,
• ,-. .
. -. .--`41i c . . i .i, i 1,4tr. --
El
_.. t iii% . - Nei,, • 7 v. S. _ 4"j_\ #aw' , -, .;,/;.*Ik4 ' • Ai- -* % - Z
it ' tik GOk. , j yJ
.- , '.l . .-'-I ft • r, .i.ja,,,,, ,..
„Ait . •
:' 1) 01-.),,,z, - ..t. . .•..„, 0
, , , --,.,- \
.Ti
NI- ,.. r .
� `` •- --T1 • A ,' .401 e' it:Xt-- '. . - :r, i . , _ -=-
..t3 • � Q LLQ Z
.1.::
v
y
Alb __I . # 7 --4 . -r. 4„7''''...-,,,t-i'
•
•
-N
-
-pa
1y _
. ► - -
CCL W
GlO 1.
•
aiOA i ✓- e •
a 6164-.' '. _ hf}
ff ' Jg-`
bin_
6, 3 �; '
o, • a ,
_
CC 1—
in ilk 8 °
. 1
I .. ,
' g
SAND FILTER°° �
_ : . =—MP _ CB f SITE 1A
--- FOREBAYS e m
o - - - I _ . r
.....,.. ,
<,
r ....
. ,
• •
O -
_, , -
d .i - `�
Z kir
cLna)o •
4 Q
s ;
Q- o
✓ ' . I i ".:?-
1-
JG
L i
Q-
:Il
• J� n
< y 1Y ` Q a) 3 ' ' ' 4, * l'' . ''''l 1 o
- - _ • \ Q i Y Y O
E r 3 �, 7i, GRAPHIC SCALE Z y
wo
Z
0 s0 too 200 w E = o a
I
_;. f e - .- o o v o
r
3t'+if _ a'' rr _ 11 ( IN FEET ) SHEET
1 inch = 100 ft. 1 A
\ '\ `\\ �,;�,_= = ______=--11—___---__„_:-.27////_ /-/ \/ � , ) � _ �� �\ ---_- WIIIIIIIIIIIIIIIIIIIIIIIIIIZ �
\ \ \ \ \ \ \ ▪ \\ __// /' \ I \ / 1 \ \ \ s / \ d x
• \, \, \ \ \ - II / \ / 1 \ \ `� PRIORITY. 1 Z 4,
` � 11 i \ \ \\ \, \\ \ \ \\ \ \-__- \\\-1' \` , \� -• LEVEL V' iNE =:*/:
....
`\1 ..,/
/� / �� \ , 86� I / - / , 7I :\ \ \\ \ \ \ — -- / \I �, / 1� / /,/. I I. \ IIIII\ 1 I 1\ \ \\ \\ \ \ \ \ ----- 1 \ // // , �\ I -_ / ? 8730 I/ / IIIIIIII\I 1 lam / 1' \_ I \ \ \ \\ \ \ - \ / / // �\ 1\ /^_' '') I /// 1 I I I I\ \ \ 1 I \ \ 1 / IIIIZ oWa
1 1 \ \ \ \ `\\ `\ `� �`�, - \ / / / \ \__ i '' l l`/ I •\ ) 1 \\\\ \ 1 I \ I I X l W W .
I 1 1 \ \ \ \ \ _ ---___ - `• � ---\ 1 / /' ` \\ �\ •7 ,�'�1 I dI •'' 1 1 • 1 I 1 \\\ 1 / I / /� //
I \\ 11 \\ \\ \ \\\\ \\�` ---` \ - �- \ �� -_\•\ - _-�/ \I \\ ti. ' !' I I • \ j I j 111 1 / I // // /'/ /
I \\ \ I \\ I \'--------•
-\\ -----' �\ \ ,\ 1Ni \
- -/' I I ^_/.'/ i / ! f.' 1 / I / ) \ 1 I I / I`
\ \
%/II
— 1 1 \\ \\ \ �_�-- ` \_ 11 / •\`��/^ �/ �i." -- / ,ire // ----L—__ // // ///, -- -, \ I�1
1 \ •N \- _ \ - ---' / // / l/ // / / // //�_'- // /.. // --- — " //1// \/V
\\ __ _ l\` \ -moi 1' - --- // �' / , / l• . / i / ////�'�-'/-----/ I / I / /i\•\- i// l \'/
\ -�� \�-�-- N \\ \ \ \ _-' \ ` �/ /• 'i% / / / / I l /// /' / i , 1 I I \ �- / �N I /. -
\ \ 1 \ - --. \ \ ,-8-62-0-
-' // // I 1 I.'/ / / 1 I I I 1 I I / / / / l / I /i ///--- I/' // // Q
`\ ` - _ _;-\\-- - / / c_ i I I / I / I 1 1 I 1 1 l 1 \ I , / / i' \ / 1i
I _ _---' '� ` „. \ _ 1 \SI! t ///7'4t17/2
I \ I 1 1 / / / / \ `i/ �/ /
\ / rONQ
.-='' ' ^ .% \\ \ I \\ 4 \\\_ / // li-
_ell - ' 1\ , \• ..-.--•, ,
• - / ,/ / // - // / GP // //// // // // // - \\ /// / ' U 0
1 -� \ // \\ / -82t 'z y / // // /� ' //� 1111 // /// /,/�1\ �/ \\ r/ // -/ // M WZ
---•--.//`-;6. 1 --Ir
�- � --.,;"'e
,// J /�...I. ./-•..
-7 \I \ / / N m = � , 1111 /�' /� /// /,i///// /i/� / /r i(J I \Ivy// / / /�/�' / W O
/ / / -7\ /i-� / / -i /�
/ 1 \ / �'\� / �' /// J 8689.9 ��� / / // \ \ / V
i \ \ ado / _ i / / / / , \ /i/ / i /
•/ I 1 I \ \ '_6 y �E�/ / / p --- ' - - - / / / / 1/ \ ' T I / /i /� 1 // / ��-___
I l \I /I �, - 'CP // ��/�/// /// / 8688.8 / I \// /' t----
/
- // // // / �i�/ ,i/11 1 (`\-/ \\ /l / / l ///�---;58-Z-3-7--...-2-�%/ CC
Q \ _ l /,'./ , , / ` / /I l / - / / ,/ / /, // 87 / I I l \ - I/ / / / , \ 111 O
��_:. , -_- /- / / / 1 / 1\ SII I / / /, /, / / _ ( �� 1 - l / 1 f / / /l X / W
�� \ _ ' ) '/ • �// ////i/ /// / 11/' ) I j Io 1, 1'`. -/ // /, /, / X y- ,� �\ ♦\ /� CO \ / / / 1 I I l 1 \iJX/
\ +a. - - i / / / / / / / I I I I �' / // // / / / \ I / / / I \ \ \ \ M
O I �� �y/ 1111/ / / / 1 \111\ / III / III \ / ��� /� // ,, / f/\\ /// ---� \ •\ Jl/ _\ e/I l 1 \\\-_--1� (�/ IL M�
- /' • - / / / / / -_ V \\/ II l `I I \I I /' / / // //, �/ _ J / /// 0 1 / 1 \ I 8P1 VJ
o I \-� / /, /' /� ,'- 863- °-- /-/♦ / \�/�� \ / I I I / /1 / I I ) / / / ice_-� / �\ _/ i / o / I 1 N \` \\
/
/
r.i j�l / / /,�. -4/'.---/---.....--
/ , --- / / ///// \`/ \ / / I I 1 I I / I I 1 / / // / / _ / /'-_-- J 1 cj-\ /I \ I \ 1\ •1 \\\,
-,Ln
et i // /iii / % / /' __-----_- r . / \ / \ L/ I SAKI) FFLTEJ�' /( /- /' -\ -- / /' --- / \ 1 \ I 1 1 1 ,`
Lo i�i� m/ \1.•.7 1 I I ' / //� i - rP`8691.3 ca" 1 / 11 I 1 /SITE/1/I► 'h4/ /'� j/ \1 /'�_ / /' __ /'" -� \ j J/� I
I ,!..--
..././.2P;'":-..--'.'-.--.
