HomeMy WebLinkAboutLot 5 Geotech report.pdf H P
Hepworth-Pawlak Geotechnical,Inc.
5020 County Road 154
e _)rtecI-•i Glenwood Springs,Colorado 81601
Phone:970-945-7988
HEPWORTH-PAWLAK GEOTECHNICAL Fax:970-945-8454
email:hpgeo@hpgeotech.com
PRELIMINARY SUBSOIL STUDY
FOR FOUNDATION DESIGN
PROPOSED RESIDENCE
LOT 5, ELK MEADOWS SUBDIVISION
1632 BUFFEHR CREEK ROAD
VAIL, COLORADO
JOB NO. 114 086A
JULY 11, 2014
• PREPARED FOR:
ELK MEADOWS DEVELOPMENT, LLC
ATTN: SHARON COHN
141 E.MEADOW DRIVE, SUITE 211
VAIL, COLORADO 81657
(sharon(a,solarisvail.com)
•
Parker 303-841-7119 • Colorado Springs 719-633-5562 • Silverthorne 970-468-1989
TABLE OF CONTENTS
PURPOSE AND SCOPE OF STUDY - 1 -
PROPOSED CONSTRUCTION - 1 -
• SITE CONDITIONS - 2 -
FIELD EXPLORATION - 2 -
SUBSURFACE CONDITIONS - 3 -
FOUNDATION BEARING CONDITIONS - 3 -
DESIGN RECOMMENDATIONS - 4 -
FOUNDATIONS - 4-
FOUNDATION AND RETAINING WALLS - 5 -
FLOORSLABS - 6 -
UNDERDRAIN SYSTEM - 7 -
SITE GRADING - 7 -
SURFACE DRAINAGE - g -
LIMITATIONS - 8 -
FIGURE 1 - LOCATIONS OF EXPLORATORY BORINGS
FIGURE 2 - LOGS OF EXPLORATORY BORINGS
FIGURE 3 - LEGEND AND NOTES
FIGURE 4 - SWELL-CONSOLIDATION TEST RESULTS
TABLE 1- SUMMARY OF LABORATORY TEST RESULTS
Job No. 114 086Atech
PURPOSE AND SCOPE OF STUDY
This report presents the results of a preliminary subsoil study for a proposed residence to
be located on Lot 5, Elk Creek Meadows Subdivision, 1632 Buffehr Creek Road, Vail,
Colorado. The project site is shown on Figure 1. The purpose of the study was to
develop recommendations for the foundation design. The study was conducted as part of
our proposal for geotechnical engineering services to Elk Creek Development, LLC dated
March 24, 2014. We previously performed a preliminary subsoil study for Lots 1 through
3 at the subdivision and presented our findings in a report dated April 18, 2014, Job No.
114 086A. Potential geologic hazards at the site have been addressed by others and are
beyond the scope of this report.
A field exploration program consisting of exploratory borings was conducted to obtain
information on the subsurface conditions. Samples of the subsoils obtained during the
field exploration were tested in the laboratory to determine their classification,
compressibility or swell and other engineering characteristics. The results of the field
exploration and laboratory testing were analyzed to develop recommendations for
foundation types, depths and allowable pressures for the proposed building foundation.
This report summarizes the data obtained during this study and presents our conclusions,
design recommendations and other geotechnical engineering considerations based on the
proposed construction and the subsurface conditions encountered.
PROPOSED CONSTRUCTION
A single family residence is planned on the lot shown on Figure 1. The residence will be
two story wood frame structure with the lower level retaining cut of the hillside slope.
Ground floors will be slab-on-grade. Grading for the structure is assumed to be relatively
minor with cut depths between about 3 to 8 feet. We assume relatively light foundation
loadings, typical of the proposed type of construction.
Job No. 114 086A Gtech
- 2 -
When building location, grading and foundation loading information have been
developed, we should be notified to re-evaluate the recommendations presented in this
report.
SITE CONDITIONS
The lot is vacant and the ground surface appeared mostly natural. There is some fill
along the north side of the site from construction of Buffehr Creek Road. The terrain is
strongly sloping down to the northwest towards Buffehr Creek Road. Slope grades are
estimated at about 5%to 7%. Elevation difference across the assumed building area is
estimated at about 5 to 6 feet. Vegetation consists of thick grass with aspen trees on the
valley side slopes. There are several scattered boulders on the ground surface.
