HomeMy WebLinkAboutF16-0030_FP1_1478899031.pdf72 heads for Unit A
34 heads for lower level
26 heads for main level
12 heads for upper level
2ND UNIT MAIN LEVEL FLOOR
PLAN FINISHED FLOOR
8162' - 0"
ROOF PLAN
8186' - 0"
2ND UNIT UPPER LEVEL FLOOR
PLAN FINISHED FLOOR
8174' - 0"
2ND UNIT LOWER LEVEL
FINISHED FLOOR
8150' - 0"
PRIMARY UNIT LOWER LEVEL
FINISHED FLOOR
8147' - 6"
PRIMARY UNIT MAIN LEVEL
FINISHED FLOOR
8159' - 6"
PRIMARY UNIT UPPER LEVEL
FINISHED FLOOR
8171' - 6"
1
2
3
4 5
6 7 8 9 10 11
BEDROOM #2
210
BATHROOM #2
211
BEDROOM #3
214
KITCHEN
115
UNIT A ENTRY
112
POWDER
120
MASTER
BATHROOM
118
GAME ROOM
016
BAR
017
BATHROOM #4
024
KITCHEN
101
LIVING ROOM
103
BAR
002
CLOSET #3
006
W.C.
005
PROPOSED FUTURE PROPERTY LINE
EXISTING GRADE
SIM
CURVED LED
LIGHTING COVE
6 16 16
5151 Bannock St.
Denver, CO
80216
303-291-1012
303-383-5023 FAX
firesprinkler@afssco.com
A FIRE SPRINKLER
DESIGN COMPANY
ACCEPTING THIS COPY IS DEEMED AS AGREEING TO THE FOLLOWING: THIS DRAWING COPY, ITS CONTENTS,
INFORMATION AND PRINCIPALS OF DESIGN ARE THE EXCLUSIVE PROPERTY OF THE FIRE PROTECTION
CONTRACTOR LISTED AND MILE HIGH DESIGN GROUP, LLC AND IS BEING SUBMITTED TO YOU WITH THE
UNDERSTANDING THAT IT IS NOT TO BE REPRODUCED, COPIED OR MODIFIED IN ANY MANNER; NEITHER SHALL
IT BE RELAYED IN WHOLE OR IN PART TO ANY OTHER INDIVIDUAL OR FIRM FOR ANY OTHER PROJECT OR
EXTENSION OF THIS PROJECT EXCEPT THRU WRITTEN AGREEMENT WITH THE FIRE PROTECTION CONTRACTOR
AND MILE HIGH DESIGN GROUP, LLC. ERRORS AS A RESULT OF THIS FILE BEING ELECTRONICALLY
TRANSMITTED ARE BEYOND THE CONTROL OF AND ARE NOT THE RESPONSIBILITY OF THE FIRE PROTECTION
CONTRACTOR OR MILE HIGH DESIGN GROUP. MILE HIGH DESIGN GROUP IS NOT RESPONSIBLE FOR
INSTALLATION OR INSPECTION OF WORK INSTALLED. THESE PLANS ARE DIAGRAMMATICAL ONLY. ON SITE
COORDINATION MUST BE ARRANGED WITH ALL OBSTRUCTIONS, i.e.: MECHANICAL, ELECTRICAL, AND
STRUCTURAL. ANY ALTERATIONS FROM ENGINEERED DRAWINGS MUST BE APPROVED BY MILE HIGH DESIGN
GROUP. MILE HIGH DESIGN GROUP IS NOT RESPONSIBLE FOR LAYOUT DESIGN ISSUES OR CONFLICTS WITH
ANY OBSTRUCTIONS. IF ADDITIONAL FIRE SPRINKLER PIPING AND/OR FIRE SPRINKLER HEADS ARE REQUIRED
THIS WILL BE THE RESPONSIBILITY OF THE FIRE SPRINKLER CONTRACTOR. ALL CHANGES MUST ME APPROVED
BY MILE HIGH DESIGN GROUP, LLC
THE OWNER IS RESPONSIBLE TO PROVIDE SUFFICIENT HEAT THROUGHOUT THIS BUILDING TO PREVENT
FREEZING OF WATER IN THE FIRE SPRINKLER SYSTEM -
MIS-REPRESENT THE EXACT LAYOUT OF THE
LAYOUT & CALCULATIONS.
AID THE AUTHORITY HAVING JURISDICTION WITH
SPRINKLER SCHEMATIC MAY IN SOME CASES
SPRINKLER SYSTEM. IT IS INTENDED TO HELP
3 heads
T/S T/S
SCALE: 1/8" = 1'-0"
PLAN
NORTH
FIRE SPRINKLER PLANS
1 2 3 4 5 6 7 8 9 10
SECTION A
Vail Fire & Emergency Services
06/28/16