/ l / 1 ( I j j /�-- / -_�`-_-� - /' ` / / / /� . 1 ,/% /I T7 // /11 I / \ ,/J / -// / / /'/I 1\I \
Lni __--/ 1 / I I 1 1 11 1 / / �- \ 1 r� l / 1 •, / / // / -- \-,-- / / _-__ / _ JI 1 I I / / 1 1/--\ // / / //, /-i.l l \\1\ \ 1 I m
.Q / - I I I 1 \ 1 I / / \ \ I / _- // , / /� 8751.1 / \ \ 1 1 \ I r I / / 1 I I
X / /.• \ / / 1 I 1 \ I / I I 1 Iallb '01 / /,--\ \ // /// / ) I 1 I\ 1 1 / _ / / \ // /
% / I 1 1 \ 1 , I I I / / / // \ \ \ `555r 33� -•)' I I \\ J I ` r I •
' ,/,,./....,.///
\ \ I ) I l 1 \ 1 X I / / I / ! top / / 1-II \\ \ -�/ / =/i/
/ / / •' / / \ 809 d I 1 J I/ I I \ / /' I X 1 v I I - /
/ / I � ' \ I / / / / I \ 1 \ \ I\ I / I 1 / / l I III ) \\ �/ ,,/�87p. 1 / \\ 1 I I \ 1I ' / / /------- 7/
--� i
/ / / \\ / 1 /// // / / / // I / 1 \ \\ \\ II I / / I / I / / / IIt`a�6o \\\�/// / / I /i /� / /�^ I 789p8 \\/ 1 1 I I / 1/ - I
l.'1 / , /I / ( I ( ! / I 1 \\\ , I I I / I / l / // , / / / / ,�// / /I I I I I / //
o F 1 / / \ 1 \ \ I 1 1 / / -,\ \ ) / l , - // �/ /� X / / / 1 I \1 Iii///' //
ly I 1\\ \ \ \ \ \ I ,/ / `\\_l p 1 / / �' / / 1 I / I / //, \ /// / / / / / 1 _ \ I• I / / /
of / / \ \ \\ \ \ \ I I / / \ \ /1 I / I / / I I I -\ \ '' / // 1� / / , / / / I/ \ I ) I I 1/711 // /
I / \ \ \ \ \ I I / / 7 \ / / / 1 I ' ///- / / / / /' 11 I I l,Il ,/ N
/ / / / \ \\ \\ \ \ \ \ \ I/ // / ._./1 IJ / I I ( I I I / 11 \��/i /� / // 87Fj6 /i // 1 / - \ `J /'
� 1 I 1 1 / l- / // z
a / / / / \ \ \ \ \ \ \ \ \ 1 1 \ I r /// X / e / // I 1 I 1 1 1 / \ / , // / // 7./,- / / / `\\\ \/1 1 I l / vc�
/7/
/ I \ \ \\ \ \ 1 1 11 r - / / I 'I \ I l --'//7'/7/7/ / % ///i / 1 / % / \ 11 I • I I/i s
\ \ I 8698.61 I / I / / / , /
/ I / / I 1 \ 1\ \ �6 \ 1 1 I 11/ 1 / / 1 1 0 1 \ 1 // / / // / // // / / / \\ y / I 1 \
m / 1 \ \ I \ \ I \�/ / / \ I I I \ / / / I 6/ - I I \1 / Ix
/ / / / 1 1 1 1 \\ \ \ 1 \ \ \ \\ —7 / / \ / / 1 / I 1 \ I1 \`�,/ ,moi / x//66.1 1 // /7/ // / /I / \1 // / I I 1 1 `. 11 /
N // / // / / I 1 1 I • \ \ \ \ \ \ \ \\-_-0' / / I / / l I \ \ 1 / /// / X // , ,/` �J / / / / ,/j / Po /,1 \\\J I /// 1 \" I t
1/ \ \ \ - \/ /' I / `I I O I I 1 / / / '//,7/' R / i// , / i, I // / / 11 \ \\ •\ \\
/ 1171 / // I I I 1 \ \ \ \ \ \dai, \ \\ - X / / I I , , / , / / �� // °��-/� II \\ // I \ o
/ / / /'bEN$E TREES / / / I ` \ \ \ \ al \ d \8696.5 / / / I l I I/ / /,i // / / - / I I I \- \\\
l / 1/ // / l l \ \ \ \ \ ��o\ 1 / // -! 1 I 1 I j 1111// \ %,%,/�� ,' / / /'�� `�/ I / II / / / /i I i \1 \\�\` \\\\\\
I \ 1 \ \ \ \ \ / Io 1 I / /, //i / ��� / ,/ // --_ I 1 ,-- ./////` i / I 1 \\\ \\\
E) / / / / c / / I •i I 1 1 \ \ \ \ \ 1\/ // \` / / / 1 I 1 / / /// // // -t /� __ __ XI / / 1 I 1 \\\ d
/ /� / I \ / / / \ 1 1
o / 1 / / , / / I I 1 \ \ \ \ \ I / / I / I I / / / //�, /;Py>P j / / / �� i 1 I \/ l l / / / I / I 1 I/
L7 7,/ 7 , /-- �- _____„.7. / 1 II I 1 1 \ \ \ \ I // I l 1 1 / / / // / // // // / / --- --7 I / / /
// / _� / , / II 1 \ I \ \ I / / �/ / / I I I I 1 / // L \ � / / // -- -/'11• I 1879•-- I � 1 / // 7 / / //� '6
Q , /// // ,/�/-- 7111 ,/ / I 1 1 1 \ \ 1/ // I / / / I I / I 1 // / 877 .0� I / / / o--- \ 7/ 1 1 / /// / / / // / /1 o e
/ _i - \ I // / // / o \ / /I I / / •
.... / / / . - ----------- r / I/, 1 I / . .. 1 / / .,' •_../ / / / ,o.. / / i u7 /7 7'/ / / /7 c ,
—' / / / i/ moi. ----/ / /1/ /
I I l / , //'. ,/ 1 / l I }c 1 /i //r71/1 / / // /-\ 1 1\ // / / / / / / �/� /� 1 /{// i 1 0 = r v o
_ _ / - i --_ //// •/ I I // / l / I/ l I 1 I 1 I /// \ , /1 \ \ \_/ //,--/ I l II / PI1JlL /s��iJ 1 E z z
p -__-- / 7/ / /' � ,// -// '/, I 1 I \ / / /� // I // 1/ / / / I \ \ \ / / // Z% / / //1 \` \ /7// '-'\ �' 1 J /J/l w rc x o a
/ / / / / \ / J I I / W
/ \ - I / 50 \ 190, 200 a c''''
I-"
al • ------r_ / /' 7 1111/ /' ///7 /1 I \ I / 1 /1 / 1 / l l I \ \ 1 / / // / ////,,II 9--_- _�_J; 1 , , I li / 1 0 0 0 0
\`,. -/ ///,/' l /II l/ / I I 1 1 / / �' / / I \ \\\ \/% j I // / I // �J7/'N) I ��
- \\ \ -- /, , /,----\ I 1 I I / I 1 / / / i' / I o I \ �, \ /�-I / 1 1 / I \ _-_--_ \ I / / r/ / I r /
o `\ `� - / ,' \ -/ / I I ) / I i
/ 1 1 1 / / I
I I 1IV /y -/1/ 1 I 11 0,_�'---` 1 I // / 11 X \ I I / / / , / /
_ \\ `\`- / / __ / 1 II \ ` j 1 / / / / I`/ / / / I I i \L /�/ / 1 I \_�- \ / / / / / � � I / / // // 5/IN FEET ),/ SHEET
> \\ \ \\, - // 1 ,----- /, //l1 \ \ , / /
/ l l / l l I I /I� // / I \�-//� / / / / / I ::05.5 / ,
_ I , / / \ 1 / / / / I `y �•1/ I / / / / // / 1/inch =....1.90' ft 1B
a \\,\• \\ \\\ ` J// �/' -i�/- _/......./„..7"
/ice/ I 111 j / / / / l ,i'' 1 '' 1\//l / o/7,ii i d \ / �/'JIf \ 0 1\\ - l J� / /�� / I/ --� ,l /, /,o,.<0
//1171/�3p /7/
�. - ., •' ,a. ' ,Ir ,: .: - ;. WIIIIIIIIIIIIIIIIIIIIIIIIIIZ ���
1A. Gore Creek Station 622+00, Adjacent r' w',•'.:- .: F , Li
to I-70 below 1-70 Truck Ramp ;# •Y ", ;. 't :�,:.:�' k 'iI' ..- a' ;. Z c�
Proposed BMP Recommendation: Forebays '�� ;. `� :R. r a j` .. y" — -� r W�.