FIELD EXPLORATION
The field exploration for the project was conducted on June 12, 2014. Two exploratory
borings were drilled at the locations shown on Figure 1 to evaluate the subsurface
conditions. The borings were advanced with 4 inch diameter continuous flight augers
powered by a truck-mounted CME-45B drill rig. The borings were logged by a
representative of Hepworth-Pawlak Geotechnical, Inc.
Samples of the subsoils were taken with 1% inch and 2 inch I.D. spoon samplers. The
samplers were driven into the subsoils at various depths with blows from a 140 pound
hammer falling 30 inches. This test is similar to the standard penetration test described
by ASTM Method D-1586. The penetration resistance values are an indication of the
relative density or consistency of the subsoils. Depths at which the samples were taken
and the penetration resistance values are shown on the Logs of Exploratory Borings,
Figure 2. The samples were returned to our laboratory for review by the project engineer
and testing.
Job No. 114 086A GecgPtech
- 3 -
SUBSURFACE CONDITIONS
Graphic logs of the subsurface conditions encountered at the site are shown on Figure 2.
The subsoils encountered, below about 2 to 3 feet of organic topsoil, consisted of medium
stiff, very sandy silty clay with gravel that occasionally graded to very clayey silty sand
underlain at depths from about 10 to 14 feet by loose to medium dense, silty gravely sand.
The silty gravely sand soils extended down to the depth drilled of 26 feet in Boring 1 and
to a depth of about 16 feet in Boring 2 where relatively dense, silty sandy gravel with
cobbles and possible boulders was encountered. The silty sand soils became more
gravelly with depth. Drilling in the dense granular soils with auger equipment was
difficult at times due to the cobbles and possible boulders.
Laboratory testing performed on samples obtained from the borings included natural
moisture content and density, and percent finer than sand size gradation analyses. Results
of swell-consolidation testing performed on a relatively undisturbed drive sample of the
silty sand soils, presented on Figure 4, indicate generally moderate compressibility under
conditions of loading and wetting with a low hydro-compression potential. The clay soil
samples were disturbed due to their medium stiffness and higher moister contents and
were not tested for swell-consolidation. The laboratory testing is summarized in Table 1.
No free water was encountered in the borings at the time of drilling or when checked 1
day later and the subsoils were very moist to moist becoming slightly moist with depth in
Boring 2.
FOUNDATION BEARING CONDITIONS
At assumed excavation depths for the residences, we expect the subgrade soils will
consist of the very sandy silty clay soils that are considered moderately compressible.
Lightly loaded spread footings bearing on these soils should be feasible for foundation
support of the building with some risk of settlement. The risk of settlement is due
primarily to the compressible nature of the very sandy silty clay soils. Extending the
Job No. 114 086A ettech
- 4 -
footings down the bear entirely on the sand and gravel soils would provide a lower risk
foundation.
DESIGN RECOMMENDATIONS
FOUNDATIONS
Considering the subsurface conditions encountered in the exploratory borings and the
nature of the proposed construction, we recommend the building be founded with spread
footings bearing on the natural soils with some risk of settlement.
The design and construction criteria presented below should be observed for a spread
footing foundation system.
1) Footings placed on the undisturbed natural soils should be designed for an
allowable bearing pressure of 1,200 psf. Based on experience, we expect
settlement of footings designed and constructed as discussed in this section
will be about 1 to 11/2 inches for the assumed light loadings. We should
review the settlement potential when foundation loadings are available and
make recommendations to mitigate the settlement if needed.
2) The footings should have a minimum width of 18 inches for continuous
walls and 2 feet for isolated pads.
3) Exterior footings and footings beneath unheated areas should be provided
with adequate soil cover above their bearing elevation for frost protection.
Placement of foundations at least 48 inches below exterior grade is
typically used in this area.
4) Continuous foundation walls should be heavily reinforced top and bottom
to span local anomalies and better withstand the effects of some
differential settlement such as by assuming an unsupported length of at
least 14 feet. Foundation walls acting as retaining structures should also
be designed to resist lateral earth pressures as discussed in the "Foundation
and Retaining Walls" section of this report.
Job No. 114 086A Gegtech
- 5 -
5) The topsoil and any loose or disturbed soils should be removed and the
footing bearing level extended down to the firm natural soils. The exposed
soils in footing area should then be adjusted to near optimum moisture
content and compacted. Unstable subgrade conditions will need to be
corrected prior to the footing construction.
