Mike Vaughan
Town of Vail Fire Marshal
Vail Fire&Emergency Services
42 West Meadow Drive
Vail, Colorado 81657
Re: Penthouse Unit 572 Remodel at The Lodge at Vail
08/13/14
Mike,
Scope of Work:
We have been contracted by SRE Building Associates to perform work to the existing
SimplexGrinnell FACP located at The Lodge at Vail, 174 Gore Creek Dr.Vail Co. 81657 for the
remodel improvement to the residential Penthouse Unit.572.
In this package we are including a pdf of the modified floor plan, cut sheets of new devices,
battery calculations for the affected panel,new circuit addressing chart for the affected SLC and
this letter. Please consider this package as our request for a permit to be issuedfor the following
work:
Prior to Construction:
1. Install and wire six new Heat Detectors with new bases.Extend 24v aux power to new
Sounder Bases.
•
During construction:
2. Relocate two existing wall mount Speakers in larger Bedrooms to new locations on wall.
Reconnect to existing Speaker circuit.
3. Two existing wall mount Speakers in smaller Bedrooms to be removed and new ceiling
mount Speakers tobe installed.Reconnect to existing Speaker circuit.
4. Install four System Sensor CO Detectors and four IAM Monitor Modules in bedrooms.
5. Remove and cover existing Pull Station in Elevator Lobby. Existing Smoke Detector in
Elevator Lobby shall remain.
6. Remove and cover existing wall mount Speaker/Strobe in Elevator Lobby, and install
new ceiling mount Speaker/Strobe in Elevator Lobby. Connect to existing Nac and
Speaker circuit in Elevator Lobby.
7. Remove and cover three existing Smoke Detectors. •
8. Remove existing FCU control switches in Entry Foyer.Existing automatic functions
related to the fan coil units shall be maintained.
9. All Speakers in unit 572 will be set at 1/4 watt.
Post Construction:
10. Replace Heat Detectors installed prior to construction with Smoke Detectors.
11. Install all devices roughed in during construction.
12. Pretest all changes prior to final inspection.
13. SimplexGrinnell will call for the final AHJ inspection.
Please let us know if we can furnish any other information to aid in your review process.
Thank you,
JJ
Nancy Wiltsie
Project Engineer
NICET III (Cert. # 93727,thru 3/01/15)
SimplexGrinnell
6240 Smith Road
Denver, Colorado 80216
Phone: 303-355-0500