P Y y f ,�:_ III III bj m.,
and Sand Filter to provide treatment and • r M 1 •., '" ....^ `�" �—=-. ' J w
�� � � � s "; r IIIIIIII IIII le
remove pollutants, including sedimentation, ,_: ' a I a t Q IIIIIIII
filtering, and adsorption of constituents. - i `�'••, � '•' ••4 ?�' j� — �Illz
.- -_^...
•
Pollutant Sources: Pollutant wash—off from -� _^' ''';',.‘,'.."5:;;,....- �y�. "� > .: •
::r-x •,-,51(: •^ :s14-,7 !,.. 7:_"..',: ,.`(1' - - .'` •+i, _ Yf 1 1 '
y ` . :x . � . r,10,44'ti r ,''`�'.' _ fix: r',..'A 1, r
1-70, sediment, cinders, hydrocarbons, trace <" 01.'• ,'_. �r, ��: : "; - ; r" „•..:;,; 5'.i ''
:=.. .",:~• .y..•_:;`-'":(�.;.��-`,•.:i�b'--v-).
1 �f�_ �'i _�/•: .V `•'�:ty'. u�: .y^�; ' ". .'i �'i '' � (
metals, road salt and deicing chemicals. �- -- � r _ :a,'. _� =„ '�• .--� ; :� ��
• � �� c.- - - ^.'_„ - '•k'µ'� r �ty ,�.:_ Ili
Ute
Property Ownership: 1-70 R.O.W., USFS 4 ti' x t1 ' :' y` ' ' �3,w :fir , *�
fir= k�i 1 -u ::; " _, �'., j r
...�,�, 2 n ,.. { - .
Lat/Long: 39°37'31.24"N, 10616'41.34"W ; - ;�.;K;.:. '; ';� ,, ' :�.
'' • '; •;�.,� rr[ ,mac
Potential Permitting] CDOT, USFS y - - '' wrr' :h, ; ; v, .:i 1 r ,•7r yT
- ..tr nR„•�''▪�'�• '•rte•'•• .L•;'T�:,: 1 Al-4' .7• TT ..}� ~�"•-
Potential Partnering: CDOT, TAP grant � ,,4 I -Y`. . 4•:A' `j�'n� -It A,
,� " I. . .i -: .; ”, ` .'.1,i:': ';-r:':F i J 0
Estimated Cost: ;: ;' :. �y ,• P �.x 1 n Z
Construction: $110,000 c4 s f r-.-. - 4 , +. YA r+:y;;:�, , pd.i,••
x , !'a+r:
0 04
Design and Permitting: $44,000 " rz. _- r •. .�� . • ,,die • A. • _ .. rw.r.> .°:, F
" _ zr 000
Total: $154,000 }�sr ,._ _'I, �.„ .. - _ - ' � '-' `r *.` t, - ,:.
5.
al Notes: Sand Filter and Forebays. ttF 'Kt:.:r; i. � c ;
Q Next Steps to Proceed to Preliminary Level: ._ , }. I �J a�
^' Detailed Field Topography, Utilityxx"=z ` _ - 1.
'm '1,- "
Existing ,.
Locates, Geotechnical Evaluation, Ie•'?'' •�- -'`'' +: -� j
4. F
. I ' <-11` ,gyp :1 •'{ ': - - i:: ‘„a.r Ot.;. _ -�i:'
Environmental Clearances, and engage CDOT ,s. q r. u ,. i:ti •
o in discussions. § k:.5;•••41C :3.:. 'x` ,� ' � - 0
N '• •% :}.., ?,A.�a'. 1. 4za "r: :• Y:" _ •.4•+f ' kr :'A.:. •.w 1•y .3'. /C
:0/4
., S .•).r •L'--',i i' '.;''4,'/-" R.•F. :f' A "r. r��r '. ' •I e '-'..H
%Ld , •%_ //o/�
Ln Priority: Rated Level 1 because there is a f y •��•.���� �':..�.� r.:�� � •S . �6'�RC' ;' � -
.--I ��, _• '.b ✓'A yet. 'if .-p'•itk, '''• '
= large amount of traction sand and other ' �'',I '�
I. pollutants from 1-70 with poorlymaintained ' ' '� - - :'° )' -• .
x treatment or catchment. There appears to •
.moi :. , . " ' '� � �;.•� r�•y 2. i • ; '; ry IA k-,
0 be space to provide Sand Filters and to , "
r1� � r.
Qprovide and improve Forebays.
0
61
N SEDIMENT FOREBAY
.:
RIM
yam•, -_ PER PLAN
1 / r0oq? RIM 0 (TYPICAL) z
Ci. '.".'=""...
_ I I I Ii
�Qa INSTALL FABRIC MIN 4" ABOVE — I I I I I I 15
Tr
F® SAND LAYER, KEY IN AND
Z
•, II. 1 R7 STAPLE. OVERLAP FABRIC BY CLEAN OUT WITH (2) ce
M4,1. 18" MINIMUM AT SEAMS 45'BENDS WITH
I FOREBAY TREATMENT BMP III= WATERTIGHT CAP
TOP OF SAND FILTER , •
rr
U) RIPRA - - 4.5'L x 4 5W TYPE L - ,�
i OR PLUNGE 000E MM)
V RIPRAP RIPRAP BOSBE
v - PLACED OVER _ > If z
p GEOTEXTID FABRIC - _ III III III II III TI ETl" OUTLET PIPE
AND VOIDS TO BE _ \
Y FILLED WITH CLASS C I I—I 1 1 I I -III IIIIII -- b
FILTER MATERIAL —�i i
Qi FOREBAY TREATMENT BMP III- 4(MIN. UNDERDRAIN -:a
D e , a !