6) A representative of the geotechnical engineer should observe all footing
excavations prior to concrete placement to evaluate bearing conditions.
FOUNDATION AND RETAINING WALLS
Foundation walls and retaining structures which are laterally supported and can be
expected to undergo only a slight amount of deflection should be designed for a lateral
earth pressure computed on the basis of an equivalent fluid unit weight of at least 55 pcf
for backfill consisting of the on-site soils. Cantilevered retaining structures which are
separate from the main buildings and can be expected to deflect sufficiently to mobilize
the full active earth pressure condition should be designed for a lateral earth pressure
computed on the basis of an equivalent fluid unit weight of at least 45 pcf for backfill
consisting of the on-site soils. The backfill should not contain topsoil or oversized rocks.
All foundation and retaining structures should be designed for appropriate hydrostatic and
surcharge pressures such as adjacent footings, traffic, construction materials and
equipment. The pressures recommended above assume drained conditions behind the
walls and a horizontal backfill surface. The buildup of water behind a wall or an upward
sloping backfill surface will increase the lateral pressure imposed on a foundation wall or
retaining structure. An underdrain should be provided to prevent hydrostatic pressure
buildup behind walls.
Backfill should be placed in uniform lifts and compacted to at least 90% of the maximum
standard Proctor density(SPD) at a moisture content near optimum. Backfill in pavement
and walkway areas should be compacted to at least 95% SPD. Care should be taken not
to overcompact the backfill or use large equipment near the wall, since this could cause
excessive lateral pressure on the wall. Some settlement of deep foundation wall backfill
Job No. 114 086A Gtech
- 6 -
should be expected, even if the material is placed correctly, and could result in distress to
facilities constructed on the backfill. Use of a select granular import material such as
road base and increasing compaction to at least 98% SPD could be done to reduce the
settlement potential.
The lateral resistance of foundation or retaining wall footings will be a combination of the
sliding resistance of the footing on the foundation materials and passive earth pressure
against the side of the footing. Resistance to sliding at the bottoms of the footings can be
calculated based on a coefficient of friction of 0.35. Passive pressure of compacted
backfill against the sides of the footings can be calculated using an equivalent fluid unit
weight of 375 pcf. The coefficient of friction and passive pressure values recommended
above assume ultimate soil strength. Suitable factors of safety should be included in the
design to limit the strain which will occur at the ultimate strength, particularly in the case
of passive resistance. Fill placed against the sides of the footings to resist lateral loads
should be a suitable granular material compacted to at least 95%of the maximum
standard Proctor density at a moisture content near optimum.
FLOOR SLABS
The natural on-site soils, exclusive of topsoil, are suitable to support lightly loaded slab-
on-grade construction. There could be some slab settlement due to the compressible
nature of the clay soils. To reduce the effects of some differential movement, floor slabs
should be separated from all bearing walls and columns with expansion joints which
allow unrestrained vertical movement. Floor slab control joints should be used to reduce
damage due to shrinkage cracking. The requirements for joint spacing and slab
reinforcement should be established by the designer based on experience and the intended
slab use. A minimum 4 inch layer of free-draining gravel should be placed beneath
basement level slabs to facilitate drainage. This material should consist of minus 2 inch
aggregate with at least 50% retained on the No. 4 sieve and less than 2%passing the No.
200 sieve.
All fill materials for support of floor slabs should be compacted to at least 95% of
maximum standard Proctor density at a moisture content near optimum. Required fill can
Job No. 114 086A c; tech
- 7 -
consist of the on-site soils devoid of topsoil and oversized rocks, or a suitable granular
material such as road base can be imported.
UNDERDRAIN SYSTEM
Although free water was not encountered during our exploration, it has been our
experience in mountainous areas and where clay soils are present that local perched
groundwater can develop during times of heavy precipitation or seasonal runoff. Frozen
ground during spring runoff can also create a perched condition. We recommend below-
grade construction, such as retaining walls, crawlspace and basement areas, be protected
from wetting and hydrostatic pressure buildup by an underdrain system.
