HomeMy WebLinkAboutBegin_Workflow-04-13-2015_12-58-56.pdfClick Here to Save Eform as PDF...
Review Information Permit Information Contact Information Resources Checklist Report (0)Routing Slip
Review Coordinator Shelley Bellm ( sbellm@vailgov.com )
Review Cycle 1
Workflow/Activity Name Begin_Workflow / ApplicantResubmit
Activity InstructionsPlease review all sections of the eForm and drawing markups and resubmit the required
information prior to completion of task.
Current User Logon Paul Roberts ( paulr@zehren.com)
CHANGEMARKS Review Cycle:1
Filter Changemarks by Keyword: SEARCH SHOW ALL
Click Here to Load Changemarks...
Click Here to Publish Changemarks to PDF...
Sorting:
Resolved Status File Cycle Department File Markup Description Details Applicant Response
Yes | No No 1
Public
Works
Engineers
L1.2.pdf csalli PW 002
version 3 showed bollards to installed, they are not
shown on version 4. Were they deleated from the
proejct? if not, please resubit correct layout and
mtrls plan
Yes | No No 1
Public
Works
Engineers
L1.1.pdf csalli PW 001
version 4 of L1.1 showed the removal of the 3
sacred (holy trinity) cottonwood trees. this version 5
shows them to remain. please provide correct
updated planting plan
Yes | No No 1
Public
Works
Engineers
L1.1.pdf csalli PW 003
civil drawing show a landing at the bottom of the
stairs tieing in to the concrete walk. please
coordinate drawings. a landing is required as shown
on the civils
In addition to clarification regarding certain
cottonwoods, please provide details on plantings
required per previous condition of approval.
DEPARTMENT REVIEW Review Cycle:1
CYCLE DEPARTMENT REVIEWED BY STATUS & NOTES
1 BUILDING
FLORENCIO MONDRAGON
JMONDRAGON@VAILGOV.COM
NO REVIEW REQUIRED
VIEW CHECKLIST
PLAN REVIEW AND/OR ASSIGNMENT COMPLETE
1 PLANNING
JONATHAN SPENCE
JSPENCE@VAILGOV.COM
CORRECTIONS REQUIRED
PLAN REVIEW AND/OR ASSIGNMENT COMPLETE
1 PUBLIC WORKS
CHAD SALLI
CSALLI@VAILGOV.COM
NO REVIEW REQUIRED
VIEW CHECKLIST
Complete Save And Close
Building Process V1
PLAN REVIEW AND/OR ASSIGNMENT COMPLETE
1
PUBLIC WORKS
ENGINEERS
CHAD SALLI
CSALLI@VAILGOV.COM
CORRECTIONS REQUIRED
PLAN REVIEW AND/OR ASSIGNMENT COMPLETE
I have reviewed and addressed the Checklist Comments provided on the "Checklist" tab above. Please click on the tab and review each item. Each comment will be
indicated as "Met" or "Not Met". If you would like to export a list of the comments to Excel, click on the "Export to Excel" link in the upper right hand corner of the popup
window.
I have addressed all of the items listed in the Changemarks section above that were identified during the Plan Review.
I have uploaded the revised drawings into the "Drawings" folder and, if requested, uploaded any revised documents into the "Documents" folder using the SAME file name as
the original files. I am ready to complete my assigned task.
Task Instructions