U) 23" DEPTH CDOT PERFORATED
H A-2000 a - 0 n
C INSTALL MIRAFl ao
�-I HEADWALL(IF OR APPROVED EQUALTERWEAVE PERFORATED PIPE) /// r v �n
01 CLASS C FILTER MATERIAL OR EQUAL / Q = 0
,,,
SAND TREATMENT BED / e, o
.� REQUIRED) BELOW SAND LAYER NOTE: THE SAND SHOULD BE MOISTENED AND z z w z
TREATMENT VOLUME c> W W z
0 INFLOW AS SPECIFIED(SEE MODIFIED TYPE C LEVELED WITH LITTLE OR A COMPACTION. THE
INLET SUBGRADE SHOULD BE SCARIFIED ABOUT 6 TO 8 w rc x p
DESIGN CRITERIA)EINCHES DEEP AND LEVELED WITH LITTLE OR NO 0 0 " 0
I / CHECK AM COMPACTION TO INCREASE SOIL INFILTRATION
ii
OREBAYI/ TREATMENT RMP0-1 CHARACTERISTICS.
RIPRAP APRON NTS. SHEET
CR PLUNGE POOL D SAND FILTER EXTENDED DETENTION BASIN TYPICAL DETAIL 1C
0
a
.. , .
a r PRIORITY:
► yZllllllllllllllllllllllllllZii i
�P
....kirvik - ' .--"J s
•
r ...
.., _
.,. „ .. . ....., ,„,� _.:�` �_•.•__,... 4,411.--:.N2(
�. *.• CB ��� LEVEL 1 .. a �
4.
•�- - `.( �- , •-- [�• - - F �. 1111111� IIZ X05
ItSt
Iiiii,„ _ . ,
. a 111111 2.%.
•
I
•
ot '14 lilt
' \If 1
F' I " • I 0\GN3RNr Ilk,N....1',...„
\y ` 1 II 1 0
lik .a n
y b Ii
ili.:
/ \-- r:. • 7-— > CON
WI ,+ i0 . s r • UUPO/ A
•
I
- - - - - _t ✓ -z _ - / 7
illk
4.
/ aCC
"Ilk . �/ 1 1 W
iVl` / I I "4 / / W2ArC
. ._ U
IM Ir
a — I .€ � oo � 0
N I SITE 1B * sit ........_
6ti5=
r:.; 1 ,vir* ...
TOIV O` I,• 4
.� i t ' 'ki el ` �"`�
lli
:. �
N ; •
/*IL
I46,
_ Ar idt
BIIIIIIII
r
y
•
IL;*. '- t- 41. "41‘" -,' •'- '. 1 Air
.., • , ..._
_. , ,
L ...
iF Vi
-I • e • .'I!: :IN' ' . - 4 i:.'
T. lliPk-
621- Z lip, .. . ' ''?-'5°C' ,Ig 3. ‘O'4" ,,, ir 1 ill- ,Z:4"'C-1 ' 1 j'' ''' '1 di*: .../
er.
•c
__ 140 f - ja „ III
a s
_ --
Q
V1 • _
ro P r\k. _ I 1' g19x00 J n 111111111
•
I
4 O
Q £
/')Ik'. •i 'a1 — . / _ 818+� ` ai _ �I
o
6, ; 11111111
s
hi ... 4411.k•- , . . .
411,4
Q S Y Y O
�, o rc) ; _ GRAPHIC SCALE W w o
0 \\-\\ \� / f - - - / + -- - 5r �` '�• ' - 24"CMFO z 6 z
I _---- CB f 0 50 100 200 E E = q' a
\ /\co , \ —
FEET SHEET
O — 1 s • s ` / a 1 inch 100 ft 2A
o -
L �cIdH \ cb
6
N
------\
-_ -_� i
�s. \ � \ \ 6a. .4,I f
\\ 1 \I 1 ,\ , , \\ \ \ 1, /CB \ \ . \ \ \ ` 1\._:
\ I \ \ I - � \\ `\ \ ` " '' '/ ( III III ug.
/ A\ I .\ \ \ \ \ \ \ . \ I \\\ \ 1 `\ • N \ \ \ \ \-, \ r. \ 1 -- ` , --' - LL,
/ ( \\\\s/1
\ I • ` \\ \\\\ \ / _\\ \1\\\ ��?\ \ \ 1 / \\\86584 \ \\ \ \\\ \ \ `_r�---------' / IIIIIIII IIIIZ �'�
\ \� \ \ \ \\� \•\ \ / a4 .7c\ \\\\ I ��\ � \ \ \ \ ` Ili'/ _— \`� ` �/ /✓ ��� / — /• III (7 0
\ 951' • ,► \_ _ \\N\ 1 \\ \ \ \ , �s --- -- J IIIIZ oWa
\ \ ' \ \ \\\\\`\\� \\ \\\\\\ I \\ \\\ \ � \ -ice _---- ( ,// \ \�-i \ /.
c \ \\\ \ \k ,\ / ill \ \ \ \ \ \\\ N\\ \ ,\\ •\\\\\ / \ / _......
I �` \ /01111: \ ... . ,
410.A'‘' ‘Nk '
_ I \ \ \ \ \ N. \\\ \ \\\\\ I 1 lei \ _ \\ \� <�_- �_i / - - 1 I
. \
..,
1 \ \ / , \ I \\\ \\ \ 411 , \ •\ \ \ \ �\ \ ` \\�\` _ �� \\\� /- \�� \�� I ------ / I i / ,ice\ \\\\
,, , ,
I/ I \ \ ' \ \ \ \\ ‘ \ \ 1 1 ‘ \ \\ N,,,,,..,‘,„ \
1 / \ / \ \\ \\ \ - , N. \ \ 1 1 � 1 \\ •`\ `. ����\ --� /\�\� \_ / Opo/ --/// i/ \\\ \\ //r : i7'
� Z
1 /\ � \ \ \ N \ NN1
5519, \\ \ \ � v m
•
11 •\\ \ \ 1 \\ \ , ��-\ \\ \\ \ \, \\ \ \ \\ •` \ •\ \\ \\ --- iii// /' `• '/ -1 % 1
•
7.
\\ \ I \ I \ \I I 111 11 1 \\\\ \ \ `\ \ \ \ ,��- \ \\ r \ / - - '// / -\ I II /'-`�J/^\\ \ \ / .' I 11\1::.:.':
11 .
�, \ `, 1\ 1\ T \ \ ♦ I I \ \\ 1 �QRECS<4Y �� _ 1 \ 11:
---'/ i--- , 1 I 1\1::/-864° 1
I _____/-.;;;r//1,;,_,//;11/:
/; i\; r 0 U rLr
I \ I \ / \ / 1 \ \ \ , \ „ \ \ \ \ \ 30- \\ ---- ��'/ �- 1 I 1 , E5A0'� I ( / - ,/ I ,:
1 f
Ill) � A I 1 I \ \ V A A v __ / w v /
/ \ I I I 1 X 1 I I 1 1 \\ \ \\ \\ -- \ \\ ---\\ ' / \\ \ \% . 1 w O
MEI / I `\ \ 1 859.3 1 f \ 1 \ \ \ \ \ — ` \ \ / / / i W /IL� �/�
, , i I ,, ........ I t ,/44,,,„„„„......7 j \ \ I 7 /
\ V -' -----•--,
/ .1c /.7)
` i I 85•:.9 \// I I \ ` 1B — —�\ I \— + \ _ \ \ \ �i ��-'i o •/ -- /
CI 1 I \ •\ \� \ \ / I 1 1 • 1 //
�_ / ! 1 \ \\ /// ,�/ \ co
1\ \\ �I© TEN_TIOI`�1 `_ �\ \� \\\\ --' --' 111 - --I-/ //II ,/ ✓'( 'II.