The drains should consist of drainpipe placed in the bottom of the wall backfill
surrounded above the invert level with free-draining granular material. The drain should
be placed at each level of excavation and at least 1 foot below lowest adjacent finish
grade and sloped at a minimum 1% to a suitable gravity outlet or sump and pump. Free-
draining granular material used in the underdrain system should contain less than 2%
passing the No. 200 sieve, less than 50% passing the No. 4 sieve and have a maximum
size of 2 inches. The drain gravel backfill should be at least 11/2 feet deep and covered by
filter fabric such as Mirafi 140N.
SITE GRADING
The risk of construction-induced slope instability at the site appears low provided the
building is located as planned and cut and fill depths are limited. We assume the cut
depths for the basement level will not exceed one level, about 10 feet. Embankment fills
should be limited to about 8 to 10 feet deep and be compacted to at least 95% of the
maximum standard Proctor density near optimum moisture content. Prior to fill
placement, the subgrade should be carefully prepared by removing all vegetation and
topsoil and compacting to at least 95%of the maximum standard Proctor density. The fill
should be benched into the portions of the site exceeding 20% grade.
Job No. 114 086A CSE Ptech
- 8 -
Permanent unretained cut and fill slopes should be graded at 2 horizontal to 1 vertical or
flatter and protected against erosion by revegetation or other means. The risk of slope
instability will be increased if seepage is encountered in cuts and flatter slopes may be
necessary. If seepage is encountered in permanent cuts, an investigation should be
conducted to determine if the seepage will adversely affect the cut stability.
SURFACE DRAINAGE
Positive surface drainage is an important aspect of the project. The following drainage
precautions should be observed during construction and maintained at all times after the
building has been completed:
1) Inundation of the foundation excavations and underslab areas should be
avoided during construction.
2) Exterior backfill should be adjusted to near optimum moisture and
compacted to at least 95%of the maximum standard Proctor density in
pavement and slab areas and to at least 90% of the maximum standard
Proctor density in landscape areas.
3) The ground surface surrounding the exterior of the building should be
sloped to drain away from the foundation in all directions. We
recommend a minimum slope of 12 inches in the first 10 feet in unpaved
areas and a minimum slope of 3 inches in the first 10 feet in paved areas.
Free-draining wall backfill should be capped with filter fabric such as
Mirafi 140N and about 2 feet of the on-site finer graded soils to reduce
surface water infiltration.
4) Roof downspouts and drains should discharge well beyond the limits of all
backfill.
5) Landscaping which requires regular heavy irrigation should be located at
least 5 feet from foundation walls.
LIMITATIONS
This study has been conducted in accordance with generally accepted geotechnical
engineering principles and practices in this area at this time. We make no warranty either
Job No. 114 086A Gtech
- 9 -
express or implied. The conclusions and recommendations submitted in this report are
based upon the data obtained from the exploratory borings drilled at the locations
indicated on Figure 1,the proposed type of construction and our experience in the area.
Our services do not include determining the presence, prevention or possibility of mold or
other biological contaminants (MOBC) developing in the future. If the client is
concerned about MOBC, then a professional in this special field of practice should be
consulted. Our findings include interpolation and extrapolation of the subsurface
conditions identified at the exploratory borings and variations in the subsurface
conditions may not become evident until excavation is performed. If conditions
encountered during construction appear different from those described in this report, we
should be notified so that re-evaluation of the recommendations may be made.
This report has been prepared for the exclusive use by our client for design purposes. We
are not responsible for technical interpretations by others of our information. As the
project evolves, we should provide continued consultation and field services during
construction to review and monitor the implementation of our recommendations, and to
verify that the recommendations have been appropriately interpreted. Significant design
changes may require additional analysis or modifications to the recommendations
presented herein. We recommend on-site observation of excavations and foundation
bearing strata and testing of structural fill by a representative of the geotechnical
engineer.
Respectfully Submitted,
HEPWORTH - PAW e . GEOTECHNICAL, INC.
.08tt ata ogee
. °em �? aw
.:.
shy
David A. Young, P.E. •
e ts '
=•g '`-216
Q
tee# 9kSi '"a �,
DAY/ljg f* -,
MAL1d
cc: Elk Meadows Development—Brian Redinger(brian@solarisvail.com)
Job No. 114 086A ec h
/ O
APPROXIMATE SCALE
1" = 30'
BORING 1
•
Q I z
Lu
Y I w
W I Q
r LU
C
IL
= J
W H
LL
LOT 5
m
1632 BUFFEHR
CREEK ROAD
BORING 2
•
114 086A ~
Ch LOCATION OF EXPLORATORY BORINGS Figure 1
Hepworth—Pawlak Geotechnical
BORING 1 BORING 2
ELEV.= 100' ELEV.= 96'
0 0 _
/. ...
