HomeMy WebLinkAboutB14-0138 COMCheck - Suite 204.pdfProject Title: Suite 204 GALLERY Report date: 04/11/14
Data filename: J:\2699.00 - Solaris 204 & 205\Ltg Calcs\269900LC02 - UNIT 204.cck Page 1 of 2
COMcheck Software Version 3.9.3
Interior Lighting and Power
Compliance Certificate
90.1 (2007) Standard
Section 1: Project Information
Project Type: New Construction
Project Title : Suite 204 GALLERY
Construction Site: Owner/Agent: Designer/Contractor:
Lot P, Block 5-D
Vail Village Filing No.1
Vail, CO 81657
AE Design Group, Inc
1900 Wazee St. Ste 350
Denver, CO 80202
303.296.3034
Section 2: Interior Lighting and Power Calculation
A
Area Category
B
Floor Area
(ft2)
C
Allowed
Watts / ft2
D
Allowed Watts
(B x C)
Retail:Sales Area 2605 1.7 4429
Allowance: Other retail highlighting / Fix. ID: F1 2605(a)1 1856(b)
Total Allowed Watts =6285
(a) Area claimed must not exceed the illuminated area permitted for this allowance type.
(b) Allowance is (B x C) or the actual wattage of the fixtures given in Section 2, whichever is less.
Section 3: Interior Lighting Fixture Schedule
A
Fixture ID : Description / Lamp / Wattage Per Lamp / Ballast
B
Lamps/
Fixture
C
# of
Fixtures
D
Fixture
Watt.
E
(C X D)
Retail:Sales Area (2605 sq.ft.)
Linear Fluorescent 1: F1: 4' RECESSED LINEAR FLOURESCENT: 46" T5 HO 54W:
Electronic:
1 32 58 1856
Linear Fluorescent 2: F1A: 4' LINEAR FLUORESCENT: 46" T5 HO 54W: Electronic: 2 2 117 234
Halogen 1: F2: MR16 MULTIPLE: Halogen MR-16 50W:6 2 300 600
LED 1: F3: LED TAPE LIGHT: Other:1 1 35 35
Halogen 2: F4: MR16 MULTIPLE: Halogen MR-16 20W:3 11 60 660
Halogen 3: F7: MR16 ADJUSTIBLE: Halogen MR-16 20W:1 29 20 580
Linear Fluorescent 3: F8B: 2' RECESSED WALL WASHER: 22" T5 HO 24W: Electronic: 1 7 26 182
Linear Fluorescent 4: F8D: 4' RECESSED WALL WASHER: 46" T5 HO 54W: Electronic: 1 25 58 1450
Total Proposed Watts =5597
Interior Lighting PASSES: Design 11% better than code.
Section 4: Compliance Statement
Compliance Statement: The proposed lighting design represented in this document is consistent with the building plans, specifications and
other calculations submitted with this permit application. The proposed lighting system has been designed to meet the 90.1 (2007) Standard
requirements in COMcheck Version 3.9.3 and to comply with the mandatory requirements in the Requirements Checklist.
Name - Title Signature Date
Section 5: Post Construction Compliance Statement
4/11/2014
Jeff Mullikin 4/11/2014
Project Title: Suite 204 GALLERY Report date: 04/11/14
Data filename: J:\2699.00 - Solaris 204 & 205\Ltg Calcs\269900LC02 - UNIT 204.cck Page 2 of 2
Record Drawings and Operating and Maintenance Manuals:
❑1. Construction documents with record drawings and operating and maintenance manuals provided to the owner.
Lighting Designer or Contractor Name Signature Date
4/11/2014
4/11/2014
4/11/2014
4/11/2014
4/11/2014