/// / // �//// /j/��,
'.11
rNiO'_Ln / / - - N \ \ 1 \\\ \- N \ \ 8 I ( • / / /W /1 ,/,//
// //
I /� / / i1 \iii\ , I \ \ \ -8620 I - •1. / / 1111 /
CV' �•��./� / \ I \� \\ \\ \\\` \\° \\ \\���---���� �•�-.���`\ -.7...____________T--_:•-,,,,.._________,
\, \�� ' I I /\ I /F �/. �. , �7I./ / I I III 1, \\�
ri l N.N... lie
\\\\/11
\ �� ` \ \\ `\ I -_\ _, -- ( /- �\�\\����. I \ % / /�// //OErtse r/d�s I I 1 \ \ \\ m
x-r 1 \ -. \ ... ---\.
-_-„,,,-...,-.,:- _‘1 • -:_-- -----........------_.:-.- ---- ___
N -\-„,... •-•„„. ----ill* __ __-,
•
N
m l \� \ \ i -- \..J \ \ �, .r \ iet
446_
- J \ \ • • • ---- . -
. •i / / / - - 0 /
1 \ --:8, -- 'lir '2., •--: -- ' / .7 •-• --- 7 7 7
d /1 \ \. ` 1 -k' ,2-- 1 _ \ - iii \ /7N- 1 \ �1 (�` 4111\ R• i��- D ----' -�-- // -'- -�' �/ --- �' S
CO
LII'
\\ s.• \\ \ I�l - - % _-' -- f -' --�� I \i I I , '�� '�/ i// � iii �� i� ;
/ \\\ \ ..\\ -J \ \ \ ii'- / /----.-:"----:>.�• . • 4.
\ / _-� 0 / •/ o ---- / d - -- -- -i
�-\ ; \`\\ _/-- - i• I I, / \ •`-� - \\ •` \ ` // /� //✓ v 86899. -- -- - - - - / /
I v V --
` -� i l I I , / — C / / / / / / / i 86888. • / \�/ ------ '- - / // / /1
o � \ \ •s I\ \,6'1 W I \ \\ + ----'I --/ iii//////i✓ �� / I'1/ ) 1 / / 11° I I I ---' ' //////// // X/
I
\ •\ \ \ v / \ / 1 / III / \ -- -/ I 1 cI'N
/ 11\\ III/ 1 1 - --1 I I / 6 • --- — -- -- / / / -/ \ / I / / 1 / I -1 7///4!.• , / - — 23630 _ --// 1 I \ / ` I I / I / // I/ N , \./
I I l / J --- --- G— // — a = r v o
- I r' / --- / \ / \ 1 f / ' I / / / rA� CC�Ak.E/ w o
1 J / I I I r / 1-= --_ CBS / I / / so/- ioo 2 - w o
`r Z ) J �' ( 1 I GNF 8691 3 / / / / / / /� -/ , 1 i' o o v o
o. �_ f 1 1 I / ^� _ / / I I1 J / / /
r___40,. �• l I / ' Q- �. -i•�F I / 1 1 1 1 1 I / / - \ / k. -1- _ / 10E/ / / ,/ J/ '
\ � .• .( X �858 .1 \ I / I , I \ \ I / J \ 1 S / I / / / -' 8751.
E.- / - �/t" I I 1 I / 1 I I / / / \ II \ j / // / / / / /--, / --
o _ \ I 1 I -�� \ I / I / / / /7-7_ -
' 7ss w \ X )' I \` \ \ / I I 1 \ 1 ! 1 / / �- / / / / \ (IN/ T� SHEET
r V \ \✓/ / I A I 1 1 / I / I 1 / / / /// v , A ",�
> \ 8582.7 1 \ 0 i'-/ \ I I 1 \ \ I• \ \X 8�o9.Q I / / / I tw / yv0 ft/'
I I 1 / / / III I \ 1 in / 2B
- - - I I / / I I / I I 1 / / I III /// //i % / X/, /
O �� \ / 1 \ v 1 / / I 111 \
a GO \ 1� - i - . ,t \ / /ic. l ! / / 1 1 \,� 1 / I / �l i i l I ��\--' // ii,/. `•//i// /
WIIIIIIIIIIIIIIIIIIIIIIIIII Z �
1B. Gore Creek Station 619+50, Z — a^
1-70 Bighorn Road Overpass W= ',t = air d•
na
Fr.::-•
.w � •. I•f. "��.." aIII III W�"' ' 'r, Jw �„
Proposed BMP Recommendation: Forebay and .,, • ;,4 -� '
• s' � c � . poiBioretention (Rain Gardens) to provide treatment .-, + a 11111111cDand remove pollutants, including sedimentation, '' - :� •""•' _ 4 r `,'I.` h.-a- IN '' ' IIIiw oWafilterin adsor tion eva otrans iration andw '`g� P P P , - - _.�rL• - T L �_ z
biological uptake of constituents. � {*: '' ° } ,- '. r •'
;F is
•
Pollutant Sources: Pollutant wash—off from 1-70 - '' LI -.
and Bighorn Road, sediment, cinders, hydrocarbons, ' ` :,;1•'f-`�I.,K _ .,
trace metals, road salt and deicing chemicals. '`` T `Li..':` '''''' e'.`
Property Ownership: 1-70 R.O.W., USFS IL :,;.;' ;
Lat/Long: 39°37'35.04"N, 10616'43.39"W - .. .a : r: _r . _ '02 2014 09 02 2014 4 J
Potential Permitting: CDOT, USFS, NEPA "" a
Potential Partnering: CDOT, TAP grant , . : ' O
_.,* `.: 44404e% ''Niz,, : ''', '-:,',.'.•f' - 0 m
"IIIIIIIIIIIIr
Estimated Cost: PoPi—
_ ` >-
Construction: X140,0004: ' _ 3"' '' ,;, V
6 Vic, �11, { .; O
�, Design and Permitting: $56,000 a:� :' ` Nge% ,�' s; ^ " . b 'A' ::; WZ
Total: $196,000 ri • ,_; •
..',7'....,..„,,,'L ;..;:-, ' - 44 w. I'I
. . L3
'f-it'''''' 'r r r � .r °'''
.'s •. ... ,x-
00 Notes: Bioretention and Forebay. .,� - ' Y -,,f, :,,,--,-.4„--.J._e,". - M
(•.J :„1. :,''• ts'B.. I .- %,.C+ 1M %a.Cl/
CS Evaluate site to see if wetlands creation is _` ;-°'•�'_ ' `” `= '°"
.: appropriate. ti, . _ S : _ ;IN, .. T • - :. .i4-4:. V �i
y • .:-.-4.'';'•.4`..,":"-- - :-
IE
p fir.;. '' L.-, '':;-.. ;s .
N Next Steps to Proceed to Preliminary Level: _. -.Lus:;4ti• , - -•. _,-.•;_--.A • CC 1—
I
Detailed Field Topography, Existing Utility Locates, I F "Y f' 'r � _: ' r
(NI.
8 `n
Geotechnical Evaluation, Environmental Clearances, 4 - �,f _�
a
= Wetland Delineation, and engage CDOT in 3 �I k ,•�,�
X discussions. rig ;, -...:..t.,_.'",
_J 5 09 02 2014
o Priority: Rated Level 1 because there is a large .. `= * - °J'. "•;' -"-iw='
m amount of traction sand and other pollutants from
O 1-70 with no visible treatment or catchment.