-
�i I 4/12 3/12 —
/ rl /
5 ' 11/12 ' 4/12 5 —
' / WC=19.1
DD=79
—
/ / / ' -200=50 —
/
/ —
/ —
10 ' 4/12 C.;E 6/12 10 —
/ WC=17.4 6 -
DD=95
' -200=45 —
—
u_ 15 8/12 ".�'''� 10/12 15 —
L : WC=10.8 1';: WC=15.9 — -
p. DD=108 c6 DD=112
CD — — a
p a *. -200=33
_ ":;1X
20 1
p
13/12 4 73/12 2C)
iT
f
2523/12 25
30 30
LOT 5
Note: Explanation of symbols is shown on Figure 3.
H
114 086A C7Q Ch LOGS OF EXPLORATORY BORINGS Figure 2
HEPWORTH-PAWLAK GEOTECHNICAL
LEGEND:
... TOPSOIL; organic sandy silty clay, soft, very moist, dark brown.
N
. CLAY(CL); silty, very sandy to occasionally very clayey silty sand, medium stiff/loose, moist to very moist,
L red-brown, low plasticity, calcareous.
7 SAND (SM); silty, gravelly, loose to medium dense, moist, red-brown.
GRAVEL (GM);with cobbles, sandy, silty, dense, slightly moist, brown.
Relatively undisturbed drive sample; 2-inch I.D. California liner sample.
x■ Drive sample; standard penetration test (SPT), 1 3/8 inch I.D. split spoon sample,ASTM D-1586.
4/12 Drive sample blow count; indicates that 4 blows of a 140 pound hammer falling 30 inches were
required to drive the California or SPT sampler 12 inches.
NOTES:
1. Exploratory borings were drilled on June 12, 2014 with 4-inch diameter continuous flight power auger.
2. Locations of exploratory borings were measured approximately by pacing from features shown on the site plan
provided.
3. Elevations of exploratory borings were approximated by hand level and refer to the ground surface at Boring 1 as
assumed elevation = 100'. Boring logs are drawn to depth.
4. The exploratory boring locations and elevations should be considered accurate only to the degree implied by the
method used.
5. The lines between materials shown on the exploratory boring logs represent the approximate boundaries between
material types and transitions may be gradual.
6. No free water was encountered in the borings at the time of drilling or when checked 1 day later. Fluctuation in
water level may occur with time.
7. Laboratory Testing Results:
WC = Water Content(%)
DD = Dry Density(pcf)
-200 = Percent passing No. 200 sieve
114 086A1-iP,,�
�D@Vd ch LEGEND AND NOTES Figure 3
HEPWORTH-HAWLAK GEOTECHNICAL
Moisture Content = 10.8 percent
Dry Density = 108 pcf
Sample of: Silty Sand
From: Boring 1 at 15 Feet
0
1
Compression
° upon
0 wetting
co 2
a.
E
0
v 3
4
0.1 1.0 10 100
APPLIED PRESSURE-ksf
114 086A GegtleCh SWELL-CONSOLIDATION TEST RESULTS Figure 4
Hepworth—Pawlak Geotechnical
V
a b 3
co q >,
o cks ct
o wa U
V. rx
V. O Z
p 0
CO
O 0 N CO cd 2 g r+ p
c_.) O � � 4
0) .00' 4 rrf t)
3 > O
Z
0
oa
2-
O-
ctLL
a N
U Li)
a J
Z J O
D
J co O
Q W . Nw e
U x f aZ
co z a-
W
✓ H m
W )- re2r
pk _a-
W O0 a JJ
U' r Q _
Y W X FO
J m m UNN> to O M
a Q re kr) v. n m
< I- J 0-0-Z Ca
IL U-
= O
I- >- °
CC I z a :?.•`
O C ocn
a
a
I t=i) 2 > o
a
CC
J
0 K CO 0 kr) O\ N
r0Z a 0\ O9 n 1-4
a 0
Z
J�t-
KD W00 •-• CA
co -
rNO O� kr;
2
ZCO)
Z I
O
w n
O in
1- a x ti .-y --i
a0U
0
J
W
a
O
M z
a ° N
co 0