There is space to provide Forebays and
Bioretention and possible wetlands creation.
N
O
a SEDIMENT FOREBAY o
a s
9 1 WRAP AU.CEOTEXTLE FABRIC TO
TOP OF SOL.ATTACH FABRIC
.: . DRAAND SHRUBS FIRMLY TO WALLS OR TRENCH ADES
CU YM1D
CO .-moi'; _. PER LANDSCAPING.DO NOT USE SOD PLL SIDE SLOPES}1 OR RAILER
ALL ADE SLOPES 3:1 OR WRAP ALL FABRIC TO (4:1 OR FLATTER PREFERRED) INLET AND RIM
iiii
FLATTER(4:1 OR FLATTER TOP CF SOIL IL ATTACH
FABRIC UNLESS VERTICAL WALL IS USED PER PLAN o
PREFERRED)UNLESS FRMLY TO WALLS OR TRENCH SIDES ALL INLETS (TYPICAL)
PROVIDE r MIN.HEAD
CU L •ii � AtAX: PROM ALL SINLETS HEAD VERTICAL WALL IS USED wOCv
N FOREBAY W°F DRYLAND GRASSES WATER
L TREATMENT BMP RFACE SURFACE
V �•.• = SU REALE WILDFLOWERS OR SHRUBS INLET AND RIM
PER LANDSCAPING.DO NOT USE SOD PER PLAN O
RIPRA• ON (TYPICAL)
--......m. 31,---\ ij �113RT.!7/� V/\
OR PLUNGE -00L /I 1 \ \/%`\ \� � ��\//\/\
Q \\\\\\ 7YPE L PoPRAP(FILL __ _ /\ \\\ \
'it
D i SDC ALTER MMATERIAL)S MTN COOT CLASS //\ "tB SAND/COMPOST lO1L ASM C-33 SKID /\/\
N UNDERLAIN w/FILTER /\\ LAYER 309.TOPSOIL/ORGANIC \ VOIOC FILTER MATERIAL) IB-''.."'""b<'."-"C°."'''''''
AN�D/ POS7 CpAP05T/SIftEDDED �LAIE M Y
a] CLOTH / - j // ` J PAPER M'I /*
/// Q S Y Y O
MATTER ,I 30 MIL PVC UNER TO BE
(p �/\ \ \ PLACED BELOW PoPRAP AND >• \ \
\/\\/. ////////\\\\/////'//\\// \� WOVEN CEOEXTILET�FABPoCILE FABRIC : P w 1o I IA
Z Z Y Z
FOREBAY TREATMENT BMP ASTM D4751-AOS US STD.SIE CLEAN OUT WITH(2)c45. N Q W m
0 WOVEN GEOEXRA FABRIC MEETING: 0 TO I�/O Ar GTH I MN BENDS WITIi WATERTIGHT CAP
C ASIA D475gg177-AOS US STD.SIEVETAPE 2LBS. IN.O STRENGTH 100% 4-MIN.UNDERDRAI 6 E 6 O g
�—I HEADWALL(IF TAPEIADAL TEAR STRENGTD SIEO'il X 60 LBS.NLN.OPEN AREA OF 4$.30 MIL PVC UNER TO BE PLACED (CONTECH A-2000
REQUIRED) 60 LBS MIN.OPEN AREA OF 40 BELOW GEOTE%TILE FABRIC PERFORATED PIPE)OR EQUAL
- TREATMENT VOLUME SCARIFIED SUBCRADE WTI1 PER CaCAD ON
`--I INFLOW AS SPECIFIED(SEE RATES EXCEEDING 20 MINUTES PER INCH 6.DEPTH COOT
CLASS C FILTER MATERIAL
G DESIGN CRITERIA) SAND TREATMENT BED
0 AM NITS
� FULL INFILTRATION RAIN GARDEN NON INFILTRATION RAIN GARDEN SHEET
> OREBA�RFATMFNT RMS 2C
o O RIPRAP APRON A TYPICAL BIORETENTION SECTION B TYPICAL BIORETENTION SECTION
IS: OR PLUNGE POOL
PRIORITY: Ung og.
_� r , t s LEVEL 1 — z s„
JIIIIII , n
Mill zm��
-Al ;m
N
F° 1111111 z
R�rqc w w
.
•
SHALLOW CHECK DAM
with BIOSWALE AND
TF�STq /� ��� ,_ UNDERDRAINS (TYP.)" a cr
. \\, ,, 0. e. ,
,'rte Q J
4
\ \ -P: 'N yr�-''-� Y' �� BIORETENTION x
.. `" ��4 R F 8 WN
SHALLOW CHEet. ., B /\
- , '- • SHh BIOSWALE ? '� \ \\ �J U 0
>. '.: \` UNDERDRAINS (TY" �: �\ _ _ - Q WZ
"` \ \ SHALLOW CHECK DAMSIli 1
``+ ` 4 �.� with BIOSWALE AND
- 4ikiRAISE INLE \ . " ,� b UNDERDRAINS (TYP.) W Q
ia� /
PROVIDER 1 W 3 a
_ / C
v > - BIORETENTION• \ ` / / / - ,_ . _ U
CC
. , ., , , r. 4 \
„^ ilkliop
f
FA' / CB BIORETE $ \ p. #
\ / / 'a s k h a
/ .
\ : . . .
/ SHALLOW CHECK �•
811111111
c=n t • \ \ INSTALL RISE ----� J
^ ` CONNECT with BIOSWALE AND
-� t t t:,� UNDERDRAINS (TYP. \ •
i,,4 i. \ S �'� S AND ei/ `��
P.F3 E ham/ / ”• ; r�
c \ BI ENilON / \ _
f
v *� 98X / 8/6X/ ,.__:_,:_\_FOREBAY
°° << °R . 11111111
v
N ROS r / ,� 4\\
0
•
Rte_ \. - - - a_
CSF\.. :::N
ING / -\ \ \ Q = Y a o
g GRAPHIC SCALE • o o o
0 50 100 200 • • - - .'�
o
.. is a
> :�
? :, 1 inch = 100 ft. SOz*• t h :
_, 1\'� _ .. -.-. ulllllllllllllllllllllllllll_' �
�;� - ,;� \ PRIORITY: Z Z daR
�\ 8382.4 8 ����_ ` \\ �\ \ O `\ C� •�X
- --__,--.0 0 --__ \N.`\\\\`, LEVEL 1 a Z = ,
. 78.6 \,„� ` -� 0� \` ,„-„-.\\\ \\ ` `
\ \\._ '-', ---...._.`.`
a\\ \`�\`\\��\ J 11111111 11112 ri
\ ,\ 8382.9 ��\ ---__\ \ ` `\ ` \" II II �ol
\\\�\\ __--- \X RpNq ` .` \ a \\\`\�\ IIw oWa
NNNN
�.��`\`N\ S •
o _\8381.1 4 • \ \ \ \
/' �' ``�N ------ \ - __, Si3ALLe :.ECK DASI .` `\ -�
I `� \�� /N \\\\\\ S I �� - - 8378.9 ,with-E1.10 : D `\\\\`\\\\\ \♦
/t `\`\\\\\ QRS _ \ Net
X �1TVi1ERDRAIN� (T `• \`\ `\ .24•� \� .\
N\ \\ \\`� ,. JO i1 `\ `N\ ---?O\ _
NN.�N NN ��•�N.\ � -\ i ,\\\\ �• \\\ `\ \\♦ `\`\`\
- 71bC'
83 • 2 N N N\ 1 N\ \\\\\\ ��\ \` \ ` ���\ ! \` \���11$ \\ `\\ ` Ate`\\`\`\\�\
�! '\`�`\` \ '\�� \\`��\ 8385.0 \\�\�o \'�_� ���� I _ s ♦ ``\ \`\` ♦ ...
\` �\`\`\ \`\ \
\ \ �"......2..,� \ \\ \, `�� X �\ \\ \�_-�\ 8372.6".° o `• 0\ `\ \• \\ `\ ‘`..,"*"\...„.„.'„\ \` `
\ 83 \5 `�\ \ 8379.1 /- `��\ ` \ ` \ X Y> *�` `�I f �EiCfQ�f\ ` \ `\ `\` \` Q J
X \ \ \ I \„ p
4
\ \ •\ ` ` ``�\ `� \ 8381.2 \� / \.7C°\\\\• _ / / / �.I ` I I ` ` ` ` \ \ 'l \ \ \
\ \ \ 8371.1• \ \ \ \ \ \ \ �\ \\
\ .....
\ \ ` `�' `• ��\\`�\ `\ \ X \�„ `� o\\ I ``$372.8 \\ `\ \ `\ `\ `\ `\ N. \.„ , ...• \ ...
0
\ a \ I \ C \ s.
• \\ \ \ `•\ • 8387.4 \ \ \ _ - -1 < \• \ Li,
N.
\ \ \ L9GV\ CK GAMS \ • `_ o • \ \ \
\ ---._::-. 348.:6,...:, \ �\ N. \\\\ A\ \ ` `l ` `\ /i�S O'er `� �\ ♦\ \ ISH\LL� r1�aCK D A � -, ` .-- `,.. �..\ \ ` `\\ `�\ �\\ \ \N ... \ X C \ \� 8388.8 /i ��- 372.7 \ \\\\`o I ` Wl `B,IOS,WAC AAL `\ `\ \` -- L WLrb \�� \�\\\ \` ` \\\ `\ ` `� \`�\�._�\\ \\ l �/! , 384.1 \�\ 1:::1
�� \\\ \\ \ \ /�-�`� `\ \� ` \` ''Ii�\ \ \ \ \ \ 8383.2 ` `y �♦ . \ ` \ '� DE QIIV'.� \"R� `\ ` \ -� -`,\ �+ Q O\ \ \ \ 1 \ ` XIT180 \ \ - r \ ` \ \ \ \
W CC
493+°° \\� \ \ \\\ \ \ \- gliN/ \ fc
� / \ `� ` ^\ • \� I \ \ \ \\ \ \ • \ \ \ \ \ \ - \ O.(I)
\ r\ \\ \ \ \ \ \ \ ,.....416,7,•'
/ • ��- \ /� \o \ ` `� 85.1 ` `\ `\ ` `� `\ `\ •.\ `\\ �+ //C
i'
8342.4�` `\ `�\ \\` �� \ �-\j I s- - `�``\ \/coNc. i 8389.7 - \ �\ \�\\ \ \ / _\C\ \\ , X \\ ♦\ \�` �� \ \\\ \\ N�\
frill 0
. - \ . \- . __. 8 1:0
-4 \ • �- \ \�\ `\`` / _� N. •., X`\��-�/� 4111 /I `\ \ 8391.4 \\ \ \ \\ / ���� `\ ` �� \ `�
u5 8343.7 /` \ 411% \ / \ \ \ \ \ ` ` \ \
o x e `` \ \\ \ `SC �SiaB \ / BIORETE -- IN ` \ ' \� .\)\ / \ ``\ \
\\ 8361.2 I / \
\\ ♦ _ I \ _ \ \ /� \ \ \
-Ln
\ `\ \\\ \`,_8360.8 N..,„\f �n \\ / \\ •4, N4�L k C.'H`\ECK D. S\ \\ .���,, `\ ` `�\.��� `\ m
l=/7 I \ 3' ` �� •' L RISER \ \` \ 8361.1 S ����'.�iilaT ; \ r,. `\ \ \\\ \\ .O \ .\ \ / J \ \.0 .�
\ �\ ,�• ` lwd'�hJ BIOS AND \ _ • \ \ \
i I \ 4 AI"._ -a\N c,�* \\ I \,\ X \ S YP.) `\ / \� --- \ \`\�.
X -------- eIN RAI1\l
\ X • \ 11 S PIP �`,\\\ Q/y l\° \ •
\ a.. ••� `\\ \\ �\ • / / \ `�\ \� \ ( \\
X -7l \ \ \\\\ \ of '\ \\\ \` \ \ I \ \ ` \
83.44.6 \ \ "OVI i \ \\\ \ I \ ` - . \ \ \ \` `\ \`\ \ `\N PON \ ��i-Nom\ NN
8343.5 \ \ \ \\ ti/ \ \ \ \ \��/ i-- --� \ \`
\ \N \\\Z 859.6 \ / � ) \ \\ \ \ \ \ \ \ ,\ i �, -, / \ \.
C, X 1 : . •RET • \`,\y ,,,, x /-` \ / ,...2„,..\ \`�\` \ \ \ `\ / .� \ \ _ \ X��
N. \ \\ X 361.9 �\ / \ \ \ Ni \\ ,
I I ,\ \ / • \\ \ \ \ \ \ \ \ \ \ \ 8399.7 \
// •
\ \ \\\\, \\i 8359.3 x J \` ` `N N�� `\\ ��\ ` `\ N �� ,I \\`=__� \\
i _ , \ 1 \ \ \ tip/ �'iJ \ \ / \ \ \ • \ \ \Alifr
/ ��� •
\ \ , \ / `\835.5 \* \ \ ` �`\,`\��\\`\ \ N. N. / `� o
\ , \ �i- \,\ \ "..N.,":\N. \\ \ \ i ,\ i
•
Q \ i 8347.3 \ '\ \ \ -...3•„„ N \ v"k , \ \ \ i • \ \ \ • ••• ••\`\ _ 60. \
I 1 �� \. 8354.5\ \\\ \ <14 \ \`�\\ \ / -- 11 ` N\`N N �N \ N` \ ` ` '
Q \ \ \ 1 �/ - \ \ \ / --J \
•
•
\\\•. GRA-PHI: SCA I •\ . - \ I ` \ \ \ \\` \ / w co W
o
�\\a\\\\ • 50 1\ •
10c 1 200 / -, \ ��\\\\\ /- \ / / \ \\\\ \\ l\ / � \\\\\ \,\\\\ I
cri \� 8349.5 �_�___\ • •.L\\ \\\\ `\ \`�\``�V ���` L / ,�7I ---` ��\\\ SHEET
0 \ \- •\ - -_ •• X ` \\�---- - �\ \\ SMP - ---_
\\\`\`\ ittc)i "1OA\ft. -- •. • - _. _ _ `` \ \`----D_-----------:-"---. _ `
a. \ `� ! \` \ / I.1� ��\ ` ,\`\o p \ 8367.3 \\ \ ` \
ZIIIIIIIIIIIIIIIIIIIIIIIIIIZR
�
7. Gore Creek Station 498+50, a z 'a• l
Big Horn Road, 1-70 Exit 180. J III III „
Idi
41Iso IIII w ."
Proposed BMP Recommendation: Forebay - ��� cp il8a
and Bioretention (Rain Gardens) to provide - -• .. n_ - �� 141.11 _ :" i" ����w W
o
treatment and remove pollutants, including - ''r° �� .
sedimentation, filtering, adsorption, �J-- - . - _ ,�-- 4..
evapotranspiration, and biological uptake of �� w ��.�n• �. _ s -
--..1: = `3i"t .-. - _'• 4,......,
-:..i . L w i -,.\ .•.:
constituents. Check Dams with Bioretention ' - * : =;; E: _ . K ,.. , R
Media and Underdrains. *ter;•... - _ „lit
. �, .
18.
r' _�V' --.7
�• ` '"�^ :Yrs.',.' lam. *"-
"may' ■ 1 _-. --- ..� r
•
Pollutant Sources: Pollutant wash—off from _ -- -4-4=-,„--t-
I-70 and Bighorn Road, sediment, cinders, _, •-� �,� �` ' ,� -'��: _ � � ., . .
hydrocarbons, trace metals, road salt and ,Y: .; ..-74..-1:-� t ;
deicing chemicals. J.y. Fa'S. -'o- zi..,4 _ ;:nr_F .,,;Sv -
Property Ownership: CDOT a
- Z
Lat/Long: 39°38'40.19"N, 106°18'27.70"W
F
-.‘1.444. O
Potential Permitting: CDOT, TOV •- � n 0 °
6 ,
Potential Partnerin3
g: CDOT, TAP grant in -. •..u3 i , Q ..WZ
2017
Ali
._ . „Am. _
w ,
.,
.: ,:.H .., Q�
..,..
a Estimated Cost: � - �. " � a
Construction: $400,000 ., :.:,. a . 7•-,-• :`�°:' :ate- ' Vit,., iP` :- - U �
M •
Design and Permitting: $160,000 = .: K__ : r,Sn,. Ili _ 1wed - . __ It
Total: X560,000 ,c: ; xr. � '
Notes: Bioretention, Bioswale, Check Dams ct , :, ` } ;r,>4
�5 r: O (1)
L' and Forebay. �F.:.�: ,. :1. ;::' • .
06
r. Next Steps to Proceed to Preliminary Level: „.
x Detailed Field Topography, Existing Utility .- -
0
Locates, Geotechnical Evaluation, `'°� �
0
Environmental Clearances, and engage CDOT
in discussions.
6-, BIOSWALE SEDIMENT FOREBAY
N Priority: Rated Level 1 because although FAST DRAINING BIOSWALE NOTES
OSWALE ELEVATION SHALL BE MIN. 6"
the area is pretty well stabilized and SOLID MIX TO INCLUDE BELOW THE LOWEST ADJACENT ELEVATION 1 /�
o • 50%COURSE SAND 2. BIOSWALE SHALL NOT BE CONSTRUCTED
vegetated with some impervious area, a • 20%PEAT MOSS UNTIL ALL CONTRIBUTING DRAINAGE AREAS
L • HAVE BEEN STABILIZED z
a • 30%SANDY LOAM •, p
substantial amount of traction sand and I BIOSWALE 3. COORDINATE PERFORATED PIPE UNDER =11N
d PLANTING DRAINAGE SYS MS WITH CIVIL DRAWINGS FOREBAY 5
m pollutants from roads were observed in the - TREATMENT BMP E
N field without apparent treatment or SEE 'L RIPRA A ON
a) — — — lip
��� — OR PLUNGE -OOL
catchment and there appears to be space ...2) .--"----"--':* „.„.___....__-/----..----
to provide Forebays and Bioretention as i, l� _ d well as Check Dams with Bioswales. ,I—III= 111_111— �� —II
III=111 =11110
111 II—III _II-
-=----111-1=-, 111,- Z
FAST DRAINING A • -a--I
L.p II BIOSWALE SOIL d a °II— FOREBAY - TREATMENT BMP N
111 1— ° MIX 1 0• MIN.
Q 1=III -3.0' MAX. _ - III 3:1 SIDE C
0 -, _ �-I HEADWALL(IF w
III II -�a III II_, SLOPE MAX. o
Q7 it III 1_�I=I\\- /REQUIRED)TREATMENT VOLUME wQ = r o
ra - INFLOW AS SPECIFIED(SEE
S DESIGN CRITERIA
UNDISTURBED �= - CHECKRI )AM z z r z
Cr73IO
SUBGRADE - I /
FRENCH DRAIN I- OREBAYI/ TREATMENT BMP o o 6 co o
SYSTEM W/10” MESH �~
OR APRON
� AND 4" PERF. PIPE 10 OR PLUNGE POOL
0
CI
SHEET
5 8C
H
0_
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
Appendix C
Existing Site Photos
Prepared by RESEPC, Inc.
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
Exit 180 Site
%
I
•41111100111111111111111111110.1111. ..-- .«-k- - - ' ' 4i,.._. ..i.,.., -74,1,-6 4 ..
71-I- i: - •. - r. JJ 4
Mi
_ -- ___,_ •ti,
-- . mi. ..
Looking east at area between Big Horn Road Looking north across the WB I-70 on ramp
and the EBI-70 on ramp toward the outer road
i' - ' •' kli4ilto] ' '
•
iiiltiii,i;ail , iii Vk,,,,..........-.14110! , .. ,i,e„MP '. ' . , ,
Looking east at the EB 1-70 on ramp from the Looking west along the WB I-70 on ramp
north side of the on ramp
'. r. A.: &
!
.. - IQs •�
.. �'iT.4'''P. .rel
'f' SPRINGS . Ev +. ....
S i
is - , -i ,
DENVER.II. - " • '
'F' k 3;.
r
Looking north from the bottom of the EB I-
70 on ramp
Looking east at WB I-70 off ramp
Prepared by RESEPC, Inc.
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
Snow Cast Off Area �,y�
. V 7 .' ''' '. '.:7 ' 1 1W 1:1 ''''!IPI il 0 .. ,
C4 -- - ' I,,,,,,,,,,,, I ' L:' . ,
+.
,, ,.. ,_ , . .4,„:.
" ' Looking toward Big Horn Road under the
•�.••• .0...i. - - M.,
:.' -, " •r, ,�. WB 1-70 bridge
Looking toward Upper Gore Creek&the EB
1-70 bridge from under the WB 1-70 bridge
AL • y
Looking at Upper Gore Creek&erosion of
embankment under the WB I-70 bridge
•
S•.
moi.._.._. � 4
1
Looking toward Upper Gore Creek&the EB
1-70 bridge from under the WB 1-70 bridge
Prepared by RESEPC, Inc.
Conceptual Alternatives Report
1-70 East Vail Landscape and Water Quality Improvements
Truck Ramp Site
. tom_
• AI
r46
•
,:~ L.-4, �f 6... +['iii F, ,4-s!,
,i4
•
ll • �
lei
tilligM
Lookingeast at surface sediment basin off ,
the shoulder of WB I-70 " {' ate_ {
^, . Looking east at inlet in I-70 median
Nti 1. ..,
_is.r l ..r..� ._n •iii ._
; -- Looking east at inlet in shoulder of EB I-70
• ', —' IA-.p..•
� 'iter. r 1�'' 'f.: -•. _ ;C.
r,.. -•2 ►i.•"'mi: .
•, C T....r .5_. Nef`. .. - ,-,:- t.:.e --Ar. 4.
Looking east at inlet downstream of surface
X .
sediment basin off the shoulder of WB 1-70 _. •---- }''' ~ T
Extreme erosion of Upper Gore Creek
embankment off EB 1-70 shoulder
Prepared by RESEPC, Inc.